Commune/Sangkat Fund
Technical Manual
Volume I
Study and Design Guidelines
2009
VOLUME I:
STUDY AND DESIGN GUIDELINES
CONTENTS
PREFACE ...................................................................................................................... iv
List of Abbreviations ..................................................................................................... v
PART 1: INTRODUCTION .............................................................................................. 1
1
Introduction ......................................................................................................... 2
1.1
Preamble .......................................................................................................................... 2
1.2
1.3
1.4
2.1
Introduction ..................................................................................................................... 7
2.2
2.3
2.4
2.5
2.6
Transportation Infrastructure, Group Output Code 1010000 ...................................... 8
2.6.1 Form T11 Transport: Roads ........................................................................................... 9
2.6.2 Form T12 Transport: Structures .................................................................................. 17
2.7
2.7.1
2.7.2
2.7.3
2.8
Water Supply, Group Output Code 1030000 .............................................................. 51
2.8.1 Form T31 Water Supply ................................................................................................ 51
2.9
Education Facility, Group Output Code 1040000 ....................................................... 62
2.9.1 Form T41 Education Facility ........................................................................................ 62
2.10 Health, Group Output Code 1050000 .......................................................................... 70
2.10.1 Form T51 Health ........................................................................................................ 70
2.11 Sanitation, Group Output Code 1100000 .................................................................... 77
2.11.1 Form T101 Sanitation ............................................................................................... 77
3.1
3.2
3.3
3.4
3.4.1
3.4.2
3.4.3
3.4.4
3.4.5
3.4.6
3.5
AutoCAD Standards ..................................................................................................... 89
3.5.1 AutoCAD Version .......................................................................................................... 90
3.5.2 General settings ............................................................................................................ 90
3.5.3 AutoCAD file name ....................................................................................................... 90
3.5.4 Drawing number ........................................................................................................... 90
3.5.5 Paper size ...................................................................................................................... 91
3.5.6 Pen assignment for plotting ........................................................................................ 91
3.5.7 Layer definition ............................................................................................................. 91
3.5.8 Text style and fonts ...................................................................................................... 92
3.5.9 Line types / widths ........................................................................................................ 93
3.5.10 Hatch .......................................................................................................................... 93
3.5.11 Dimensions................................................................................................................ 93
3.5.12 Blocks ........................................................................................................................ 94
3.5.13 External references (x-ref) ....................................................................................... 94
3.5.14 Viewports ................................................................................................................... 94
3.5.15 Plotting....................................................................................................................... 94
4.1
4.2
4.3
4.4
5.1
Introduction ................................................................................................................. 110
5.1.1 Limitations ................................................................................................................... 110
5.1.2 Using the design guidance ........................................................................................ 110
5.2
Transport Infrastructure: Group 101 ......................................................................... 111
5.2.1 Sub-Group 10101 and 10102: Roads: Form T11 ...................................................... 111
5.2.2 Sub-Group 10103 to 10108: Road Structures: Form T12 ........................................ 117
5.3
5.3.1
5.3.2
5.3.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
I-iii
PREFACE
This book is the first volume of Commune Sangkat Fund Technical Manual produced by the
National Committee for Sub-National Democratic Development (NCDD) with the help of the
Ministry of Rural Development (MRD), the Ministry of Water Resources and Meteorology
(MoWRAM), and others. Commune Sangkat Fund Technical Manual consists of 7 parts which
are divided into 3 volumes as the followings:
x
This first volume states mainly the study and design guidelines for the implementation of smallscale infrastructure projects financed by Commune Sangkat Fund. It comprises 5 parts among 7
parts of Commune Sangkat technical manual as the followings:
x
Part 1 : Introduction
For part 6 which instructs on specifications for construction materials and works is in Volume II;
while the final part- part 7 is in volume III which explains about contract supervion by the use of
Construction Check Lists.
I-iv
List of Abbreviations
ADT
Applet
AASHTO
BOQ
CBR
CSO
C/S
CIP
DFT
DCP
DoLA
DBST
EA
EIA
EMP
ExCom
FWUC
GPS
GTFM
HFWL
IO
LAU
NGO
MEF
M&E
MoI
MRD
NCDD
O&M
PBC
PCU
PFT
PIM
PMC
PRDC
PSDD
PDoWRAM
SBST
ST 1
ST 2
ST 3
T
TSO
TSU
TRRL
I-v
PART 1: INTRODUCTION
I-1
Part 1: Introduction
1 Introduction
1.1 Preamble
The principal and first order document for implementation of projects under the
Commune/Sangkat Fund (C/S Fund) is the C/S Fund Project Implementation Manual (PIM).
The C/S Fund Technical Manual (this document) is a second order document dealing only with
technical aspects of C/S Fund infrastructure projects and particularly the interface with the C/S
Fund Project Generator software developed for infrastructure projects. C/S Fund service
projects are not dealt with by the Technical Manual.
If there is a conflict between the C/S Technical Manual/Project Generator and the PIM then the
PIM takes precedence.
The core template program function has been retained but rewritten on a flexible
software platform; it incorporates standard design drawings (prepared in AutoCAD but
saved and accessed in PDF format) linked to spreadsheets which calculate quantities
and costs according to variable dimensions.
The concept of checklist-type feasibility study PIM forms from the Seila Template
process have been upgrade to interactive Technical Forms built into the Project
Generator software in combination with the Template program component. Hence the
forms call in the outputs of the template program automatically by use of links and
dropdown menus allowing rapid and quality assured assembly of a project portfolio.
The new technical forms in project generator provide design guidance where
technical design is required. The user must answer simple questions by either filling
data or choosing answer from multiple choice answers.In some technical forms, advice
on type and dimensions of infrastructure will be provided in order to choose project
output. To obtain the advice, you need to do some calculation by using several small
Excel programs called Applet. The programs are interactive, the user can change
some design requirements, or in some cases vary the design criteria used, until an
acceptable design is produced. The user can choose the final design choice which can
be less than recommended if there is good reason.
I-2
Part 1: Introduction
The Project Generator can be expanded to cover other requirements of the PIM.
The drawings are easy to read, by people who do not have high technical education (If
you think that the drawings are not easy to read, please complain and we will try to
improve them!);
The project outputs shown in the drawings are easy to construct, without a lot of special
equipment;
The designs do not need a very high quality of construction technique, to achieve a
successful project. For example, concrete structures built using the designs will be
strong enough, even if the quality of the concrete is not very good.
