Version: Demo
QUESTION 1
Identify the missing word(s) from the following sentence. A project is a temporary organization that is
created for the purpose of delivering one or more business products according to an agreed?
A.
B.
C.
D.
Senior User
Business Case
Change
Cost
Correct Answer: B
QUESTION 2
According to PRINCE2, which of the following is a characteristic of a project compared to that of business
operations?
A.
B.
C.
D.
Incurs cost
Introduces business change
Delivers benefits
Creates products
Correct Answer: B
QUESTION 3
Which of the following is FALSE?
A.
B.
C.
D.
Correct Answer: A
QUESTION 4
According to PRINCE2, which of the following are the aspects of project performance to be managed?
A.
B.
C.
D.
Correct Answer: D
QUESTION 5
What environment does PRINCE2 assume?
A.
B.
C.
D.
Third party
Customer/Supplier
Fixed-price contract
Management and Specialist
Correct Answer: B
QUESTION 6
A characteristic of a project is that they come with an element of uncertainty. Which of the following
PRINCE2 themes will help with the identification and management of such uncertainty?
A.
B.
C.
D.
Quality
Risk
Change
Organization
Correct Answer: B
QUESTION 7
Which is a benefit of using PRINCE2?
A.
B.
C.
D.
Correct Answer: A
QUESTION 8
Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
A.
B.
C.
D.
Correct Answer: D
QUESTION 9
Which is NOT a PRINCE2 integrated element?
A.
B.
C.
D.
The principles
The techniques
The themes
Tailoring PRINCE2 to the project environment
Correct Answer: B
QUESTION 10
Which is a characteristic of a project?
A.
B.
C.
D.
Correct Answer: D
QUESTION 11
Which is one of the six aspects of project performance that needs to be managed?
A.
B.
C.
D.
Issues
People
Benefit
Tolerance
Correct Answer: C
QUESTION 12
Identify the missing words in the following sentence... A principle of PRINCE2 is that a project has defined
and agreed?
A.
B.
C.
D.
Correct Answer: A
QUESTION 13
Identify the missing words in the following sentence... A PRINCE2 project is and controlled on a stage-bystage basis?
A.
B.
C.
D.
Planned, monitored
Developed, reported
Designed, assigned
Planned, produced
Correct Answer: A
QUESTION 14
Identify the missing word in the following sentence... A PRINCE2 project has defined for each project
objective to establish limits of delegated authority?
A.
B.
C.
D.
Allowances
Tolerances
Roles
Deviations
Correct Answer: B
QUESTION 15
Identify the missing word in the following sentence... A PRINCE2 project focuses on the definition and
delivery of, in particular their quality requirements?
A.
B.
C.
D.
Benefits
Products
Activities
Outcomes
Correct Answer: B
QUESTION 16
Which of the following is a TRUE principle of a PRINCE2 project?
A.
B.
C.
D.
Correct Answer: B
QUESTION 17
Identify the missing words in the following sentence... A Project is a that is created for the purpose of
delivering one or more business products according to an agreed Business Case?
A.
B.
C.
D.
Temporary organization
Skilled environment
One-off Endeavour
Unique team of stakeholders
Correct Answer: A
QUESTION 18
Which of the following statements is TRUE?
A.
B.
C.
D.
Correct Answer: B
QUESTION 19
Which of the following statements is FALSE? PRINCE2 provides projects with . . .
A.
B.
C.
D.
Correct Answer: C
QUESTION 20
Which of the following does PRINCE2 recognize as being project characteristics?
1. Projects are the means by which we introduce business change
2. Projects have a defined start and end
3. No project is unique
4. Projects often cross the normal functional divisions within an organization
A.
B.
C.
D.
1, 2, 3
1, 2, 4
1, 3, 4
2, 3, 4
Correct Answer: B
QUESTION 21
The PRINCE2 principle 'continued business justification' states that a requirement for a project is that...
There is justifiable reason to start the project and justification should remain valid throughout the life of the
project. Which one of the following does PRINCE2 also state for this principle?
A.
B.
C.
D.
Correct Answer: D
QUESTION 22
Which of the following PRINCE2 elements are described as being the aspects of project management that
must be addressed continually and in parallel throughout the project?
A.
B.
C.
D.
The Principles
The Processes
The Themes
Tailoring PRINCE2 to the project environment
Correct Answer: C
QUESTION 23
Which of the following PRINCE2 elements are described as being the guiding obligations and good
practices which determine whether the project is being managed using PRINCE2?
A.
B.
C.
D.
The Principles
The Processes
The Themes
Tailoring PRINCE2 to the project environment
Correct Answer: A
QUESTION 24
Which of the following are the integrated elements which make up the structure of PRINCE2?
A.
B.
C.
D.
Correct Answer: A
QUESTION 25
Which of the following are benefits of using PRINCE2?
1. Provides a common vocabulary for all project participants, promoting effective communication
2. Promotes regular progress meetings for senior management
3. Plans are carefully designed to meet the needs of the different levels in the project organization,
improving communication and control
4. Defines a thorough but economic structure of reports
A.
B.
C.
D.
1, 2, 3
1, 2, 4
1, 3, 4
2, 3, 4
Correct Answer: C
QUESTION 26
The PRINCE2 principle 'focus on products' states that a successful project is which one of the following?
A.
B.
C.
D.
Output oriented
Activity oriented
Benefits oriented
Resource oriented
Correct Answer: A
QUESTION 27
Effective risk management is a pre-requisite to which of the following principles?
