Anda di halaman 1dari 55

IMPALA PLATINUM

4 ROPE KOEPE WINDER


ROPE--UP SAFETY
ROPE
PREPARATION

PATRICK DE LA HUNT

We respect, care and deliver

INTRODUCTION

We respect, care and deliver

INTRODUCTION
Impala Platinum has recently successfully and safely
roped up 2 newly installed, 4 rope, man and rock, tower
mounted Koepe Winders on the 16# project.
This was the first of Koepe winders installed on Impala
Platinum.
This presentation will discuss some safety related
matters that were dealt with upfront and during the actual
rope up. A detailed rope-up procedure will be presented
at this forum at a later stage.
We respect, care and deliver

PRESENTATION CONTENTS

Presentation contents
1.
2.
3.
4.
5.
6.

Back ground, winder and rope-up equipment details


Upfront safety preparation
On site safety considerations
Photos
Video clips
Conclusion

We respect, care and deliver

IMPALA 16 SHAFT HEADGEAR LAYOUT


On top, Cooling towers for the water cooled drives
7) Koepe Upper level
6) Koepe Lower level, brake hydraulics
5) Transformer level and Drives
4) Deflection sheave level
3) Service winder sheave Level
2) Tipping level
1) Conveyor level

Bank Level
Personnel Loading level (Sub Bank)

We respect, care and deliver

IMPALA 16 SHAFT KOEPE WINDERS ROPE-UP

1. Back Ground
This new complex was started in October 2004 and the first
stoping and mining operations are expected to start in
September 2013 (nine years). This is the second of the new
generation shafts that will secure jobs for around 4500
people.
Hoisting 226 ktpm of reef out of a 10 metre diameter shaft.
The vent shaft is 6.8 metre in diameter. The skip payload is
25 ton.
The shaft depth is 1675 metres below collar, hoisting 2300
persons per hour with a two deck 300 persons cage (150
persons per deck).
We respect, care and deliver

IMPALA 16 SHAFT KOEPE WINDERS ROPE-UP

Back Ground contd.


Considering all the effort over the past nine years and also
the future of the shaft, the rope up of the Koepe winders was
on the critical path and of utmost importance to be completed
on schedule and SAFELY
The initial rope up was planned at 13 days per winder

We respect, care and deliver

IMPALA 16#, 4 ROPE KOEPE WINDERS

We respect, care and deliver

DETAILS OF WINDING SYSTEM

Winding Distance
Motor Detail
Drum Diameter
Brakes

Conveyance Mass
Payload
Rope Details 4 Head
Ropes and 4 Tail Ropes
Rope Speed

Man Winder Koepe

Rock Winder Koepe

1601m

1640m

4300kW @ 57.3 rpm

4300kW @ 57.3 rpm

6.5m

6.5m

4 Channel Disc Brake,


Escort Controlled

4 Channel Disc Brake


Escort, Controlled

Cage: 26,5 ton

Skips: 26,5 ton

CW: 42,25 ton


22.5 ton

25 ton

Head Ropes: 54 mm Full


Lock

Head Ropes: 54 mm Full


Lock

Tail Ropes: 59mm Non-spin

Tail Ropes: 59mm Non-spin

16 m/s

16 m/s

We respect, care and deliver

IMPALA 16 SHAFT CROSS SECTION


South
Skip
25t

Skip
25t

Cage 26.5t. Payload 22.5t

East

West

Service
Cage

Counter
Weight
42.25t

Service
Cage

North
We respect, care and deliver

IMPALA 16 SHAFT KOEPE WINDERS ROPE-UP

The rope handling equipment used during the rope-up was


selected to ensure safe handling whilst installing the ropes.
The 4 head ropes installed simultaneously and the four tail
rope ropes were also installed simultaneously from surface.
The following slides will be showing the actual rope up
equipment used for the rope-up:

We respect, care and deliver

FRICTION WINCH
A mobile 1700 kN Friction winch, designed to handle 6
ropes simultaneously. It will also be used on Impala 17 shaft

We respect, care and deliver

DEFLECTION SHEAVES AND COMPRESSION BEAMS

We respect, care and deliver

CLAMP AND LFTING DEVICE (CLD)


1700 kN Double sided, four rope clamp and lifting devices (CLD),
one for the rock and one for the man winder

CLIP

We respect, care and deliver

MESSENGER WINCHES AND DEFLECTOR SHEAVES

We respect, care and deliver

ROPE REELERS

We respect, care and deliver

RELIANCE CLAMPS AND ACCESSORIES

We respect, care and deliver

LAY OUT OF ROPE UP EQUIPMENT TO ROPE-UP SAFE!!


