Anda di halaman 1dari 117

Nadia Slattery

APC Revision Document

November 2008

Nadia Slattery
APC Revision Document

Contents

Definitions

M001 Accounting Principles & Procedures (Level 1)

M002 Business Planning (Level 1)

M006 Conflict Avoidance, Management & Dispute Resolution (Level 1)

M007 Data Management (Level 1)

14

M009 Sustainability (Level 1)

16

M010 Team Working (Level 1)

21

M003 Client Care (Level 2)

22

M004 Communication & Negotiation (Level 2)

25

M008 Health & Safety (Level 2)

26

M005 Conduct Rules, Ethics & Professional Practice (Level 3)

33

T013 Construction Technology & Environmental Services (Level 3)

46

T017 Contract Practice (Level 3)

49

T022 Design Economics & Cost Planning (Level 3)

79

T062 Procurement & Tendering (Level 3)

90

T067 Project Financial Control & Reporting (Level 3)

108

T074 Quantification & Costing of Construction Works (Level 3)

109

T010 Commercial Management of Construction (Level 3)

113

T016 Contract Administration (Level 3)

114

Topical / Current Issues

115

November 2008

Nadia Slattery
APC Revision Document

Definitions
Adjustment of Completion
Date
All Risks Insurance

Annual Turnover
Assignment
Balance Sheet
BCIS

Benchmarking
Bond
BREEAM
Brown Roof

Building Cost Index

Building Regulations

Capital Allowances

Cash Flow Forecast

Category A Fit-Out
Category B Fit-Out
CDM Regulations

Clerk of Works
Collateral Warranty

Conflict of Interest
Contract at Large
Contingency

November 2008

Extension or reduction to Date for Completion stated in the


contract due to one of the Relevant Events. Provides relief to
contractor for breach of contract and liability of LAD's
Insurance for physical loss or damage to work executed, site
materials and reasonable cost of removal and disposal of debris
which results from such loss (with exceptions).
Income or revenue that a company receives from its normal
business activities, usually from the sale of goods and services.
The transfer of rights under a contract to another party i.e.
Developer to Tenant.
A snapshot of a company's financial condition used to
determine its net worth (assets - debts).
Subsidiary of RICS, providing cost data for construction cost,
operation and maintenance and rebuilding. Based on tender
analyses submitted by members.
The use of historical data from projects of a similar nature as a
comparison or cost check of the cost of project.
Arrangement whereby obligations of one party are financially
guaranteed by a third party.
Method of assessing environmental performance of a building.
Planted with sedum, soil and stones to replace habitat lost
during construction bringing with it wildlife friendly space and
benefits to biodiversity.
Measures movement of basic labour and materials costs to the
Builder. Used to forecast inflation during the construction
phase.
Legislation ensuring compliance of reasonable, adequate,
appropriate functional requirements regarding the built
environment.
Tax relief on capital expenditure for acquiring, constructing,
refurbishing or fitting out a property. Plant and machinery, land
remediation.
Graphical representation of anticipated expenditure during
project. Used to assist client in assessing timing and amount of
future payments.
Fit out of functional areas. Including raised floors, suspended
ceilings, M&E installation beyond risers.
Further specific fitting out for end user. Including internal
partitions, underfloor power, IT and data.
A code of practice which places statutory duties on clients,
CDM co-ordinator, designers and contractors to plan, manage
and co-ordinate health and safety throughout project.
Appointed by the Employer to act solely as inspector on his
behalf under the directions of the CA.
Side agreement which establishes a contractual link that would
otherwise not exist due to privity of contract. A separate
contract.
Where members interests conflict with a clients or where two or
more clients interests conflict
The fixed completion date ceases to apply due to interference,
prevention or continuation after breach of contract.
A sum of money used to fund unknowns, risks etc. May be
construction, design reserve, risk or client contingency.
Construction contingency may be included as an undefined
provisional sum or held below the line.

Nadia Slattery
APC Revision Document

CPI

Co-ordinated project information.

Dayworks

If works cannot be properly valued by measurement then


dayworks are used as a fair and reasonable measure of works.
Defects, shrinkages or other faults in the works due to materials
or workmanship not in accordance with the contract.
Methods of dealing with conflict between parties.

Defects
Dispute Resolution
Disruption

Energy Performance Cert

Regular progress of the works is materially affected by a


Relevant Matter. Contractor is entitled to L&E which he would
not be reimbursed by payment under any other provision in the
contract
Also known as reverse bidding. Tenderers in auction situation
in knowledge of lowest/required sum.
Employer may, with consent of Contractor, use or occupy site
(or part thereof) before PC. Insurers must confirm policy not
prejudiced. Contractor cannot unreasonably delay or withhold
consent.
Employers representative who may perform the functions of the
employer.
Brief which outlines what the employer requires in the form of
an outline specification and drawings.
Gives an energy efficiency rating to a building.

Enhanced Capital
Allowances
E-Tendering

Enhanced rate of tax relief for energy saving and green plant
and machinery.
Electronic, paper-free form of tendering process.

Ethics

Standards of what is right and wrong in terms of obligations,


fairness and benefits to society
Insurance clauses. Contractor not required to indemnify
Employer under All Risks insurance for injury, death or damage
resulting from Excepted Risks.

Dutch Auction
Early Use by Employer

Employers Agent
Employers Requirements

Excepted Risks

Expert Witness
Extension of Time
Facilities Management
Force Majeure

Green Roof
Heads of Claims
Health & Safety File

Indemnity
Insurance
Joint Names Policy

November 2008

Excepted Risks include radiations, contamination by


radioactivity etc.
A professional that can be called into a dispute by a party to
give expert evidence of their opinion to support a dispute.
Adjustment to Completion Date due to delay caused by a
Relevant Event.
Management of the operation and maintenance of a property.
A Relevant Event. Acts of God or man-made events beyond
the control of the parties i.e. war, strike, riot, crime, flood,
earthquake.
Note: Exceptionally adverse weather, civil commotion and strike
are all covered as separate Excepted Risks therefore coverage
of force majeure actually very limited.
As brown roof but planted.
Prolongation, disruption, loss of profit, head office overheads,
finance charges.
Record of information for client or end users which focuses on
H&S. Alerts readers to key health and safety risks that need to
be dealt with during maintenance, repair and construction work.
Compiled by CDM Co-ord (or Contractor under D&B).
Guarantee, compensation.
Method of providing indemnity. Equitable transfer of risk in
exchange for a premium.
Insurance policy in names of both parties. Removes
opportunity for subrogation.

Nadia Slattery
APC Revision Document

KPI

Used to benchmark projects against set of standards.

Latent Defect

Any defect which becomes apparent after the end of the


Rectification Period / issue of Making Good Defects.
Letter outlining intention to enter into contract.

Letter of Intent
Life Cycle Costing

Liquidated Damages
Loss and Expense

New Civil Procedure Rules

Novation
Parent Company
Guarantee
Partial Possession

Performance Bond
PFI

PPP
Practical Completion
Prime Cost
Prolongation

Provisional Sum

Profit & Loss Statement

Preambles
Preliminaries

November 2008

Consideration of costs over the whole life of a building not just


the capital costs i.e. understanding both capital and running
costs. The 3 Rs: running, repairs, replacement.
Genuine, pre-estimate of loss to be suffered in the event of noncompletion.
Any loss suffered or expense incurred by the contractor due to
a Relevant Matter for which he would not be reimbursed by
payment under any other provision in the contract.
Reforms to civil justice system proposed by Lord Woolfe.
Improved the speed of litigation, reduced the cost and improved
chances of early settlement.
The transfer of rights and obligations under a contract from one
party to another, under a separate contract.
Alternative to a Performance Bond. Parent Company
guarantees fulfil obligations at own cost in the event of nonperformance or insolvency.
Employer may take possession of part of site in advance of PC.
By mutual consent, not previously agreed. PC deemed to have
occurred on the Relevant Part.
Guarantee of performance. Guarantor pays for loss up to value
of bond.
Form of procurement. A long term service contract between a
public sector body and private sector operator. Privately
financed projects are repaid by government over a period of
time. Much like a mortgage.
Form of procurement where relationships formed between
private sector and public bodies.
When, in the opinion of the CA, practical completion of the
works is achieved.
Sum of money to be expended on works by nominated
subcontractors or goods by nominated suppliers.
Extended site presence due to a Relevant Matter for which the
Contractor would not be reimbursed by payment under any
other provision in the contract.
Sum for work that the Employer may or may not decide to have
carried out or which cannot be accurately measured at tender
stage.
Defined Where item can be described and approximately
quantified to extent that Contractor can make allowances within
their prelims and programme.
Undefined Where scope of work is unknown and cannot be
adequately described therefore Contractor not able to make
allowances within their prelims or programme.
A financial statement that indicates how revenue is transformed
into net income. Indicates whether the company has made or
lost money in the period.
Preliminary introduction explaining the purpose and any implied
points i.e. indicative list, not exhaustive.
Measured under SMM7. General and particular items relating
to the project generally (site set up, location), the contract
(bonds, insurance), employers requirements (security, safety,
quality standards), contractors general cost items
(management, accommodation etc)

Nadia Slattery
APC Revision Document

PII

Quantum Meruit

Relevant Event
Relevant Matter

Retention
RIBA Plan of Work
RICS Rules of Conduct
RICS Member Support
Levy
Risk
Risk Management
Run Off Cover
Schedule 2 Quotation

Site Materials

Step-In Rights
Subrogation

SMM7
Specifications
Specified Perils

Star Rate
Sustainability

SWMP
Tender Price Index

November 2008

Insurance to indemnify client in event of financial loss due to


professional negligence. Protect firm from loss it cannot meet
due to a claim for professional negligence.
As much as he has earned. A claim for a reasonable sum as
payment for services rendered. Used where there is no
contractual basis for assessing amounts due.
Occurrences which entitle Contractor to extension of time
should they affect regular progress of the works.
Occurrences which entitle Contractor for Loss and Expense for
which he would be not be reimbursed by payment under any
other provision in the contract.
Monies retained to fund rectification of any defective works
which the Contractor fails to make good.
Breakdown of the processes for a project from inception to
completion. Clearly describes key activities and deliverables.
Set of professional parameters and expectations for members
behaviour.
A support fund to protect members who find themselves being
sued personally and have no access to PII protection.
Introduced following Merrret v Babb
An uncertain event which, if it were to occur, would have an
effect on the project.
Identification, assessment and ongoing management of risks.
Continuation of PII cover for a further 6/12 yrs following ceasing
practice. RICS recommends 15 yrs.
Quotation to be provided upon request by CA. To include
adjustment to contract sum, completion date, any L&E,
reasonable cost of preparing quote and, if requested, additional
resources and method statement.
All unfixed materials and goods delivered to and placed on or
adjacent to the works which are intended for incorporation
therein.
Allow party to step-in and perform contract if original party is
unable or unwilling to do so i.e. collateral warranties.
The right to sue in the name of the assured any person who
could have been sued by the assured in respect of the loss i.e.
for loss caused as a result of negligence, breach etc.
A recognised system of measurement utilising the CAWS.
Defines precise nature and extent of works.
Produced by design team to detail scope, materials and
workmanship required.
Insurance Option C = Joint Names Policy required for existing
buildings and contents against loss or damage due to SPs.
SPs are fire, lightning, explosion, storm, flood etc.
Loss or damage caused by SPs?:
- Contractor entitled to EoT (but not L&E)
- Either party can terminate
If terminated due to SP caused by Employer negligence then
contractor is entitled to L&E.
Where a rate cannot be valued simply from contract rates, a
star rate is derived using contract rates as a basis.
Constructing with consideration for the environment and not at
the detriment of future generations. Considering the long term
social and economic implications of a development.
Records amount and type of waste produced on site and how it
will be reused, recycled or disposed of.
Analysis of accepted tenders to predict future movement in the
market. Used to forecast inflation up to construction phase.

Nadia Slattery
APC Revision Document

Terrorism Cover

Value Engineering
Value Management

Variations

Variations in D&B

Warranty
WRAP

November 2008

Insurance provided by a Joint Names Policy to cover physical


loss or damage to works, site materials or existing structures
caused by terrorism.
REACTIVE. Providing required function, at required quality for
lowest cost. Making most efficient use of resources.
PROACTIVE. Understanding what value means to the client,
communicating that to the team and maximising the delivery of
those benefits whilst minimising use of resources.
Alteration or modification of the design, quality or quantity of the
works and the imposition of obligations of restrictions regarding
access to site, limits on working space, working hours or order
of completing the works.
Called changes. Any change in the ERs which makes
necessary the alteration or modification of the design, quality or
quantity of the works etc as above.
Written guarantee of quality of a project
Advises how to reduce waste and increase recycling, making
better use of resources and helping tackle climate change.

Nadia Slattery
APC Revision Document

M001 Accounting Principles & Procedures (Level 1)


Annual Turnover
-

Income or revenue that a company receives from its normal business activities

Usually from the sale of goods and services to customers

Balance Sheets
-

Assets debt = net worth (value)

A snapshot of a companys financial condition

Use to value a company

Use to evaluate creditworthiness

Use to evaluate the money a company has available in the short term

Profit and Loss Account


-

A financial statement that indicates how revenue is transformed into net income

Shows whether the company has made or lost money during the period

Ratio Analysis
-

Evaluates relative strength or weaknesses of potential investment

Return on equity indicates firms profitability and potential growth

Taxation
-

CIS Scheme introduced from October 2007

Verification service to address issue of counterfeiting of old style registration

Sets out the rules for how payments to subcontractors for construction work must be
handled

CIS can apply to all types of businesses that work in the construction industry in the
UK, including:
o

Self-employed individuals working as sole traders

Partnerships

Companies

Limited liability partnerships (LLPs)

Also:
-

Revenue and Capital Expenditure

Credit Control

Profitability

November 2008

Nadia Slattery
APC Revision Document

M002 Business Planning (Level 1)


-

Principles of Law Parliament, legislation, tort, common law etc

Short/Long Term Strategies

Market Analysis

Five Year Plans

Business Support Services administration, secretarial, HR, IT etc

Staffing Levels recruitment/turnover

Employment Law

Employment Policy

How does your business ensure it is making a profit?


o

Timesheets

Resource forward planners

Financial management software

Fee/cost reconciliation

November 2008

Nadia Slattery
APC Revision Document

M006 Conflict Avoidance, Management & Dispute Resolution (Level 1)


How Standard Forms Of Contract Deal with Conflict Avoidance and Dispute Resolution
JCT
-

Incorporates adjudication

2005 dropped arbitration in favour of litigation


o

Not actually cheaper in practice as parties have to pay for arbitrator and
venue (court and judges are free in litigation)

Litigation has improved, judges at the construction courts are often


construction specialists

Civil Procedure Rules have improved the speed of litigation, reduced the cost
and improved chances of early settlement

Greater use of adjudication has reduced number of cases going to court so


now quicker to reach court (not wait months to book a slot)

Arbitration can still be selected if desired

NEC / ECC
-

Incorporates adjudication

Early warning provisions

Dispute resolution built into principle of contract

Conflict Avoidance
How to avoid a dispute:
-

Clearly state in all tender / contract documents exactly what is required of all parties

Ensure continuous effective communication between all parties

Put everything in writing to ensure there is always documented evidence should a


dispute arise

Negotiation
General:
-

Discussion that ends in agreement by both parties

Suitable for simple matters, easily resolvable, compromises made

Such as of conditions of contract etc.