When the Commune Council implements a project, they must follow technical guidelines from
the Ministry that is responsible for the sector. For example, road projects should follow
guidelines from the Ministry of Rural Development, and irrigation projects should follow
guidelines of the Ministry of Water Resources and Meteorology.
Because the Ministries have helped to produce the Technical Manual (and the earlier Seila
Technical Manual), the drawings in the Manual follow Ministry guidelines. If the Commune
chooses a drawing from the Manual for their project, they know that the drawing follows the
guidelines. However, the Commune can choose to use a different drawing (one that is not in
the Manual) if they prefer.
The drawings show technical designs for project outputs. Before choosing a drawing for the
project outputs, the project designer must decide what types of outputs are needed, how big the
outputs must be and where the outputs must be. However, provided that the basic field data is
collected the interactive Technical Forms in the Project Generator will provide most of the
information required to assemble the design file.
I-3
Part 1: Introduction
Re-check overall objective and revise if project differs from its initial purpose
I-4
Part 1: Introduction
I-5
I-6
2 Technical Forms
2.1 Introduction
This section describes how to comply with the requirements of the Project Implementation
Manual (PIM) that for an infrastructure project the Technical Assistant prepares Technical
Information Forms. These forms are part of the core process of Project Preparation and
Technical Clearance.
It is required that the Technical Assistant will assist the Project Management Committee to
study the technical aspects of the project at the project site in close cooperation with the User
Groups and local community organizations to collect important and necessary information for
filling in the Project Information Form and Technical Information forms.
The general information and technical information will be used to prepare the project design.
The technical information is different according to the type of project. The different technical
forms are listed below:
Infrastructure type
Code
1010000
1020000
Description
Transportation
Infrastructure
Irrigation System
Technical forms
Form No.
Project type
Status of form
Form T11
Transport: Roads
Active in project
generator
Form T12
Transport: Structures
Active in project
generator
Form T21
Irrigation: Project
Active in project
generator
Form T22
Irrigation: Earthworks
Active in project
generator
Form T23
Irrigation: Structures
Active in project
generator
1030000
Water Supply
Form T31
Water supply
Active in project
generator
1040000
Education
Facilities
Form T41
Education
Active in project
generator
1050000
Health
Form T51
Health
Active in project
generator
1060000
Market
Infrastructure
Form T61
Markets
Form to be prepared
1070000
Agriculture
Infrastructure
Form T71
Form to be prepared
1080000
Social
Infrastructure
Form T81
Social infrastructure
Form to be prepared
1090000
Energy
Form T91
Energy
Form to be prepared
1100000
Sanitation
Form T101
Sanitation and
drainage
Active in project
generator
1110000
Flood Protection
Infrastructure
Form T111
Flood protection
structures
Form to be prepared
I-7
It will be noted in the status of form column that that there are Forms to be prepared for five
of the infrastructure group. This is because at the time of writing this manual there are no
templates loaded into the Project Generator for these groups and very few such projects have
ever been executed. This is anticipated to change in the future and it is intended to develop
additional Technical Forms at that time when the precise requirements for the forms will be
known.
Generally only one Form T11 will be required provided the road width and surface type is the
same for the full length of the road. If it changes, e.g. because of increased traffic after a road
junction, then more than one T11 might be filled.
There must be one Form T12 for each road structure, e.g. if there is one 5 m concrete bridge
and three 1.0 m diameter pipe culverts then four T12 must be filled.
I-8
Entering into Applet T11 Average Daily Traffic for existing road to determine MRD
Class A or B and a total of 24 hour from classified traffic count at busiest part of road.
Entering DCP test results with GPS coordinates (Enter each DCP test result to Applet
T11 and get the 20 percentile DCP strength).
You will then get the advices on road type, surface and pavement thickness in the next
worksheet of Applet T11.
After that you must create output according to the advises from the Applet, but you can choose
another type of road surface and pavement thickness with appropriate reasons.
Then go to technical form T11 to answer the questions on:
x
General project information this fills automatically from information previously filled
immediately when creating project.
Project location enter the GPS coordinates of the start and finish of the road.
Type of roadworks required option for five descriptions covering new, rehabilitated,
and improvement by widening and/or upgraded surface.
Existing structures and new structures required manual entry describing existing
structures and anticipated number(s) and type(s) of new structure (the actual number,
type and size of structure is decided using Form and Applet T12).
Type of existing road construction, its condition, and main cause of damage a variety
of questions and options describing the existing road, what wheeled traffic can pass in
the wet and dry season, and the main cause of damage.
Materials available for road construction a variety of questions about locally available
road construction material, its quality, and haul distance to the site.
Proposed fill and cut slopes Choose cut and fill slopes according to type of cut and fill
material (this is used for quantity calculations).
Example
The example shown is for 4.25 km improvement of a sub-tertiary road Type ST3.
For this example the attachments generated by the Project Generator will be:
1. Template 1010102 drawings together with a profile pro-forma drawing in AutoCAD file
used with Excel spreadsheet.
2. Spreadsheet for calculation of quantities to allow calculation of cost estimate (see Part 4
of this Technical Manual).
Study and Design Guidelines
I-9
I-10
Traffic count
DCP
measurements
ADT
Soils and
20 percentile DCP
Surfacing
option(s) applet
(advice)
Create Output
General
information?
Location?
Road
classification?
List new
structures?
Existing road
construction?
Condition
of road?
Main cause
of damage?
Materials
available?
Slopes?
Pavement type
and thickness?
x Drawings
x Interactive
quantities SS
I-11
District : Sreisanthor
S/C:Roseisrok
Ending point
X of GPS
Y of GPS
X of GPS
Y of GPS
304010
1528230
308350
1528250
I-12
Yes
No
culvert
drift
vented causeway
6
9. Type of existing road: is there existing path, car-track or road ?
Yes
No
Yes
No
Motorcycle
Motorremorque
Koyun or
small truck
for carrying
goods
Car or truck
for carrying
people
heavy truck
for carrying
goods
Can
Can
Can
Can
Cannot
Cannot
Can
Can
Can
Can
Can
Cannot
13. Main cause of road damage: What causes the main damage?
If Something else, answer the below question
Flooding
I-13
Can meet specification for Type 3 material by mixing with imported material
Can meet specification for Type 1 material by mixing with imported material
Borrow pit
Stream bed
Borrow pit
Stream bed
quality
Punley mountain
15
Poor
I-14
Limestone
Sandstone
Limestone
Sandstone
Domestic well
27. Road traffic: what are the proportion of the cars and trucks using the road?
*Write in percentage.
