Birgit Vignes, Petroleum Safety Authority Norway, and Bernt S. Aadny, the University of Stavanger
Summary
A number of serious well failures in recent years led to investigations of well-integrity issues. The Petroleum Safety Authority
Norway (PSA) performed a pilot well-integrity survey based on
supervisory audits and requested input from seven operating companies, 12 preselected offshore facilities, and 406 wells. The wells
were a representative selection of production and injection wells
with variation in both age and development categories.
The pilot project indicates that 18% of the wells in the survey
have integrity failure, issues, or uncertainties, and 7% of these are
shut in because of well-integrity issues. The selection of wells and
the companies indicate that the statistics are representative.
The well incidents in the past and the results of the pilot wellintegrity survey revealed that the industry needs to increase focus
on barrier philosophy. Control of barrier status is an important
health, safety, and environment (HSE) factor to avoid major incidents caused by unintentional leaks and well-control situations.
Knowledge of well-integrity status at all times enables the companies to take the right actions in a proactive manner to prevent
incidents.
The paper presents the results and the conclusions from the
pilot survey. In addition, a number of technical well failures will
be presented, identifying critical elements such as corrosion,
leaks, and operational factors. In particular, the understanding of
barrier regulations, standards, and implementation was found to
be inadequate.
Introduction
A number of well incidents had been reported to the PSA with
significant impact and potential for serious accidents (several companies and various well categories). These were typically aging
or design effects, unclear understanding of barriers, weaknesses
in well design and planning processes, insufficient validation of
premisses, and other reasons.
PSA experienced shortcomings in the industrys handling of
well-related management of change and well conversion and lack
of recognition of the entire well-barrier envelope. In addition,
safety critical equipment and elements were not included in the
companies maintenance system.
Information from the employees and union representatives
indicated varied comprehension of well barriers, lack of overview,
or variable approaches for corrective actions. An example is the
difficulty for key personnel to get access to essential well data
when well-control situations occurred. There were differences in
the way the well-barrier concept was implemented.
There were examples of insufficient systematic control of
the technical capability of entire barrier envelopes and limited
standardization according to the NORSOK D-010 (2004) recommendations for well barriers. Examples include design capabilities
exceeded in operation, excessive exposure time with aims for
increased oil recovery, and missing continuity from design through
operation and maintenance.
Furthermore, there were examples of insufficient transfer of
critical information during license acquisitions and change of
operatorship, and there was a general need for improved handover
documents for operations.
Yes
Well-integrity
failure/issue?
Well barrier
intact
No
(or uncertainty)
Yes
No
Impact?
Yes
No
Shut in well?
Well
OK
active
Cat. A:
Cat. B:
Well is
shut In,
Working
under
conditions/
exemptions
e.g.: Leaks,
over criteria,
well contr.,
Cat. C:
Insignificant
deviation
for current
operation
Cat. D:
External
Conditions
Determine injury/damage/
production impact/
financial loss
Cat. E:
Cat. F:
Cat.G:
Shut in
on the
basis of
reservoir
related
Issues
Shut in
because of
topsides
bottlenecks,
planned
testing and
maintenance
Shut in
while
awaiting
P&A
was documentation such as well-barrier sketches, handover documentations, and other relevant material describing well-integrity
status for 85 preselected wells (see Appendix A).
The received documentation was analyzed by the PSA Drilling
and Well Technology engineers in cooperation with consultants
for selected areas.
A form with barrier drawing and template based on NORSOK
D-010 was used for assessment of selected well-barrier documentation. The operating companies replies and documentation
were used in this form. This form was used to evaluate gaps, to
identify need for clarifications, and to provide detailed comments
to the companies.
PSA had clarification meetings with the companies. The purpose was
To get a correct and consistent understanding of received
documentation about well integrity
If relevant, to calibrate and verify received documentation
Communicate PSAs opinion of received documentation
Well
details:
e.g. WAG,
Impact?
water
A: Well is
injection, Well
shut in
gas Integrity
B: Working
injection, oil problems
under
Risk
producer, [Y/N], If
water [N] go to Type of barrier conditions/ex reducing
Well bore
Well bore producer, Column element failure/ emptions measures/
uncertainty? C: Well ok conditions
name Type of well status disposal, N.