Requires the co-operation of both parties

Quick and inexpensive

The threat of more formal proceedings should act as encouragement for an


agreement to be reached

November 2008

Nadia Slattery
APC Revision Document

Process:
-

Agreement between parties to negotiate

Set objectives

Compile supporting evidence

Establish what your non-negotiables are

Identify areas of compromise

Determine what the opposing parties targets are

Give opposing party an opportunity to retract their position

Demonstrate and emphasis that your target is reasonable

Facilitated Negotiation:
-

Neutral facilitator

Requires co-operation of both parties

Cost of facilitator can be high

Mediation
General:
-

Consensual process

Most popular form of ADR

Informal and reasonably inexpensive fees split 50/50

Private

Non-binding decision unless agreed otherwise by parties and no legal backing to


decisions

Neutral party assists in settlement of dispute

Process:
-

Settlement negotiations in the presence of a neutral Mediator who will facilitate but
not make a judgment

Mediator will make recommendations but resolution and the terms of such lies with
the parties

Conciliation
General:
-

Similar to mediation

Conciliator is empowered to express his views and opinions but not make judgment

Conciliator is independent and impartial

May chair an open discussion but this is not common

Process:
-

Conciliator talks to each party in private

November 2008

Nadia Slattery
APC Revision Document

Will make recommendations but resolution lies with the parties

Adjudication Part II Housing Grants, Construction and Regeneration Act


General:
-

UK Statutory dispute resolution procedure

HGCR Act 1996 introduced it into every construction contract

Employer may delete adjudication clause but rights under Act will reinstate

Adjudicator or nominating body (i.e. RICS) can be named in contract

Decision is binding until referred to legal proceedings (arbitration / litigation)

Decision cannot be appealed until PC

Adjudicator must

Act impartially

Decide the matters in the dispute

Provide reasons if requested

Adjudicators fee is split equally unless adjudicator says otherwise

Process:
-

Referring party serves a Notice of Adjudication to other party

Adjudicator must be appointed within 7 days of the Notice

Referring party must serve their referral document within 7 days of the Notice

Responding party have 7 days to respond to referral

Adjudicator makes a decision within 28 days

Can be extended a further 14 days if both parties agree

Decision is binding until PC

If losing party fail to comply, courts will enforce the decision (even is a mistake)

Arbitration Arbitration Act 1996


General:
-

Arbitration Act 1996 introduced to revive and improve the process

Act reformed and clarified the process

It must be a joint decision to arbitrate

Parties must go to adjudication first

Arbitrator appointed by nominated body i.e. RICS, RIBA

Costs awarded at Arbitrators discretion

Private

Cheaper and faster than litigation

Decision is binding

Can appeal on point of law only

Favoured over litigation due to privacy, flexibility etc

November 2008

10

Nadia Slattery
APC Revision Document

Process:
-

Parties prepare a case

Preliminary hearing in court in the presence of an Arbitrator

Followed by agreed timetable of document submissions etc by the claimant, to which


the defendant can respond

Concludes with a formal hearing

Power of Arbitrator:
-

Rectify contract so it accurately reflects the agreement of the parties

Award any sum which ought to have been included in any certificate

Open up, review and revise any certificate, notice, decision, requirement

Determine matters in dispute as if no certificates or notices had been given

100 Day Arbitration:


-

Introduced by Society of Construction Arbitrators

An attempt to resuscitate the construction arbitration procedure by introducing fasttrack procedure

Applicable for all types of dispute

Cheaper than traditional arbitration or litigation

Places a duty on the Arbitrator to make his award within 100 days from service of the
defence

Litigation
General:
-

Very formal and adversarial process

Long and expensive procedure

Legally binding can appeal

Very public

Parties often end up agreeing a settlement before reaching the courts

Will inevitably damage relationships

Process:
-

Parties prepare a case to be heard in court in the presence of a judge

Both parties present case to judge

Decision is based on evidence presented

Expert Witness
-

A professional that can be called into a dispute by a party to give expert evidence of
their opinion to support a dispute

Gives an unbiased and independent opinion

November 2008

11

Nadia Slattery
APC Revision Document

A party can seek an alternative expert witness should one provide them with an
unfavourable report

The expert witness is entitled to a fee (unlike a witness of fact)

Part 35 of the Civil Procedure Rules (CPR) & Civil Evidence Act 1995

Independent Expert Determination


-

Appointment of an individual professional

The expert has the freedom to make decisions and investigate the background rather
than just reply on the evidence presented

The experts decision is final and legally binding no appeal process as parties agree
to be bound by the decision

Informal

More ideal for highly technical disputes

Expert is liable for his decision

Pre-action Protocol for Construction and Engineering Disputes


General:
-

Objectives are to:


o

Encourage exchange of early and full information about prospective claims

Enable parties to avoid litigation by settling a claim before proceedings


commence

Support efficient management of proceedings where litigation cannot be


avoided

General aim to ensure:


o

parties have provided sufficient information to know the nature of each


others case

each party has opportunity to consider, accept or reject the case against
them at earliest possible stage

there is more pre-action contact between parties

better and earlier exchange of information

better pre-action investigation by parties

parties have met formally at least once with a view to define and agree issues
and explore possible ways to resolve the claim

that parties are in a better position to try to settle cases early without litigation

proceeding will be conducted efficiently if litigation does occur

November 2008

12

Nadia Slattery
APC Revision Document

Process:
-

Letter of Claim:
o

Prior to commencing proceedings claimant sends a letter to defendant


containing:

Names and addresses of parties

Clear summary of the facts of the claims

Basis on which claim is made

Nature of relief claimed

Where claim previously rejected, why claimant believes wrongly


rejected

Defendants Response:
o

Acknowledge receipt of letter of claim within 14 days

Notify any objections to the courts jurisdiction or the named defendant within
28 days

Which facts are agreed and which disagreed

Which claims are agreed and which disagreed

Which damages are agreed and which disagreed

Summary of facts if contributory negligence is claimed

Any counterclaim

Names of any experts instructed

Claimant must respond to any counterclaim within 28 days

Pre-Action Meeting:
o

Send letter of response within 28 days identifying:

Parties should meet within 28 days of responses

Limitation of Action

November 2008

13

Nadia Slattery
APC Revision Document

M007 Data Management (Level 1)


Building Cost Information Service
-

The BCIS is a subsidiary of RICS, established in 1962

Collates and analysis data submitted by members of the service

Incorporates material from other relevant sources

Information available online and through several publications

Provides information on:


o

Construction costs

Maintenance and operating costs

Used for early cost advice

For life cycle cost plans

Rebuilding costs

Insurers use to quote more accurate premiums for buildings


insurance

BCIS 5 Year Forecast


-

Long term annual forecast of national average tender price inflation

Published forecast in August 2008

1Q06

1Q07

1Q08

1Q09

1Q10

1Q11

1Q12

to

to

to

to

to

to

to

1Q07

1Q08

1Q09

1Q10

1Q11

1Q12

1Q13

Annual % change

Tender Prices

+4.8% +2.9% +4.5% +3.9% +3.4% +4.3% +4.9%

Summary:
o

New work output expected to fall in 2008

To remain static in 2009

Return to trend growth in 2010

Tender price rises are expected to be driven by input cost pressures

As new work output moves ahead of trend in 2011 and 2012, tender prices
are likely to outstrip input cost rises, as contractors try to improve their
margins

Building Cost Index (BCI)


-

The BCI measures movement of basic labour and materials costs to the Builder

The proportion of labour to material is assumed to be 40:60

The labour element is based on the change in the cost of "all in hourly rates" for
building operatives paid in accordance with the Construction Industry Joint Council

November 2008

14

Nadia Slattery
APC Revision Document

The materials element is based on BERR (formerly DTI) material price indices

Refers to contractors costs i.e. labour, plant and materials rates

Used to forecast inflation during the construction phase

Tender Price Index (TPI)


-

TPI reflects changes in the level of pricing contained in the lowest accepted tenders
for new work

The TPI measures movement of market conditions


o

Labour

Market

Economic climate

Inflation

Data from prices tendered for construction projects

Inclusive of labour, plant, materials, preliminaries and OH&P

Used to forecast inflation up to construction phase

Pricing Books
-

Spons (by DL)

Wessex (by BCIS)

Laxtons

Other Information:
-

Data Base Use Generally

Employers In-House Data Storage and Filing Systems

Scheduling

Libraries

Data Protection Act

November 2008

15

Nadia Slattery
APC Revision Document

M009 Sustainability (Level 1)


Sustainable Development / Construction
Definitions:
-

Meeting the needs of the present without compromising the ability of future
generations to meet their own needs

Constructing with considerations of the environment and not at the detriment of future
generations

Three principles of sustainability are:


o

Social

Developments should respond to needs of wider community

Provide public transport links

Amenities schools, welfare, education etc

Environmental

Prevent harmful and irreversible impacts on the environment

Careful use of natural resources

Minimise waste and energy

Economic

Efficient use of resources

Value for money

Why Its Important to Construction:


-

Critical global issue facing our generation

Construction makes up 10-15% of worlds GDP

40% of global waste comes from construction

Environmental Concerns:
-

Climate change

Carbon emissions

Water management

Waste management

Depletion of fossil fuels

Renewable energy sources

Sustainability Techniques:
-

Recycled materials

Locally sourced materials (reduce waste and energy)

Sustainable energy (solar, wind, geothermal)

Passive energy design (building orientation, solar shading, daylighting)

November 2008

16

Nadia Slattery
APC Revision Document

Natural ventilation

Produce less waste and recycle (landfill tax increase is encouraging this)

Reduce consumption of energy during construction and end users

Reduce carbon emissions during construction & end users

Low or zero carbon technologies

Regulations and Codes of Practice for Sustainability


-

Building Regulations (Part L conservation of fuel and power)

Code for Sustainable Homes

Energy certification of buildings

Site waste management plans

BREEAM assessment

Specific Legislation:
-

Landfill Tax
o

Discourages disposal of waste in landfill sites

Encourages recycling

Aggregate tax sustainability fund


o

Commercial exploitation of aggregates

Encourages use of recyclable materials

Part L of the Building Regs (conservation of fuel and power)

Energy Performance Certificates:


-

All sales and lettings to have EPC

Assesses how energy efficient a building is

Assesses estimated energy use, CO2 emissions and fuel costs

Provides a summary of energy performance related features e.g. wall and loft
insulation

Rated from A to G (much like white goods)

Gives recommendations to improve the performance

Other Incentives:
-

Capital allowances for the remediation of contaminated land

Enhanced capital allowances


o

tax relief on first year spending on qualified energy saving plant, machinery
and water conservation plant and machinery

Grants for renewable energy sources

November 2008

17

Nadia Slattery
APC Revision Document

Building Regulations
How can you meet Part L?
-

Wind turbines

Photovoltaic cells

Combined heat & power (CHP) captures the byproduct heat for heating purposes
close to the plant rather than emitting into the environment

Ground source heat pumps

Geo-thermal energy

Rainwater harvesting

Solar thermal water heating

Biomass boilers

BREEAM
General:
-

Building Research Establishment Environmental Assessment Method

Assesses environmental performance of building

Most widely used method for buildings

Can be undertaken on all types of building and new, refurbishment or existing

Gives a rating of pass, good, very good, excellent or outstanding

Areas of Assessment:
-

Management (considerate contractors, monitoring waste etc)

Health and wellbeing (natural daylighting, ventilation etc)

Energy (CO2 emissions, energy use etc)

Transport (access to public transport, cycle racks and showers etc)

Water (water saving, meters, leak detection etc)

Materials (re-use existing materials, sustainable sources, recycling etc)

Land Use and Ecology (remediation, managing existing ecosystem etc)

Pollution (use of refrigerants, insulation spec etc)

Benefits:
-

Demonstrates level of achievement

Lowers environmental impact

Improves internal environment which increases productivity

Reduces operating costs

Improves marketability

New Developments:
-

Two stage assessment process (design stage and management stage)

Mandatory credits introduced

November 2008

18

Nadia Slattery
APC Revision Document

New Outstanding rating level introduced

Contaminated Land
-

New contaminated land provisions introduced to encourage recycling of brownfield


sites

Capital allowances for remediation of contaminated land

Landfill Tax
-

Discourages disposal of waste in landfill sites and encourages recycling

Finance Act 1996

Licensed landfill sites

Tax levied on owners of landfill sites

Revenue raised is put back into waste minimisation initiatives

Aggregate Tax
-

Tax on every tonne of primary material extracted

Introduced to discourage use of primary material and encourage recycled or


secondary aggregate

Site Waste Management Plan


-

Under Clean Neighbourhoods and Environment Act 2005

Compulsory from 6 April 2008, for projects over 330k

Different rules for projects over 500k

To raise awareness of how much waste is being produced

Contractors can then take steps to minimise

Works shouldnt commence unless SWMP in place

Live and updated throughout project

Early consideration made for waste reduction reusing and recycling site-gained
materials

SWMP includes:
-

Type/ description of waste removed

Who removed

Environmental permit or exemption held by site where material taken

Contractor Responsibility
-

Update at least every 6 months

Obtain info from subcontractors

Keep on site during project

Allow access to it during project

November 2008

19

Nadia Slattery
APC Revision Document

Keep a copy for two years

Level of detail depends on estimated contract value

WRAP
General:
-

Waste and Resources Action Programme

To help identify how to increase recycled content through product substitution

Identifies recycled content found in market for each product type


o

E.g. roof insulation Isowool Frame Batt HP 70%

Promotes market for materials with increased recycled content

Identifies 3 levels of recycled content standard, good, best

Aims to minimise and avoid waster and landfill use

Makes better use of resources

Benefits:
-

Contributes to sustainable goals of clients

Satisfies planning and development authorities

Financial savings if recycling materials locally

Diversion of waste from landfill

Less demand on finite natural resources

Possible to use equivalent products with higher recycled content with no negative
effect on cost, performance or availability

JCT Consultation Paper on Sustainability (January 2008)


-

Should construction contracts should include clauses which put requirements on


contracting parties with regard to sustainability?

Specification of products

Construction process

Supply chain

Examples of Sustainability on My Projects


-

BREEAM on 7 Dials

Rooflights on Stannary Street to introduce natural daylight

Green roof on Stannary Street roof top biodiversity through extensive planting

Looking at prefabrication on phase 2 minimise site waste

November 2008

20

Nadia Slattery
APC Revision Document

M010 Team Working (Level 1)


-

Understand the Role of Team Members client, design team, consultants,


contractors

Appointing the Project Team

Relationships with Other Team Members

Communicating with Other Team Members

Partnering and Collaborative Working

Strategic Alliancing

Supply Chain Management

European Legislation for Selecting Project Teams OJEU etc

Construction the Team Latham Report

November 2008

21

Nadia Slattery
APC Revision Document

M003 Client Care (Level 2)


Principles of Client Care
-

Identifying clients
o

Consider existing and new clients

Client care for existing clients is vital

Requires active management

How to identify new clients

How to attract new clients

Types of client
o

Different industry sectors have varying structures

This affects the nature of the client, their general objectives and interests

Behaviours
o

RICS guidance on ethics and conduct rules

Delivering good client care includes behaviours such as:


Clarity of remit

Clear communication

Setting realistic expectations

Ensuring timely delivery

Ensuring quality of outputs

Managing the process of client care:


o

On projects:

Clear communication

Ongoing dialogue

Clear and defined deliverables

Timely delivery

Quality of outputs

Generally:

Structured account management

Maintaining regular contact away from current projects

Understanding how can assist clients business objectives

Feedback
o

Formal and informal

Client satisfaction surveys

Use of KPIs

November 2008

22

Nadia Slattery
APC Revision Document

Collecting and responding to feedback

Project reviews

Complaints
o

Complaints handling procedure (RICS requirements)

Appointed complaints handling officer

Collect data to analyse and define the needs of clients


o

Briefing process:

To ensure a clear scope of work is defined

Job planning:

Internally planning how clients requirements can be met

Example Stannary Street:


-

Established who main contact within the client organisation was (Marc Seale)

Established other stakeholders (i.e. Steve Hall and Charlotte Milner)

Identified importance of Architect to this client

Ensured I established a close working relationship with them

Maintained client care by meeting the clients expectations for deliverables, clear and
ongoing communication and feedback processes

Developed relationship further by understanding the clients business and future plans

As project progressed, obtained client feedback both formally (client feedback forms)
and informally (conversations with client)

QS Tendering
-

Terms and conditions

Outline scope of services

Services exclusions
o

Detailed examination of financial claim

Steps towards resolving disputes

Fee breakdown

Potential drawdown or expenditure cash flow

QS Appointment Documents
-

Deed of appointment (terms and conditions)

Outline scope of services


o

Develop budget

Lead procurement process

Lead tender process (inc prepare tender and contract documentation)

Review tender returns

November 2008

23

Nadia Slattery
APC Revision Document

Lead post tender interviews

Carry out and prepare cost reporting, valuations and FA

Ensure delivery of best overall value for money

Control costs in accordance with approved budget, cost plan, cash flow
projections

Advise client on matters affecting cost, delays and advise measures to


reduce and avoid

Communicate and report to the architect on clients requirements

Report to project manager

Service exclusions (detailed examination of financial claim, steps towards resolving


disputes)

Fee breakdown

Potential drawdown or expenditure cash flow

Establishing Fees
-

Calculate on scope of services and resources required

Key Performance Indicators (KPIs)


General:
-

Benchmarking a project / company against a range of performance criteria across the


industry

Measure of performance that is critical to success

DTIs Constructing Excellence KPIs:


-

Time

Cost

Quality

Client satisfaction

Health and safety

DLs use of KPIs:


-

Client feedback forms which make use of industry standard KPIs

Enables us to measure our performance against DTIs published KPI data for
consultants

November 2008

24

Nadia Slattery
APC Revision Document

M004 Communication & Negotiation (Level 2)


Oral Communication:
-

Phone calls

Reporting at meetings

Facilitating/chairing meetings

Client and bid presentations

Staff presentations

Contractor interviews

Public speaking at seminars etc

Listening skills

Written/Graphical Communication:
-

Letters, memos and emails

Report writing

Compiling tender and contract documents

Programming

Using drawn information checking scales and revisions

Using CAD documents

Negotiation:
-

Establishing negotiating position

Setting objectives

Compiling supporting evidence

Establishing non-negotiable areas

Identifying areas of compromise

Assessing other sides position

November 2008

25

Nadia Slattery
APC Revision Document

M008 Health & Safety (Level 2)


Health and Safety at Work Act 1974
-

Primary piece of legislation covering occupational health and safety in UK

Sets out general duties employers have towards employees and members of the
public

Sets out general duties employees have to themselves and each other

Law requires good management and common sense

Penalties under the Act include:


o

Enforcement notices

Fines

Prison

Corporate manslaughter

Director disqualification

The Management of Health and Safety at Work Regulations 1999


-

Generally make more explicit what employers are required to do to manage health
and safety under the Act

Main requirement on employers is to carry out risk assessments (and implement


measures identified within it)

Construction (Health, Safety and Welfare) Regulations 1996


-

Set of modern and simplified construction regulations

Explain detailed ways of working in construction activities

Aimed at protecting health, safety and welfare of everyone who carries out
construction work

Also give protection to other people who may be affected by the work

Construction (Design and Management) Regulations 2007 CDM


-

Places statutory duties on clients, CDM Co-ordinator, designers and contractors to


plan, manage and co-ordinate health and safety throughout project

A code of practice

Advises on complying with HSE law

Improves safety on site through design, planning and management

New regulations require clients to be more involved in construction process

Does not apply to domestic clients

Notifiable Projects:
-

More than 30 days or 500 person days

November 2008

26

Nadia Slattery
APC Revision Document

The 3 Cs
-

Co-ordination

Competence

Co-operation

Roles, Responsibilities & Obligations


All
-

Ensure client is aware of his duties

Provide information for the H&S file

Co-operate and co-ordinate with others on project and neighbouring/adjacent projects

Ensure works dont commence until a suitable and adequate H&S plan is in place

Client
-

Appoint a competent CDM (in writing) before design starts and principal contractor,
consultants and contractors

