Originator/Responsible Engineer
Scope Change
Determine Preliminary Impact
Review with Drafting
Prepare ECN
Drafting Specifications
Assign ECN Numbers
Perform Where-Used Check
Prepare Change Package
Submit for Review and Approval
Section K10.0
Page 1
November 1987*
{}
Responsible Engineer
Perform Review
Identify Reviewers and Verifiers
Identify Distribution Requirements
Review as Applicable
Engineering Interface
Materials
Procurement
Manufacturing
Cost Estimating
Quality Assurance
Document Quality
Spares and Renewal Parts
Technical Publications
Figure 10-1. An Algorithim for Engineering Changes. Need for Change Identified.
GENIUM PUBLISHING
* New
DRAFTING MANUAL
Update 78
Gary Whitmire
Section 10.1
Page 1
June, 2008
1.0 General
This section defines practices for revising documentation such as a drawing, parts list, wiring list, data list, etc.
Drawing changes usually originate from suppliers, manufacturing, and inspection where errors have been found in
the documentation or due to the complexity of the product. The following is the flow of a typical change system:
A. A change is recommended by submitting a Document Change Request (DCR).
B. Engineering determines the impact of the change.
C. If a change is acceptable, engineering prepares a Document Change Notice (DCN).
D. A DCN number is assigned.
E. A change package is prepared.
F. The suggested change is reviewed and approved.
G. As applicable, the change is reviewed by:
Engineering
Materials
Procurement
Manufacturing
Cost estimating
Quality Assurance
Document quality
Spares and renewal parts
Technical publications
H. Distribution requirements are identified.
I.
ASME Y14.24
Update 78
Gary Whitmire
DRAFTING MANUAL
Revision of Engineering Drawings
ASME Y14.34
Associated Lists
ASME Y14.35
ASME Y14.38
Section 10.1
Page 2
June, 2008
3.0 Definitions
Advance Document Change Notice (ADCN) The advance change notice is an approved revision that will be
incorporated on the drawing at a later date. A pre-released ADCN requires only the approval of the design
activity. It is used for rapid changes where an emergency condition exists or when other changes may be pending.
The ADCN is issued only for one drawing.
Approval An endorsement applied manually or electronically attesting to the correctness of a document or a
revision made to a document. Approval is different from the approval of the design.
Associated Documents General reference to documentation supportive of and directly related to drawing
content, such as a parts list, wiring list, etc.
Bill of Material (BOM) The "parts list" of components needed to complete an end-item.
Canceled Drawing A drawing that has been removed from the drawing system and from all next assemblies. A
superseded or obsolete drawing is considered a canceled drawing. The drawing number is no longer used.
Commercial and Government Entity Code (CAGE Code) A five digit numeric code listed in the Cataloging
Handbook H4/H8 which is assigned to commercial and government activities that manufacture or develop items
for the government. For the commercial sector, where there is no requirement for the CAGE Code; line through
the CAGE Code in the title block.
Configuration Management (CM) A discipline applying technical and administrative controls to:
A. Identification and documentation of physical and functional characteristics of configuration items.
B. Any change to characteristics of those configuration items.
C. Recording and reporting of change processing and implementation of the system.
Data List A compilation of all engineering drawings, associated lists, specifications, standards, and associated
data. A data list is a company document necessary to meet technical design disclosure requirements.
Design Activity, Current The current design activity is the party, be it a governmental entity, commercial
vendor, contractor, company, department, or other entity, currently and actively responsible for the product
design, preparation and maintenance of drawings, and related documents for the item.
Design Activity, Original The original party responsible for the product design, preparation and maintenance
of drawings, and related documents for the item. The original design activity may, or may not, be the same entity
as the current design activity.
Update 78
Gary Whitmire
DRAFTING MANUAL
Revision of Engineering Drawings
Section 10.1
Page 3
June, 2008
Digital Data Data created and stored on a computer system that employs a display on which the user and the
computer interact to create layouts, drawings, numerical control tapes, CD-ROM, DVD or other removable or
permanent engineering data.