A. Continued business justification
B. Manage by exception
C. Focus on products
D. Tailor to suit the project environment
Correct Answer: A
QUESTION 28
In respect of the project's organization structure, one of the seven principles of PRINCE2 is that every
project must have which one of the following?
A. Defined and agreed roles and responsibilities with an organization structure that engages the business,
user and supplier primary stakeholder interests
B. People allocated to clearly defined management jobs, assigned to them on a one-to-one basis
C. As many stakeholders as possible from the customer environment involved in key decision- making
throughout the project life cycle
D. Stakeholders who are responsible, accountable, consulted and informed throughout every stage of the
project
Correct Answer: A
QUESTION 29
Which of the following is NOT a PRINCE2 Principle?
A.
B.
C.
D.
Correct Answer: B
QUESTION 30
Which of the following best defines an output?
A.
B.
C.
D.
Correct Answer: D
QUESTION 31
Which of the following best defines a dis-benefit?
A.
B.
C.
D.
Correct Answer: B
QUESTION 32
Which statement regarding a project's outputs, outcomes and benefits is correct?
A.
B.
C.
D.
Correct Answer: D
QUESTION 33
Which best describes the purpose of a Business Case?
A. Used to define how and when a measurement of the project's benefits can be made
B. Documents the justification for undertaking the project, based on estimated costs, the benefits to be
gained and offset by any associated risks
C. Allows the Project Board to manage by exception throughout the project through providing continuous
justification
D. Describes the specific risk management techniques and standards to be applied throughout the project
Correct Answer: B
QUESTION 34
Which best describes the purpose of a Benefits Review Plan?
A. Used to define how and when a measurement of the project's benefits can be made
B. Documents the justification for undertaking the project, based on estimated costs, the benefits to be
gained and offset by any associated risks
C. Provides all the right infiormation for decisions to be made regarding continued business justification
D. Describes only those benefits to be delivered during the project
Correct Answer: A
QUESTION 35
Which best describes a purpose of the Business Case theme?
A. Provides full details of any risks related to the project
B. Provide a forecast for the project objectives and the project's continued viability
C. Establish ways of judging whether the project is, and remains viable, desirable and achievable to assist
with decision making
D. Specifies the ways in which the project will deliver the chosen business solution
Correct Answer: B
QUESTION 36
Any project outcomes perceived as negative by one or more stakeholders would be documented in which
product?
A.
B.
C.
D.
Correct Answer: C
QUESTION 37
What purpose does the Benefits Review Plan fulfill after the project has closed?
1. Defines how a measurement of the achievement of the project's benefits can be made
2. Defines what benefits assessments need to be undertaken
3. Records the results of all benefit measurements
4. Identifies the activities required to measure the expected project's benefits
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Correct Answer: B
QUESTION 38
What is a purpose of the Business Case theme?
A. Ensures the establishment of procedures to monitor and evaluate actual achievements versus those
planned
B. Establishes methods to judge whether the ongoing project is justified, in order to support decision
making
C. Improves the potential for project success through assessment and control of uncertain events or
situations
D. Describes how, when and at what cost products can be delivered so facilitating communication and
control
Correct Answer: B
QUESTION 39
If, for whatever reason, the business justification disappears once the project is underway, what does
PRINCE2 suggest should happen?
A.
B.
C.
D.
The project should continue until the next end stage assessment
A benefits review should be undertaken
The project should be stopped or changed
An exception assessment should be held to approve an Exception Plan to recover from the situation
Correct Answer: C
QUESTION 40
What is a purpose of the Business Case?
A.
B.
C.
D.
Correct Answer: D
QUESTION 41
Identify the missing words in the following sentence... A Benefits Review Plan is used to show how and
when a measurement of the achievement of the can be made.
A.
B.
C.
D.
Project's objectives
Project's benefits
Project's costs, benefits and risks
Project's outputs and outcomes
Correct Answer: B
QUESTION 42
Which of the following would be carried out as part of a post-project benefits review?
A. An assessment of whether the project fulfilled its original objectives
B. A review of the performance of the project's products in operational use and identification of whether
there have been any side-effects
C. An assessment of the project's risk management procedure
D. A review of the performance of the project management method and the project management team
Correct Answer: B
QUESTION 43
Identify the missing words from the following sentence... It is a PRINCE2 principle that a project must have
justification?
A.
B.
C.
D.
Senior manager
Continued business
Consistent user
Business operational
Correct Answer: B
QUESTION 44
Which product provides the answer to the question, is the investment in this project still worthwhile?
A.
B.
C.
D.
Business Case
Risk Management Strategy
Issue Register
Benefits Review Plan
Correct Answer: A
QUESTION 45
Which of the following products would be at the centre of any impact assessments of risks, issues and
changes?
A.
B.
C.
D.
Highlight Report
Business Case
Lessons Log
Risk Management Strategy
Correct Answer: B
QUESTION 46
The outputs from a PRINCE2 project are considered to be what?
A.
B.
C.
D.
Correct Answer: B
QUESTION 47
According to PRINCE2, a benefit is which of the following?
A. An improved business operation
B. The measurable improvement resulting from an outcome which is perceived as an advantage by one
or more stakeholders
C. The tangible or intangible product resulting from a planned activity
D. The result of change, normally affecting real-world behaviour and/or circumstances
Correct Answer: B
QUESTION 48
In PRINCE2, the information regarding the business justification for the project is normally documented in
which management product?
A.
B.
C.
D.
Business Case
Benefits Review Plan
Project Product Description
Communication Management Strategy
Correct Answer: A
QUESTION 49
The Business Case describes the reasons for the project based on estimated costs, the risks and which
one of the following?
A.
B.
C.
D.