Ensures the CDM Co-ordinator carries out all his duties

Responsible for pre-contract H&S

Provide pre-construction information for designers and contractors

Ensure mobilisation periods are adequate in relation to the size and complexity of the
project

Retain and provide access to the H&S file

Before construction phase begins ensure adequate welfare facilities and construction
phase plan are provided

Allow sufficient time and resources to enable work to be carried out without H&S risk

Designers (now including QS)


-

Ensure work on projects doesnt commence until CDM Co-ordinator been appointed

Report obvious risks

Ensure adequate resources and competence with regard to H&S

Apply principles of eliminating hazards and reducing risks

Consideration of the Workplace Regulations incorporated into design

CDM Co-ordinator
-

Advises and ensures client meets and fulfils his obligations of H&S matters

Assist client with providing information

Manage and co-ordinate the flow of H&S information

Check suitability of information provided by designers for contractors

Prepare H&S file (contractor in D&B)

Give client advice on construction H&S risk matters

November 2008

27

Nadia Slattery
APC Revision Document

Principal Contractor
-

Construction phase plan is prepared and received by employer before construction


work commences

Welfare facilities are provided for duration of construction phase

Provides info to CDM Co-ordinator for preparation of H&S file

Plan and manage the construction phase to minimise risk

Provide relevant information and training

Develop and comply with the H&S plan

Responsible for post contract H&S

Prepare H&S file (D&B only)

Consult the workforce on matters affecting their health, safety and welfare

Ensure they and any s/c is competent and adequately resourced

Monitor safety

Site induction site risks, how to report problems, respond to emergencies

Differences between CDM 1994 and 2007


-

Further simplification and clarity of existing regulations

Terminology changes

Reducing paper work

QS now a designer

Focuses on managing risks on site

Encouraging team work

Getting the right people for the right job at the right time

Less than 30 days, 500 man days and domestic projects not notifiable

Suitable provision for welfare is made

F10 Notice
-

Notifies HSE of site, duration, location, numbers on site, when, local authority

Client is only signatory

Pre-Construction Information Pack


-

Part of tender documentation

Was pre-tender health and safety plan

Includes:
o

Description of works

Client considerations and management requirements

Environmental restrictions

Design and construction hazards

Format and presentation of the H&S file

November 2008

28

Nadia Slattery
APC Revision Document

Contractor Mobilisation Responsibilities (Start on Site)


-

Prepare and develop a written plan and site rules

Make sure suitable welfare facilities are provided and maintained throughout

Check competence of who they appoint

Secure site

Liaise with CDM Co-ordinator

Health and Safety File


-

Document recording key H&S matters to advise owners and users how to manage
structure safely

Prepared by CDM Co-ordinator

Brief scope of works

Remains with building at completion for use by tenant/ landlord

Key risk and residual hazards and how dealt with e.g. surveys for asbestos,
contaminated land, soil investigations, existing services routes, etc.

Structural information e.g. safe working loads of floors and roofs, pre or post
tensioning

Hazardous materials e.g. lead paint, pesticides, asbestos

Information regarding removing or dismantling plant or equipment

Information necessary regarding use, maintenance, adoption of the building

O&M information

Construction Phase Health and Safety Plan


-

Developed during construction phase by contractor

Reviewed and signed off by CDM Co-ordinator and client at completion of


construction phase

Risk Assessment
-

To protect people as reasonably practicable from harm

Process:
o

Identify the hazards (anything that may cause harm)

Decide who might be harmed and how

Evaluate the risks and decide on precautions (different material, barriers,


PPE, site inductions)

Record your findings and implement them

Review risk assessment and update if necessary

Construction Skills Certification Scheme (CSCS)


-

Demonstrates vocational and H&S competence

Employees of participating companies required to undertake H&S test

November 2008

29

Nadia Slattery
APC Revision Document

Card valid for 5 yrs as legislation changes

Personal Safety Procedures When Visiting Site


Site precautions:
-

Slips, trips and falls

Working at height

Confined spaces

Joint fire code

Hot works permits

Inadequate supervision

Access and egress

Handling, storage and transportation

Contact with overhead lines

Unintended collapse of part of a building

Accident Prevention on Site:


-

Accident book

Visitors log (fire evacuation)

First aid kit

Fire extinguishers

PPE

Site security

Handrails, ladders

Signs/ posters

Personal Health and Safety at Work RICS Publication Surveying Safely


-

Guide to personal safety at works, published by RICS

Reporting of Injuries, Diseases and Dangerous Occurrence Regulations 1995 (RIDDOR)


-

Fatalities and major injuries Notify HSE immediately

Dangerous occurrences Notify HSE immediately

Off work for 3+ days Report to HSE within 10 days

Considerate Constructors Scheme


General:
-

Aims to improve image of construction

Promote delivering the best in considerate site practice

Targets delivering standards and benefiting the neighbourhood, environment and


workforce

Not regulated but committed, voluntary effort

November 2008

30

Nadia Slattery
APC Revision Document

Code of Considerate Practice


-

Considerate
o

Considers the needs of site personnel, visitors, general public

Environment
o

Awareness of environmental impact

Minimise noise, light and air pollution

Use local resources where possible

Attention to waste management reuse and recycle where possible

Cleanliness
o

Keep site clean and in good order

Surplus material and rubbish not to accumulate on site

Minimise dirt and dust

Good neighbour
o

Provide general information for all affected by work

Communicate with neighbours regarding programming and site activities

Respectful
o

Respectful and safe standards of dress at all times

No tolerance of derogatory behaviour or language

Pride in management and appearance of site

Safe
o

No building activity should be a security risk to others

Construction operations and site vehicle movements carried out with care
and consideration for safety

Responsible
o

Ensure all associated understand and comply with the code

Accountable
o

CCS poster to be displayed where visible to general public

Contact details provided for those affected

Control Of Substances Hazardous To Health (COSHH)


Hazardous Substances:
-

Adhesives

Cleaning agents

Paints

Fumes

Grain dust

Biological agents (bacteria)

Asbestos (own regulations)

Lead (own regulations)

November 2008

31

Nadia Slattery
APC Revision Document

Effects:
-

Skin irritation

Asthma

Cancer

Losing consciousness

Measures:
-

Assess risks

Decide precautions

Prevent or control exposure

Ensure measures are used and maintained

Monitor exposure

Carry out appropriate health surveillance

Prepare plans to deal with accidents, emergencies

Ensure employees properly informed, trained, supervised

Control of Asbestos at Work Regulations


-

Asbestos found in:


o

Cement (roofing)

Insulation board (ceilings and walls)

Coatings (steelwork fireproofing)

Insulation (pipe laggings)

Regulations prohibit the importation supply and use of asbestos

Regulations include the duty to manage asbestos in non-domestic premises

Asbestos must only be removed by licensed contractor

ASB5 notice into HSE, 14 day notice period, must include method statement

Asbestos can be sealed in if it is undamaged and wont be disturbed in future

November 2008

32

Nadia Slattery
APC Revision Document

M005 Conduct Rules, Ethics & Professional Practice (Level 3)


General
-

Founded 15 June 1868

Motto is Est Modus in Rebus there is measure in all things

International HQ in London (Great George Street)

World regional offices in Brussels, Dubai, Hong Kong, New York and Sydney

Members in 146 countries

34,000 students on 400 accredited degree courses

500 industry research and policy papers published every year

50 national associations

160 diverse specialisms represented across 17 faculties

Levels of membership:
o

Fellow

Professional Member

Technical Member

Honorary Member

Student Member

Key Roles of RICS


-

Regulate and promote the profession

Maintain the highest educational and professional standards

Protect clients and consumers through a strict code of ethics

Provide impartial advice, analysis and guidance

RICS structure
-

Governed by a 70-strong International Governing Council, chaired by the President,


including RICS members from all world regions

Who is President of RICS?

Peter Goodacre ex-Principal of CEM

Who is Senior Vice President?

Max Crofts

Who is the Chief Executive Officer?

Louis Armstrong

Who is the Chief Operating Officer?

Sean Tompkins

Who is Chairman of the const/QS faculty?

Michael Sullivan

Faculties
-

3 basic market groupings


Land
Property
Built Environment

November 2008

33

Nadia Slattery
APC Revision Document

Divided into 17 areas of specialisation - the faculties.

Each with its own board and elected chairman.

Can belong to a maximum of 4 faculties, although further subscriptions can be paid to


join more.

The 17 faculties are:


1. Arts and Antiques
2. Building Control
3. Building Surveying
4. Commercial Property
5. Dispute Resolution
6. Environment
7. Facilities Management
8. Geomatics
9. Machinery and Business Assets
10. Management Consultancy
11. Minerals and Waste Management
12. Planning and Development
13. Project Management
14. Residential Property
15. Quantity Surveying and Construction
16. Rural
17. Valuation

What The Faculties Do:


-

Primary role is to develop technical standards, generating professional guidance and


information

Responsible for setting and maintaining APC/ATC competencies

Provide technical advice to all other areas within RICS

Contribute to RICS public policy agenda

All but one are responsible for maintaining alternative designations e.g. chartered
quantity surveyor; chartered facilities management surveyor

RICS Rules of Conduct


-

Set out standards of professional conduct and practice expected of members and
firms

Over and above obligations placed on members by general law, for example in the
areas of discrimination and employment

Reduced to short bullet points within two separate documents for members and
firms.

November 2008

34

Nadia Slattery
APC Revision Document

There are 9 Rules for Members, divided into two sections:

Part One: General


1. Interpretation
Member means a Fellow, Professional Member, Technical Member or Honorary
Member of RICS or a member of the Attached Classes.

2. Service of Documents
Any notice or other document required by or for the purposes of these Rules to be
given or sent to a Member may be given to them personally or sent by post

Part Two: Personal and Professional Standards


3. Integrity
Members shall at all times at with integrity and avoid conflicts of interest and any
actions or situations that are inconsistent with their professional obligations.

4. Competence
Members shall carry out their professional work with due skill, care and diligence
and with proper regard for the technical standards expected of them.

5. Service
Members shall carry out their professional work in a timely manner and with proper
regard for standards of service and customer care expected of them.

6. Lifelong Learning
Members shall undertake and record appropriate lifelong learning and, on request,
provide RICS with evidence that they have done so. Exemptions for pregnancy,
redundancy, ill health and any other exceptional reason.

7. Solvency
Members shall ensure that their personal and professional finances are managed
appropriately.

8. Information to RICS
Members shall submit in a timely manner such information, and in such a form, as
the Regulatory Board may reasonably require.

9. Co-operation
Members shall co-operate fully with RICS staff and persons appointed by the
Regulatory Board.

November 2008

35

Nadia Slattery
APC Revision Document

Firms are required to register for regulation. A regulated form is one that has 50% of more
partners or directors who are RICS members.

What is required for registration?


1. Type of business
2. Statutory regulated activities
3. Nature of clients
4. Complaints handling procedure details and records
5. PII details
6. Whether the firm holds clients' money

The 15 Rules of Conduct for Firms are divided into three sections:

Part One: General


1. Interpretation
Interpretation of the Rules

2. Service of Documents
Any notice or other document required by or for the purposes of these Rules to be
given or sent to a Firm may be given or sent to the Contact Officer personally or
sent by post to the last address of the Firm notified to RICS.

Part Two: Conduct of Business:


3. Integrity
A firm shall at all times at with integrity and avoid conflicts of interest and any
actions or situations that are inconsistent with its professional obligations.

4. Competence
A firm shall carry out its professional work with due skill, care and diligence and
with proper regard for the technical standards expected of it.

5. Service
A firm shall carry out its professional work with expedition and with proper regard
for standards of service and customer care expected of it.

6. Training
A firm shall have in place the necessary procedures to ensure that all its staff are
properly trained and competent to do their work.

November 2008

36

Nadia Slattery
APC Revision Document

7. Complaints handling
A firm shall operate a complaints handling procedure. The complaints handling
procedure must include a redress mechanism that is approved by the Regulatory
Board.

8. Clients' money
A firm shall preserve the security of clients' money entrusted to its care in the
course of its practice or business.

9. Professional indemnity insurance


A firm shall ensure that all previous and current professional work is covered by
adequate and appropriate PII cover which meets standards approved by the
Regulatory Board.

Part Three: Firm Administration


10. Advertising
A firm shall promote its professional services only in a truthful and responsible
manner.

11. Solvency
A firm shall ensure that its finances are managed appropriately.

12. Arrangements to cover the incapacity or death of a sole practitioner


A firm which has a sole principal (i.e. a sole practitioner or a sole director in a
corporate practice) shall have in place appropriate arrangements in the event of
that sole principals death or incapacity or other extended absences.

13. Use of designations


A Firm registered for regulation must display on its business literature, in
accordance with the Regulatory Boards published policy on designations, a
designation to denote that it is regulated by RICS.

14. Information to RICS


A Firm shall submit in a timely manner such information about its activities, and in
such form, as the Regulatory Board may reasonably require.

15. Co-operation
A firm shall co-operate fully with RICS staff and any person appointed by the
Regulatory Board.

November 2008

37

Nadia Slattery
APC Revision Document

RICS Core Values


Core values replaced by a set of standards in helpsheet entitled Maintaining Professional
and Ethical Standards.

These standards replace the nine core values and supersede the guidance notes published
on professional ethics.

There are now 12 standards which members are expected to follow, both professionally and
personally:

1. Act honourably
Never put you own gain above the welfare of your clients or others to whom you have
a professional responsibility. Always consider the wider interests of society in your
judgements.

2. Act with integrity


Be trustworthy in all that you do - never deliberately mislead, whether by withholding
or distorting information.

3. Be open and transparent in your dealings


Share the full facts with your clients, making things as plain and intelligible as
possible.

4. Be accountable for all your actions


Take full responsibility for your actions and dont blame others if things go wrong.

5. Know and act within your limitations


Be aware of the limitations of your competence and dont be tempted to work beyond
these. Never commit to more than you can deliver.

6. Be objective at all times


Give clear and appropriate advice. Never let sentiments or your own interests cloud
your judgement.

7. Always treat others with respect


Never discriminate against others.

8. Set a good example


Remember that both your public and private behaviour could affect your own, RICS'

November 2008

38

Nadia Slattery
APC Revision Document

and other members' reputations.

9. Have the courage to make a stand


Be prepared to act if you suspect malpractice of any sort or a risk to safety.

10. Comply with the relevant laws and regulations


Avoid any action, illegal or litigious, that may bring the profession into disrepute.

11. Avoid conflicts of interest


Declare any potential conflicts of interest, personal or professional, to all relevant
parties.

12. Respect confidentiality


Maintain the confidentiality of your clients affairs. Never divulge information to others
unless it is necessary.

LLL
The RICS does not prescribe a set number of hours for lifelong learning. It simply requires the
learning to be effective, enabling members to do their work more competently. The outcome
of the learning is more important than the number of hours spent on it.

Disciplinary Procedures
First, there is a formal investigation by the Head of Regulation who then decides whether the
RICS will take any further action.

On completion of the investigation, if he considers disciplinary action is required, the Head of


Regulation can initiate one of the following three actions:

1. Serve a Fixed Penalty notice upon the member


2. Make a Consent Order
3. Refer to matter to the Disciplinary Panel

Fixed Penalty Notices:


Administrative fines for minor/minimal breaches of the Rules, such as late return of a firm's
annual return.

Consent Order:
Used for more serious breaches, such as for some minor breaches of the members accounts
regulations which could easily be corrected. A fine may also be levied.

November 2008

39

Nadia Slattery
APC Revision Document

Action by Disciplinary Panel:


Used in the most serious cases. Penalties available to the board are:

1. Issue a caution against repetition of the conduct in question


2. Reprimand or severely reprimand the member
3. Require an undertaking as to future conduct
4. Impose a fine
5. Impose conditions upon future continued RICS registration
6. Expulsion from membership or remove a firm
7. Require costs to be paid
8. Require publication of the results of the hearing in a local newspaper as well as RICS
website

On what grounds can a member be expelled from the RICS?


1. Failure to pay membership fees
2. Failure to renew PII
3. Failure to undertake LLL
4. Misconduct under Rules of Conduct

Professional Indemnity Insurance


Insures against breach of duty and negligence in professional role

Reasons PII is needed:


-

Firm is protected from financial loss it cannot meet as a result of negligence claim

To protect firm against any consequences of its inability

The firms clients do not suffer financial loss which the firm cannot meet

Limit of Indemnity:
Firms Turnover in Preceding Year

Minimum Limit of Indemnity

100,000 or less

250,000

100,001 to 200,000

500,000

200,001 and above

1,000,000

Run off cover:


-

Insurance against a claim arising from work previously undertaken

Required for a minimum of 6yrs (under hand) or 12 yrs (under deed)

RICS recommend should be purchased for 15 yrs

Compulsory Professional Indemnity Insurance (CPII) Regulations


-

Set the requirements / benchmark for PI Insurance

November 2008

40

Nadia Slattery
APC Revision Document

Merrett v Babb
-

Employer went bankrupt so PII was cancelled

Client sued employee instead (Mr Babb, a retired surveyor)

In response, RICS set up Member Support Service Levy to protect members who find
themselves being sued personally and have no access to PII protection. RICS would
provide defence and advisory services

Starting a Practice
RICS Compliance
1. Register with the RICS for regulation of the firm
2. Appoint a Contact Officer for all RICS communication
3. Prepare a Complaints Handling Procedure to be sent to all clients with the Terms of
Business
4. Appoint a Complaints Handling Officer and Money Laundering Reporting Officer
5. Obtain PII and send details to RICS
6. Set up financial systems to comply with members' accounts regulations, if holding
clients' money
7. Members who practice as surveyors, who are directors of a limited or unlimited
company, must ensure that the Memorandum and Articles of Association of the
company include a clause confirming that the business will be conducted in
accordance with the RICS Bye-Laws, Conduct Regulations and Practice Statements
8. Obtain an up to date logo kit from RICS to use for the production of all practice
material to ensure compliance with the new designation 'Regulated by RICS'

Statutory Compliance
1. Display names of partners or company name on business stationary
2. Register with the Office of the Data Protection Commissioner
3. Fully comply with the requirements of the applicable legislation i.e. DDA, H&S

Fees
-

Fee calculation is an accurate assessment of resources required to carry out


professional duty on a project + OH&P

Cannot submit a fee with prior knowledge of a competitors

Cannot change a fee based on knowledge of a rival bid could re-evaluate scope of
duties included in fee and resubmit

If you run out of fee, must carry out works as per fee agreement but check if there is
any grounds for payment of additional fees

November 2008

41

Nadia Slattery
APC Revision Document

Terms of Engagement
-

Fees

Payment of expenses

Manner in which expenses and disbursements are to be calculated

Members complaints handling procedure

Members Accounts
-

Dont accept cash electronic payment only!