One place to another in
commune
10%
90%
10%
28. the proportion of the cars and trucks using the road is:
* Put it into percentage.
Belong to people who live in the
commune
48%
52%
29. Foundation soils: what kind of soil the structure stand on?
* if other, mention in the following question:
Normal clay
Sandy soils
Gravels
Other.
Horizontal
I-15
Horizontal
34. Fill with the thickness of the road pavement choosing above:
Road pavement
thickness
Laterite
300mm
35. Road maintenance: Does the commune have a Commune Road Sub-Committee?
Yes
No
Sangkat/Commune
Others
37. Write the person who is responsible for road maintenance if you choose other
38. Remark:
You must upload Applet in which you entered your data to get the answers and the
advices about road pavement. If you chose the road pavement that is not suitable less
or more than recommendation from Applet T11, give your reason on Advice Tab.
I-16
Choosing the structure type envisaged, and changing it if it will be different from the
recommended structure after filling hydrology and hydraulic data.
Filling hydrology and hydraulic data details of the catchment draining to the structure if
this can be determined (area, elevation of stream bed for slope, catchment soils,
vegetation, land use and whether in a normal or high rainfall area).
After that you must create output according to the advice from the Applet, but you can choose
another type and size of drainage structure with appropriate reasons. (NOTE: It is strongly
recommended not to select a smaller type and size of structure than advised).
Then go to technical form T12 to answer the questions on:
x
General project information this fills automatically from information previously filled
immediately when creating project.
Project location by entering the GPS coordinates of the structure the Project Generator
creates a location plan.
Road classification and standard the road classification, standard and width is entered
manually, but if Form T12 has been generated by a Form T11 then the information is
entered the same as the road form.
Scope of Works requires information on the type, size and condition of the existing
structure if there is one.
Foundation soils including results for DCP tests description options for type of soil and
DCP test results with GPS coordinates (Possibly enter each DCP test result to Applet
T11 and get the 20 percentile DCP strength).
Required hydraulic capacity of structure the design flow and velocity from Applet T12
or engineer.
Example
The example shown is for one of the replacement pipe culverts on the previous example Form
T11 for a road.
For this example the attachments generated by the Project Generator will be:
1. Template drawing for output code 1010303 (see Part 3 of this Technical Manual)
2. Quantities table to allow calculation of cost estimate (see Part 4 of this Technical
Manual).
3. Specification (see Part 6 of this Technical Manual).
4. Construction check lists (see Part 7 of this Technical Manual).
The flow chart and example Project Generator output follow below.
I-17
Hydrological
measurements?
Create output
of structure?
General
information?
Location?
Road
classification?
Existing
structure
information?
Materials
available?
DCP
measurements
Soils and
20 percentile DCP
Hydraulic capacity
of structure
x Drawings
x Quantities
I-18
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
Y of GPS
304010
1528230
3. Road Classification :
* Road classification: T, ST1, ST2, or ST3. *Road standard: A or B
Classification
Road standard
ST3
4. Scope of work: is the structure part of a road project to be carried out at the same
time or is the work for the structure only?
Structure only.
Yes
No
I-19
Number of
pipe
diameter (m)
Pipe material
Headwalls
0.6
Concrete
Masonry
Carriageway
width over
culvert
3
Width (m)
Height
Walls
Road slab
Carriage
width over
culvert
Width of
each
span
Height of
each span
Abutment
material
Piers
Deck
material
Deck
carriageway
width(m)
Number
of spans
Width
of each
span
Height
of each
span
Abutment
material
Piers
Deck
material
Deck
carriageway
width(m)
Width of
each
span
Height of
each span
Abutment
material
Piers
Deck
material
Deck
carriageway
width(m)
ramp slope
Difference in level
between road on
embankment and
crossing (m)
road material
carriageway
width (m)
I-20
Width of
crossing
(m)
ramp
slope
Difference in
level between
road on
embankment
and crossing
(m)
road
material
carriageway
width (m)
Size of
opening
Width/Dia
Size of
opening
Height
source
distance
(km)
sand
0.1
Need
borrow
pit
Need
source
of
sands
borrow
pit
distance
(km)
gravel
Need
source
of
gravel
borrow
pit
distance
(km)
2
15. Part 2
* Source of stone: quarry or stream bed. Type of stone: hard metamorphic rocks
(granite, basalt, etc).
Stone
Source of
stone
type of
stone
distance
(km)
Need
quarry
Limestone
water
supply for
concrete
Need
source
distance
(km)
pump
from
village
0.5
Normal clay
Sandy soil
I-21
Gravel
Others
location
Stream bed road centre line
Right bank abutment
Stream bed downstream
Yes
No
I-22
Irrigation is generally the most complex and also usually the least successful infrastructure
output supported by the C/S Fund.
Form T21 is used to establish the requirements and constraints for irrigation. Even if the
proposed output(s) are only an element of a larger irrigation system, it is strongly advised to
complete a Form T21 to define the requirements for the C/S Fund investment. This form is
required only one time for one irrigation system.
Form T22 is used for irrigation earthworks; these can be dams or dykes, canals or drains.
There must be a separate T22 for each earthwork, e.g. if a project comprises a dam and two
canals there must be three T22.
Form T23 is for irrigation structures, e.g. spillway, head regulator, cross regulator, culvert, etc.
There must be a separate T23 for each structure, e.g for the dam and canals above there may
be one spillway, one head regulator, two cross regulators and two culverts requiring six T23.
General project information this fills automatically from information previously filled
immediately when creating project.
Project location by entering the GPS coordinates of the structure (for irrigation projects
choose an identifiable location, e.g. the dam across a stream).
Description of the project manual entry summarising details of the project, if the output
is part of a larger project, describe the larger project and the purpose the output will
serve in relation to that project.
Operation and maintenance responsibilities manual entry for proposed operation and
maintenance of the project (Note: failure to implement operation and maintenance
procedures is a primary cause of failure of C/S Fund irrigation investments).
Irrigation system requirement these questions establish what the community expects
from the project, in both the dry and wet season.
Flooding questions about flooding establish if, when and for how long the irrigated
fields flood each year because this determines the periods and quantities of irrigation
water required (remember that paddy rice is traditional grown on land that floods part of
each year).
Existing irrigation systems these questions establish the existing irrigation systems,
their condition, whether they work and the perceived cause of problems.
