Erb West Field : The World's First Offshore Level 6 Multilateral Well
Noren Samsudin, Abdullah Kassim, M Zaidan Khalid, A. Aziz A. Rahman, Abu Bakar Che Mad (Petronas), Richard Liau,
Matthew Jabs, Ben Lim (Baker Oil Tools)
Introduction
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the Society of Petroleum Engineers is
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
Abstract
The oil industry has lately seen the introduction of more
complex, purpose built multilateral wells of the TAML
(Technology Advancement Multilateral) levels 4 and 5
categories. The debris management issues, junction integrity
and the risk involved in the well construction are still
perceived as operational challenges to operators. In reviewing
the risk profile, operators and service companies alike have
sought to look into techniques outside the realm of
conventional well construction methods. Expandable tubular
technology is one such area. The manufacturing concept is to
form a junction with a 9-5/8 trunk casing branching into two
separate 7 liner legs. This junction is then pressed and formed
in order for it to be able to pass through the drift ID of 13-3/8
casing. The junction is then reformed downhole using an
innovative downhole swaging process.
This paper describes the process of deploying the TAML level
6 multilateral junction in the Erb West Field (offshore
Malaysia) during the EWDP-A Revisit 4 Campaign (well EW117S1). The discussion follows the full cycle of well
construction for a level 6 multilateral junction. It encompasses
the well planning phase, the deployment and the installation
phase, the lateral drilling phase, and finally the completion of
the level 6 multilateral well. The result is a multilateral well
construction technique which eliminates the debris
management, reduces well construction risk and provides a
hydraulically sealed junction, integral with the trunk casing.
SPE 68729
ERB WEST FIELD : THE WORLD'S FIRST OFFSHORE LEVEL 6 MULTILATERAL WELLABU
Depth
5,651ft MD
8,971ft MD
@ 67deg
Depth 8,483ft MD
@ 67Deg
Pilot Well
Well
Path
#1
Well
Path
#2
14,910ft MD
SANDS
MNSands
LATERAL
LEG #2
15,260ft MD
LATERAL
LEG #1
SPE 68729
ERB WEST FIELD : THE WORLD'S FIRST OFFSHORE LEVEL 6 MULTILATERAL WELLABU
lateral liner, and perforate the lateral liner with coiled tubing
conveyed perforating guns.
Independent Access into the 3-1/2 Laterals. Independent
access was considered a prerequisite for several reasons.
Firstly, it was anticipated that there may be a need to
selectively isolate sections of the production interval if water
ingress is detected. Secondly, with the view to minimize
formation damage, consideration was made in the design to
eliminate the process of killing the well after underbalanced
perforating. This design consideration necessitates that the
laterals are independently accessible with through-tubing
devices and coiled tubing conveyed perforating guns.
New Technology - The Level 6 Formable Junction
Various multilateral options were considered from the
conception of the Erb West project. The necessity of achieving
hydraulic isolation across the junction was a key deciding
factor in the selection of multilateral junction types. This
prerequisite for hydraulic isolation narrowed the choice of the
junction type to the TAML level 5 or level 6 junction category.
Further consideration was made in the risk profile comparison
between the TAML level 5 and level 6 junction types. The key
feature that made the level 6 junction a superior choice over
the level 5 junction was the exclusion of debris management
issues. The level 5 well construction process requires a
window to be milled in the trunk casing, and a subsequent
process to mill over the lateral liner stub. The mill cuttings
generated by these two processes needs to be carefully
managed. This key consideration led to the adoption of the
level 6 junction for the Erb West multilateral development.
The level 6 junction is a 9-5/8 X 7 X 7 preformed junction.
Unlike all other previous junctions, where the junction
construction process is carried out down hole, the construction
of the level 6 junction is initiated at its manufacturing
facility. The junction is then pressed to enable it to pass
through a 12-1/4 hole. Once it is placed at depth, a swaging
assembly is run to the junction depth to re-form the junction to
its original dimension, thus creating a 9-5/8 X 7 X 7
junction downhole.
SPE 68729
ERB WEST FIELD : THE WORLD'S FIRST OFFSHORE LEVEL 6 MULTILATERAL WELLABU
was set in the 7 leg#2 1.5ft below the junction area. This
close placement was achieved by running a No-Go hanger
below the packer in the 3-1/2 liner string. The No-Go hanger
landed on a profile manufactured in the leg#2 of the junction.
The drilling diverter for leg#2 was then retrieved and the well
switched to completion fluid. A dual completion was run
utilizing 3-1/2 tubing. A Dual Completion Module (DCM)
tool was run at the bottom of the dual tubing stings. The DCM
allowed a seal stack located at the end of the tubing for leg#2
to be directed into leg#2 and land in the completion packer
located 1.5ft below the junction. A dual completion packer
was run with the dual completion and placed above the DCM
at a depth of 8,385ft. The dual tubing was run to surface with
gas lift mandrels placed at predetermined points in the tubing.
Coiled tubing was to be run for final liner clean out and
perforation. However, as of Aug 15, 2000 coiled tubing was
unable to reach bottom due to friction lock. A solution is
being worked on.
Challenges and Continuous Improvements
Undereaming the 17.1/2 section for the junction deployment
The concern with the underreaming operation was the high
deviation at the junction deployment section. The deviation at
that section was 63 degrees +/- , and it was anticipated that
unbalanced loads may be created by high inclination of the
tool axis during underreaming. It was initially planned to
underream a 150ft long section, which is 50ft longer than the
recommended minimum distance, in order to gain a longer
landing distance in case the junction landed high. However,
due to the tough well/formation conditions a total underreamed section of only 100ft was achieved.
Forming the junction using the swaging process
The swaging process was executed with no problems. It was
observed that the volumes pumped correlated closely with the
stroke dimension of the swaging piston to within 5-10 gallons.
In the swaging operation, the pump rates were monitored by
observing the water level movement in the tank versus time.
This method proved accurate in determining the amount of
displaced fluid.
Achieving drift runs through the junction
After the junction was deployed, swaged, and cemented in
place an initial clean up run was made with a 6 bit slick
assembly. The drilling BHA was run to junction depth and
rotated during junction pass through to facilitate entry into
lateral leg #1. The 6 hole section was drilled using various
directional drilling assemblies consisting of 1.3deg AKOs
(adjustable kick off sub) and 5-7/8 OD stabilizers. Both
roller and PDC bits types were used in drilling. Slight rotation
of some drilling assemblies was needed to impart smooth
entry from the junction into lateral #1. Therefore, to ensure
unrestricted entry of the completion equipment, drift runs
were made with the largest OD and length completion
SPE 68729
ERB WEST FIELD : THE WORLD'S FIRST OFFSHORE LEVEL 6 MULTILATERAL WELLABU
SPE 68729
ERB WEST FIELD : THE WORLD'S FIRST OFFSHORE LEVEL 6 MULTILATERAL WELLABU
ft
0
EBW117s1TARGET4-P
1000
2000
3000
4000
5000
6000
7000
8000
9000
ft
10000
ft
ft
-5500
-6000
-5500
-6000
-6500
-6500
L12.0
L14.0
M1.0
M2.0
M3.0
GOC-6803
M4.0
M4.5
-7000
EW117L1
OWC-6930
N2.0
-7000
N3.0
N4.0
N5.0
N6.0
N7.0
-7500
N7.5
-7500
N8.0
-8000