Verification testing of work should be focused on quality aspects most important to satisfying the
design. Hayward Baker Inc. makes no representation or warranty as to the applicability of this
specification to a particular design or use and shall not be liable for the use of this draft
specification, whether in whole or in part.
GENERAL
The work covered in this specification consists of providing all labor, equipment and materials and performing all
operations in connection with site improvement to reduce the risk of structure settlement and future sinkhole
activity by pre-treatment of the foundation soils with compaction grouting.
1.01
INTRODUCTION
A.
Compaction grouting for sinkhole pre-treatment involves the injection of a low-slump, mortar-like
grout, under high pressure to fill voids, seal the bedrock surface and compact and displace the
adjacent soils near the throat of, and above, any potential sink within the treatment area.
B.
In situ soil:
Typically porous or residual soils overlying a weathered rock stratum just above
a solution-prone (karst) limestone rock.
C.
Applications:
1.02
The intent of the compaction grouting specified herein is to provide soil improvement within the limits
indicated on (..............................) drawings nos. ........................ to achieve the required degree of
improvement detailed in section 3.02 of these specifications.
1.03
REFERENCES
A.
This specification.
2.
Project drawings:
a.
b.
c.
Grout injection point layout, as detailed in the Submittals section 1.06 of these
specifications.
1.04
3.
4.
Contract documents.
DEFINITIONS
A.
Compaction grout : A material blend of fine aggregate, fines and water to achieve a pumpable,
thixotropic, viscous grout of a low slump to enable pumping at high pressure and remain intact
after injection. Material components can include sand, silt, clay, cement, ground slag, flyash, water
and other inert materials. Strength of grout is designed to be [spec strength or % cement minimum
here] and to provide a permanent, non-erodible material.
1.05
1.06
B.
Karst: A type of geology in which the overburden soil overlays an eroding limestone formation.
C.
Field Quality Control Representative: The individual given specific inspection tasks identified in
this specification.
SCOPE OF WORK
A.
The work shall consist of performing, monitoring and testing of compaction grouting within the
limits indicated on (..............................) drawing no.................. to meet the acceptance criteria
presented in Section 3.02 of these specifications.
B.
In connection with the compaction grouting program, as shown on the drawings, the grouting
contractor shall provide all labor, materials and equipment to accomplish the following items of
work:
1.
2.
3.
4.
Record compaction grouting process, including pressures, depths, injected volumes, and
movements for each stage and location.
5.
SUBMITTALS
A.
The following shall be submitted to the Owners representative by the grouting contractor with the
bid documents:
1.
B.
A list of at least five previously completed projects of similar scope and purpose for
approval by the Owners representative. The list shall include a description of the
project, relative size, and contact person with phone number.
The following shall be submitted to the Owners representative by the grouting contractor _______
weeks prior to the start of the work:
1.
2.
3.
A mix design for the project indicating sources and types of grout materials,
with volumetric proportions, and field test data from previous projects
indicating compressive strength and slump of ....... to ........ inches (.......
to .............. mm) or less achieved. If the grouting contractor intends to deviate
from the gradation provided in Section 2.03 of this specification, it shall
submit, with the bid, evidence of satisfactory use of the proposed material from
past projects with similar soil conditions.
C.
1.07
Work procedures and control criteria (including volumes and pressure for each
stage).
5.
A general Work Procedures Plan outlining the spacing, location, depth and estimated
quantity of grout to achieve the specified criteria detailed in Section 3.02 of these
specifications.
The following shall be submitted to the Owners representative by the grouting contractor during the
work:
1.
Accurate daily records of all grout pipe installation, compaction grouting quantities,
including stage data, volume, pressure and depth for each grout pipe location.
2.
3.
Verification of rock depth and quality during drilling, as evidenced by drilling resistance
recorded on drilling logs.
QUALITY ASSURANCE
A.
The compaction grouting program, including installation of grout pipes, shall be performed by a specialist
grouting contractor with at least ten continuous years of documented experience in compaction grouting.