Koepe Winder (free-wheeling)
Koepe Rope Reelers

Permanent Deflection Sheaves


CLDs

Friction Winch

Temporary Deflection Sheaves

Compression Beams & Deflection Sheaves

Messenger Winches

We respect, care and deliver

2. PRIOR SAFETY CONSIDERATIONS


Co-ordination (Several different contactors on board)
Contractors involved including Impala:
- RSV
- FLSmidth
- ABB, Local and overseas partners
- Murray and Roberts
- Shaft Sinkers
- Winder Controls/Siemag, Local and German partners
- DRATS and WORLEY PARSONSTWP, Involved on the
17# project, use same rope up equipment
- (Local and international visitors)
We respect, care and deliver

PRIOR SAFETY CONSIDERATIONS contd


EPCM, Contractor selection and adjudication
Very important to select the correct EPCM contractors to manage
the project. Ensure the correct quality controls are in place and are
adhered to. Generally you have to demand quality. If you do not
have quality your system is not safe.
Designs and Reviews
Ensure the scope of work and specifications are properly detailed
and reviewed. It is much easier to rectify matters during reviews
than at implementation phase.
Greater frontal engineering will ensure better implementation
success.
Regulations and SANS codes applied.
Hazards identification / Risk Assessment
Combined Risk assessments through out the process was carried
out to identify hazards (EPCM, OEM, Mine)
We respect, care and deliver

PRIOR SAFETY CONSIDERATIONS contd


Training

Winding engine drivers

Friction winch operators

Messenger winch operators

Clamp and lifting device operators

Rope capping

Tow vehicle, tractor driver


Initial rope-up procedure
Very important, a combined effort amongst the OEM, EPCM and the
Mine were put in to compile a detailed rope-up procedure. (Animated
Procedure) This was reviewed many times
Hazards were identified with in the procedure and a risk assessment
was carried out to mitigate and control the risks.
We respect, care and deliver

PRIOR SAFETY CONSIDERATIONS contd


Quality Control
Several inspections were conducted locally and
internationally to ensure quality products.
The rope-up equipment was inspected and factory tested by
EPCM and the Owners team.
Rope Cutting Procedure
Procedures were developed to ensure the ropes were cut
accurately and safely.
Platforms and life lines were installed in the shaft to safely
access the ropes and attachments.

We respect, care and deliver

PRIOR SAFETY CONSIDERATIONS contd

Friction Rollers
Friction rollers were incorporated on the friction winch as the
main source of friction between the rope and the coiling
sleeves of the friction winch.
In addition the rope reelers were designed to pull through a
brake generating a 2 ton rope pull (T2) as backup to the
friction rollers if they had to fail preventing the rope from
slipping

We respect, care and deliver

1700kN FRICTION WINCH & FRICTION ROLLERS

Friction
Rollers

We respect, care and deliver

ROPE REELER BRAKES


CLIP

We respect, care and deliver

3.

SITE SAFETY CONSIDERATIONS

Below a list of items taken into consideration on site


- Review of the rope-up procedure with all parties
involved, twice a day
- Rope-up concurrently with other construction
work. Co-ordination of eight different contractors
involved i.e. Work in head gear and in the shaft and
plan to put the shift down
- Communication at all times, leaky feeder / two way
radio, 6 channels
- Worked two shifts, handover and briefing sessions
took place 06h00 to 07h00 and the again 18h00 to
19h00
We respect, care and deliver

ON SITE SAFETY CONSIDERATIONS contd

Cleaning solvents, no diesel to be used to clean


the head ropes (Slip could occur at reliance
clamps and CLD)
Barricading all the equipment to prevent
unauthorised access
PPE, grinding, cutting etc.

We respect, care and deliver

ON SITE SAFETY CONSIDERATIONS contd

Daily task risk assessments


Heavy lifts
Load testing of cranes
Lifting and lowering of platforms
Tools with thongs used when working at heights and in
the shaft
Potential energy, tension in ropes and snatching areas
Moving equipment and machinery
Interface between the equipment i.e. either CLD or
Friction winch operational one at a time, not both.