Project approach
Acceptance criteria
Products to be produced
Expected benefits
Correct Answer: D
QUESTION 50
Which of the following would contain the business option of doing nothing, regarding the project's
investment?
A.
B.
C.
D.
Project approach
Business Case
Risk Management Strategy
Benefits Review Plan
Correct Answer: B
QUESTION 51
What's the purpose of the 'Plan' step within the risk management procedure?
A. Create a Risk Management Strategy for inclusion in the Project Initiation Documentation
B. Establish the Project Board's specific risk management responsibilities and assign them as owners of
specific risks
C. To plan the Communications Management Strategy in order to identify and capture any external
stakeholder risk information requirements
D. To identify suitable management responses to be implemented to manage a risk, should the risk occur
Correct Answer: D
QUESTION 52
Which of the following are uses of the Risk Register during the Controlling a Stage process?
1. Obtain details on risks to include in a Highlight Report
2. Obtain details of risks that may affect the Stage Plan for the next stage
3. Capture uncertainties identified when authorizing a Work Package
4. Obtain details of any potential impacts that may affect the Business Case while reviewing the stage
status
A.
B.
C.
D.
1, 2, 3
1, 2, 4
1, 3, 4
2, 3, 4
Correct Answer: C
QUESTION 53
Which is a recommended response type to respond to either a threat or an opportunity?
A.
B.
C.
D.
Fallback
Reject
Share
Reduce
Correct Answer: C
QUESTION 54
Which of the following describes risk proximity?
A.
B.
C.
D.
The timeframe over which the risk mitigation actions should be implemented
The schedule for the risk management activities related to a plan
The timeframe over which a risk will be monitored by the risk owner
The timeframe for when the risk might materialize
Correct Answer: D
QUESTION 55
Which statement describes risk cause?
A.
B.
C.
D.
Correct Answer: B
QUESTION 56
What is the purpose of the risk budget?
A.
B.
C.
D.
Correct Answer: C
QUESTION 57
Which of the following are valid risk responses for threats?
A.
B.
C.
D.
Correct Answer: C
QUESTION 58
Identify the missing word in the following sentence... A risk consists of a combination of the of a perceived
threat or opportunity occurring and the magnitude of its impact on objectives.
A. Outcome
B. Probability
C. Dis-benefit
D. Proximity
Correct Answer: B
QUESTION 59
What is the goal of the 'identify context' step as part of the risk management procedure?
A.
B.
C.
D.
Correct Answer: B
QUESTION 60
Which statement best describes the responsibilities of a risk actionee?
A.
B.
C.
D.
Correct Answer: C
QUESTION 61
Which is NOT a recommended response type to respond to a threat?
A.
B.
C.
D.
Avoid
Reject
Share
Transfer
Correct Answer: B
QUESTION 62
Which of the following Plans are approved by the Project Manager?
A.
B.
C.
D.
Project Plan
Team Plan
Exception Plan
Stage Plan
Correct Answer: B
QUESTION 63
Identify the missing word(s) in the following sentence... The [?] is used by the Project Manager to capture
and maintain information on all of the identified threats and opportunities relating to the project.
A.
B.
C.
D.
Risk Register
Risk Management Strategy
Issue Register
Risk owner
Correct Answer: A
QUESTION 64
Which of the following would NOT be classified as a threat to a project?
A. A competitor may launch a rival product first thus affecting the expected market share for the product
B. It is possible that the product completes user acceptance testing in a single test cycle rather that the
scheduled two
C. A prototype may be damaged in transit
D. A critical meeting could be affected by air travel disruption
Correct Answer: B
QUESTION 65
Which of the following is NOT a purpose of the Risk theme?
A.
B.
C.
D.
Correct Answer: C
QUESTION 66
Which of the following represents the threshold levels of risk exposure that, when exceeded, will trigger an
Exception Report?
A.
B.
C.
D.
Risk proximity
Risk tolerance
Risk allowance
Risk profile
Correct Answer: B
QUESTION 67
Which of the following statements describes a risk cause?
A.
B.
C.
D.
Correct Answer: B
QUESTION 68
Which of the following statements describes a risk event?
A.
B.
C.
D.
Correct Answer: A
QUESTION 69
Which of the following statements describes a risk effect?
A. The area of uncertainty in terms of the threat or the opportunity
B. The situation that gives rise to the risk
C. The impact(s) that the risk would have on the project objectives should the risk materialize
D. How soon in the future the risk is likely to occur
Correct Answer: C
QUESTION 70
What is the purpose of the Risk Management Strategy?
A. Describes in detail each risk identified in the project and how each risk should be managed
B. Describes how each risk owner and risk actionee will manage and fund the actions to mitigate each
risk
C. Describes the risk response actions taken to mitigate the project's risks
D. Describes the techniques and standards to be applied and responsibilities for achieving effective risk
management procedures
Correct Answer: D
QUESTION 71
Which of the following products is used after the Starting Up a Project process to capture and maintain
information on all of the identified threats and opportunities relating to the project?
A.
B.
C.
D.
Correct Answer: B
QUESTION 72
Which of the following risk responses can be used to seize an opportunity to ensure a risk 'will' happen
and the impact 'will' be realized?
A.
B.
C.
D.
Accept
Exploit
Enhance
Fallback
Correct Answer: B
QUESTION 73
What is the name given to an individual who is responsible for the management, monitoring and control of
all aspects of a particular risk assigned to them?
A.
B.
C.
D.
Risk Actionee
Risk Coordinator
Project Risk Manager
Risk Owner
Correct Answer: D
QUESTION 74
What is the name given to the individual assigned to carry out a risk response action or actions to respond
to a particular risk or set of risks?