All monies to be kept in separate account, clearly identifiable with Client in name

Inform client immediately of account name, bank/building society and whether the
account is accumulating interest

The money must be available on demand

Maintain accurate records of all transactions/dealings

Complaints Handling Procedure


The firms Complaints Handling Procedure (Rule 5 of the Rules for firms) must include:
-

Contact name/details

Internal timescale of firms procedure

Recognition of the right to complain

Reference to the possibility of mediation

Recognition to take complaint to an independent third party

Handling a complaint:
-

Keep a written record of the complaint

Investigate fully and firmly

Ensure the client feels the matter is being taken seriously

Give client a timescale for a response

Face to face meetings often lead to more constructive and satisfactory solutions

Solutions could include an apology, agreeing to waive fees, offer of compensation or


the agreement to go to dispute resolution

Analysis is a vital form of client feedback

DLs complaint procedure (referred to in our Standard Terms of Engagement):


-

Contact Mark Hackett (who is appointed to deal with complaints)

Where complain is initially made orally, client is requested to send written summary of
complaint

Timescales for responding to the customers written complaint are:


o

Initial response (DLs understanding of complaint) 14 days

Full response (outcome of investigation) 21 days from date of initial


response

November 2008

42

Nadia Slattery
APC Revision Document

If complainant is dissatisfied with the handling of the complaint, he may refer the
matter to the Senior Partner who will undertake separate review of complaint

If complainant remains dissatisfied, despite the Senior Partner's intervention, then


further stages can be implemented, namely:
o

the mediation procedure as per the Centre for Dispute Resolution Model
Mediation Procedure, or the mediation process adopted by the RICS

If complaint still not resolved then refer complaint to Surveyors Arbitration Scheme

Conflicts of Interest
Where members interests conflict with clients or where two or more clients interests conflict.

Examples of conflicts of interest:


-

Acting for both a developer and contractor

Acting for two competing developers/contractors

Acting on behalf of a family member

Action to be taken:
1. As soon as you are aware, disclose to client in writing, the possibility and nature of
conflict
2. Advise client in writing that neither member nor members firm can continue to
represent unless:
a. unconditionally, the client requests you to do so
b. the client finds it acceptable and approves, in writing, the specific conflict
handling arrangement put in place

What is the Agenda for Change?


In 1998, the modelling of the current structure of the RICS was initiated by the Agenda for
Change, led by Richard Lay in his role as President.

It aimed to shape the RICS' structure and policy in three main ways by responding to three
perceived needs:
1. The need to be perceived as a global organisation, not just in the UK
2. The need to become more relevant to its members in the 21st century
3. The public's desire to see more accountability and understanding as to the role and
duties of a Chartered Surveyor

Key changes included:


1. The introduction of new stringent educational threshold standards for uni courses
2. The establishment of world regions and national associations
3. The replacement of 7 divisions by 16 (now 17) faculties

November 2008

43

Nadia Slattery
APC Revision Document

4. New criteria for attainment of Fellowship grade"

What is the Brooke Review?


Following the outcome of the radical changes from the Agenda for Change, there was
widespread unease among members in respect of the new structure and workings of the
RICS.

The Brooke Review Committee was established by RICS President Nick Brooke in 2003 to
recommend:
1. Improvements in two-way communication between RICS and its members
2. How to encourage more awareness of, and involvement in, RICS affairs
3. Better arrangements for considering members' opinions and complaints

Following consultation, a report was published setting out more than 40 recommendations.

Key recommendations included:


1. More power and responsibilities should be devolved to national and regional boards
2. Composition of Governing Council should be reviewed
3. Greater representation of Matrics at all levels of decision-making
4. Communications with members should be more cost-effective, better co-ordinated
and more user-friendly

The recommendations were adopted by the RICS International Governing Council in June
2004.

Initiatives implemented include:


1. A new RICS website with a members' only zone
2. The production of a simple guide to the RICS
3. Streamlined and targeted email alerts and correspondence to members

What is the Carsberg Report?


The RICS appointed Sir Bryan Carsberg in September 2004 to conduct a thorough internal
and external review of the regulation of the RICS.

Key recommendations included:


1. Regulation should continue to be carried out by internal bodies
2. RICS should develop a structure that separates regulatory functions from
representational functions
3. Establish a conduct board to operate disciplinary structures
4. RICS should regulate firms as well as members

November 2008

44

Nadia Slattery
APC Revision Document

5. A review of CPD arrangements to better protect the consumer

Following the recommendations of the report, a new regulatory board was appointed to
deliver a more independent, fairer and more efficient means of regulation of the RICS.

Current RICS issues and initiatives


-

Peter Goodacre wants to promote technical grade

Lecture series Surveyors in Society aims to highlight significance of the Chartered


Surveyor in business and the community

Dealing with global warming and population growth

Skills shortage QS now added to list of skills shortage

November 2008

45

Nadia Slattery
APC Revision Document

T013 Construction Technology & Environmental Services (Level 3)


Construction Technology
Substructures:
-

Piling Choice affected by ground conditions and site restrictions


o

Bored

Casing driven in

Reinforcement cage

Concrete poured in

Casing removed

Driven

Continuous flight auger

Auger driven in

Concrete poured in as auger is removed

Reinforcement placed in wet concrete

Sheet piling

Precast RC piles driven into ground

Corrugated metal sheets percussion driven into ground

Foundations
o

Strip

Pad

Raft

Piled

Measure

Excavate trench

Disposal of excavated material

Earthwork support

Compaction

Blinding

Hardcore

Formwork

Reinforcement

Concrete

Superstructures:
-

Concrete frame
o

Precast

In situ

Cast off site or in situ

November 2008

46

Nadia Slattery
APC Revision Document

Steel frame
o

Rolled sections

Hollow sections

Metsec systems

Portal frames

Comparison of concrete/steel frames


o

Steel frame quicker from concept to completion

Cost of steel governed by complexity and repetition

Late variations not easily incorporated in steel frames due to long lead-ins

Steel frame is lighter

Steelwork is high quality as fabrication is controlled off site

Steelwork can take greater spans, less intermediate columns

Concrete does not require any additional fire proofing treatments

Concrete can endure high temperatures from fire

Outstanding resistance to explosion or impact = safer

Concrete can use recycled aggregates

Concrete more readily available (steel has high demand in China, ME)

Types of fire protection


o

Intumescent painting

Sprayed vermiculite cement

Sprayed mineral fibre

Fire resistant boarding

Brick size = 215 x 102.5 x 65mm

Cladding/Glazing:
-

Unitised curtain walling

Semi-unitised curtain walling

Stick and panel systems

Ventilated facades

Triple glazed facades

Services Technology
-

Electrical systems
o

Modular wiring

Mechanical systems
o

Note: Air based systems require more ceiling/riser space for ducts

Four pipe fan coil units

VAV

VRV

November 2008

47

Nadia Slattery
APC Revision Document

VRF

Air displacement

Chilled beams

Chilled ceilings

Internal/external drainage

Mains services

Fire safety systems

Security systems

Environmental controls

Data systems

Building Regulations:
-

National standards applicable to all types of development

Published by ODPM

(Part A) Structure

(Part B) Fire safety

(Part C) Site preparation and resistance to moisture

(Part D) Toxic substances

(Part E) Resistance to the passage of sound

(Part F) Ventilation

(Part G) Hygiene

(Part H) Drainage and waste disposal

(Part J) Combustion appliances and fuel storage systems

(Part K) Protection from falling, collision and impact

(Part L) Conservation of fuel and power

(Part M) Access to and use of buildings

(Part N) Glazing - safety in relation to impact, opening and cleaning

(Part P) Electrical safety

Disabled Discrimination Act 2005:


-

Imposed in December 2006

No such thing as DDA compliance, about what is reasonable

Building Regs Part B and Part M apply

Increasing and creating rights rights for the disabled

Also:
-

Building Control

Planning

Party Wall Issues / Rights of Light

November 2008

48

Nadia Slattery
APC Revision Document

T017 Contract Practice (Level 3)


Construction Act Housing Grants, Construction and Regeneration Act 1996, Part II
-

Key objective is to influence the culture of the construction industry

Aim of reducing confrontation, and facilitating better cash flow and fair play

Ensures contracts incorporate minimum provisions with regard to payment and


dispute resolution

The main elements are:


o

Contracts must contain payment provisions:

If project exceeds 45 days, contractor is entitled to stage or interim


payments

Contract must provide for a due date for payments and a final date
for payment

Paying party must serve a notice of intention to receiving party,


stating amount and basis

Payments cannot be withheld unless a notice of intention to withhold


is given, stating amount and grounds for withholding

Prohibition of conditional payment provisions

Clauses making payment conditional on payment from a third party


are unenforceable except in the case of insolvency

Contractor may suspend performance for non-payment (must give 7


days notice) and completion date is automatically extended

Introduced the right to refer to a dispute to adjudication

Scheme for Construction Contracts Regulations 1998


-

Where there is contravention of Construction Act, the statutory default provisions in


this statutory instrument apply

Contains a Schedule in 2 parts


o

Part 1 Provides rules for the selection of an adjudicator with the powers to
make enforceable decisions

Will apply where contract contains no adjudication provisions; or

Where the provisions do not comply with the Act

Part 2 Provides payment rules

Will apply where contract fails to make provisions; or

Where parties have failed to agree on details such as timing of


payments

November 2008

49

Nadia Slattery
APC Revision Document

Principles of Contract Law


-

A contract is a legally enforceable agreement

Components of a contract:

Offer

Acceptance

Consideration

Also:

Intention (to make the agreement legally binding)

Capacity (to enter into that type of contract and mentally)

Legality (enforceable by the courts)

Repudiation - an implied or express refusal by one party to perform their obligations


under the contract

Statute of limitations maximum period of time, in common law, after an event that
legal proceedings may be initiated

Express terms
o

those contained in the main contractual document

those contained in other documents to which the main contract document


refers

Implied terms
o

those terms which are implied by law

Also may incur legal liability under the law of tort

Tort a civil wrong


o

Negligence

Nuisance

Trespass

Current Case Law


-

Amsprop sues Wilks Head & Eve for negligence over Regent Street disease

Cleveland Bridge v Multiplex

Choosing a Contract
-

Consider client, project and approach

Consider what tenderers are familiar and comfortable with to perceive lower risk

Unfamiliar contracts may attract a risk premium

Standard Forms of Main and Sub Contract


JCT Main Contracts
-

Approximately 80% of contracts issued under JCT form

New suite published in 2005

Drafted by Joint Contracts Tribunal representing employer and contractor bodies

November 2008

50

Nadia Slattery
APC Revision Document

Risk allocation historically criticised by employer, thus often heavily amended

Perceived as having an adversarial approach

NEC/ECC 2005
-

Recommended by Latham

Partnering style approach, avoids blame and claim culture, less confrontational

Suitable for all types of construction and engineering project

Little case law to see how stands in court

3 main aims

Clarity clear and simple language in present tense

Flexibility can be tailored to suit specific requirements

Stimulus to good management less adversarial

Available in 6 main options including:


o

A & B Priced contracts

C & D Target contracts

E Cost reimbursable

F Management contract

No reference to QS or CDM Coordinator

PM assumes full authority on behalf of employer

PM controls time and cost as an administrative function

PM updates risk register and issues instructions

Final account must be settled within 4 weeks of completion

Widely accepted that it generates a large volume of paperwork and admin

Programme is a contract document

Requirement for parties to give early warnings (or risk penalty) for:
o

Increase costs

Delay completion

Delay key date being met

Impair performance of the works in use

Compensation events give rise to variations and EOTs

LADs and retention are secondary options

PM assesses amount due and certifies payment within one week of each assessment
date

PM can withhold 25% of the valuation if contractor has not submitted first programme

PPC2000
-

PPC200 Project Partnering Contract

Latham called it the full monty of partnering and modern best practice

Used on offices, housing, schools, hospitals, universities

Just relaunched in October following feedback from users

November 2008

51

Nadia Slattery
APC Revision Document

GC/Works/1 1998
-

Originally established as a suite of contracts for government

Risk allocation in favour of employer

Rarely used now

Four volumes:
o

With Quantities General Conditions

With Quantities General Conditions

Single Stage Design & Build General Conditions

Model Forms & Commentary

ICE Conditions of Contract (7th Edition)


-

Civil engineering construction works

Suited to the scale and imprecise nature of civils projects

Suits technically complex projects

Re-measure on completion

No reference to QS

Association of Consultant Architects PPC2000, TPC2005


-

PPC 2000 was first standard form for Partnering

Direct result of Egan report Rethinking Construction

Covers whole procurement process including design development

Integrates the entire project team

FIDIC Conditions of Contract


-

International contract

Amending a Standard Contract


-

If not qualified to do so, DONT

Can destroy delicate balance of risk allocation

Can create legal uncertainty created by amending individual clauses which form part
of a complex web of interacting cross-referred terms

Amendments may fall foul of the Construction Act

Can attract a cost premium to tenders

Write clause not used rather than deleting and trying to renumber

Amendments must be reasonable and comply contract legislation

Courts can strike out amendments if contrary to good faith

November 2008

52

Nadia Slattery
APC Revision Document

Bespoke Contracts
-

Expensive to draft (legal fees)

May be badly drafted

Not familiar to other parties including CA

Untested in court

Unappealing to contractor

Roles and Responsibilities of Parties


Some implied some express

Employer
-

Give site access

Ensure any transfer of authority over and above what is normal within the contract is
communicated to the contractors

Make payments in accordance with the contract

Pay for any loss and expense incurred

Take out any necessary insurance provisions (clause 6.7 B or C)

Confidentiality

Contract Administrator
-

Supply information

Give instructions

Inspection and monitoring of the contract work

Adjudication and certification

Employers Agent
-

Employed as a representative to exercise the powers and function of the Employer

Administers contract

Monitors execution of project

Ensure all parties adhere to conditions of contract

Not responsible for making qualitative or design judgements

CDM Co-ordinator
-

Prepare Pre-Construction Information document

Assist client and ensure obligations are met

Issue F10 notices

Prepare health and safety file

Amend health and safety file as works progress

November 2008

53

Nadia Slattery
APC Revision Document

Quantity Surveyor (JCT)


-

Interim valuations

Valuing variations

Prepare statement of final account

Ascertaining loss and expense (if so directed)

Only use rates in priced document for purposes of the contract

No role in D&B contract

Contractor
-

Construct works in accordance with contract documents

Carry out works regularly and diligently

Health and safety

Take out any insurance, bonds and/or warranties

Project Manager (ECC)


-

Manages programme

Manages risk and value registers

Ensures clients needs and duties are covered

Assignment
-

Transfer of contractual rights only (not obligations)

i.e. developer may transfer rights for claiming defects to purchaser

Novation
-

Transfer of rights and obligations

Common in D&B contracts

Occurs when contract is being let

IN D&B, stated in ERs that consultants appointment is to be novated

Possible conflict of interests:

Consultant still has a duty of care to client

Consultant may be influenced by contractor i.e. VE

ERs and CPs must be clear and well prepared for novation to work effectively

Contracts (Rights of Third Parties) Act 1999


-

Privity of contract
o

The private relationship between those persons party to a contract

A person not party to the contract cannot enforce it, nor acquire rights or
incur liabilities under it, even if the contract is intended to benefit a third party

But, there are often third parties with financial stakes in the project (i.e. funders,
tenants, purchasers) who are not party to the building contract

November 2008

54

Nadia Slattery
APC Revision Document

In the absence of direct contract, third parties can only sue in tort of negligence, but
this is limited in scope (cant claim for pure economic loss)

Rights of Third Parties Act and collateral warranties provide this link

Contracts (Rights of Third Parties) Act


o

Applies to contracts made after 11 May 2000

Gives direct, enforceable contractual claims to a third party if:

The contract expressly provides that he may; or

The term purports to confer a benefit on him

The third party must be identified in the contract by name or class (i.e. future
tenant, even if not in existence when contract executed)

Provides an effective alternative to collateral warranties

Only imposes benefits, not obligations

Act can be excluded from a contract

Collateral Warranties
-

Side agreement which establishes a contractual link between two parties which would
otherwise not exist

Provide third parties with contractual remedies against parties to original contract i.e.
o

Employer to subcontractor

Tenant to contractor

Allows third parties to enforce the terms of the contract

Many standard forms including JCT, British Property Federation and Construction
Industry Council

Types:
o

Contractor to Purchaser or Tenant

Contractor to Funder

Subcontractor to Purchaser or Tenant or Funder

Subcontractor to Employer

Third Party Rights v Collateral Warranties


-

In JCT05 referral to Third Party Rights eliminates the need to collateral warranties,
although they are still included within the contract