Water resources these questions establish where the irrigation water will come from,
what periods of the year it is available, and how it will be delivered to the fields.
I-23
Rainfall records the nearest available rainfall record should be entered, each province
should keep on file and update annually the rainfall records so that they are available for
such purpose.
At this stage use applet T21 to calculate the irrigation water requirement on a monthly basis; it
is only necessary to enter the catchment area and chose the month of planting, and then copy
the answer from Appet to the generator.
If it is a reservoir project the applet determines:
x
It is probable that at the first attempt there will be too little water for the reservoir or river intake
proposal to work. The planting date, irrigated area and other design inputs can be adjusted to
find the best solution.
Do not be surprised if a solution is not possible, especially in locations outside the
Mekong floodplain. In many such places the landscape and rainfall patterns are
such that reliable supplementary irrigation by traditional methods is impossible to
achieve.
A final choice is made confirming the work proposed for the irrigation project.
Example
The example shown is for repair a Khmer Rouge earth dam, and canals for supplementary
irrigation of wet season rice. The work includes a new reservoir spillway and new head
regulator using medium size water gate.
For this example the attachments generated by the Project Generator will be:
1. 4No Form T22 (for one dam and three canals)
2. 7No Form T23 (for seven structures)
The flow chart and example Project Generator output follow below.
I-24
Flowchart for
Technical Form T21
Irrigation: Project
General
information?
Location?
FWUC?
O&M?
Irrigation
requirement?
Flooding
Existing
irrigation?
Rainfall
records
Planting
date?
Irrigation water
requirement
Confirms whether
reservoir or is viable
One Form T22 or T23
generated for each,
earthwork and structure
Confirm
outputs
Forms T22
each
earthwork
Forms T23
each structure
I-25
S/C:Roseisrok
Code of S/C : 31411
Yes
No
Yes
No
I-26
Operate the
pump (if the
scheme needs
a pump)?
No needed
Collect water
user fees?
Organize
maintenance
work?
Solve disputes
between
farmers about
the water?
commune
council
Gate keeper
commune
commune
paid by
council
council
commune
8. Irrigation system requirement: what is the irrigated area in hectares?
* Remark: if the project will be a part of a big irrigation project, only describe the part that
will be affected by the project.
Wet season
100
dry season
0
9. What is the main type of crop that will be grown on the land?
wet season
Rice
dry season
Nothing
10. How much of the land that has enough water every year already?
Wet season
0
number of families
0
dry season
0
number of families
0
11. How much of the land that has enough water some years?
Wet season
50
number of families
40
dry season
0
number of families
0
12. How much of the land never has enough water at present?
Wet season
50
number of families
40
dry season
0
number of families
0
number of families
80
dry season
0
number of families
0
14. Flooding: Do the fields flood for some days each year?
If Yes, answer the following questions, if No, skip to question 18.
I-27
Yes
No
Yes
No
French era
Sihanouk era
1980 to 2000
After 2000.
20. Under what program or which donor paid for the project?
21. Does the system work?
Working
Working 50%
I-28
Works a little
Not working
22. What are the main components of the system and what is their condition?
River intake
Reservoir
Dam
Spillways
Canals
< 1 month
1 to 2 months
3 to 4 months
5 months
6 months
> 6 months
condition
Not working
Collapsed
Not working
A lot of damage
A lot of damage
I-29
25. What do you judge as the main problem with the existing irrigation system?
There is no way of controlling the water, the water does not flow long enough to
guarantee irrigation for rice, but for one month or longer the fields flood and there is
too much water.
26. How can a new irrigation project overcome these problems?
It will make the reservoir work, it will store water for later in the season and help
control flooding. The canal will deliver water to the fields.
27. Do you have any other comments relevant to the proposed irrigation project?
The community does not want to pay to form a FWUC, they say they can manage
amongst themselves as they always have. This may be true but they will have
problems later paying for large maintenance. They need some support on
organisation, O&M and agricultural extension
28. Water resource: where will the water come from?
River
Reservoir
Flood lake
Canal
29. What is the water depth existing river, reservoir, lake or canal each month of the year and
is the water stationary or flowing (include largest river flowing into or out of an existing
reservoir)?
Month
depth (m)
flowing, not flowing
Jan
0
not flowing
Feb
0
not flowing
Mar
0
not flowing
Apr
0
not flowing
May
0
not flowing
Jun
0.1
not flowing
Jul
0.2
not flowing
Aug
0.5
flowing
Sept
0.1
flowing
Oct
1.2
flowing
Nov
0.9
flowing
Dec
0.3
flowing
30. How will the water be delivered from the source to the distribution canals and fields?
By pumping
I-30
By gravity
31. What is the difference in between the lowest water level at the source and the level of the
fields (m)?
* It is recommended to measure the difference in level with a survey instrument.
1.2
32. Irrigation water requirement: remark
Use Applet T21 to get monthly water requirement for irrigation and gravity flow
capacity per second.
33. Works proposed for irrigation project: What are the main works items include size that will
be repaired or newly constructed for the Irrigation Project?
* For these following questions, answer only about situation and size of the structures
chosen in this question.
Reservoir
Dam
Spillways
Head regulator
Secondary canal
Tertiary canal
Off-take
Culverts
Area (ha)
61
Volume (m3)
2200000
I-31
length (m)
800
length (m)
........
Repair or New
length (m)
drop (m)
4
Number
1
Number
1
Length (m)
1500
Number
1
number
1
number
2
I-32
General project information this fills automatically from information previously filled
immediately when creating project.
Project location enter the GPS coordinates of the start and finish of the earthwork.
Description of earthwork select from choice of: dam, dyke, canal or drain, also select
whether it is: new, improve, repair or maintenance.
Traffic use of earthwork these questions determine whether the earthwork will be used
as a track or road and therefore the required crest width and surfacing (note: it is
common for embankments to serve a dual purpose as a public road and irrigation
earthwork, this complicates maintenance because traffic damage can compromise
irrigation operations.
Condition of existing dams and dykes if the earthwork is a dam or dyke the condition
must be entered manual and then a choice made from a list of common causes of
damage.
Condition of existing canal and drain - if the earthwork is a canal and drain the condition
must be entered manual and then a choice made from a list of common causes of
damage.
Soils select either the soils that will be use as (a) fill or (b) excavated for canals or
drains. The advises whether the material is suitable as fill, safe fill or cut slopes, and
whether canals or drains should be lined are provided next to the choices.