A.
B.
C.
D.
Risk Manage
Risk Coordinator
Risk Actionee
Risk Owner
Correct Answer: C
QUESTION 75
Which of the following is TRUE regarding risk?
A. A Risk Register contains details of the risk management techniques and standards to be applied
B. The PRINCE2 risk management procedure consists of five iterative steps: Identify, Assess, Plan,
Implement, Communicate
C. A Risk Management Strategy is produced by a risk owner
D. PRINCE2's approach to risk does not involve stakeholders
Correct Answer: A
QUESTION 76
Which of the following is NOT one of the five risk management procedure steps?
A.
B.
C.
D.
Assess
Identify
Plan
Register
Correct Answer: D
QUESTION 77
Where would the mechanism for the control of and access to a risk budget be defined?
A.
B.
C.
D.
Correct Answer: A
QUESTION 78
Which of the following steps looks at the probability, impact and proximity of a risk?
A.
B.
C.
D.
Communicate
Assess (estimate)
Identify (context)
Plan
Correct Answer: B
QUESTION 79
Which of the following steps looks at the aggregated net effect of all risks within the project?
A.
B.
C.
D.
Plan
Assess
Implement
Assess
Correct Answer: D
QUESTION 80
Which of the following steps would involve the sending of information regarding project threats or
opportunities to any external stakeholders?
A.
B.
C.
D.
Identify
Communicate
Implement
Plan
Correct Answer: B
QUESTION 81
Which of the following steps would involve the identification of threats or opportunities to the project in
terms of their cause, the event and the affect on objectives?
A.
B.
C.
D.
Identify
Assess
Implement
Identify
Correct Answer: D
QUESTION 82
Which of the following steps would involve the actioning of any planned risk responses and monitoring
their effectiveness?
A.
B.
C.
D.
Identify
Assess
Implement
Identify
Correct Answer: C
QUESTION 83
What is risk appetite?
A. An organization's unique attitude towards risk taking that in turn dictates the amount of risk that it
considers acceptable
B. A stakeholder's perception of how a risk effects them
C. The net financial effect of all risks when aggregated together
D. The levels of risk exposure that, when exceeded, will trigger an Exception Report
Correct Answer: A
QUESTION 84
Identify the missing word(s) in the following sentence... Effective risk management helps to ensure the [?]
are met
A.
B.
C.
D.
Correct Answer: C
QUESTION 85
What is used to pass responsibility to a Team Manager for the production of one or more products?
A. Exception Plan
B. Work Package
C. Product Description
D. Checkpoint Report
Correct Answer: B
QUESTION 86
Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?
A.
B.
C.
D.
Exception Plan
Exception Report
Off-specification
Lessons Report
Correct Answer: B
QUESTION 87
To which role should a forecast breach of benefits tolerance be referred?
A.
B.
C.
D.
Project Manager
Executive
Senior Supplier
Corporate or programme management
Correct Answer: D
QUESTION 88
Which is NOT an event-driven control?
A.
B.
C.
D.
Highlight Report
Exception Report
Project Initiation Documentation
End of a stage
Correct Answer: A
QUESTION 89
Identify the missing words in the following sentence... PRINCE2 management stages equate to [?], which
is a factor that differentiates them from technical stages
A.
B.
C.
D.
Correct Answer: D
QUESTION 90
In which product would a product's quality tolerance be defined?
A.
B.
C.
D.
Correct Answer: B
QUESTION 91
Which of the following would the Project Board only authorize one at a time?
A.
B.
C.
D.
Work Packages
Stages
Team Plans
Product Description
Correct Answer: B
QUESTION 92
Which is NOT an objective of PRINCE2 stages?
A.
B.
C.
D.
Correct Answer: B
QUESTION 93
The Project Board needs to assess project viability at certain points as defined in the Project Plan. How
does the Progress theme assist this?
A.
B.
C.
D.
Correct Answer: B
QUESTION 94
What is a purpose of a Daily Log?
A.
B.
C.
D.
Correct Answer: B
QUESTION 95
The purpose of the Progress theme is to do which of the following?
A.
B.
C.
D.
Correct Answer: B
QUESTION 96
Which of the following statements are correct regarding the use of management stages?
1. Provide review and decision points
2. Enable key decisions to be made prior to the detailed work
3. Facilitate the manage by exception principle
4. Enables the project manager to have complete autonomy over the products to be produced
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Correct Answer: A
QUESTION 97
Which of the following are correct regarding the definition of a technical stage?
1. Technical stages never overlap
2. They are typified by the use of a particular set of specialist skills
3. Cover elements such as design, build and implementation
4. The work can be grouped by the set of techniques used
A.
B.
C.
D.
1,2,3
1,2,4
1,3,4
2,3,4
Correct Answer: D
QUESTION 98
Which of the following are factors that need to be taken into consideration when identifying management
stages?
1. Where the key decisions points need to be
2. The amount of risk within the project
3. The number of technical stages
4. How confident the Project Board and Project Manager are with proceeding
A.
B.
C.
D.
1,2,3
1,2,4
1,3,4
2,3,4
Correct Answer: B
QUESTION 99
The creation of an Exception Plan often follows which of the following situations?
A. A time or cost slippage occurring during a management stage
B. An Exception Report being submitted to the Project Board in the case of a management stage being
forecast to exceed its tolerance
C. A Stage Plan updated due to an urgent corrective action being taken by the Project Manager
D. A newly identified risk being captured and documented in the Risk Register
Correct Answer: B
QUESTION 100
What type of progress control is a Checkpoint Report?