Advantages of Third Party Rights:


o

Much simpler then executing collateral warranties

Even small projects can generate large numbers of warranties

Less administration

Standard forms of warranty often amended and bespoke forms often used

Warrantor (or their insurer) often seeks to insert limitation clauses

November 2008

55

Nadia Slattery
APC Revision Document

Collateral warranties can sometimes be difficult to procure

Collateral warranties must be assigned every time tenant leaves

Disadvantages of Third Party Rights:


o

Little case law to rely on

No physical warranty which beneficiaries feel more comfortable with

Consultants and contractors wary of granting rights to unknown beneficiaries

Difficult for developers to impose rights on subcontractors as they are not


party to the building contract

No rights exist until developer and consultant or contractor agree and


complete the main contract

Party Wall Act


-

Prevents and resolves disputes relating to party walls, boundary walls and
excavations near neighbouring buildings

Must give adjoining owners notice of intention, even where work will not extend
beyond centre line of a party wall

Contract Documents
-

Form of Contract
o

Articles of Agreement

Conditions of Contract

Schedule of amendments

Design information
o

Drawings

Specifications

Work schedules

Pricing document
o

o
-

Option A Priced specification or work schedules

Pricing schedule

BoQ

Option B Contract sum analysis or schedule of rates

Information release schedule


o

Programme for issuing design information so as not to impede works

Pre-Construction Information

In D&B or where there is a CDP:


o

Employers Requirements

Contractors Proposals

In NEC Contractors programme

Relevant post tender correspondence

November 2008

56

Nadia Slattery
APC Revision Document

Letters of Intent
General:
-

A letter outlining a clients intention to enter into contract

Intention to create legal relations

Not a substitution for a binding, executed contract

Effect of the LOI depends entirely upon its wording

Does not bind contractor to carry out any works

If contractor carries out work on basis of LOI, a contract is created to pay for that
work

Enables contractor to undertake work before formal contracts are exchanged

Allows orders for long lead-in items to be placed

No guarantee contractor will sign the contract (and he is under no obligation to do so)

Financial limit may be reached before contract is signed

Can be with limited or unlimited authority


o

Limited

Use where still a number of outstanding matters to be agreed

Acknowledge certain items are still to be agreed

Maximum liability under letter is stated

Unlimited

Use where all details of contract have been finalised

Confirm basis upon which contract docs will be prepared

Requesting and authorising contractor to commence works

Undertaking to pay for such work even if contract is not executed


(unless contractor goes back on matter previously agreed)

Only intended to apply for a few days whilst contracts are being
prepared

Should Include:
-

Works to be subject to LOI

Value of works

Form of contract to be entered into, and key terms

Contract sum (if agreed)

Date for possession

Date for completion

Insurance provisions required

Method of payment

Expiry date of letter

State intention to enter into formal contract

State employers reservation of right not to award the contract for whatever reason

November 2008

57

Nadia Slattery
APC Revision Document

Risks to Employer:
-

Tend to lead to execution of formal contract drifting

Contractor may postpone agreement of contract and/or any outstanding matters

Employer loses incentive in negotiations

No protection if contractor becomes insolvent

May not be binding in court if express terms are not agreed

Quantum Meruit
-

As much as he has earned

Claim for a reasonable sum as payment for services rendered

Where there is no contractual basis for assessing amounts

Bonds
-

Obligations / Contractual duties owed by one party to another are financially


guaranteed by a third party

Provided by banks and insurance companies

Typically 10% of contract sum

Conditional or on demand
o

Conditional

Only payable if condition has been met or event occurs

And loss has resulted

On Demand

Can be called at any time

Not dependant upon conditions

Types of bonds:
o

Performance Bond

Guarantee of performance

Guarantor pays for loss up to value of bond

Normally activated upon insolvency or retention fund not sufficient for


making good defects

Advanced Payment Bond

Used where contractor has high mobilisation costs

Security against the advance payment

Payment for Off-Site Materials and/or Goods

November 2008

Security against listed items which not yet been delivered to site

Retention Bond

Employer calls on bond if defects arise

In lieu of retaining cash, helps contractors cash flow

Expires after Certificate of Making Good Defects is issued

58

Nadia Slattery
APC Revision Document

Difference between a Bond and Collateral Warranty


-

Bonds are contained within the contract

Collateral warranties are a side agreement to the contract

Warranties
-

Written guarantee of quality of a project

an assurance by one party to the other that certain facts or conditions will happen

the other party is permitted to rely on that assurance and seek remedy if it is not
followed

From a supplier, subcontractor

Parent Company Guarantee


-

An alternative to a performance bond

Contractors parent company guarantees to fulfil obligations at own cost in the event
of non-performance or insolvency

Contractual performance is underwritten by parent company

Not limited by value

Free to obtain

Insurances
General:
-

Risk of damage and injury related to construction projects is high

Therefore insurance provision an essential requirement of construction contract

Two basic types of insurance


o

Liability insurance financial cover for legal liabilities owed to others

Loss insurance providing cover for losses, which fall directly on insured
parties

Indemnity guarantee, compensation

Insurance method of providing an indemnity

Joint Names Policy


o

Policy in names of two or more parties (i.e. contractor and employer)

Prevents insurer from using rights of subrogation against parties named in


policy

Subrogation
o

The right to sue in the name of the assured any person who could have been
sued by the assured in respect of the loss

Example, contractors negligence causes a fire in the existing building.


Insurer can pay out and then sue contractor for negligence to reclaim his loss

November 2008

59

Nadia Slattery
APC Revision Document

Three main categories of risk:


-

Injury or death to persons

Damage to property other than works

Damage to works

Injury to Persons or Property:


-

Clause 6.1 Liability of Contractor Personal Injury or Death


o

Requires contractors to indemnify Employer

Injury arising out of, or in the course of, or caused by, the carrying out of the
Works

Liability does not extend to injury or death as a result of an act or neglect by


any of the employers team

Clause 6.2 Liability of Contractor Injury or Damage to Property


o

Requires contractors to indemnify Employer

Injury or damage to property arising out of, or in the course of, or by reason
of, the carrying out of the Works

Includes non-physical injury to property but where enjoyment of a right has


been affected i.e. loss of light caused as a result of construction works

Liability does not extend to injury or death as a result of an act or neglect by


any of the employers team

Where a statutory undertaker is working as a domestic subcontractor, the


contractor is liable for injury or damage caused by them

Excludes the Works, works executed and/or site materials

Clause 6.3 Injury or Damage to Property Works and Site Materials Excluded
o

Excludes Works, work executed and site materials from Contractors liability
to indemnify Employer under clause 6.2

Insurance against Personal Injury and Property Damage:


-

Clause 6.4 Contractors Insurance of his Liability


o

Requires contractor to provide insurance for indemnities in clauses 6.1


and 6.2

For personal injury and death to third parties and damage to property

Not less than the sum stated in the Contract Particulars

Employer can request documentary evidence that insurance in place

Employer can take out insurance and recover the cost from the contractor in
the event that the contractor defaults

November 2008

60

Nadia Slattery
APC Revision Document

Clause 6.5 Contractors Insurance of Liability of Employer (optional)


o

Non negligent damage insurance

Excludes damages caused by neglect, default or omission

Stated in Contract Particulars if it is required

Cost of policy added to contract sum

Contractor must take out joint names policy

Insurance against liability of Employer for damage to any property caused by


collapse, heave, vibration, weakening or removal of support or lowering of
groundwater

Clause 6.6 Excepted Risks


o

The contractor is not required to indemnify the Employer or insure against


injury, death or damage resulting from Excepted Risks

Insurance of the Works


-

Clause 6.7 Insurance Options (A, B & C, set out in Schedule 3)


o

All Risks insurance must be in joint names

Must cover all subcontractors, or include a waiver by the insurers of their


rights of subrogation against subcontractors

Option A New Buildings All Risks Insurance of the Works by the Contractor
o

For construction of new buildings

Insurance by Contractor

If the contractor has existing All Risks policy, do not need to take out an
additional policy providing that the scope of the policy is sufficient

If loss or damage occurs, the contractor must give written notice to the
architect and employer of the extent, location and nature of loss / damage

No account is taken of loss or damage in calculating contractors payments

Following completion of insurers inspections the contractor must reinstate the


loss or damage

The contractor will be paid to reinstate work as certified by the architect

The contractor authorises the insurers to pay all sums due under claim to
employer

Option B New Buildings All Risks Insurance of the Works by the Employer
o

For construction of new buildings

Insurance by Employer

Operates the same as Option A except Employers obligations

If loss or damage occurs, the process is the same as Option A except the
reinstatement works are treated as a variations

November 2008

61

Nadia Slattery
APC Revision Document

Option C Insurance of Existing Structures Insurance of Works in or Extensions to


Existing Structures
o

For projects involving work to an existing building

Refurbishment

Repair

Fitting-out

Extensions

Arranged by the Employer

Need to insure existing structure, its contents and the Works

CDP Professional Indemnity Insurance


-

Clause 6.11 Obligation to Insure


o

Where there is a CDP, contractor must take out professional indemnity


insurance

Contractor to maintain insurance for period stated in Contract Particulars


(provided it remains available at a commercially reasonable rate)

If no longer available at commercially reasonable rates, contractor must notify


employer

All Risks Insurance


-

Insurance of physical loss or damage to work executed and Site Materials and
against reasonable cost of removal and disposal of debris arising from such loss

Excludes cost of:


o

Property which is defective due to:

Wear and tear

Obsolescence

Deterioration, rust or mildew

Works or site materials damaged as a result of defective design, plan,


specification, material workmanship

Loss or damage caused by or arising from:

War etc

Disappearance or shortage

Excepted risk (ionising radiations, radioactive contamination etc)

Joint Fire Code


-

Applies where Contract Particulars state so

If Joint Fire Code is amended or revised, the cost is borne by the party named in the
Contract Particulars

November 2008

62

Nadia Slattery
APC Revision Document

Specified Perils
-

Fire, lightning, explosion, storm, flood, earthquake, articles dropped from aircraft etc.

Interim Valuations and Payment Provisions


General:
-

Valuation of works completed

Stage or periodic payments

Usually monthly

Up to date of Practical Completion

Final valuation at end of Rectification Period or issue of Certificate of Making Good


Defects (whichever later)

Interest payable on any overdue payment (at 5% above BoE base rate)

Contractor may suspend works for failure to pay

Includes:
-

Total value of works properly executed

Variations under val rules, prov sums, approx quants

Variations valued under Schedule 2 Quotations (with confirmed acceptance)

Value of any listed materials (off-site materials)

Items not subject to retention:


-

Additional insurance premiums

Fees and charges not already included or relating to the CDP

Royalties, damages and other monies for infringement of patent rights in complying
with CAIs

Costs of opening up or testing if result is in accordance with contract

Cost for taking out and maintaining Liability of Employer insurance

Loss and/or expense (including antiquities)

Restoring, repairing or replacing any loss or damage or removing the disposal of


debris treated as variations under Schedule 3

Amounts allowable to contractor under Fluctuation Option

Deductions:
-

Not amending errors arising from inaccurate setting out

Defects, shrinkages or other faults instructed to be not made good

Employer employing others to execute any work which contractor did not comply with
after notice given

Work, materials or goods not in accordance with contract (which is instructed to


remain)

November 2008

63

Nadia Slattery
APC Revision Document

Activity schedule:
-

Used to chart progress of works with lump sums against each activity to be included
in valuations

Used in NEC contracts

Process:
-

Contractor may submit application 7 days in advance of issue of interim certificate

Assess contractors submission

Visit site to check progress, materials on site


o

Look for defects, works not in accordance, security of materials on site

View documentation regarding materials off site

Assess preliminaries fixed and time related

Assess any additions which should not be subject to retention

Ask CA to confirm any works not in accordance with contract

Provide details of any adjustment to contractors application

Issue recommendation to CA including retention statement and check last certificate

Payment = 14 days after Interim Certificate

Notice of Payment = 5 days after issue of Interim Certificate

Withholding Notice = 5 days prior to final date for payment

14
7 Days

Interim Certificate:
-

Certificate stating amount due to contractor from employer

Identifies:
o

Gross valuation

Less retention

Less any Advance Payment

Less amount due in previous certificate

Less any works not in accordance with contract

Materials On Site
-

Payable if:
o

Not brought to site prematurely

Adequately stored and protected

Delivery receipts and invoices correspond

November 2008

64

Nadia Slattery
APC Revision Document

Contractor can remove materials from site if:


o

Damaged

Contaminated

Presents a security problem

Safety hazard

Materials Off Site


-

Payable if included as a Listed Item in the contract

Process:
o

Check is a Listed Item

Visit manufacturers / storage facility

Ensure separately stored

Clearly identified as for client

Clearly identified as for works

Vesting certificate in place

Insurance provided

Bond provided for uniquely identified items (if required in Contract


Particulars)

Bond provided for not uniquely identified items

Retention
-

Percentage (3% default) of interim payment withheld for making good defects

Alternative is a retention bond

Half is released at Practical Completion, the remainder at end of Rectification


Period/issue of Certificate of Making Good Defects

Final Account (Adjustment of Contract Sum)


General:
-

Final payment due to contractor

Includes all additions and omissions (including L&E)

Additions to contract sum include:


-

Variations
o

CAI

CVI

Confirmed acceptance of Schedule 2 Quotation

Provisional sums

Variations to Prime Cost Sums

Adjustment of provisional quantities

L&E (including antiquities)

November 2008

65

Nadia Slattery
APC Revision Document

Fees and charges not already included or relating to CDPs

Royalties, damages and other monies for infringement of patent rights in complying
with CAIs

Costs of opening up or testing if result is in accordance with contract

Cost for taking out and maintaining Liability of Employer insurance

Restoring, repairing or replacing any loss or damage or removing the disposal of


debris treated as variations under Schedule 3

Amounts allowable under Fluctuation Option

Deductions to Contract Sum include:


-

Not amending errors arising from inaccurate setting out

Defects, shrinkages or other faults instructed not to be made good

Employer employing others to execute any work which contractor did not comply with
after notice given

Work, materials or goods not in accordance with contract (which is instructed to


remain)

Employer employing others to carry out remedial measures for breach of Joint Fire
Code (after notice given)

Amounts allowable to Employer under Fluctuation Option

Process:
-

6 months after PC = Contractor must provide all information to QS

3 months after receipt of info = QS must prepare statement on FA

Valuing Change
Definition of a Variation:
-

Alteration or modification of design, quality or quantity of the works including:


o

Addition, omission or substitution of work

Alteration of materials or goods

Removal of any works executed or materials or goods

Obligations or restrictions regarding:


o

Access to site

Limits on working space

Limits on working hours

Execution or completion of works in a specific order (contractor can make


reasonable objection)

Valuation of Variations and Provisional Sums:


-

Value to be agreed by both parties or otherwise to be valued by QS in accordance


with valuation rules

November 2008

66

Nadia Slattery
APC Revision Document

Valuation Rules:
o

Where work is of similar nature, use contract rates

Where not of similar character, use fair rates and prices

Make fair allowance for changes in conditions/quantities

Make allowance for preliminary items

If cant be properly measured, use dayworks

Same rules apply for CDPs to be valued

If, as a result of variation, there is change to conditions for other work, then
that work to be treated as if a variation and subject to valuation rules

Schedule 2 Quotation:
-

CA instructs contractor to provide quotation in accordance with Schedule 2

Confirmed Acceptance provided

Method of agreeing costs and identifying programme effects prior to instruction

Provides cost certainty

Speeds up final account

Quotation must include:


o

Amount of adjustment to contract sum

Effect on any other work

Any adjustment to time

Amount of L&E to be paid in lieu of ascertainment under clause 4.23

Fair and reasonable cost of preparing quotation

If specifically required, any additional resources required and method


statement

Deferment of Possession
-

If applicable, for maximum of 6 weeks

Entitled to EOT

Extensions of Time
General:
-

Contractor must always use best endeavours to avoid/minimise delays

EOT is adjustment to completion date

Relieves contractor of LADs and breach of contract

Entitlement if regular progress of works affected by Relevant Event:


o

Variations

Instructions for:

November 2008

Discrepancy or divergence in the Contract Docs

Postponement of work

Expenditure of Provisional Sums

67

Nadia Slattery
APC Revision Document

Instructions on antiquities (and separate L&E provision)

Schedule 2 Quotation

Opening up for inspection or testing (excluding if in Contract Sum or


if shows to be not in accordance with contract)

Deferment of possession

Suspension by contractor due to non-payment (following notice given)

Any impediment, prevention, default by employers team

Carrying out of statutory undertaker, or failure to carry out such work

Exceptionally adverse weather conditions

Loss or damage by Specified Perils

Civil commotion

Strike, lock-out etc

Exercise after Base Date by government of any statutory power

Force majeure

Extraordinary event or circumstance outside control of parties

Prevents one or both parties from fulfilling their contractual


obligations

Such as war, strike, riot, crime, act of nature (floods, earthquake,


volcano)

Note: items above covered by separate Relevant Events so coverage


of force majeure actually limited.