Availability of fill material if the earthwork is a dam or dyke answers on the type,
questions must be answered concerning the quality, location and distance from site of fill
materials.
Design of dam or dyke if the earthwork is a dam or dyke questions the design water
level must be entered, the freeboard to calculate earthwork crest level, whether the
earthwork is a road, the crest width and road surfacing, the upstream and downstream
slopes, the method of slope protection for each slope, the class, thickness and filter
requirements if rock riprap is used on the upstream slope.
Capacity of canal Manually multiply the flow rate of canal to the irrigated areas. A
default flow of 2 l/s/ha to the area of fields supplied is used but can be overridden. If the
canal is supplied by pumps the hours pumped each day must be entered to calculate the
pumping rate.
Capacity of drain Manually multiply the flow rate of canal to the irrigated areas. A
default flow of 3.5 l/s/ha to the area of fields drained is used but can be overridden.
There are some questions to establish the concept for drainage (this is often overlooked
and becomes another cause for failure). If the drain receives flow from a larger
catchment area, details of this catchment must be entered in the same way as Form T12
Road: Structure in Applet T22 External catchment flow. The required flow capacity of
the drain is the sum of the flow from the fields and that from a larger catchment area.
Hydraulic design of canal or drain Having established the required capacity of the
canal or drain the hydraulic calculations are the same and the same applet is used for
both types of channel. It is necessary to enter the upstream and downstream bed levels,
the side slopes and bed width, the freeboard. The calculation is iterative. A water depth
is entered: if it is too small Applet T22 instructs to Increase depth; if it is too large the
I-33
Applet instructs to Decrease depth; if the depth is correct (within a band of tolerance)
the Applet prints Depth OK. The Applet then outputs the: minimum height of banks
above bed level; width between tops of bank; and velocity of design flow.
x
Responsibility for operation and maintenance these questions check whether there is
a FWUC to take responsibility for design and maintenance and if not who will carry out
design and maintenance.
Example
The example shown is for rehabilitation of a Khmer Rouge canal downstream from a reservoir.
But in this example the canal must also operate as a drain. Therefore it is necessary to
calculate the required capacities as both a canal and a drain; then use the larger of the two
flows for the hydraulic design of the channel.
For this example the attachments generated by the Project Generator will be:
1. Template drawing(s) when available for chosen output code(s) (See Part 3 of this
Technical Manual).
2. Spreadsheet for calculation of earthwork quantities (See Part 4 of this Technical
Manual).
3. Quantities table to allow calculation of cost estimate (See Part 4 of this Technical
Manual).
4. Specification (see Part 6 of this Technical Manual).
5. Construction check lists (see Part 7 of this Technical Manual).
The flow chart and example Project Generator output follow below.
I-34
Flowchart for
Technical Form T22
Irrigation: Earthwork
Create
Output?
General
information?
Location?
Description of
earthwork
Traffic use
Condition of dams,
dykes
canals or drains?
Soils?
Design dam or
dyke
Calculation
manually in
Generator
Capacity of
canal?
Capacity of
drain?
T22 External
catchment flow.xls
Hydraulic design
canal or drain
Calculation
manually in
Generator
Applet calculates
size of channel
T22-Design canal
or drain.xls
I-35
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
Y of GPS
1528030
1528230
Periodic maintenance
4. Traffic use of earthwork: Is the earthwork used as a public road or for farm access?
If Not used skip to question 11.
Public road
Farm access
Not used
5. Has the earthwork ever had Laterite or any other kind of improved surface in the past?
Yes
No
6. Is there any Laterite or any other kind of surface on the earthwork now?
I-36
Yes
No
Passenger car
People walking
Motorcycle
Motor-remorque
Bicycle
Animal cart
Light vehicle/van
Koyun
Mini-bus (4 tyres).
8. Approximately how many of these vehicles use the earthwork per day?
* In PCU units, you can use Applet T11 to help your calculation of the number of vehicle.
0
9. According the traffic of vehicle above, what type of pavement is suitable for this
earthwork?
* if the number of vehicle is < 21 Earth surface is satisfactory.
* if the number of vehicle is < 25 Light Laterite surface is satisfactory
* If number of vehicles is <100 Medium Laterite surface is satisfactory
* If number of vehicles is >100 Too much traffic for Laterite surface consider other
option.
10. Condition of the existing dams or dykes and Canals or drains: describe the condition of
the existing earthwork.
The banks are eroded, breach and broken down so that water from the reservoir
goes everywhere and often floods the fields.
I-37
Others
Blocked by weed
Silted-up
Bank erosion
Clay group, stable slope: upstream 1:2.00, downstream 1:1.75, Canal and drain
1:1.25
Sandy group, stable slope: upstream 1:2.50, downstream 1:2.00, Canal and
drain 1:1.50
Silty soil, stable slope: upstream not suitable, downstream not suitable, Canal
and drain 1:1.50
Dispersive clay, upstream not suitable, downstream not suitable, canal and
drain : Line canal
Organic soils, upstream not suitable, downstream not suitable, canal and drain
: Line canal.
I-38
source (km)
3
17. Sands
* Source: borrow pit, stream bed.
Source
distance (km)
18. Gravel
* Source: borrow pit, stream bed
.Source
distance (km)
19. Laterite
* Source: borrow pit, stream bed. Quality: Good, medium or poor.
Source
Quality
distance (km)
20. Stone
* Source: quarry, stream bed. Type: granite, basalt, limestone
Source
type
distance (km)
distance (km)
1
22. Design of dam and dyke: What is reservoir full supply level at dam or flood levels at dyke
(m)?
23. What freeboard will be allowed (m)?
* You can get the values of freeboard from PIM.
24. Dam or dyke crests level (before any road surface is added), (m).
25. Will the dam or dyke be used as a road?
26. What is the crest width?
27. Will the crest be surfaced?
If Others, answer the following question.
Not surfaced
I-39
Laterite
Others
None
Grass
Rock riprap
Others
Class A
Class B
Class C
Class D
35. What thickness of riprap in millimeters (300 mm minimum for Class A)?
36. What filter will be placed below riprap?
150mm gravel
None
Grass
38. Capacity of canal: Will the canal be irrigated continuously (24 hours) by gravity or by
pumping?
If Gravity, answer the question 40, then skip the question 41. If Pumping, skip the
question 41, then answer the question 41.
I-40
Gravity
Pumping
Separate drain
Canal as a drain
No drain
42. Explain how excess rainfall and flood water will be drained from the fields?
43. Drain capacity
* Recommended flow rate 3.5l/s/ha, or another higher flow rate.