A.
B.
C.
D.
Event-driven
Exception-based
Time-driven
Ad hoc-based
Correct Answer: C
QUESTION 101
Which of the following is NOT within the authority of the Project Board?
A.
B.
C.
D.
Correct Answer: D
QUESTION 102
Which of the following is a Project Board control?
A.
B.
C.
D.
Project-level tolerance
Stage-level tolerance
Checkpoint Report
Quality Register
Correct Answer: B
QUESTION 103
Which level of management in the project management team has the ability to review progress and decide
whether to continue, change or stop the project?
A.
B.
C.
D.
Project Manager
Project Board
Team Manager
Corporate or programme management
Correct Answer: B
QUESTION 104
There should be at least two management stages in a PRINCE2 project. Which of the following options
describes those stages?
A.
B.
C.
D.
Initiation as the first stage, the remainder of the project as the second stage
Initiation as the first stage, closure activities as the second stage
Procurement as the first stage, design and implementation as the second stage
Pre-project work as the first stage, initiation as the second stage
Correct Answer: A
QUESTION 105
Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested
by the Project Board. Team Plans and the use of seperate people as Team Managers are optional in
PRINCE2)
A.
B.
C.
D.
Correct Answer: B
QUESTION 106
The Project Board have overall control at what level?
A. Day-to-day control for a management stage within stage tolerance
B. Work Package level within Work Package tolerance
Concession
Tolerance
Contingency
Allowance
Correct Answer: B
QUESTION 108
If any type of issue or risk (or aggregation of them) cannot be resolved within the tolerances set by the
Project Board, which of the following products would first be sent to the Project Board to inform them of
this deviation?
A.
B.
C.
D.
Exception Report
End Stage Report
Highlight Report
Updated Risk and Issue Registers
Correct Answer: A
QUESTION 109
Tolerance forms a key element of allowing the Project Board to manage by exception. Which of the
following statements are correct regarding tolerance?
1. The Project Board sets project tolerances
2. Tolerances can be applied for Time, Cost, Scope, Quality, Benefit and Risk
3. The Project Manager sets Work Package tolerance
4. Cost tolerance should not be used to pay for authorized requests for change
A.
B.
C.
D.
1,2,3
1,2,4
1,3,4
2,3,4
Correct Answer: D
QUESTION 110
When it is forecast that one or more tolerances are to be exceeded, what should happen first?
A.
B.
C.
D.
The next higher level of management will begin to execute management by exception
The appropriate level of management must refer the matter to the next higher level
The Project Plan will be replaced by a fallback plan
The appropriate level of management will automatically produce and execute an Exception Plan to
recover from the deviation without referral
Correct Answer: B
QUESTION 111
Which product produced by the Project Manager would contain information on 'products completed in the
period'?
A.
B.
C.
D.
Correct Answer: C
QUESTION 112
Which product would the Project Manager use for gathering Work Package progress information?
A.
B.
C.
D.
Highlight Report
Daily Log
Checkpoint Report
Product Status Account
Correct Answer: C
QUESTION 113
Which of the following is FALSE regarding an Exception Report?
A.
B.
C.
D.
Correct Answer: C
QUESTION 114
Which product produced at project closure would document any unfinished work, ongoing issues and
risks?
A.
B.
C.
D.
Correct Answer: C
QUESTION 115
Which product would contain information on project and stage tolerance status, products completed during
the period and a summary of actual or potential problems and risks?
A.
B.
C.
D.
Correct Answer: C
QUESTION 116
What is a purpose of a Lessons Log?
A.
B.
C.
D.
Correct Answer: C
QUESTION 117
Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the
End Stage Report is not used to 'capture and maintain' information regarding issues and risks. This would
be in the respective Registers.)
A.
B.
C.
D.
Correct Answer: D
QUESTION 118
What is a purpose of a Lessons Report?
A. Used to understand the detailed nature, purpose, function and appearance of a product
B. Allow the corporate group responsible for any quality management system to refine, change and
improve the standards
C. Provide useful information regarding product status
D. Keep the Project Board and any other stakeholders informed of stage progress
Correct Answer: B
QUESTION 119
What is a purpose of quality planning?
A.
B.
C.
D.
Correct Answer: D
QUESTION 120
What is a purpose of the Project Product Description?
A.
B.
C.
D.
Correct Answer: C
QUESTION 121
Once a product has been completed, from who would the Team Manager get approval for its completion?
A.
B.
C.
D.
Project Manager
The authority defined in the quality responsibilities section of the product's Product Description
Quality Assurance as part of their independent audits
Project Support
Correct Answer: B
QUESTION 122
Who carries out audits independent of the project to check that the processes are in place for quality
planning and control?
A.
B.
C.
D.
Project Board
Project Assurance
Quality Assurance
Project Support
Correct Answer: C
QUESTION 123
Which product would be updated with the planned quality management activities for the next stage of the
project?
A.
B.
C.
D.
Correct Answer: D
QUESTION 124
Which of the following information does a Product Description provide?
1. Necessary abilities of the people needed to produce the product
2. Why the product is needed and what it will look like
3. Necessary abilities of the people needed to review the product
4. Time and cost needed to produce the product
A.
B.
C.
D.
1,2,3
1,2,4
1,3,4
2,3,4
Correct Answer: A
QUESTION 125
Identify the missing word(s) in the following sentence... Quality planning provides the definition of the
required products with their associated [ ? ] as a foundation for Project Board agreement.
A.
B.
C.
D.
Correct Answer: C
QUESTION 126
Which statement correctly describes the differences between Project Assurance and quality assurance?