We respect, care and deliver

ON SITE SAFETY CONSIDERATIONS contd

In order to prevent tension in ropes between the


messengers winch and friction winch, the rope of the
messenger winch was paid out and coiled in a figure
eight before pulling with the friction winch
Positioning and securing of equipment
Reeving of main rope, spotters with radios at critical
positions
Piloting of the bridles, conveyances and crossheads
through the shaft. The service winder was used in
this instance

We respect, care and deliver

ON SITE SAFETY CONSIDERATIONS contd

In addition on each shift an engineer was legally


appointed
Supervisors were appointed for each task
All the equipment was tested to ensure proper control
and protection before the rope-up commenced
Emergency controls were put in place i.e. remote alarms
and stops

We respect, care and deliver

ON SITE SAFETY CONSIDERATIONS contd

Koepe winder free wheel through out the duration of the


rope-up i.e. brakes hydraulically locked in the off
position and motor torque disabled (Critical). Winder
Brake off indication installed at friction winch driver.
Working at heights, harnesses inspected and life lines
installed and used
Access control i.e. hard barricading & colour-coded hard
hats
At all times the T1/T2 tension in combination with the
clamping and releasing of the ropes were taken in
to account ensuring that no slip of the rope occurs
We respect, care and deliver

ON SITE SAFETY CONSIDERATIONS contd

12 Hours shifts continuously for 13 days were worked.


Fatigue of personnel were taken into consideration.
Lunch packs, soft drinks, tea and coffee were provided.
Portable toilets were positioned in close vicinity.
Containers with tools and equipment were also
positioned close to the activities.
GOOD HOUSE KEEPING WAS OF THE ORDER FOR
THE DURATION OF THE ROPE-UP

We respect, care and deliver

PPE: COLOR CODED HARD HATS

We respect, care and deliver

POSITIONING OF FRICTION WINCH (150 TON)

We respect, care and deliver

PREPARATION FOR SOCKETING AND FITTING OF


ATTACHMENTS

Good housekeeping

We respect, care and deliver

ROPE REELERS BARRICADED

We respect, care and deliver

PROPER CONNECTIONS TO REEVE THE MAIN ROPE

CLIP

We respect, care and deliver

LIFTING HEAVY LOADS

We respect, care and deliver

CLEANING SOLVENTS (NO DIESEL ALLOWED)

We respect, care and deliver

CLOSING SHAFT AND INSTALL LIFE LINES

We respect, care and deliver

PROTECTION WHERE SNATCHING WAS DONE

We respect, care and deliver

TAIL ROPE CROSS HEAD AND LIFTING BEAM

Head Ropes

Tail Ropes

We respect, care and deliver

COMPRESSION BEAMS

We respect, care and deliver

MARKING, PREPARE AND ROPE CUTTING


MARKING

FINAL CUT

FINAL CUTTING MARK

ROUGH CUT
We respect, care and deliver

TAIL ROPE CLAMPING PLATFORMS INSTALLED


CLIP

We respect, care and deliver

HYDRAULIC JACKS TO BALANCE TENSION IN HEAD ROPES


PUMP

JACKS

We respect, care and deliver

MESSENGER WINCH CONTROL AND SAFETY

We respect, care and deliver

DEFLECTOR SHEAVE ROPE RETAINER

We respect, care and deliver

CRANES INSTALLED

We respect, care and deliver

CONVEYANCE INSTALLATION FLAT CAR

We respect, care and deliver

TESTING CLD AND FRICTION WINCH FULL LOAD

We respect, care and deliver

TESTING CLD AND FRICTION WINCH FULL LOAD


Koepe Winder (free-wheeling)
Koepe Rope Reelers

Permanent Deflection Sheaves


CLDs (1700kN Rope Pull)
CLD PULLING FORCE TEST
1700 kN
FRICTION WINCH
BRAKES ON

Friction Winch

Temporary Deflection Sheaves

Compression Beams & Deflection Sheaves

Messenger Winches
We respect, care and deliver

1700 kN FRICTION WINCH SUPPLY CABLES & EARTH

We respect, care and deliver

KEY LESSONS LEARNT

Being a project some activities fall behind and hence need


to be accelerated or activities need to run concurrently not
planned for in the schedule in order to meet deadlines.
Additional planning is then required to ensure safe
completion
A lot of patience and a good team spirit is required

We respect, care and deliver

CONCLUSION

The process followed, the rope-up equipment obtained,


together with the dedication from top management and all
parties involved the rope-up was completed safely with out
any incident.
THANK YOU!
QUESTIONS?
CLIP

We respect, care and deliver

Anda mungkin juga menyukai