* Flow capacity (m3/s) = area (ha) x flow rate (m3/s/ha)
Drainage area (ha)
100
44. Will the drain collect water from catchments beyond the fields?
* E.g. a stream flows into the head of the drain from a small catchment or another
irrigation system? If Yes, answer the following questions, if No skip to question 48.
Yes
No
I-41
external catchment or get help from engineer to calculate the total flow (with the flow in
the catchment above).
1.5
46. The flow rate of external catchment (m3/s) is:
Use Applet T22 external catchment then copy form column C32.
If the flow system of the external catchment is too complicate, you have to discuss with
the engineer to get the flow capacity of this catchment.
2.61
47. Total drain design flow (m3/s) is the flow from irrigated area + flow from external
catchment.
* Value of question 43 + value of question 46.
2.96
48. Hydraulic design of canal and drain: remark
Use Applet T22 Hydraulic design of canal and drain to calculate the minimum water
height, bottom width and design velocity.
49. Responsibility for operation and maintenance: is there a Farmer Water Use Comity
(FWUC) or similar group of people who are responsible for operation and maintenance
of the earthwork.
Yes
No
I-42
For Small Irrigation Flow Control Structures calculating irrigated and/or drainage flow
(If your irrigation project consists of both earthwork and structure, use the earthwork
flow).
For Miscellaneous Irrigation Structures using Applet T23. In this applet you need to
answer some questions about the hydrology of the catchment similar to Form T12 Road:
Structure. Also the weir crest level and the maximum safe and acceptable upstream
water level must be entered. The applet then outputs the length of the weir. These
answers will need to be entered in the part of Spillways and diversion weirs belw.
After that create output of Irrigation Structure then answer T23 questions on:
x
General project information this fills automatically from information previously filled
immediately when creating project.
Proposed structure select the structure type from the list, the remaining sections of the
form appear as required by this choice.
Foundation soils including results for DCP tests description options for type of soil and
DCP test results with GPS coordinates (Enter each DCP test result to Applet T11 and
get the 20 percentile DCP strength).
Road crossing questions on whether a road crosses the structure, the type of road and
the numbers and types of vehicle using the road.
Hydraulic capacity questions require entry of the hydraulic capacity of the structure
depending on whether it is a canal or drain (these answers come from the flow
calculated above). There is also an important question whether the capacity can be
exceeded (e.g. if a drain receives flow from an external catchment, or if a spillway
passes a larger than design flood). The circumstance and consequences of an
overdesign flood must be stated (this may require specialist advice).
Spillways and diversion weirs questions will need to be answered if this type of output
is proposed by copying from the applet T23 used above.
Pumping capacity if the output is a pump then the pumping capacity must be
confirmed, this may come from Form T22.
Responsibility for operation and maintenance these question check whether there is a
FWUC to take responsibility for design and maintenance and if not who will carry out
design and maintenance.
Example
The example shown is for a concrete spillway as part of the works to rehabilitate a Khmer
Rouge reservoir and irrigation system.
For this example the attachments generated by the Project Generator will be:
1. No template drawing(s) are available for chosen output code(s), for the example shown
a template is not suitable and a custom drawing will be needed on all occasions (See
Part 3 of this Technical Manual).
I-43
2. No quantities table to allow calculation of cost estimate (See Part 4 of this Technical
Manual).
3. Specification (see Part 6 of this Technical Manual).
4. Construction check lists (see Part 7 of this Technical Manual).
The flow chart and example Project Generator output follow below.
I-44
Flowchart for
Technical Form T23
Irrigation: Structure
Applet T23 calculates
design flow and
length of weir
(Miscellaneous
Irrigation Structures)
Spillway weir.xls
Design flow
Create
Output
Control Structures)
and use Study and
Design Guideline to
determine the output
Spillway weir.xls
General
information?
Location?
Materials
available?
DCP
measurements
Soils and
20 percentile DCP
Road
crossing?
Hydraulic
capacity?
Spillway/weir
size?
From Form(s)
T22
Pumping
capacity?
x Drawings
x Quantities
I-45
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
Y of GPS
1528230
3. Fill type 3
Source: borrow pit
Source
Borrow pit
4. Sands
Source: borrow pit or stream bed.
Source
Borrow pit
5. Gravel
Source: borrow pit or stream bed. Remark: for concrete work, the gravel from stream
bed is not permitted.
Source
Borrow pit
6. Stone
Source: quarry or stream bed. Type of stone: Hard metamorphic rock (granite, basalt,
etc), limestone and sandstone.
Source
type of stone
I-46
Source
Bottom of reservoir
Normal clay
Sandy soil
Gravel
Others
location
stream bed road centre line
left bank abutment
stream bed downstream
Yes
No
District to district
I-47
District to commune
Commune to commune
Commune to village
Village to village
Farm acces
Passenger car
People walking
Motorcycle
Motor-remorque
Bicycle
Animal cart
Light vehicle/van
Koyun
Mini-bus (4 tyres).
15. Flow capacity: what is the design flow capacity (can be from T22), (m3/s)?
* Calculated from canal capacity. You can skip this question for spillways or river intake.
Generally, if the design structure is passed by the irrigation flow and drainage flow, you
must design the structure the drainage flow, because its value is always higher.
16. What is the flow capacity at the structure (m3/s)?
I-48
* Calculated from canal capacity. You can copy skip question for spillways or river
intake. Generally, if the design structure is passed by the irrigation flow and drainage
flow, you must design the structure the drainage flow, because its value is always
higher.
17. Can this flow capacity be higher than design one?
If Can, answer the following questions, if Can not skip them.
Can
Can not
18. Describe the circumstance and consequence for the structure also what provision will
be provided to survive an extreme flow?
Using the design guidance spillways is sized for 1 in 50 year flow into the reservoir; the
reservoir freeboard allows some of the flood to stay temporarily in the reservoir until it
call all pass over the spillways. A concrete stilling basin and erosion protection will be
provided downstream.
19. Did you use Applet to determine the design flow and length of structure? (Spillway and
diversion weirs)
* if you dont design the spillway or river intake, skip them.
Yes
No
20. Spillway and diversion weirs: is the structure for reservoir or river intake?
Reservoir
River intake
21. What is the design flow for spillway or river intake (m3/s) ?
* Copy from Applet T23, worksheet GTFM: C32.
15.35
22. What is the maximum safe water level at the upstream of structure? ( higher than this
level, it can be flooded, overtopped).