A. Project Assurance provides assurance to the project's stakeholders whereas quality assurance
provides assurance to the wider corporate or programme organization
B. They are both the responsibility of the Project Board, but Project Assurance may be delegated
C. Quality assurance is internal to the project, whereas Project Assurance is independent of the project
D. Project Assurance must be independent of the Project Manager, whereas quality assurance is the
responsibility of the Project Manager
Correct Answer: A
QUESTION 127
Correct Answer: D
QUESTION 128
Which of the following is a specific quality review role responsible for submitting questions on a product?
A.
B.
C.
D.
User
Approver
Reviewer
Project Support
Correct Answer: C
QUESTION 129
Which of the following is an objective of a quality review?
A.
B.
C.
D.
Correct Answer: C
QUESTION 130
Which of the following is a specific quality review role responsible for checking a product is ready for its
review?
A.
B.
C.
D.
Project Assurance
Developer
Chair
Project Manager
Correct Answer: C
QUESTION 131
Which are the specific roles of the PRINCE2 quality review technique?
A.
B.
C.
D.
Correct Answer: A
QUESTION 132
Which of the following is a prioritized list of measurable definitions of the attributes required for the set of
products to be acceptable to key stakeholders?
A. Acceptance criteria
B. Quality criteria and related tolerance
C. Project Product Description
Quality criteria
Customer's quality expectation
Acceptance criteria
Acceptance record
Correct Answer: A
QUESTION 134
Which one of the following is a specific objective of a quality review?
A.
B.
C.
D.
Correct Answer: A
QUESTION 135
The reviewer(s) and approver(s) of a particular product are identified in which of the following?
A.
B.
C.
D.
Correct Answer: C
QUESTION 136
When producing an Exception Plan for a stage, why would the Quality Register be updated?
A.
B.
C.
D.
Correct Answer: B
QUESTION 137
According to PRINCE2, the quality review technique complements the use of which of the following?
A.
B.
C.
D.
Product Descriptions
Quality Assurance
Issue and change control procedure
The customer's quality expectations
Correct Answer: A
QUESTION 138
In which product are acceptance criteria documented?
A.
B.
C.
D.
Correct Answer: A
QUESTION 139
According to PRINCE2, which of the following is a statement about the quality which the customer requires
from the project product?
A.
B.
C.
D.
Correct Answer: A
QUESTION 140
Which product contains the customer's quality expectations?
A.
B.
C.
D.
Quality Register
Quality Management Strategy
Project Product Description
Business Case
Correct Answer: C
QUESTION 141
Which of the following documents the quality techniques, standards and procedures to be applied during
the project?
A.
B.
C.
D.
Quality Register
Quality Management Strategy
Project Product Description
Quality assurance
Correct Answer: B
QUESTION 142
Identify the missing word in the following sentence... The purpose of the [ ? ] theme is to define and
implement the means by which the project will create and verify products that are fit for purpose.
A.
B.
C.
D.
Plans
Change
Organization
Quality
Correct Answer: D
QUESTION 143
What is the purpose of a change budget?
A.
B.
C.
D.
Correct Answer: B
QUESTION 144
Which of the following is FALSE regarding the Change theme?
A. Change control should be used to prevent changes being made to baselined products
B. Issues can affect the project's performance targets of time, cost, quality, scope, benefits and risk
C. A pre-requisite of effective issue and change control would be an appropriate configuration
management system
D. Without issue and change control being applied, a project will become unresponsive to its stakeholders
Correct Answer: A
QUESTION 145
Who are allowed to raise an issue?
A.
B.
C.
D.
Correct Answer: B
QUESTION 146
Which product would be updated to show that a decision has been made on an off-specification which has
now been closed?
A.
B.
C.
D.
Quality Register
Daily Log
Issue Report
Risk Register
Correct Answer: C
QUESTION 147
If a product's weight was specified to be 300 grams but could only be built to a weight of 400 grams, which
of the following would be created?
A.
B.
C.
D.
Exception Plan
Request for change
Off-specification
Exception Report
Correct Answer: C
QUESTION 148
What is a purpose of the Change theme?
A.
B.
C.
D.
Correct Answer: B
QUESTION 149
Which product confirms the version numbers of all products being developed within a given stage?
A.
B.
C.
D.
Correct Answer: D
QUESTION 150
Identify the missing word from the following sentence... PRINCE2 uses the term [ ? ] to cover any relevant
event that has happened, was not planned, and requires management action?
A.
B.
C.
D.
Risk
Change
Issue
Exception
Correct Answer: C
QUESTION 151
According to PRINCE2, as well as holding informal problems/concerns, which product can also be used to
record required actions or significant events not caught elsewhere?
A.
B.
C.
D.
Daily Log
Risk Register
Issue Register
Project notebook
Correct Answer: A
QUESTION 152
Which option describes something that should be provided by the project, but currently is not (or is
forecast not to be) provided?
A.
B.
C.
D.
Problem/concern
Concession
Off-specification
Exception Report
Correct Answer: C
QUESTION 153
According to the Change theme, which of the following contains the steps of the recommended issue and
change control procedure?
A.
B.
C.
D.
Correct Answer: D
QUESTION 154
Which of the following describes the situation when an Issue Report would be produced?
A. When ever the Project Board instruct the Project Manager
B. It is only created for those issues that need to be handled formally
C. Every time someone wishes to bring anything to the attention of the Project Manager
D. Only if the Project Manager feels it is necessary
Correct Answer: B
QUESTION 155
A pre-requisite of effective issue and change control is the establishment of which of the following?
A.