Document A drawing, specification, list, standard, pamphlet, report or other printed or typewritten material
pertaining to design, procurement, manufacturing, testing, acceptance or inspection of an item, process or service.
Document Change Notice (DCN) A document that gives authorization for changes that has been incorporated
on a drawing. The DCN is issued only against one drawing.
Document Change Request (DCR) A document used to officially request drawing changes. The DCR
constitutes a request until approved by the responsible design activity. A DCR may be initiated by personnel
outside or within the design activity. After the DCR is approved it is implemented by drafting as an ADCN or
DCN. The DCR is issued only against one document.
Document Management System (DMS) A computer system (or set of computer programs) used to track and
store electronic documents and images of paper documents. This is also called Document Control.
Drawing An engineering document or digital file that portrays, directly or indirectly, the physical and
functional requirements of an item. The drawing may be graphical, textual or a combination of both.
Drawing Change A change authorized and recorded on a Drawing Change Notice (DCN).
Engineering Change Notice (ECN) A document which records or authorizes a change to a design. The reasons
for the change may also be recorded.
Engineering Change Order (ECO) Same as an ECN.
Engineering Change Request (ECR) Same as a DCR.
Fit The ability of an item to physically interface or interconnect with or become an integral part of another item.
Form The physical parameters of an item such as shape, size, mass, and other physical properties.
Function The action(s) of what an item is designed to perform.
Inactivated Drawing Removing a drawing from active status and no longer using. Inactivate documents are
retained and may be reactivated for use in the future.
Interchangeable Items capable of being installed, removed or replaced without sustaining damage, or causing
misalignment, damage to, or interference with adjoining parts or portions of the complete assembly without
modification or selection. Interchangeable items are equivalent in characteristics of operation, performance,
durability, serviceability, structural strength, material, protective finish and safety.
Item A nonspecific item reference to any specific product, part, assembly, equipment or unit.
Update 78
Gary Whitmire
DRAFTING MANUAL
Revision of Engineering Drawings
Section 10.1
Page 4
June, 2008
Obsolete Drawing (inactive, canceled) An obsolete drawing is one which has been replaced by another
drawing with the same number, and shall be marked OBSOLETE. The replacement drawing shall have the next
higher revision letter and all previous revision entries removed and REDRAWN WITHOUT CHANGE or
REDRAWN WITH CHANGE with a description of the changes.
Original The design activitys original document.
Parts List A compilation of all parts and bulk materials used in an item. It does not include consumables used
to support the process, such as cleaning solvents or cutting fluids.
Product Definition The sum of the geometry, dimensional information and related documentation that
identifies the form and function of a part.
Redrawn A new original drawing with the same drawing number that has been substituted for a previous
original drawing that has been destroyed or lost.
Revision Changes made to an original or associated document, after release, that require the revision level to be
advanced.
Revision Authorization Document A document that is the recognized authority for making a change such as a
Engineering Change Notice (ECN) or Engineering Change Order (ECO).
Revision History Block A designated area on the drawing reserved for describing or summarizing revisions to
the drawing and for recording certain specifics regarding the revisions.
Revision Symbol A small circle approximately .375 inches in diameter placed near where the change is being
made. It encompasses the revision letter and change item number such as B3.
Superseded A notation in the revision block to indicate that a document has been replaced by another document
with a different document number or to indicate a new original.
DRAFTING MANUAL
Update 78
Gary Whitmire
Section 10.1
Page 5
June, 2008
Update 78
Gary Whitmire
DRAFTING MANUAL
Revision of Engineering Drawings
Section 10.1
Page 6
June, 2008
5.0 Drawing Advance Document Change Notice (ADCN) or Document Change Notice (DCN)
(Approval signatures on an ADCN or DCN are equal to those on the drawing).