WAG
Yes
Oil producer
ORANGE Sub sea Producing with gas lift Yes
A: Well is
Casing leak shut in
B: Working
under
Annulus conditions/
communication exemptions
Other reasons
Well barrier
schematic
with barrier
element
assessment
available,
Estimated
loss of
similar to
Norsok D-010 When was
production
(NB To be the well Main reason pr. day/
attached) shut in? to well barrier impact of
[Y/N] [MM,YYYY] failure
failure
Enhanced
monitoring
Yes
Barrier failures
in planning
and
implementatio
n. Casing
wear
jan. 04
XXX
Production
without gas
lift
Yes
jan. 06
Other impact
of failure
(measures to
secure/ SD&P
action /
restoration
demand)
Intervention
demand.
Thread
failure?
Corrective
action needed
XXX
Wells
closed by
other
reasons
than
integrity
problems
Yes
Category reference to
flow diagram:
D. External conditions
E. Reservoir technical
When was
F. Topsides bottlenecks,
the well
planned testing &
maintenance, SD&P.
shut in/
G. Abandonment,
Securing secured
awaiting P&A
method [MM,YYYY]
G. Abandonment,
awaiting P&A
Installed
deep set
plug mar. 06
Number of Wells
29
75
48
27
30
25
20
15
9
2
10
5
Design
Formation
Fluid barrier
TRSV
Fig. 3Production wells, injection wells, and total wells reported with integrity failure, issues, or uncertainty in this survey.
Packoff
Packer
Cement
GLV
Casing
Tubing
ASV
Total
Conductor
Injection
DHSV
Production
Wellhead
Number of Wells
Fig. 4Number of wells with integrity failure, issues, or uncertainty and category of barrier-element failure.
A: Shut In
B: Working
Under Conditions
C: Insignificant Deviation
for Current Operations
Production
323
18
22
Injection
83
10
16
Total
406
28 (7 %)
38 (9 %)
9 (2 %)
147
15 to 19
20 to 24
25 to 29
Age (years)
Wellhead
ASV
Casing
Packoff
Fluid barrier
DHSV
Tubing
Cement
Chemical inj.line
Design
Conductor
GLV
Packer
TRSV
Formation
Kpreformance
indicators
10 to 14
Jreliability analyses
5 to 9
Lother challenges
Iopenness and
exchange of
0 to 4
Awell data
Hcompetence
and training
4
2
Gmanagement
of change
Fconsistent
practise within the
ENORSOK D-010
10
Dregular condition
Number of Wells
12
Chandover
documentation
14
B well documentation
Number of Companies
16
Well Failure: Example 4. Tubing leaks were found in 14 production wells on an offshore platform. Because the leak rates exceed
the acceptance criteria for NORSOK D-010, an investigation was
initiated. It was difficult to establish a root cause. However, the
conclusion was that it was likely leaks through the polished-bore
receptacle (PBR) (telescopic expansion joints in the tubing). These
were considered weak points in the production tubing. A possible
explanation was wear damage when the production tubing was
tripped into the well. The operating company decided that the PBR
will be shielded during installation in future wells.
Well Failure: Example 5. An offshore production well had tubular
collapse in both the production casing and the production tubing
at the same depth. These had to be removed in one operation, a
task that was complicated and time consuming. During this operation, a well-control incident happened during perforation of the
production casing. The investigation revealed that the well-control
procedures were not applied. The root causes were leaks from the
reservoir to the outside of the production casing and installation
of one single casing joint (grade 47 lbm/ft) in a 53.5-lbm/ft casing
string. The incorrect casing joint collapsed.
Summary Well Failure 15. There is a common denominator
between these five examples:
Operational decisions during abnormal situations often lead
to the well failures.
Design issues such as long-term effects are not sufficiently
considered.
The challenge is to account for rare events that may lead to
major incidents. The normal approach is to focus on frequent and
low-consequence incidents.