* Copy from Applet T23, worksheet GTFP: C33.
23
I-49
23. What is the proposed weirs crest level? ( it is a full water level of a reservoir or river
level intaking to the system).
* Copy from Applet T23, worksheet GTFM:C34.
22.5
24. Required weirs length (m):
* Copy from Applet T23, worksheet GTFM:C35.
26
25. Pumping capacity: provide the pumping capacity (m3/s).
* Answer if there is a pumping, see the irrigation project form T22.
26. Responsibility for operation and maintenance: is there a Farmer Water User Comity
(FWUC) or similar group of people who are willing to take responsibility to operate and
maintain the structure?
Yes
No
I-50
Number of proposed outputs enter the number or sizes of the proposed output
selected above.
Purpose of water supply Select from four options: domestic, school, health facility or
other.
Information about number of users the questions identify the number and type of
users; these are for statistical purposes not for calculation although the information can
be used for a hand calculation if needed (see Part 5 of this Technical Manual).
Maintenance manual entry of who will maintain the water supply facility.
Existing water supply the questions are focused on where the people who will use the
new water supply are getting water at present, this provides an indication of the benefit
of the new water supply.
Information about site of proposed facility the questions focus on ownership of the land
used for the water supply and whether there is a flood risk which could interrupt or
permanently contaminate the water supply.
Existing wells for any water supply project that includes a new well or pond information
from existing wells is the best indicator of water depth and variation over the year, water
quantity and quality, the type of ground or rock where the well is sunk. Take time to
collect and consider the information from as many wells as is practical. The questions
are answered for each existing well.
Proposed well(s) if new wells are required the questions concern the location, well
depth, water depth and ground conditions at the well site, and potential causes of
contamination. Some of the questions may be difficult to answer but make best use of
information from existing wells or other local knowledge. The questions are answered
for each well proposed.
I-51
Suitable pump for well the dynamic water level for the proposed well determines the
type of pump which can be selected.
Proposed pond the main issues for a pond are where the water will come from to fill it
and whether it will have any water during the dry season. Ponds in sandy soil will may
fill by groundwater flow but if groundwater level drops below the bottom of the pond
during the dry season any water in the pond will soak away. Ponds in clay soils will not
leak but rely on rainfall, water from a stream or deeper well during the dry season.
Each form is completed by confirming the required outputs which will generate the
drawings and quantities for template designs which have been loaded into the Project
Generator. Where no template exist, the description and quantities will have to be
prepared separately.
Example
The example is for a school water supply and comprises two outputs:
x
For this example the attachments generated by the Project Generator will be:
1. Template drawings for the drilled well with VN No6 pump. At the time of preparation of
this manual there was no template for a plastic rainwater tank and roof collection
system, the particular requirements will have to be prepared for the project e.g. by
reference to MoEYS standards (See Part 3 of this Technical Manual).
2. Quantities table to allow calculation of cost estimate will be produced by the project
generator. The water tank can be measured as 1 item (See Part 4 of this Technical
Manual).
3. Specification (see Part 6 of this Technical Manual).
4. Construction check lists (see Part 7 of this Technical Manual).
The flow chart and example Project Generator output follow below.
I-52
Flowchart for
Technical Form T31
Water Supply
Create
output?
General
information?
Location?
List
proposed
outputs?
What will be
supplied?
Number of
users?
Responsibility for
maintenance?
Existing water
supply?
Site
information?
Existing well
information?
Water Supply
Continued
below
I-53
Water Supply
Continued
from above
or
or
Proposed
well(s)?
or
or
Proposed
Pond(s)?
Proposed
Tank(s)?
Proposed pipe
system?
Confirm well
outputs?
Confirm pond
outputs?
Confirm tank
outputs?
Confirm pipe
outputs?
Well output
codes
Pond output
codes
Tank output
codes
Pipe output
codes
Recommended
Pump (advice)
x Drawings
x Quantities
x Drawings
x Quantities
x Drawings
x Quantities
x Drawings
x Quantities
I-54
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
Y of GPS
1528230
Purpose of water supply: for what purpose is the water supply used?
If the Village, answer the question 5, if School or Health center, answer question 6.
Village
School
Health centre
Information about number of users: how many people use the water supply? In which
village do they live?
* Totalize the numbers above and write it down in the last row.
Name of village
people in village
I-55
* If you chose School in the answer above, write down only the number of rooms and
number of students. If you choose Health post write down only the number of users in
the health center.
Number of school rooms
8
Existing water supply: how many families use the existing water supply?
* if the existing water supply is for school, write down only use for school.
Use for school
Have the families who will use the supply agreed to form a Water Supply Committee?
Yes
No
Where does the domestic water used by these people come from now?
* Source: watercourse, natural pond, dug pond, rain water harvesting, spring, village
well, household will, water-point piped. Totalize the number of users, and then write it
down in the last row.
Source
Village well
Family well
number of users
250
200
Information about proposed facility: Who owns the land where the new facility will be
constructed?
* if the land is in private ownership, answer the question 12.
Community
Private
Does the landowner agree to construction and unrestricted use of the facility?
Yes
Study and Design Guidelines
I-56
No
Yes
No
Existing well: what type of well are in the village or near vicinity?
* You should choose the existing well which is closest to the new well
Dug well
Drilled well
Mixed well
17. Provide the coordinates of GPS
Type of well
Dug well
X of GPS
304090
Y of GPS
1528230
18. What is the distance (closest) from the existing well to the proposed well (km)?
0.30
19. Who owns this existing well?
villagers
20. Is the existing well used for domestic water or farming?
I-57
Domestic water
Framing
21. How old is the existing well?
4 years
22. How deep is the existing well?
20
23. What is the static water level in the dry seasons?
4
24. What is the static water level in the wet seasons?
2
25. How many families use the sell?
40
26. Does the existing well have enough water all year?
Enough
Not enough
27. What does water from the well taste like?
Note taste
Salty
Bitter
28. What is the color of the water in the existing well?
Clear
Gray
Yellow
I-58
Brown
29. Does it smell?
Yes
No
30. Has the water from the existing well ever been tested for arsenic?
Yes, ever
No, never
31. What kind of soil or rock is the well sunk in?
From depth (m)
0
6
to depth (m)
6
20
32. How do you know about the information on the soil or rock?
Commune chief told me.