5.1 Revisions On Drawings - Revisions incorporated on drawings are normally authorized by an ADCN/DCN.
5.2 ADCN/DCN Rules Rules relating to the revision authorization documents identified as ADCN and DCN.
5.2.1 A revision letter to be incorporated on the original drawing is assigned for each ADCN/DCN. Each change
is described on the ADCN/DCN using the drawing zones for the change location.
5.2.2 If there are several ADCN/DCN that have not been assigned revision letters, they shall be incorporated at
the same time as a group. The incorporation of several ADCN/DCN shall raise the revision letter by one level.
DRAFTING MANUAL
Update 78
Gary Whitmire
Section 10.1
Page 7
June, 2008
6.3 Changes Not Requiring a Revision Level Advancement The following revisions must be stated in the
Revision History block without changing the revision letter or having an ADCN or DCN:
A. Adding a CAGE Code within the Title Block.
B. Adding a Distribution Statement.
C. A drawing identified as redrawn without change is replaced with a drawing of duplicate requirements of
the original. Names of the individuals whose signatures appear in the original Title Block are lettered in
the new original Title Block. The notation REDRAWN WITHOUT CHANGE shall be added to the
Revision History block.
D. Weight information.
E. Misspelled words.
F. Missing arrowheads.
G. Missing dimensions.
H. When an item is changed in such a way that it necessitates a corresponding change to an operational, selftest, or maintenance-test program. In this case, the part number identification of the item and its next
assembly and all progressively higher assemblies must be changed up to and including the assembly
where the program is affected.
DRAWING BORDER
.50
REVISION HISTORY
.60
.40
DESCRIPTION
AS REQD
DATE
APPROVED
2.40
1.20
Figure 1
7.1 ZONE Column The zone coordinates are used to locate where the revision took place. Revision A states
that the change took place in B5 and C6. For revision B the zones are listed in the description block
because there is not enough room in the zone column. Revision C states that the change is on sheet 2 zone E4
See Figure 2.
DRAFTING MANUAL
Update 78
Gary Whitmire
Section 10.1
Page 8
June, 2008
REVISION HISTORY
ZONE REV
A
B5
C6
DESCRIPTION
DATE
APPROVED
DCN 123456
(1) R.19 WAS R.12
(2) ADDED POSITION CONTROL
07-6-9
G.Whitmire
J.Doe
DCN 123462
(1) DELETED RADIUS
ZONES C3, D3, C4, D4, C6, D6
07-10-22 G.Whitmire
J.Doe
DCN 123470
(1) 1.500 WAS 1.375
07-12-2
E4
G.Whitmire
J.Doe
Figure 2
7.2 REV Column The revision column starts with the letter A.
7.3 DESCRIPTION Column The DESCRIPTION column lists the Document Change Notice (DCN) number,
and a short description of each change (shown in Figure 2).
7.4 DATE Column The date is when the drawing change took place. The date shall be in the format YEAR
MONTH DAY as shown in Figure 3.
7.5 APPROVED Column The drawing checkers authorized signatures or electronically generated signatures
shall be added. Any approval indicator symbol adopted by the design activity to indicate approval may be used.
This signature system may change as new security technology is developed.
Update 78
Gary Whitmire
DRAFTING MANUAL
Revision of Engineering Drawings
Section 10.1
Page 9
June, 2008
drawing shall be used to dictate the standards to be followed. If there are critical design standards, it shall be
specified in the general notes with dates and revision levels to avoid any confusion as to which standard applies.
8.4 Recording of Revisions When Space is Limited Revisions may be continued on another Revision History
block format on the same drawing sheet where there is room or on another continuation sheet. When the
continuation of the revision record is on a condition sheet, the Revision History block on sheet 1 shall state SEE
SHEET X OF X FOR CONTINUATION OF REVISION HISTORY and sheet X of X Revision History block
shall state CONTINUATION OF REVISION HISTORY.