B.
The grouting contractor shall provide experienced management, supervisory and key personnel as required
to implement the compaction grouting program, as follows:
C.
PART 2
2.01
4.
1.
The project manager shall have at least five years of continuous experience in
compaction grouting, with at least the last two years in the full-time employ of the
grouting contractor.
2.
The superintendent shall have at least five years of experience in compaction grouting.
3.
b.
The Owners representative will ensure that procedures and documentation conform to these
specifications and submittal requirements.
GROUTING EQUIPMENT
A.
The grouting contractor shall supply equipment capable of advancing the grout pipe through overburden,
soils and other natural obstructions to the specified depth or as required to meet the project objectives.
B.
The grouting contractor shall supply all equipment required to operate a compaction grouting system
capable of supplying the specified grout at variable flow rates and pressures, measured at the pump, up
to........psi (......... kPa) and at rates of ...... to ...... cubic feet (..... to ........ cubic meters) per minute, as
required to suit the application.
C.
The mixer shall be a continuous auger type to ensure complete uniform mixing of the materials used and
shall be of sufficient capacity to continuously provide the pumping unit with mixed grout at its normal
pumping range. The mixer must be capable of volumetrically proportioning the grout materials. Ready
mixed grout is also acceptable with an approved mix design.
D.
The grouting contractor shall provide gauges or other instrumentation (measuring devices) to
measure:
1.
2.
3.
4.
2.02
2.03
E.
The grouting contractor shall supply and install ground/structure movement monitoring equipment
in accordance with Section 3.03 of these specifications.
F.
An adequate communication system shall be maintained between the pumping location and the
injection location. As an alternative, the contractor may provide a remote control system to allow
full control (start, stop, flow rate, and reversing) of the pump, directly by the grouting technician
from the injection point.
Grout pipes, casings, and connections shall be steel casing of adequate strength to maintain the
hole and to withstand the required installation, jacking and pumping stresses. The pipes shall be a
minimum of 3.0 inches (75 mm) inside diameter in order to adequately handle the specified low
slump material without plugging [2.0 inch (30mm) inside diameter may be allowed under certain
restricted access situations]. All casing shall be flush joint threaded or a single piece tubing to
provide a smooth inner wall and unobstructed inside diameter. All fittings (elbows, bends, adapters,
reducers, etc.) shall be long sweep, gradual transition pieces specifically designed and
manufactured for high pressure grout and concrete pumping applications. Standard pipe elbows
and reducers will not be allowed. It shall be the contractors responsibility to install casing that
does not detrimentally impact the grouting procedure.
B.
Casings shall be sized and installed such that grout material will not travel in the annulus area
between the pipe and adjacent ground and escape at the surface when pumped.
C.
All grout pipes shall be advanced through at least 5 ft of continuous, competent rock to provide
reasonable assurance that the grout hole has not been terminated in a boulder floater or a rock
pinnacle.
GROUT MATERIALS
A.
B.
Fine aggregate shall be sand with a fines content (percent passing No. 200 sieve) of not less than 10
percent and not more than 30 percent. Natural fines may be supplemented with fly ash, bentonite,
or aggregate washings.
C.
Proportions of the mixture shall be as required to achieve a pumpable mix with a maximum
______inch (_____mm) slump.
D.
Upon discharge into the pump hopper or holding tank, the grout must be continuously agitated.
Mixed grout may not be held in the agitator for more than 1.5 hours unless a set retarder, approved
by the Owners representative, is used.
PART 3
EXECUTION
3.01
SITE EXAMINATION
A.
3.02
Prior to submitting a bid price for the compaction grouting, the grouting contractor shall conduct a
site inspection.
COMPACTION GROUTING
Note: Compaction grouting may be performed under either a performance-based or a method-based
specification.
Select Section 3.02A (performance-based) OR 3.02B (method-based), as
appropriate.
A.
B.