Concurrent delay
o

Two different causes of delay affecting the project in parallel

Such as adverse weather and failure of statutory undertaker

Assessment methods

The devlin approach

The dominant cause

Burden of proof

Tortuous approach

Float
o

Time available in a programme in addition to planned duration

Belongs to contractor

Can be taken into account when EOT is evaluated

As contractor obliged to use best endeavours to mitigate or prevent


delay

Acceleration
o

November 2008

Additional labour, plant, materials and preliminaries to advance works

68

Nadia Slattery
APC Revision Document

Process:
-

Contractor must give written notice


o

Material circumstances

Identify any event he considers a Relevant Event

Give particulars of expected effects including estimate of expected delay to


Completion Date

o
-

Notify CA of any material change in estimated delay or any other particulars

If, on receiving such notice, CA is of opinion


o

Is a Relevant Event; and

Likely to be delay to Date for Completion

must give an extension of time


-

In any event, CA must notify contractor of his decision:


o

Within 12 weeks of receipt of notice (or earlier if PC within 12 weeks)

State extension / or omission attributed to each Relevant Event

Loss and Expense


General:
-

To reimburse contractor for loss suffered or expense incurred which would not be
reimbursed under any other contract provision

Entitlement if
o

Deferment of site possession

Regular progress of works affected by one of the Relevant Matters

Relevant Matters are:


o

Variations (excluding Schedule 2 Quotation)

Instructions for:

Postponement of work or expenditure of Provisional Sums

Opening up for inspection or testing (excluding if in Contract Sum or


if shows to be not in accordance with contract)

Suspension by contractor due to non-payment (following notice given)

Any impediment, prevention, default by employers team

Disruption
o

Discrepancy or divergence in the Contract Docs

Reduced efficiency

Delay
o

Stopping of works

L&E must be actual loss incurred

Heads of claim can include any or all of the following:


o

November 2008

Prolongation

Site running costs for extended period

Increases in cost of labour, plant or materials

69

Nadia Slattery
APC Revision Document

Based on actual costs not contract rates

Disruption

Inefficient use of labour and plant

Loss of profit

Head office overheads

Formula may be used

Hudson, Emden

Finance charges

Must be a direct consequence of matter referred to in claim

Cannot claim for cost of preparing claim

No automatic right of recovery solely because an EOT has been granted

Conversely, can suffer L&E without EOT

Duty of CA to determine liability and entitlement

Duty of CA to ascertain amounts due (or QS if so directed)

Causation Test

But for the occurrence of the event, would the cost have been incurred

Two or more causes of delay?

Is the head of claim dominant?

Are the causes concurrent?

Remoteness Test
o

Does loss arise naturally from ordinary cause of events?

Do costs arise as a direct result of event?

Loss must satisfy both causation and remoteness test

Examine loss for evidence of mitigation


o

Was action reasonable in circumstances prevailing at the time?

Was the loss caused unnecessarily?

Could it have been readily avoided?

Process:
-

Contractor must make written application to CA

CA to form opinion that regular progress of works has been affected or if loss incurred
as a result of deferment

CA shall ascertain amount or instruct QS to do so

Contractor must:
o

Make application as soon as apparent regular progress has been affected

Upon request, submit information in support of application to enable CA to


form opinion

Upon request, submit details of L&E to enable CA/QS to ascertain amount


being incurred

Any amount ascertained as due must be added to Contract Sum

November 2008

70

Nadia Slattery
APC Revision Document

Must pay any amounts ascertained in interim valuations

L&E not subject to retention

EOT but no L&E:


-

Carrying out of statutory undertaker, or failure to carry out such work

Exceptionally adverse weather conditions

Loss or damage by Specified Perils

Civil commotion

Strike, lock-out etc

Exercise after Base Date by government of any statutory power

Force majeure

Antiquities
-

Fossils, antiquities and other objects of interest or value

Becomes the property of the Employer

Contractor:
o

Must use best endeavours not to disturb

Cease work if continuance would endanger object, prevent or impede its


excavation or removal

Take all steps to preserve object in exact position and condition

Inform CA of discovery and location

Instruct action to be taken

Only instruction contractor cannot refuse to comply with

Ascertain any EOT and L&E due

CA:

Practical Completion
General:
-

When the works are practically complete and fit for purpose

Defined in JCT05 as:

CA is of opinion it has been achieved

Contractor has supplied as-built info for CDPs

Contractor has provided all info for health and safety file

CA must consider:
o

Liable for loss of LADs if certifies too early

Contractor may claim malicious delay if certifies too late

Ensure there are no patent defects

Works must be practically complete

November 2008

71

Nadia Slattery
APC Revision Document

Process:
-

CA issues Practical Completion Certificate

Employer takes possession

Rectification Period commences

Contractors insurance obligations are relieved (employer must take out policy)

Half retention is released

LADs no longer apply

Sectional Completion
-

Pre-defined sections of work to be completed

Separate Dates for Completion and LADs apply to each section

Value of each section must be agreed for release of retention

Partial Possession
-

A voluntary agreement between employer and contractor

Contractor must give consent

Not agreed in advance (would be sectional completion)

Practical completion deemed to have occurred for that section (and all associated
provisions occur)

Remainder of works continues to operate as contract states

LADs still applicable on incomplete areas (calculated pro-rata)


o

LADs x ( (Contract Sum value of relevant part) / Contract Sum)

Time at Large
-

Where no fixed completion date exists

Contractor expected to complete works within a reasonable period

Can occur when:


o

No completion date fixed in contract

Fixed time has ceased to apply by agreement or prevention

Additional works or employer beach but no EOT

Contractor breaches contract but employer elects to continue with


performance of contract

Employer has interfered with certification process to prevent proper


administration of the contract

Project is beyond completion date with neither an EOT or Certificate of Non


Completion issued

November 2008

72

Nadia Slattery
APC Revision Document

Rectification Period
Defects:
-

Defects, shrinkages or other faults

Due to materials, goods or workmanship not in accordance with contract

Failure to comply with CDP

Must be made good at no cost to employer

CA can instruct to remain and deduct sum from contract sum

Snagging:
-

Outstanding works of a trivial or minor nature

CA considers should not prevent PC

Do not affect use of building

CA may issue a programme for completion of snagging items

Process:
-

Begins once Practical Completion has been certified

Default is 6 months (usually amended to 12 months seasons)

Schedule of Defects to be issued 14 days after end of Rectification Period

CA can issue instruction whenever considered necessary for making good defects,
shrinkage or other faults during the Rectification Period

Contractor must make good within a reasonable time at no cost to employer

CA can instruct not to make good and deduct sum from contract sum

If contractor fails to make good, employer can instruct another and

CA issues Certificate of Making Good Defects once all completed and accepted

Remainder of retention is released

Latent Defects:
-

Those which occur after the end of the rectification period and after Certificate of
Making Good has been issued

Liquidated and Ascertained Damages


-

A genuine pre-estimate of loss suffered as a result of late completion of the works

Not a penalty

Quick remedy to avoid having to prove actual loss as a result of breach of contract

Benefits both employer and contractor


o

Employer knows he will recover his losses

Contractor knows limit of his liability

Client is to calculate (not QS)

Can cover items such as:


o

November 2008

Loss or rent or other income

73

Nadia Slattery
APC Revision Document

Additional fees

Fines from statutory bodies

Costs imposed by other parties

Cost of not having facility (storage, rent, abortive costs etc)

Rate stated in contract particulars

If no sum stated in contract:


o

Unliquidated

Client claims loss through the common law

If Nil or 0 is inserted, then client has lost right to claim unliquidated


damages

Applies upon issue of Certificate of Non-Completion

Client deducts LADs from payment (not QS or CA)

Employer must inform in writing before date of Final Certificate that may withhold
LADs

Employer must also give notice not later than 5 days before final date for payment of
withholding or deducting from payment due

Insolvency
Definition:
-

Insolvency the inability to pay debts

Liquidation the closing down of a company in order to use assets to pay debts

General:
-

Insolvency practitioner appointed

Contract can be terminated immediately (not automatically terminated)

Signs of contractor insolvency:


-

Slowing down works

Supply of materials drying up

Increase in defective work

Changes in management

Requests for payments

Complaints from subcontractors

Actions following rumours of contractor insolvency:


-

Maintain professionalism

Keep it confidential

Get credit check

Monitor situation closely any reductions in site labour etc

Ensure utmost accuracy of forthcoming valuations

November 2008

74

Nadia Slattery
APC Revision Document

Speak to subcontractors

Contractor insolvency:
-

Identify insolvency practitioner

Inform parties involved

Inform bondsman (bank / insurance company)

Stop any pending payment (can defend on grounds of counter claim for costs)

Secure the site

Take ownership of materials off site (if paid for in valuations)

Schedule all plant and materials

Value works competed and value any defects

Arrange insurances

Monitor L&E incurred by employer

Establish programme and costs to complete works

Establish employers preferred way forward:


o

Terminate contract and employ others to complete

Novation

New contract

Terminate contract and do no further work on project

Allow contractor to continue to complete works

Insolvency practitioner may novate contract to new contractor

Employer insolvency:
-

Inform contractor (to enable termination)

Secure site

Assess contractors final account

Contractors works suspended

Contractor goes on list of creditors

Termination By Employer
For default by Contractor:
-

If contractor continues to default from 14 days of CAs notice, or repeats default

Defaults are:
o

Without reasonable cause wholly or substantially suspends works or design


of CDP

Fails to proceed regularly and diligently with the works or design of CDP

Refuses or neglects to comply with instruction to remove work not in


accordance with contract and as a result works are materially affected

Fails to comply with clause 3.7 (sub-letting) or 7.1 (assignment)

Fails to comply with clause 3.25 (CDM Regs)

November 2008

75

Nadia Slattery
APC Revision Document

For insolvency of Contractor:


-

Client can terminate immediately

For corruption:
-

If contractor, or any persons employed by him, commits an offence under the


Prevention of Corruption Acts

Consequences of Termination by Employer:


-

Employer may employ others to complete works (and use site, temporary buildings,
plant, materials etc)

Contractor must remove all temporary buildings, plant, tools etc (once instructed by
CA)

Contractor must provide 2 copies of all CDP documents

Contractor must assign benefits of any agreements for supply of materials and goods
within 14 days of termination

Provisions for payment and retention release cease to apply

After Completion of Works:


-

Account must be prepared for:


o

A = Expense incurred by employer

B = Amounts paid to contractor

C = Total amount which would have been paid in accordance with contract

If A + B is greater than C, then difference is a debt payable to due to employer (or


vice versa)

Employers Decision Not to Complete Works:


-

If 6 months after termination employer decides not to complete works then:


o

Notify contractor in writing

Prepare a statement setting out:

Total value of work executed at termination/insolvency

Aggregate amount of expenses incurred

Payments then due for difference between the two

Termination By Contractor
For default by Employer:
-

Failure to make payment

Interferes with or obstructs issue of any certificates due

Fails to comply with clause 7.1 (assignment)

Fails to comply with clause 3.25 (CDM Regs)

Continues to suspend works for 14 days from contractors notice for suspension for:

November 2008

76

Nadia Slattery
APC Revision Document

CAI for discrepancies, variations or postponement

Impediment, prevention or default by employer or his persons

Note: default suspension period in contract is 2 months

For insolvency of Employer:


-

Contractor can terminate immediately

Termination By Either Party


Either party may terminate if works are suspended for a further 7 days after notice of
suspension for:
-

Force majeure (acts of God)

CAI for discrepancies, variations or postponement

Loss or damage due to Specified Perils (fire, flood, lightning etc)

Civil commotion or terrorism

Exercise after Base Date by government of any statutory power

Note: default suspension period in contract is 2 months

Consequences of Termination by Contractor or by Either Party


-

Provisions for payment and retention release cease to apply

Contractor shall remove all temporary buildings, plant, tools etc

Contractor must provide 2 copies of all CDP documents

Contractor (or maybe Employer where terminated by either party) must prepare an
account within 2 months for:
o

Total value of work executed at termination

Any sums for loss and expense incurred for antiquities or relevant matters

Reasonable cost of removing items from site

Cost of materials or good the contractor has paid or is legally bound to pay

Any direct L&E caused by the termination (only if due to default or insolvency
of employer or specified perils due to negligence of employer)

After taking into account pervious payments, Employer must make any payments due
within 28 days

Fluctuation Clauses
-

Passes risk for change onto client

Items are paid for on a cost-reimbursement basis (not fixed price)

Does not apply to a Schedule 2 Quotation

Three options:
o

Option A (Default) Contribution, levy and tax fluctuations

Option B Labour and materials costs and tax fluctuations

November 2008

77

Nadia Slattery
APC Revision Document

Option C Formula adjustment uses a price adjustment formula

Named / Nominated Subcontractors


-

Nomination no longer in use under JCT 05

Can still list contractors under clause 3.8

select from list at discretion of contractor

not less than three subcontractors

can add additional persons to list with consent of other party

appointed subcontractor becomes a domestic subcontractor

Executing Contract
-

Affects limitation period for instituting proceedings

Under hand
o

6 years

As a deed
o

November 2008

12 years

78

Nadia Slattery
APC Revision Document

T022 Design Economics & Cost Planning (Level 3)


The factors that influence the construction costs of a particular design.

General
Investment Appraisal aid to decision-making with the objective of achieving the maximum
return from an investment

Project Appraisal exploring the benefits of a project and evaluating the need in comparison
with the costs involved

Shell and Core


-

Frame and external envelope

Finished core
o

Reception

Toilets

Circulation

Plant rooms

Fit out of landlords areas

Internal partitions separating landlords from tenant areas

Plant / services installations to landlords areas

Category A (Developer Fit-Out)


-

Fit out works to the functional areas

Works to tenant areas


o

M&E beyond risers

Raised floors

Suspended ceilings

Floor, wall and ceiling finishes

Category B (User Fit-Out)


-

Further specific fitting out executed by tenant

To make functional areas work for tenants business needs


o

Internal partitions to tenant areas

Decoration and branding

Installation of below floor power distribution and data cabling

Tenant standby generators and UPS

IT and telecommunications installation

Fittings and furnishings and office equipment

November 2008

79

Nadia Slattery
APC Revision Document

RIBA Outline Plan of Work 2007


A Appraisal
B Design Brief
C Concept
D Design Development
E Technical Design
F Production Information
G Tender Documentation
H Tender Action
J Mobilisation
K Construction to Practical Completion
L Post Practical Completion

Economics of Design
Cost drivers are things which influence or affect costs:

Abnormals ground conditions (remediation, water table), basements, special


architectural features

Atria these affect nett:gross ratios and also additional foundations, atrium roof
(solid/glazed), atrium roof/wall cleaning system, floor edge details, balustrades etc

Structural grid the cost of a structural frame (whether concrete or steel) is


governed by extent of abnormal spans and loadings

Structural design loads i.e. plant room areas require significantly higher load
capacities; abnormal stiffening requirements associated with core design; cantilever
structures

Wall : floor ratio the complexity/intricacy of the faade will have a direct effect on
the wall:floor ratio. This is a significant cost issue as external walls usually form 2025% of overall cost. A reasonable ratio would be in the order of 0.40, with 0.35 being
regarded as very efficient. Significant articulation/indentation can push the ratio to
0.50.

Example:
A 0.05 increase in the wall:floor ratio of a 100,000ft2 building, with a faade cost of
450/m2 will result in a circa 4% increase in the total shell and core cost.

November 2008

80

Nadia Slattery
APC Revision Document

Type of faade the type of cladding system specified will determine the cost of the
external walls i.e. unitised curtain walling -v- panel system with strip windows

Storey height Affects the overall cost, particularly with regard to external walls and
structure. Made up of two dimensions 1) the sandwich of the suspended ceiling,
structural floor and raised floor and 2) floor-to-ceiling height of the office space
between.

Example:
Each additional 100mm on the storey height can add between 0.50 and 0.75% to the
total shell and core cost, and conversely for each reduction.

Services Services form 15-25% of the total shell and core cost. Type of air
conditioning system specified is a significant key cost driver.

Types of air con system:

Chilled beams and ceilings

Four-pipe fan coil

Variable Air Volume

Variable Refrigerant Volume

Nett : Gross Ratio / Planning efficiency the higher the ratio, the more efficient the
building (best achievable approx. 85%)

Plan shape This relates to wall:floor and nett:gross, the most efficient shape being
circular with a central core i.e. doughnut shape

Definition of an Estimate
-

An accurate assessment of the cost of a project

Ensuring that:
o

the clients objectives are met

the teams aspirations are achieved

value for money is maintained

Who Needs Estimates?