8.5 Revisions Located on the Face of the Drawing The Revision History block shall state where the revision
has taken place such as the border coordinates or a statement in the description block PARTS LIST, TITLE
BLOCK, GENERAL NOTES or whatever is applicable. Revision symbol on the field of the drawing such as
B3 would be revision B, change number 3. The revision symbol may have more than one leader with
arrowheads pointing to the changes. See Figure 3. Each revision balloon symbol for changes listed on an
ADCN/DCN is assigned a suffix item number such as revision B1, B2, B3, etc. The size of the revision
symbol is approximately .375 inches in diameter. Previous revision balloon symbols shall not be removed. Where
several changes are contained within a small area of one zone coordinate, they may be recorded under one suffix
item number. Revision balloon symbols shall not be used on book-form drawings, master art work, schematic or
wiring diagrams to list a few similar documents.
B3
B3
B3
Figure 3
8.5.1 Omitting the Revision Symbol On drawings where the use of revision symbol(s) may conflict with other
symbols used on the drawing, thus creating a possible misinterpretation, the revision description in the Revision
History block will be adequate.
8.6 Drawing Revision Letters The letters X1, X2, X3, etc. are used for recording revisions to an
unreleased drawing. The initial release of the drawing uses a dash - in the revision (REV) block and there is no
statement in the description block. When the drawing is first changed, the revision level is identified by the upper
case letter A. Letters I, O, Q, S, and Z are never used. Upon exhaustion of the alphabet, revisions
are identified by letters AA, AB, AC, etc. Revision letters shall not exceed two characters.
8.7 When the ADCN or DCN Pre-assign the Revision Letter When the ADCN or DCN pre-assign a revision
letter in advance of changes being made to the document, and the ADCN or DCN describes the changes, only the
ADCN or DCN number and date needs to be identified in the Revision History block. If the changes are not
described in the ADCN or DCN, they must be described in the Revision History block. The Revision History
block must state the applicable revision letter given on the ADCN or DCN, and the ADCN or DCN number and
date.
Update 78
Gary Whitmire
DRAFTING MANUAL
Revision of Engineering Drawings
Section 10.1
Page 10
June, 2008
8.8 When the ADCN or DCN Does Not Pre-assign the Revision Letter When the ADCN or DCN does not
pre-assign a revision letter in advance of the changes being made to the document, and the ADCN or DCN
describes the changes, only the ADCN or DCN number and date needs to be identified in the Revision History
block. The next higher revision letter is used. If the changes are not described on the ADCN or DCN, they must
be described in the Revision History block and the next higher revision letter used. Note that the ADCN or DCN
number and date need to be stated in the Revision History block.
8.9 When Many ADCN or DCN Pre-assign Many Revision Letters When several ADCNs or DCNs preassign individual revision letters, they must be incorporated individually as separate revisions in alphabetical
order as stated in the ADCN or DCN. If the changes are described in the individual ADCN or DCN, only the
ADCN or DCN number and date needs to be stated for each revision letter in the Revision History block. If the
changes are not stated in the ADCN or DCN, they must be stated in the Revision History block for each revision
letter. Note that the ADCN or DCN numbers and dates need to be stated in the Revision History block to show the
change authorization.
8.10 When Many ADCN or DCN Do Not Pre-assign the Revision Letter When several ADCNs or DCNs
are incorporated at the same time and do not have pre-assigned revision letters, they shall be incorporated as a
group using the next higher revision letter. The changes shall be stated in the Revision History block in a logical
order. Note that the ADCN or DCN numbers and dates need to be stated in the Revision History block to show
the change authorization.
8.11 Complex Changes When a change description covers more than one ADCN or DCN or the changes are
extensive or complicated, but still do not require a complete redraw, a general description in the DESCRIPTION
column or on the ADCN or DCN may be used such as:
COMPLETELY REVISED THE LOCATION OF THE FUEL PUMP SYSTEM TO ZONES D3,
D4, AND D5. PREVIOUSLY IN ZONES B3, B4, AND B5.
The ADCN or DCN number(s) and date(s) needs to be identified in the Revision History block.