B.
C.
D.
Correct Answer: C
QUESTION 156
Which of the following are typical activities of a configuration management procedure?
1. Impact assessment
2. Control
3. Verification and audit
4. Status accounting
A.
B.
C.
D.
1,2,3
1,2,4
1,3,4
2,3,4
Correct Answer: D
QUESTION 157
Which statement is FALSE regarding a Product Status Account?
A. A Product Status Account is used as a control document to assist in reviewing progress
B. A Product Status Account provides information on the state of a product
C. A Product Status Account is used to inform the Project Manager of what errors were found in a product
during a quality review
D. A Product Status Account is derived from Configuration Item Records
Correct Answer: C
QUESTION 158
Which product is continuously maintained in order to inform the Project Manager of where a product is at
any time, what its status is and who is working on it?
A.
B.
C.
D.
Product Description
Highlight Report
Configuration Item Record
Work Package
Correct Answer: C
QUESTION 159
Identify the missing word(s) in the following sentence... Change can only be considered in relation to an
established [ ? ]
A. Baseline
B. Situation
C. Product
D. Specification
Correct Answer: A
QUESTION 160
Can a baselined management product be changed once it has been approved?
A.
B.
C.
D.
Correct Answer: D
QUESTION 161
According to PRINCE2, what are issues likely to affect?
A.
B.
C.
D.
Correct Answer: B
QUESTION 162
Which of the following tasks is the first to be performed on receipt of a new issue?
A.
B.
C.
D.
Correct Answer: B
QUESTION 163
Which of the following is a concession?
A. When a product fails to meet its quality criteria
B. When an off-specification is raised by the Senior User
C. When an off-specification is accepted by the Project Board or Change Authority without immediate
corrective action
D. When a known error is no longer a problem
Correct Answer: C
QUESTION 164
A stakeholder wishing to make an observation about the project would do what?
A.
B.
C.
D.
Correct Answer: B
QUESTION 165
Which product identifies how changes to products will be controlled and where the products will be stored?
A.
B.
C.
D.
Product Description
Configuration Item Record
Configuration Management Strategy
Issue Register
Correct Answer: C
QUESTION 166
Which product is used to record and maintain information regarding any issues that are being managed
formally?
A.
B.
C.
D.
Correct Answer: B
QUESTION 167
According to PRINCE2, Which of the following would be used to pay for a request for change and possibly
any analysis costs?
A.
B.
C.
D.
Contingency
Tolerance
Change budget
Risk budget
Correct Answer: C
QUESTION 168
Which of the following are tasks carried out as part of product-based planning?
1. Write a Project Product Description.
2. Identify activities and dependencies
3. Create a product breakdown structure.
4. Create a product flow diagram
A.
B.
C.
D.
1,3,4
1,2,3
2,3,4
1,2,4
Correct Answer: A
QUESTION 169
Where would a Team Manager find information regarding the specific quality required for a product?
A.
B.
C.
D.
Product Description
Quality Register
Quality Management Strategy
Checkpoint Report
Correct Answer: A
QUESTION 170
Which of the following is NOT a purpose of a Product Description?
A.
B.
C.
D.
Correct Answer: B
QUESTION 171
What is NOT identified when creating a product breakdown structure?
A.
B.
C.
D.
Correct Answer: C
QUESTION 172
Which plan is optional depending on the complexity of the project?
A.
B.
C.
D.
Project Plan
Exception Plan
Team Plan
Initiation Stage Plan
Correct Answer: C
QUESTION 173
Identify the missing word(s) in the following sentence... PRINCE2 recommends three [ ? ] to reflect the
needs of the different levels of management involved in a project.
A.
B.
C.
D.
Levels of issue
Stakeholders
Levels of plan
Types of risk responses
Correct Answer: C
QUESTION 174
Which of the following is NOT one of the three levels of plan recommended by PRINCE2?
A.
B.
C.
D.
Stage
Team
Benefits Review
Project
Correct Answer: C
QUESTION 175
The period of time for which it is possible to accurately plan in detail is known as?
A.
B.
C.
D.
Correct Answer: B
QUESTION 176
Which of the following shows the scope of a plan?
A.
B.
C.
D.
Correct Answer: B
QUESTION 177
Which product does the Project Board use as a base against which to monitor project progress on a stage
by stage basis?
A.
B.
C.
D.
Stage Plan
Project Plan
Programme Plan
Benefits Review Plan
Correct Answer: B
QUESTION 178
According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start.
Which one of the following is given as a reason for this?
A.
B.
C.
D.
Correct Answer: B
QUESTION 179
Why does PRINCE2 recommend having three levels of plan?
A.
B.
C.
D.
The more levels there are, the more stable the plan detail will become
Aspects of planning become more difficult the further into the future they extend
To reflect that there are 3 key stakeholder project interests
To reflect the needs of the different levels of management involved in the project, stage and team
Correct Answer: D
QUESTION 180
Which of the following Plans can be approved by the Project Manager?
A.
B.
C.
D.
Project Plan
Team Plan
Exception Plan at stage-level
Stage Plan
Correct Answer: B
QUESTION 181
In which process is it decided that an Exception Plan should be created to replace a Stage Plan?
A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Closing a Project
Correct Answer: A
QUESTION 182
Which product identifies the source products from which a product is to be derived?
A.
B.
C.
D.
Correct Answer: C
QUESTION 183
Which PRINCE2 theme has a purpose to facilitate communication and control by defining the means of
delivering the products?
A.
B.
C.
D.