Compaction grouting shall be performed in accordance with the approved grout injection point
layout scheme to achieve the following acceptance criteria in the in situ soil between the injection
points:
1.
2.
Post-grouting, average corrected static Cone Penetrometer tip resistance, in silts with
friction ratio less than ___________ exceeding __________tsf (..........kPa). Locations
are to be agreed upon between the grouting contractor and the Owner/Engineer.
Averaging shall include above and below two feet, eliminating values in soils with
permeability less than 1x10-3 cm/sec.
Compaction grouting shall be performed in accordance with the approved grout injection point
layout scheme. The grout shall be injected at a stage depth until one of the following occurs:
1.
2.
3.
An injected grout volume equal to ......... percent of the soil volume being
treated by that injection stage is reached.
4.
5.
When the injection pipe tip is at or below the bedrock surface, injection pressures shall
not exceed 200 psi (1380 kPa), and grout injection will continue until a steady increase
in pressure is occurring, at which time that stage will be deemed complete and the pipe
may be extracted to the next stage.
Upon attaining one of the above refusal criteria, the grout pipe shall be lifted 2 feet (0.6m) and the
process repeated.
Note: 3.02B1 to 5 may be deleted by reference to the contractors work plan
3.03
C.
Compaction grouting shall be sequenced so that grouting does not take place within _______ ft
(_____m) of locations grouted within the previous 12 hours.
D.
As compaction grouting is completed at each location, the grouting contractor shall completely fill
the grout hole to the ground surface.
A.
All compaction grouting shall be performed under the inspection of the FQCR.
B.
Monitoring and logging of compaction grouting operations for both test areas and production work
shall be done by the FQCR.
C.
The FQCR will perform slump tests of grout and take measurements of grout mix quantities to
verify the grouting contractors grout mix, as follows:
1.
2.
3.04
D.
The FQCR will require the grouting contractor to cast minimum size 3 inch by 6 inch (75 mm by
150 mm) grout test cylinders or 2 inch by 2 inch (50 mm by 50 mm) cube molds for strength
testing. One set of four cylinders or molds will be cast during each slump test, or at least once per
day.
E.
F.
As detailed in Section 1.06C, daily records shall be maintained by the grouting contractor and
submitted to the Owners representative.
G.
A level control system will be installed by the contractor for each structure
within _____ ft (_____ m) of the grouting operations.
2.
3.
The effectiveness of the proposed grouting layout scheme shall be verified as follows:
1.
The Owner may retain a soil testing firm to perform the in situ testing as
directed by the Owners engineer. Test sections will be performed before and
during production work, as follows:
a.
b.
The method of installation of the test section shall comply with Section 3.02 of
this specification and shall be performed using the same grout line sizes, grout
mix drilling and grouting equipment and procedures as that to be used for
production work.
c.
B.
3.05
Note:
Monitoring and logging of compaction grouting operations in the test areas and for production
work shall be done by the grouting contractor.
RESTRICTIONS
A.
The Owner or General Contractor or Specialty Contractor shall be responsible for obtaining any
State and municipal permits (if required) and conforming to all State and local regulations.
B.
The owner will be responsible for the precise delineation of all above and below ground utilities
and obstructions.
The following shall also be listed within this section when applicable:
1.
2.
3.
PART 4
4.01
Environmental restrictions.
Work boundaries.
Hours for construction.
PAYMENT
METHOD OF PAYMENT
A.
Layout of grout injection locations, installation of the grout casings required, and any required
secondary grouting within the limits indicated as requiring compaction grouting on
__________________drawing nos_______________ shall be a unit cost per linear foot of grout
pipe, as measured from the ground surface to the maximum depth penetrated by the grout pipe.
B.
C.
Installation of additional grout casings, placed under the direction of the Owners engineer outside
the limits indicated on _________________________drawing nos. _____________________as
requiring compaction grouting (such as areas identified as marginal - may require compaction
grouting), shall be at a unit cost per foot.
D.
E.
Testing may be priced as a lump sum or unit price based on the methods specified.