DRAFTING MANUAL
Update 78
Gary Whitmire
Section 10.1
Page 11
June, 2008
DEL
SH1
SH2
SH3
SH4
SH5
SH6
15.3 Adding Sheets Adding a sheet constitutes a revision letter change to the document and the Revision
History block on the new sheet shall state: THIS SHEET ADDED. Also, the Revision Sheet Status Level, as
addressed in paragraph 15.2, shall be upgraded.
DRAFTING MANUAL
Update 78
Gary Whitmire
Section 10.1
Page 12
June, 2008
If sheets are added between sheets 2 and 3, a decimal-number or alpha-numeric sequence shall be used such as
2.1, 2.2, and 2.3 or 2A, 2B, and 2C. The Revision Sheet Status Level on sheet 1 shall be updated and sheet 1 will
show the highest revision level, and the specific changes shall be described in the DESCRIPTION column.
REVISION SHEET STATUS LEVEL
D
SH1
SH2
SH4
SH5
SH6
15.4 Deleting Sheets When sheets are deleted, the revision level on sheet 1 shall be advanced to the highest
revision level, and the specific changes shall be described in the DESCRIPTION column. The remaining sheets
after the DEL shall not be renumbered.
REVISION SHEET STATUS LEVEL
D
SH1
SH2
DEL
SH4
SH5
SH6
15.5 Cross Reference On the face of the drawing, any cross reference to another sheet shall be updated when
sheets are renumbered or deleted.
DRAFTING MANUAL
Section K10.2
Page 1
November 1986*
GENIUM PUBLISHING
DRAFTING MANUAL
Section K10.3
Page 1
November 1986*
Table 10.3-1
Revision Change Request, Drawings
Table 10.3-2
Revision Change Request, Parts List
GENIUM PUBLISHING
DRAFTING MANUAL
Section K10.4
Page 1
July 1988*
GENIUM PUBLISHING
Section K10.4
Page 2
July 1988*
DRAFTING MANUAL
Design Quality and Checking Practices
GENIUM PUBLISHING
DRAFTING MANUAL
Section K10.4
Page 3
July 1988*
GENIUM PUBLISHING
Section K10.4
Page 4
July 1988*
DRAFTING MANUAL
Design Quality and Checking Practices
Draft angles and related radii should be specified on castings, forgings, plastic moldings, and punched sheet metal
parts.
Drawing numbers assigned only from approved blocks of
numbers should be used and shown in appropriate blocks on
the drawing form.
Surface texture values must be shown where required.
Geometric surface relationships covering necessary relationships such as straightness, flatness, runout, squareness,
symmetry, and parallelism must be shown where applicable.
Identification of part numbers, nameplates, and other
identification markings should be shown. Markings must not
deface critical surfaces.
The part number callout of each item of an assembly or
subassembly must be shown.
The proprietary and security legend must be shown, if
applicable.
tion of objectionable tolerance. Dimensions should emphasize function of design in preference to production operations
or processes and should be such as to minimize shop
calculations. Datums should be used and identified to the
maximum extent possible. Developed lengths and stock sizes
should be specified as applicable.
Revisions must be properly recorded. All lines, text, dimensions, etc., that are obliterated by erasure must
be restored. All related drawings that are affected by the
change must also be revised.
The scale should be identified. Where drawings are not to
scale, this should be indicated.
Spelling must be correct.
Symbols used should be derived from national standards. If
not, they must be clearly explained.
Symmetrically opposite parts must be properly identified.
The drawing should show the correct hand consistent with its
assembled position in the assembly.
The tide block, including approval signatures, must be
completely filled out. If a block is not applicable, a dash
should be shown in that block.
Views (full, sectional, partial) must be in proper relation to
each other to the extent possible. Cross-sectioning must
agree with company standards. Directional arrows on cutting
GENIUM PUBLISHING
DRAFTING MANUAL
Section K10.4
Page 5
July 1988*
GENIUM PUBLISHING