-

Developers
o

Purchase of land

Development appraisals

Tenant agreements

November 2008

81

Nadia Slattery
APC Revision Document

Funders
o

Security of investment

Tenants
o

Cost of occupancy

Cost of tenant enhancements

Cost of fitting out

Designers
o

Surety of scope

Design within budget

Quality check

Types of Estimate
-

Feasibility Estimate
o

Indicative cost of future project

Based on /m2 GIA or /unit rate

RIBA Stage A/B

Largely based on historical data (benchmarking)

High dependence on assumptions

Stated as a cost range in /m2 or /functional unit

Initial or Preliminary Estimate


o

Early stage cost plan

Based on /m2 elemental breakdown

RIBA stage C/D

Largely based on historical data (cost analysis)

Medium dependence on assumptions

Stated as an order of cost

Cost Plan
o

Detailed anticipated cost of work

Based on detailed measure items (quantities) /m2 per item

RIBA stage D/E

Based on subcontractor quotations and built up rates

Medium dependence on assumptions

Stated as an outturn cost

Cost Models
-

Considered estimate based on limited information and benchmarked information


RIBA Stage A/B

November 2008

82

Nadia Slattery
APC Revision Document

Components of an Estimate
-

Cover and contents

Summary

Basis

Assumptions

Exclusions

Schedule of areas

Detailed breakdown of estimate (element, quantity, unit, rate)

Important to:
-

Communicate cost plan to client


o

sit them down and talk them through the entire cost plan in detail

Reconciliation
o

ensure differences between cost plan revisions are identified and explained
to all parties

Identify areas of uncertainty and risk and subsequent contingency allowances

Managing contingencies
o

As detail develops you replace contingencies and risk with firm costings,
where appropriate

Information Required to Prepare an Estimate (dependant on RIBA Stage)


-

Drawings

Specification

Area schedule

Location

Programme

Demolition / enabling works required

Services / infrastructure

Budget

Level of detail required

Items included within an Estimate


-

Build costs

Preliminaries (usually a %)

OH&P (usually a %)

Design reserve / contingency

Basis (information used)

Assumptions

Exclusions

November 2008

83

Nadia Slattery
APC Revision Document

Exclusions from an Estimate


-

Any items not included within the estimate


o

Items for which separate allowance should be made

Items which may be required

Items thought not to be required

Must be relevant and logical (or will affect credibility of the estimate)

Can include the following:


o

Client costs

Site acquisition costs

Finance costs

Legal fees, professional fees, planning fees

Site investigations and site surveys

VAT

Any usual client direct costs

Procurement risks

Inflation beyond price date

Exchange rates

Design responsibility

Changes in market conditions

Building / Site risks

Abnormal ground conditions

Occupied sites

Accessibility

Third party risks

Planning consent

Building control

Sources of Cost Data


-

Market testing

Benchmarking studies

Previous estimates, rates from BQs and cost plans

In-house database i.e. National Cost Database, Office Specialist Group


benchmarking

BCIS database subsidiary of RICS, member firms submit completed cost analyses
on tender returns which inform the database (in much the same way as DLs NCD)

Price books i.e. Spons, Laxtons

Published cost data i.e. Building Magazine articles

Clients own cost data

November 2008

84

Nadia Slattery
APC Revision Document

Considerations When Using Sources of Cost Data


-

Check basis of the rate


o

Specification

Economies of scale

Special conditions

Check the coverage of the rate


o

Is it comprehensive

Location factors
o

Do you need to update for change in location

Location factors published in Spons

Market Inflation / Indexation


o

Tender Price Inflation (TPI)

Records and predicts market conditions (labour, materials, economic


climate, inflation)

Prices tendered for construction projects

Inclusive of labour, plant, materials, preliminaries and OH&P

Use TPI up to construction phase

Building Cost Inflation (BCI)

Actual costs

Monitors and predicts building costs considering labour, materials


and plant

Contractors costs i.e. labour, plant and materials rates

Use BCI during construction phase

Risk / Contingency in a Cost Plan


How do you deal with risk in a cost plan?
-

Provide contingency to cover unforeseen risks

Analyse and cost each risk

Include provisional sums or prime cost sums explain these to the client

As design develops, risk should be designed out or mitigated to a manageable level

Contingency levels in estimates:


o

10% - 15% at feasibility

5% -10% during cost planning stage

2.5% - 5% at tender stage

November 2008

85

Nadia Slattery
APC Revision Document

Contingency Post-Contract
-

Four categories:
o

Design Reserve to fund unavoidable design development from tender to


when design is complete

Contract Contingency to cover contract instructions emanating from


design team

Project Risk Reserve separate fund to cover any eventuality highlighted


within the risk register (where not covered in separate allowance elsewhere)

Client Contingency reserve purely to fund changes instigated by the client

Not to be used for items incapable of pricing (prov sums are for this purpose)

Level of contingency also needs to take into account:


o

Type and complexity of project (new build vs. refurb)

Information available for tender documentation

Scope of unknowns which may affect the contract

Managing budgets
If cost plan is over budget?
-

Ensure you have explained cost plan in detail

Approach matter positively

Identify areas of potential savings i.e. materials specifications, buildability, re-design

Value engineer alongside the rest of the design team

Risk
A risk can be defined as an uncertain event or circumstance that, if it occurs, will have an
affect on the projects objectives.

Risk Management
-

PROACTIVE

Identification, analysis and effective ongoing management response to risks

Manage, minimise, share or transfer

Eliminate, reduce, insure, contain

Design to avoid

Opportunities reduce with time

Risk Analysis
-

Qualitative
o

Based upon experience

A subjective assessment in terms of impact and likelihood

Use of risk analysis matrices i.e. high likelihood, low impact etc

November 2008

86

Nadia Slattery
APC Revision Document

Quantitative
o

Potential to use probabilistic analysis i.e. computer simulation

Monte Carlo simulation

Pre-Contract Risk Management Schedule / Risk Workshop


-

Identification
o

Description of risk (cause)

Consequence (effect)

Analysis (Qualitative Assessment)


o

Risk type (design, procurement, infrastructure)

Likelihood

Impact (cost, time, quality)

= risk level/ status

Allocation
o

Party / individual responsible / in control

Action planned or taken

Response
o

Mitigation method (reduce / mitigate / transfer / hold)

Monitor of current situation

Value Management
-

PROACTIVE

How?
o

Define what value means to client

Communicating it clearly to project delivery team

Maximising delivery benefits

Minimising use of resources

Maximising performance

Understanding project objectives

Efficient use of resources

Minimising cost / waste

Process of refining the performance and cost so as to produce optimum value for
money

Value Engineering
-

REACTIVE

Deliver required function at desired quality for least cost

Specific technique to optimise cost-effectiveness of an existing design

November 2008

87

Nadia Slattery
APC Revision Document

How?
o

Use resources more efficiently (people, time, money)

Establish lowest cost whilst retaining function

Drive out unnecessary cost

Life Cycle Costing


General:
-

Consideration of costs over the whole life of a building not just the capital costs i.e.
understanding both capital and running costs

Consideration of capital cost against maintenance costs / replacement costs

Understanding the clients requirements in terms of capital and lifetime costs

The 3 Rs Running, Repairs, Replacement

Example: uPVC -v- metal rainwater goods

Process:
-

Identify capital cost of alternative systems

Examine long term costs i.e. maintenance and replacement cycles

Speak to manufacturers or other specialists

Prepare recommendation

Whole Life Costing


-

The consideration of all relevant costs and revenues associated with the construction
and ownership of a building

Main Cost Headings to Consider:


-

Capital costs
o

Cost of the building

Associated site works

Infrastructure costs

Project on-costs i.e. fees, decanting costs etc

Life-cycle costs
o

Asset replacement for building and associated prelims and management


costs

Operational costs
o

Utilities

Cleaning

Administration

Security

Support services

Business costs i.e. rent, salaries and income

November 2008

88

Nadia Slattery
APC Revision Document

Maintenance costs
o

Planned service maintenance

Building fabric maintenance

Disposal costs
o

Including decommissioning the building at the end of its useful life

Capital Allowances
-

Incentive to encourage investment

Tax relief on capital expenditure for acquiring, constructing, refurbishing or fitting out
a property

Capital expenditure for qualifying items can be deducted from companies taxable
profit therefore reducing the tax bill

Who can claim?


o

Investors

Owners

Tenants for fitting out

Who cant claim?


o

Charities

Developers although can be used as an incentive to sell the building

Rate of deduction depends on nature of allowance

Plant and machinery

Asbestos removal

Blinds, carpets, suspended ceilings, raised floors

Demountable partitions

Loose furniture

Air con, hot water installation, BMS, lifts, security, fire

Door handles!

Enhanced capital allowances (100% first year allowance) for energy saving green
plant and machinery

Land remediation
o

150% relief

hydrocarbons, asbestos, fuel storage tanks, contaminated ground water

VAT
-

All building works subject to 17.5% VAT but

0% on new build residential, alterations to existing, conversions to residential and


charity work

0% on demolitions related to 0% rated construction, otherwise standard rate applies

5% on refurbishments, conversions and renovations

November 2008

89

Nadia Slattery
APC Revision Document

T062 Procurement & Tendering (Level 3)


Procurement
General:
-

Procurement The way in which a project is bought.

Procurement strategy can have a major impact on the time and cost of a project.

Procurement routes are traditional, design and build etc

Tender options are single stage, two-stage, open, negotiated etc

Key Procurement Considerations


-

Cost
o

Cost certainty

Importance of budget

Time
o

Is timescale worth a cost premium?

How important is commitment to programme?

Quality
o

Importance of quality

Control over subcontractors

Risk and Responsibility


o

Pay premium to avoid risks / risk profile of client

Single vs. multi point responsibility

Are client changes likely?

Level of design information

Contractor input

Complexity

Clients experience / knowledge

Clients required involvement

Life cycle costs / costs-in-use

i.e. end user client more concerned with buildings functionality and cost-in-use with quality
being primary concern

whereas, developer client more influenced by market conditions and being able to get best
product to market as quickly as possible with time being primary concern

COST + QUALITY

TRADITIONAL ( TIME)

COST + TIME

D&B ( QUALITY)

TIME + QUALITY

MANAGEMENT ( COST)

November 2008

90

Nadia Slattery
APC Revision Document

Risk Transfer

Employer

Shared

Contractor

Management

Traditional

D&B

Types of Procurement
Traditional
-

Contractors tender based on a complete design produced by consultants

May include provisional sums where there are gaps in the information

Assuming no significant changes, construction costs can be determined with


reasonable certainty before work begins

Pricing documents provided (i.e. BoQ, spec and drgs, schedule of rates)

Two variants are:


o

Sequential contractor submits tender once design is fixed

Accelerated contractor appointed at an early stage in design process

Advantages
-

Disadvantages

Design led so high level of design

quality
-

No overlap between design and


construction

Reasonable price certainty at contract

award

Design risk is with client (he directly


employs team)

Single point of contractual contact

Relative lack of flexibility

Contract has strong commitment to

Often adversarial relationships

complete on time (LADs apply)

dependant on culture of team

Contractor assumes financial risk

Poor info can lead to conflict

With BoQ, vos easy to price

No buildability input from contractor

Contractor carries programme and


financial risk

Reasonable price certainty from outset

Contractor has strong commitment to


complete on time

Single point of contractual contract

If BoQ, variations can be priced easily

November 2008

91

Nadia Slattery
APC Revision Document

Design and Build


-

Contractors assumes the risk and responsibility for designing and building the project
in return for a lump sum

Design team appointed to compile clients brief and produce set of ERs

ERs must be sufficiently comprehensive to explain precise needs of client

ERs must give contractors freedom to make use of their design, technical and
management expertise

Tenderers return their Contractors Proposals (CPs)

In standard contract CPs take precedence over ERs, unless amended (as DL do)

Tender return should include a Contract Sum Analysis to aid tender evaluation and
future valuations

Employers Agent appointed to represent the Clients interests

Original design team may be novated or contractor may appoint his own team

Variants include:
o

Direct a designer/contractor is appointed without competition

Competitive limited nr of contractors submit tender in competition

Develop and construct contractors develop and complete the design

GMP contractors offer a GMP and share any savings

Advantages
-

Disadvantages

Single point of responsibility

Client changes can be difficult to value


and expensive

Design and construction risk rests with

contractor

Client has to commit before detailed


design is complete

Inherent buildability is achieved

Bids may be difficult to compare

Price certainty achieved before

No design overview process unless client

construction starts
-

appoints consultants to do so

Design and construction overlapped

May be difficult for client to prepare an


adequate brief

Client as less control over


aesthetic/quality

Tenders are costly to prepare so needs to


be of reasonable value to interest
contractors

Novation
o

the contractor accepts responsibility for whole project, including the initial
work carried out prior to novation

client may employ another designer to examine the scheme from his
perspective

November 2008

92

Nadia Slattery
APC Revision Document

Construction Management
-

Client employs services of a Construction Manager as a member of the design team

All individual trade package contracts are placed directly with client

CM has no contractual links with the trade contractors

No single point of responsibility for risk

CM programmes and coordinates the design and construction activities and offers
buildability advice

CM offers professional expertise without assuming financial or programme risk

Suitable for large and complex projects

Advantages
-

Disadvantages

Design and construction overlapped so

programme reduced
-

package placed

Allows for buildability and programme

advice
-

Tendered contracts should achieve

Breakdown of traditionally adversarial

Trade packages can be let

Interfaces between packages must be


managed carefully

Open book procedure for tendering

packages
-

Strict time and information control is


required

competitively or negotiated
-

Client (not CM) is responsible for cost or


time

barriers
-

Requires an informed and proactive client


to be successful

more competitive prices


-

Price certainty not achieved until last

Flaws in design may not become


apparent until a later date

Decision on appointments of TCs made

Multi point accountability

CM prime costs (e.g. prelims) must be

jointly by designers and CM


-

Changes can be accommodated later


i.e. tenant fit-out

controlled due to risk of duplication of


costs with TCs

Management Contracting
-

Client employs services of a Management Contractor as member of the design team

MC sits contractually between the Client and trade contractors

MC takes responsibility for the works without actually carrying out the works

Suitable for medium/large projects where design information is not available at starton-site

Advantages
-

Disadvantages

Single point responsibility

Price certainty not achieved until last


package placed

Design and construction overlapped so

November 2008

93

Requires an informed and proactive client

Nadia Slattery
APC Revision Document

programme reduced
-

to be successful

Allows for buildability and programme

advice
-

Client and design team are remote from


trade contractors

Breakdown of traditionally adversarial

Less open book than CM

Client (not MC) is responsible for cost

barriers
-

Trade packages are let competitively


and transparently

Changes can be accommodated later


i.e. tenant fit-out

Unlike CM, MC carries out most of


administrative work

Facility to agree a lump sum for MCs


organisation costs

MC responsible for time (LADs apply)

Guaranteed Maximum Price (GMP)


-

A lump sum contract under which there are no adjustment of tender price except for
client variations

Contractor allows for design development risk in his tender

Can be single or two-stage

Savings made on packages are shared on an agreed basis pain/gain share but
extras are the contractors responsibility

Client variations are a cost to the client.

Advantages

Disadvantages

Price certainty and control

Risk client pays too much

Contractor carries design development

Risk of high tender value as client is

risk
-

Pre-agreement of changes

Greater control of overspending

Quicker settlement of final account

paying for contractors risk allowance


-

Scope changes tend to be exploited

Design and Manage


-

Combination of design and build and management contracts

A single firm is appointed to design and manage the building but construction work is
tendered to specialist contractors

Contractor-led design and management is more common than consultant-led

Client will normally employ an independent Architect and QS to protect their interest
in terms of quality and cost

November 2008

94

Nadia Slattery
APC Revision Document

Turnkey
-

One company appointed to deliver building (the product) from inception to


completion right up to the client moving in

A one-stop shop solution

Design-build-finance-operate (DBFO)

Build-operate-transfer (BOT)

Build-own-operate-transfer (BOOT)

Measured Term
-

Used on major maintenance projects

Contract will apply loosely to predefined work

Often limited to a fixed timescale

Serial Contracting
-

Development of the system of negotiating further contracts where a firm has


successfully completed a contract for a project of a similar type

Initially contractors tender competitively for a single project, on the legal


understanding that a number of other similar projects will be automatically awarded
using the same prices

Only adjustment would be for fluctuations in price to cover inflation

Conditions usually included to prohibit awarding of further work in case of poor


performance

Should result in lower prices for client

Suitable for school building projects, restaurant chains etc

Prime Cost / Reimbursable


-

Contractor carries out works and is paid actual cost of labour, plant and materials
plus either a pre-agreed percentage or fixed fee to cover his establishment costs and
OH&P

Suitable for maintenance or refurbishment works where extent is unknown until


exposed or emergency work or resolution of a difficult project

Can be carried out as target cost (see below)

Advantages

Disadvantages

Enables early start on site

No time or cost certainty

No premiums for abnormal risks in

No incentive for efficiency

Difficult to monitor true costs

tender
-

Flexibility to alter design, programme


and quantum of work

November 2008

95

Nadia Slattery
APC Revision Document

Target Cost
-

Contractor receives a bonus if contract completed under the target but a penalty if its
over

Public Private Partnership PPP


-

Generic term for relationships formed between private sector and public bodies

Often with aim of introducing private sector resources/expertise in order to help


deliver public sector assets and services

Private Finance Initiative PFI


-

A form of PPP

Also a form of contracting or procurement the hallmarks of which are:


o

A long term service contract between a public sector body and private sector
operator

Provision of capital assets and associated services by the operator

A single unitary payment from the local authority which covers investment
and services

The integration of DBFO into the operators proposals

Allocation of risk to party best able to manage and price it

Service delivery against performance standards set out in an output spec

A performance related payment mechanism

An off balance sheet treatment for the LA so any investment delivered


through the project does not count against borrowing consents

o
-

Support from central govt delivered through PFI credits

The objectives of PFI can be described as:


o

Risk transfer risk transferred from public to private sectors

Value for money greater level of innovation and entrepreneurial input by


the private sector should improve quality and value for money

Funding transferring financial risks to private sector reduces impact on


public sector borrowing requirements

Advantages

Disadvantages

Risk transfer

Scope for inappropriate allocation of risks

Value for money

Loss of control

Funding requirements reduced

Definition of functional/service
requirements is crucial

Partnering
-

Project partnering one-off project

Strategic partnering series of projects, long term relationship

November 2008

96

Nadia Slattery
APC Revision Document

Structured management approach to enable team working across common


contractual boundaries

Mutual aims and objectives

Requires transparency and openness in matters such as cost and performance

Agreed method of problem resolution

The agreement requires commitment

Search for continuous measured improvement

Ideal when there is a flow of future projects

Framework Agreements
-

Preferential costs and rates for long term delivery arrangement

Repeat work

Only negotiate once, rates secured

Guarantee of work stream for contractor

Non-adversarial

Doesnt always deliver value for money

----------------------------------------------------------------------------------------------------------------

Tendering
General:
-

Tendering The way in which a contractor is selected.