Plans
Progress
Organization
Change
Correct Answer: A
QUESTION 184
Identify the missing word(s) in the following sentence... The development and maintenance of a credible
[?] provides a baseline against which progress can be measured.
A.
B.
C.
D.
Product
Product Status Account
Business Case
Plan
Correct Answer: D
QUESTION 185
Which of the following would define the sequence in which the products are to be created and any
dependencies between them?
A.
B.
C.
D.
Correct Answer: B
QUESTION 186
According to PRINCE2, Project Board members would NOT be involved in which of the following?
A.
B.
C.
D.
Correct Answer: C
QUESTION 187
Which product is the Executive specifically responsible for overseeing the development of?
A.
B.
C.
D.
Project mandate
Work Package
Outline Business Case
Project approach
Correct Answer: C
QUESTION 188
Which of the following does PRINCE2 say are typical characteristics of a Project Board member?
A.
B.
C.
D.
Correct Answer: C
QUESTION 189
Who is responsible for providing the project mandate?
A.
B.
C.
D.
Project Support
Corporate or programme management
Project Manager
Project Board
Correct Answer: B
QUESTION 190
Who determines the use of a change authority and change budget during project initiation?
A.
B.
C.
D.
Project Board
Senior User
Project Manager
Corporate or Programme Management
Correct Answer: A
QUESTION 191
Which role is the key decision-maker on the project management team and is ultimately accountable for
the project's success?
A.
B.
C.
D.
Correct Answer: D
QUESTION 192
If the Project Board wish to ensure the Communications Management Strategy covers all the stakeholders
requirements for the next stage, which project management team role may they appoint to check this for
them?
A.
B.
C.
D.
Project Assurance
Project Support
Project Manager
Quality Assurance
Correct Answer: A
QUESTION 193
Which is a purpose of the Organization theme?
A.
B.
C.
D.
Correct Answer: C
QUESTION 194
According to PRINCE2, which of the following roles can the Project Manager also undertake?
A.
B.
C.
D.
Senior User
Change Authority
Executive
Project Assurance
Correct Answer: B
QUESTION 195
What is a purpose of the Communication Management Strategy?
A. Ensuring the project team can use the required reporting tools
B. Producing reports for the Project Board
C. Defining the communication method between the Project Board and corporate or programme
management
D. Ensuring stakeholders are aware of their responsibilities
Correct Answer: C
QUESTION 196
What is a responsibility of the business representative on the Project Board?
A.
B.
C.
D.
Correct Answer: B
QUESTION 197
Which is a responsibility of the Project Manager?
A.
B.
C.
D.
Correct Answer: B
QUESTION 198
Which of the following roles can the Project Manager also perform?
1. Change Authority
2. Project Assurance
3. Project Support
4. Team Manager
A.
B.
C.
D.
1,2,3
1,2,4
1,3,4
2,3,4
Correct Answer: C
QUESTION 199
What is defined within the Organization theme?
A.
B.
C.
D.
Correct Answer: C
QUESTION 200
PRINCE2 defines which of the following three primary stakeholder categories?
A.
B.
C.
D.
Correct Answer: A
QUESTION 201
User and Supplier are two of the three primary stakeholder interests that must be represented on the
Project Board at all times. What is the third interest?
A.
B.
C.
D.
Customer
Business
Programme
Corporate
Correct Answer: B
QUESTION 202
Which of the following management levels sits outside the project management team, but will be
responsible for commissioning a project?
A.
B.
C.
D.
Directing
Managing
Corporate or programme management
Delivering
Correct Answer: C
QUESTION 203
Which role organizes and chairs any Project Board reviews?
A.
B.
C.
D.
Project Manager
Executive
Team Manager in the current stage
Member of Project Support with administrative skills
Correct Answer: B
QUESTION 204
Which role is responsible for ensuring that the expected benefits are realized?
A.
B.
C.
D.
Project Manager
Project Assurance
Senior User
Executive
Correct Answer: C
QUESTION 205
Whose responsibility is it to assure the project's stakeholders that the project remains desirable, viable and
achievable at all times?
A.
B.
C.
D.
Project Manager
Corporate or programme management
Senior User
Executive
Correct Answer: D
QUESTION 206
Which role is the single focus for day-to-day management of the project?
A.
B.
C.
D.
Project Manager
Executive
Project Support
Team Manager
Correct Answer: A
QUESTION 207
Select the missing words from the following sentence... The Senior User is responsible for ensuring that
the project produces products which will deliver the desired [ ? ].
A.
B.
C.
D.
Outcomes
Benefits
Outputs
Changes
Correct Answer: A
QUESTION 208
Are the right people being involved in writing Product Descriptions is a question for which role to answer?
A. Project Manager
B. Project Assurance
C. Team Manager
D. Project Support
Correct Answer: B
QUESTION 209
Which role would have the assurance responsibility of monitoring any risks in the production aspects of the
project?
A.
B.
C.
D.
Senior User
Team Manager
Senior Supplier
Executive
Correct Answer: C
QUESTION 210
According to PRINCE2, which of the following roles cannot be shared?
A.
B.
C.
D.
Project Assurance
Project Support
Executive
Team Manager
Correct Answer: C
QUESTION 211
Which part of the project management team is responsible for briefing corporate or programme
management about project progress?
A.
B.
C.
D.
Team Manager
Project Support
Project Board
Project Manager
Correct Answer: C
QUESTION 212
Which is a specific responsibility of Project Assurance?
A.
B.
C.
D.
Correct Answer: D
QUESTION 213
Which PRINCE2 role would design and appointment the project management team?
A.
B.
C.
D.
Project Manager
Executive
Senior User
Project Assurance
Correct Answer: B