Improvement Potential
Results From the Questionnaire. Fig. 6 illustrates the issues for
improvement from A to L and the number of companies. The figure
shows that Issues B (well documentation), C (handover documentation), D (regular condition monitoring), E (comments related to
NORSOK D-010 compliance), and H (competence and training)
are issues for improvement for almost all of the companies in the
pilot well-integrity survey.
B: Well Documentation. Different approaches for transfer of
well-barrier responsibilities and insufficient transfer of critical
information during operations and license acquisitions may result
in reduced barrier control.
Improved and user-friendly access and visualization of key well
information are needed.
C: Handover Documentation. Several companies include pressure-test-verification charts in their handover documentation without interpretation. These data could be several years old and do
May 2010 SPE Production & Operations
not necessarily represent the present status. Well-integrity or wellbarrier schematic illustrations, verifications, and how-to-monitor
status were not easily accessible.
While completion schematics are included in the handover
documents and kept updated at all times, the barrier schematic
illustrations with descriptions were often inadequate.
D: Condition Monitoring. Consideration to and evaluations
of initial casing design for the lifetime of the well and possible
changes to the well usage (example, from production to injection)
are also difficult to obtain.
E: Comments Related to NORSOK D-010 Compliance. The
NORSOK D-010 defines requirements and guidelines, including
the established well-barrier philosophy. It appears to be less known
and adhered to than PSA expected at the time when the audits
were conducted.
The lack of information on well names, dates, and revision
numbers complicates easy overview of the status on well barriers.
Color coding and descriptions of the barrier envelopes vary from
company to company, but also within the same company.
In several cases, the barrier illustrations do not contain details
of perforations, the X-mas tree, and cement presence, and in some
cases they lack barrier elements. Such well details with possible
inclusion of dimensions and depth data should be included for
updated versions.
Verification details of the casing cement barriers are often lacking.
Hence, proper planned top of cement (TOC), packer-setting depth, and
later proper zonal isolation for later P&A could imply uncertainties.
H: Competence and Training. The questionnaire revealed a
need for strengthening knowledge, communication, and requirements to well barriers and status. The companies generally
expressed high interest in sharing and exchanging training material for practical use.
Conclusions
The results of the well-integrity survey revealed that the industry
needs to have an increased focus on barrier issues. Control of barrier
status is considered an important HSE factor that could limit unintentional leaks, well-control situations, and accidents. A well-known
status enables companies to take the right actions in a proactive
manner and thereby prevent potential losses and expenses.
7% of the wells were shut in because of integrity failures/
issues or uncertainty
9% of the wells were working under conditions/exemptions
2% of the wells had insignificant deviations for current operation
The integrity problems exist within barrier elements such as
tubing, ASV, casing, and cement.
The improvement potential for the industry includes the following:
Improve systems of reliability and condition-based surveillance for well barriers and well-integrity aspects to improve well
safety.
Provide better visualization of barriers for both onshore and
offshore users to improve the safety level and user friendliness.
Agree on standard ways of visualization, technical qualification, documentation, and abbreviations.
Consider developing a standard handover package containing
basic well-engineering data required to give a full overview of the
well-barrier situation from spud to abandonment.
The industry needs to further develop and acquire suitable
technology for condition monitoring of wells to improve on systematic and preventive maintenance and to keep better control on
degradation mechanisms.
Improved attention on verification and condition monitoring
of well barriers and well integrity is needed.
Improve competence and training of involved personnel both
from operators and contractors.
Start the process of updating the NORSOK drilling standards
to include recent experiences related to well barriers. This should
include the qualification process for barrier elements.
There is a common denominator between the examples of well
failures (Examples 15).
Operational decisions during abnormal situations often lead
to the well failures.
May 2010 SPE Production & Operations
Production
323 wells
1539 wells
Injection
83 wells
369 wells
Total
406 wells
1908 wells
Injection
51 wells
244 wells
Production
249 wells
1011 wells
Total
300 wells
1255 wells
32 wells
125 wells
Production
74 wells
528 wells
Total
106 wells
653 wells