Procurement routes are traditional, design and build etc

Tender options are single stage, two-stage, open, negotiated etc

Key Tendering Considerations


-

Nature, size, complexity of project

Value of main contract

Public or private client

Time period allowed

Competition is desirable

Negotiation involves a premium cost (of 5%-20%)

Tender documents must be

The most detailed possible

The most accurate possible

Have the least amount of items unresolved

The best basis for contract management

The best basis for cost control

Published codes of procedure (NJCC, CIB, JCT)

November 2008

97

Nadia Slattery
APC Revision Document

Types of Tendering
Open / Competitive Tendering
-

Client wants to obtain unrestricted tenders

Seldom used today as recognised it is a wasteful practice

Tenders attract a premium due to low success rate

Advantages
-

Disadvantages

Cheapest tender available (in theory)

but high tendering costs due to low

No control over suitability and


competence of firms who tender

success rate

Most reputable contractors avoid it

Generally accepted that large time and


cost overrun

Single Stage Selective Tendering


-

Competitive tenders sought on basis of completed design

Contractors selected for their competence and interest in job

Ability to select appropriate nr of tenderers (4 to 6)

Costs reduced as higher success rate

Employer ought to be able to accept lowest bona fide tenderer

Advantages
-

Disadvantages

Tenderers selected on competence and

interest
-

Longer programme as design must be


completed first

Costs reduced

Two-Stage Selective Tendering


-

Competitive tenders first sought on basis of preliminary tendering documents,


covering preliminary design information

Contractor selected on basis of cost of prelims and OH&P and a pre-construction fee
based on provisional sum allowances for works

Works are then packaged and tendered during pre-construction phase

Contract sum agreed at an appropriate time

Potential for GMP

Allows early appointment of contractor to work in parallel with design team

Ideal for achieving buildability

Premium paid for negotiations

Nr of tenderers at first stage 4 to 6

November 2008

98

Nadia Slattery
APC Revision Document

Advantages
-

Disadvantages

Early appointment of contractor, to work

alongside design team

Cost premium as invariably preliminary


tendering document is inadequate or
circumstances change significantly

Risk premium can occur as certain items


are not tied down until contract sum is
agreed

Negotiated
-

Single contractor selected to negotiate price with

Can negotiate with more than one contractor for competitiveness

Early contractor involvement

Allows flexibility of design development as construction proceeds

Less cost certainty prior to commitment

Main contractor competition eliminated but subcontractors tendered in competition

Advantages

Disadvantages

Early contractor involvement

Less cost certainty before commitment

Allows flexibility for design development

Cost premium to be paid

Possibility of developing better

Main Contractor competition is eliminated

relationships with team

but up to 80% of tender can be obtained


in competition from sub-contractor
-

Possibility of delay if contract negotiations


are protracted

Dutch Auction (also known as reverse bidding)


-

Tenderers in an auction situation, in knowledge of lowest tender / required sum

In competition against one another

Offering lower tender sums with no change in scope of works

May have a detrimental effect on quality of finished building

No method behind cost cutting

Can make contractors claim conscious during contract period

E-Tendering
-

Electronic exchange of tender documents

Reduces admin

More sustainable and streamlined process

Quicker

Cheaper RICS guidance note exists

November 2008

99

Nadia Slattery
APC Revision Document

Joint Venture Tendering


-

Partnership between two or more companies

Each participating company has joint and several liability for the contractual
obligations to the employer

Serial Tendering
-

Series of contracts let to a single contractor

The individual projects tend to be of same size

Where possible cost benefits should be established during competitive stage of


tender process

Disadvantage can be when projects differ in scope requiring cost effect of differences
to be ascertained

Term Contract
-

Employer agrees to order and indefinite amount of work during a fixed period

Useful of maintenance contracts where employer has large amount of property


requiring periodic renovation

Gives employer a simple method of procurement for individual projects

Contract can be terminated without incurring sanction


o

Employer can cease to issue fresh orders for work

Contractor can refuse to accept further work orders

OJEU (Official Journal of European Union)


-

For public works / services / supplies

Contracts awarded on basis of lowest price of most economically advantageous


tender

Requires publication of contract notice in the OJEU is estimated value:


o

5,150,000 for public works (central govt bodies)

133,000 for public services / supplies (central govt bodies)

Tendering Codes and Practice Notes


NJCC Codes of Procedure for Single Stage Tendering
-

Produced by National Joint Consultative Committee for Building

NJCC voluntarily dissolved in 27 June 2006 but code still used

Recommends that, irrespective of the size of the contract, tender list should contain
not more than six names

Recommends the lowest valid tender is recommended to employer for acceptance

November 2008

100

Nadia Slattery
APC Revision Document

Construction Industry Board Code of Practice for Selection of Main Contractors


-

Published by CIB in May 1997

Not as widely adopted as NJCC code

CIB ceased to exist on 29 June 2001 but code still published

Both publications codify the principles of good practice relating to selection of contractors
from preliminary enquiry to notification of results.

JCT Practice Note 6


-

Produced by Joint Contracts Tribunal

Intended to be successor to NJCC

Primarily concerned with main contract tendering procedure

Identifies procedure for tendering

Recommends that:

Construct only maximum of 6, ideally 3 or 4 tenderers

Design and Construct maximum of 3 tenderers

JCT recommends that the lowest or best value, valid tender is accepted should be
recommended to employer for acceptance

Tender Process
-

Preliminary enquiry (by letter) to proposed tenderers to confirm their interest

Prequalification

Tender procedure:

Tender documents and invitation

Tender period

Tender compliance

Tender assessment
o

Opening tenders

Examination and adjustment of the priced document

Negotiation

Tender report

Notification of results

Compilation of Tender Lists


Points to consider when selecting contractors to tender:
-

Experience of similar contracts

Experience of chosen procurement / contractual route

Past experience
o

Past projects (type, size and complexity)

Past performance (on time / on budget / approach)

November 2008

101

Nadia Slattery
APC Revision Document

Competence

Reputation for quality / QA policy

Reputation for timeous completion

Reputation for claims

Financial stability (credit check / accounts / turnover)

Size of company

Age of company

H&S policy and record

Current workload

Compilation of Tender Documents


Traditional:
-

Invitation letter

Instructions to tenderers

Form of tender

Certificate of bona fide tender

Design information (drawings / specification)

Pre-construction information

Preliminaries

Pricing document

BoQ

Schedule of works

Mini bill (an abbreviated summary of descriptions and quantities)

Conditions of contract
o

Amendments

Bonds

Warranties

Return envelope / label

Design and Build:


-

Invitation letter

Form of tender

Certificate of bona fide tender

Employers requirements

Concept design information

Programme

Pre-construction information

Preliminaries

Contract sum analysis for contractor to price

Return envelope / label

November 2008

102

Nadia Slattery
APC Revision Document

Action during Tender Period


-

Withdrawal
o

Extension
o

Refer to client

Queries
o

Keep a record

Notify all tenderers of response to prevent any unfair advantage

Correspondence
o

Refer to client

Keep a record of all correspondence with tenderers

Mid-Tender Interviews
o

Relatively common in tendering CM/MC trade contract packages

Less common (or necessary) on lump sum tenders

Record meeting

Communicate any questions/answers in writing to all tenderers

Any variations made to tender documentation during the tender period must
be sent in writing to all tenderers

Each tenderer must confirm in writing that the variation has been reflected in
their tender

Pre-Tender Estimate
o

Can take two forms

Adjust cost plan to reflect cost checks on the tender docs

Price the tender pricing document (particularly where BoQ or


schedules)

Late Tenders
o

Compromise tender procedure

Should not be accepted

Opening Tenders
-

Open in front of client representative and/or design team

Record results on tender opening form and all present must sign

Circulate to design team

Check forms of tender

Check certificate of bona fide tender

Carry out tender analysis

Examining Tenders
-

Check all necessary information has been submitted

Check documentation has been completed correctly

Check amendments notified to tenderer have been made

November 2008

103

Nadia Slattery
APC Revision Document

Check no unauthorised amendments have been made

Check all items have been priced

Check total in pricing documents equals total on form of tender

Checking pricing document is mathematically correct

Check everything priced in sufficient detail

Check rates and prices are reasonable and sensible

Check pricing is consistent throughout document

Check daywork percentages are reasonable

Check allowance for bonds are reasonable

Resolve qualifications

Check proposals for contractor designed work

Tender Analysis
-

Arithmetical errors:
o

Alternative 1 Correction not permitted

Alternative 2 Correction is permitted

Stand by original figure or withdraw

Stand by original figure, withdraw or amend (genuine error)

Front loaded tenders:


o

Not a pricing error

Request contractor removes front loading

If refuse, tender is not bona fide

Could use Advanced Payment Bond as an alternative

Tender evaluation
o

Comparison of tenders

Check for errors / inconsistencies

Compare with PTE

Check for qualifications

Include plugs where tenderers not priced element so comparing like-for-like

Contractor advises an error in clients favour?


o

Inform client

Generally dont accept as seen as an extension to tender period

Check if genuine

If yes, extend to other contractors tender period

If no, recommend rejection

Assessing D&B tenders:


o

Check CPs meet ERs

Interview tenderers to fully establish their proposals

November 2008

104

Nadia Slattery
APC Revision Document

Reasons to Re-Tender
-

Not enough tenders returned

Procedure was compromised in some way

Significant design changes

Note: NJCC does not recommend re-tendering price alone

Tender Reports
Should be completed without delay, taking account for:
-

Tender acceptance period

Clients procedure for authorising acceptance of a tender

Project programme

Content should include:


-

Basis of tender
o

Brief description of works

Form of contract

Pricing documentation

Tender period

Extensions / addendum to tender

Tenders invited
o

Original list

Substitute tenderers

Returned tenders

Alternative tenders

Review of tenders
o

Lowest valid tender

Reasons for rejecting lowest tender

Errors / qualifications

Resolution / outstanding issues

Comment on pricing level

Anticipated contract sum


o

Adjustments to tender

Contract sum build up

Reconciliation with PTE


o

Calculation of comparable sum

Comment / explanation of variance

November 2008

105

Nadia Slattery
APC Revision Document

Recommendation
o

Project teams view

Issues to be resolved

Risks

Also maybe:
o

Potential savings

Financial status of tenderers

Best Value
-

Concept that has come out of the Local Government Act (1999)

Sets out requirements that are expected

Concept being managed by the Audit Commission

It is a challenging performance framework placed on Local Authorities

Four Cs of best value:


o

Challenging

Comparing

Competing

Consulting

Supply Chain Management


-

No commonly accepted definition of supply chain management

Linkage of companies to turn series of basic materials, products or services into a


finished product for the client

Parties in the supply chain have a long-term objective to work together to deliver
added value to the client

Benefits of a well-managed supply chain include:


o

Simplification

Swifter project / product delivery

Risk reduction

Cost savings, sometimes significant

Improved visibility of the workload

Economies of scale for all parties

Traditional forms of procurement rely on choosing from a large number of suppliers,


with the aim of maintaining supplier competition and driving down costs

Supply-chain management has aim of setting up long-term relationships with


suppliers to develop leaner, value-adding and more efficient ways of working

Suppliers are encouraged to adopt similar managed relationships with their


suppliers, and so on ideally down the tiers of supply

November 2008

106

Nadia Slattery
APC Revision Document

Lean Construction
-

A derivative of the lean manufacturing process

A philosophy that is about managing and improving the construction process to


deliver profitably what the customer requires

Concerned with elimination of waste activities and processes that create no added
value

Doing more for less

Lean thinking delivering what clients want, on time and with zero defects

Lean principles:
o

Elimination of all kinds of waste

Specify value from the perspective of the ultimate customer

Identify the process that delivers what the customer values - the value stream

Eliminate all non-added value steps

Make remaining added value steps flow without interruption by managing


interfaces

Let the customer pull i.e. manufacture when needed adopt philosophy of
JIT management

o
-

Pursue perfection through continuous improvement

Lean construction techniques have been successfully applied in other industries

November 2008

107

Nadia Slattery
APC Revision Document

T067 Project Financial Control & Reporting (Level 3)


All Covered Elsewhere:
-

Post Contract Cost Control

Change Control Procedures / Change Control Forms

Cost Reporting / Cash Flows

Final Accounts

Loss & Expense

Risk Management

Value Management

Benchmarking / Best Value

November 2008

108

Nadia Slattery
APC Revision Document

T074 Quantification & Costing of Construction Works (Level 3)


Methods of Measurement
Why do we have SMM7?
-

Recognised method of measurement

More detailed

Less risk of omitting an item

Clarity as to what is deemed to be included

Code of Measuring Practice


-

Produced by RICS

Definitions for GEA, GIA, NIA

Recognised definitions

Clarity as to what is deemed to be included

Measurement from first principals


-

Quantify labour, plant and materials required to complete the works

Star Rate
-

Where works cannot be valued simply from contract rates, a star rate is built up using
contract rates as a basis

Bills of Quantities
BoQ consists of:
-

Preliminaries

Preambles (description of materials and workmanship to be employed)

Measured works

Provisional sums

PC sums

Dayworks

Appendices (bonds, warranties etc)

Advantages

Disadvantages

Easier post-contract cost control

Expensive

Easier tender analysis

Time consuming

Good for large, complex projects

Schedule of Rates
-

Nature and full extent of works unknown

November 2008

109

Nadia Slattery
APC Revision Document

Preliminaries
-

Measured in accordance with SMM7

Consists of:

Description of the nature of the works

Project particulars

Details of documentation

Contract details / bonds / warranties

Management procedures

QA procedures

Health and safety

Fixed costs
o

Paid when expended

Site set up and establishment, hoardings etc

Time related costs


o

Paid proportionate to contract period

Site staff and management, plant hire etc

Normally 8% - 15% of construction cost

Send to architect and client for verification

Prime Cost Sums


-

Presentation in accordance with SMM7 clause A51 (cross refers general rule 10.3)

Sum of money to be expended on works by nominated subcontractors or goods by


nominated suppliers

Contractor to add for profit and attendance

The following information shall be provided:


o

The nature and construction of the work

A statement of how and where the work is fixed to the building and what
other work is to be fixed thereto

Quantities which indicate the scope and extent of the work

Any specific limitations and the like in section A35

CA authorises expenditure

Provisional Sums
-

Work that cannot be accurately measured at tender stage (SMM7 rule 10)

Defined and measured in accordance with SMM7 clause A54 (in accordance with
general rule 10):
o

Defined Provisional Sum

where the item of work can be described and approximately


quantified to the extent that the contractor can make allowances

November 2008

110

Nadia Slattery
APC Revision Document

within their prelims and programme for the work

Items of Defined Work, accurately described in accordance with


SMM7 rule 10.3-4

Where execution differs from bill description, the effect on prelims and other
work will be treated as a variation

Undefined Provisional Sum

where the scope of work is unknown and cannot be adequately


described therefore the contractor is not able to make allowances
within their prelims or programme

SMM7 rule 10.6 states that contractor is deemed to have made no


allowance for programming and prelims in his tender

Expenditure results in EOT with prelims.

When calculating prov sums, allowance should be made for fluctuations up to point
work is carried out

CA authorises expenditure

Contractor Designed Portions


-

Where items of work to be designed by contractor

Contractor assumes design responsibility for those works

ERs set out criteria contractor must satisfy

Normally where there are interacting items of work

Tender return to include contractors proposals

CPs take precedence over ERs

Performance Specified Works


-

Sets out criteria contractor must satisfy

Only suitable for works of a simple nature or where non critical to visual outcomes

JCT05 omits separate clause for performance specified work


o

But provisions for contractor designed works remain largely unchanged

Just that now, all works requiring contractor design to be subject of full CDP

Tender return to include contractors statement as to how PS will be met

Statement takes precedence over PS

Makes it difficult to compare tenders

Increases tender period

November 2008

111

Nadia Slattery
APC Revision Document

Post-Contract Financial Reporting


General:
-

Overview of clients current financial commitment to project

Forecast of anticipated final expenditure

Final costs v original and current approved budgets

Used to outline, monitor and forecast project costs

Format:
-

Executive summary (including status of contingency allowance)

Basis

Exclusions

Risks

Adjustment of provisional sums

Variations instructed

Variations anticipated

Loss and Expense

November 2008

112

Nadia Slattery
APC Revision Document

T010 Commercial Management of Construction (Level 3)


All Covered Elsewhere:
-

Estimating

Establishing Budgets

Cash Flows

Reporting Financial Progress against Budget

Procurement of Labour

Procurement of Plant and Materials

Procurement of Sub-Contracts

Financial Management of Sub-Contracts

Financial Management of Multiple Projects

November 2008

113

Nadia Slattery
APC Revision Document

T016 Contract Administration (Level 3)


All Covered Elsewhere:
-

Standard Forms of Contract JCT, GC Works, ICE, NEC/ECC, ACA (PPC2000) etc

Roles and Responsibilities of Parties client, contractor, designers, QS

Roles and Responsibilities of Person Administering the Contract e.g. CA, Architect,
EA, PM, Engineer etc

Co-ordination of Parties

Design Co-ordination

Planning and Building Control

Health and Safety CDM

Monitoring Progress

Monitoring Quality

Insurances

Bonds / PCGs

Third Party Rights

Payment Provisions

Change Procedures

Sectional Completion / Partial Possession

Nominated / Named Subcontractors

Extensions of Time / Loss and Expense

Materials On / Off Site

Determination

Liquidated and Ascertained Damages

Practical Completion

Defects Liability Period

November 2008

114

Nadia Slattery
APC Revision Document

Topical / Current Issues


Current Market Conditions
-

Credit crunch
o

Difficult to get finance

Less demand for office space

UK housing market declining

Schemes less viable

Construction work slowing

Commercial orders 30% lower than same time last year

Predict activity to decrease 7% over next 3 years

Increased competition for work

TPI reducing

BCI increasing

Squeeze on contractors profit but competition still high

Lawyers predict increase in adjudication as a result

Insolvency set to increase

Emerging markets demand


o

Growth forecasts only scaled back modestly

Firm economic performance predicted

Commodity prices increasing

Demand for goods (i.e. steelwork) remains high

Current Materials Prices


-

Concrete
o

80 100/t to increase 10% in January due to increase in fuel and energy


costs

Reinforcement
o

Supply currently at 750 800/t, overall 1,300 - 1,350/t

More than doubled in 2008

o
-

Increase in European scrap prices by 95%

Escalating demand from Middle East

Prices predicted to drop by end of 2008

Steelwork
o

Prices increased by 60/t in April

Further increase of 80/t expected in 3Q and again in 4Q

November 2008

115

Anda mungkin juga menyukai