33. How are the other well ?
to depth (m)
6
20
36. How deep is the water bearing soil or rock (the aquifer)?
I-59
6
37. What is the depth of proposed well?
20
38. What is the static water level in the dry season (depth below ground in metres)?
4
39. What is the estimated dynamic water level in the dry season (drawn down by pumping)
(depth below ground in metres)?
6
40. How do you know the information on the proposed well?
Village well
41. Where will wastewater from the new well drain to?
If Other, answer the question 43.
Soak away
Watercourse
Pond
Other
42. If Other, list your answers.
43. Is there anything close to the well that could cause contamination of the well?
* If Other, answer the question 45.
None
Latrine
Animal pens
Cmetery
Chemical store
Fuel store
Other
44. If other, list your answers.
I-60
to depth (m)
50. Where will the water to fill the pond come from?
If the answer is rainwater harvesting, answer question 52, if Other, answer question 53.
Description
Plastic water
tank filled by
roof runoff
Quantity
Advice
I-61
Quantity of proposed outputs enter the number or length of the proposed outputs
chosen above.
Information about education requirement the question concern the numbers of children
from different villages who use the school, travel distance, number of existing and
proposed classrooms, availability of teachers and the school management committee.
Physical characteristics of the site questions relate to flooding, UXO, land title, whether
the site is large enough, whether there is a water supply and whether sanitation facilities
exist.
Foundation soils the form provides for filling trial pit logs and recording DCP results, as
many as necessary.
Example
The example is for:
x
primary school furniture (25 four student desks, 50 two student desk, five teacher tables
and chairs)
80 m of boundary wall,
one well
For this example the attachments generated by the Project Generator will be:
1. Template drawing(s) when available for chosen output code (See Part 3 of this
Technical Manual).
2. Forms T31 and T101 generated for outputs in Water Supply and Sanitation respectively
I-62
3. Quantities table to allow calculation of cost estimate will be produced by the project
generator (See Part 4 of this Technical Manual).
4. Specification (see Part 6 of this Technical Manual).
5. Construction check lists (see Part 7 of this Technical Manual).
The flow chart and example Project Generator output follow below.
I-63
Flowchart for
Technical Form T41
Education Facility
Create
output?
General
information?
Location?
Quantity of
proposed
outputs?
Educational
requirement?
Sanitation: Latrine
codes
DCP
measurements
Information
about site?
Soils and
20 percentile DCP
x Drawings
x Quantities
I-64
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
Y of GPS
304010
1528230
Number of children go to
the school
52
108
84
120
I-65
3
7. About the number of teachers
teachers provided by the
education department
2
Yes
No
9. Physical characteristics of the site: does the site ever flood in the wet season?
* if Ever, answer the two following questions.
Ever
Never
10. What is the maximum depth of flooding in meters?
0.15
11. What type of flooding?
Yes
No
13. Does land title exist for the site?
* If Yes, answer the following questions.
Yes
I-66
No
14. What stage is the documentation (district, province)?
Province
15. Is the site presently occupied?
* If Yes, answer the following questions
Yes
No
16. Whom or what? (E.g. building, rice field and will compensation be expected/demanded?)
Old school
17. Is the site presently walled or fenced?
Yes
No
18. Will land fill or embankments be needed to protect against flooding?
* If Yes, answer the question 19
Yes
No
19. If Yes, describe it.
20. Is there enough space for students to play sports?
Yes
No
21. Is there enough space to build more classrooms in the future?
Yes
No
Study and Design Guidelines
I-67
None
Pond
Pumping well
Piped supply from off site
23. Write down the dry season water level below ground (m)
2.6
24. How many existing latrines at the sites?
0
25. Foundation soils: (for school building construction, school fence and walls)
What kind of soil will the school be constructed on?
* Type of soil: gravel, silty sand, micaceous sand, lateritic sand, clayey sand, loams,
organic clays, lateritic clays, dandy, silty or clayey peats.
Number
of trial pit
1
X of
GPS
304015
Y of
GPS
1528220
Depth (m)
Type of soil
group of soil
0.15
1.5
organic
silt
silty sands
2.0
gravel
Fine grained,
cohesive
course grained, noncohesive
course grained, noncohesive
X of GPS
304015
304000
304030
Y of GPS
1528220
1528222
1528218
I-68
Proposed
output
Description
Quantity
1040501
primary
school
furniture
1040405
boundary wall
80m
1100102
four latrines
1030201
well
Advice
Fill form T41 Education Facility
again and only answer some
relevant questions to your chosen
output and those questions are
recommended directly in the
Project Generator.
Fill form T41 Education Facility
again and only answer some
relevant questions to your chosen
output and those questions are
recommended directly in the
Project Generator.
Fill form T101 Sanitaiono and only
answer some relevant questions to
your chosen output and those
questions are recommended
directly in the Project Generator.
Fill form T31 Water supply and only
answer some relevant questions to
your chosen output and those
questions are recommended
directly in the Project Generator.
I-69
Quantity of proposed outputs enter the number or length of the proposed outputs
chosen above.
Information about health facility the village, populations and distances travelled tpo
reach the health facility as well as the availability of trained staff.
Physical characteristics of the site questions relate to flooding, UXO, land title, whether
the site is large enough, whether there is a water supply and whether sanitation facilities
exist.
Foundation soils the form provides for filling trial pit logs and recording DCP results, as
many as necessary.
Example
The example is for:
x
one well:
For this example the attachments generated by the Project Generator will be:
1. Template drawing(s) when available for chosen output code(s) (See Part 3 of this
Technical Manual).
2. Forms T31 and T101 generated for outputs in Water Supply and Sanitation respectively
3. Quantities table to allow calculation of cost estimate will be produced by the project
generator (See Part 4 of this Technical Manual).
4. Specification (see Part 6 of this Technical Manual).
I-70
I-71
Flowchart for
Technical Form T51
Health
Create
output?
General
information?
Location?
Quantity of
proposed
outputs?
Health service
requirement?
Sanitation: Latrine
codes
DCP
measurements
Information
about site?
Soils and
20 percentile DCP
x Drawings
x Quantities
I-72
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
Y of GPS
304010
1528230
I-73
Ever
Never
9. If Ever, what is the maximum depth of flooding in meters?
10. If Ever, what type of flooding?
Yes
No
12. Does land title exist for the site? If yes, at what stage is the documentation (district,
province)
Province
13. Is the site presently occupied? If yes, list them.
* e.g. building, rice field will compensation be expected/demanded?
Old health post
14. Is the site presently walled or fenced?
Yes
No
15. Will land fill or embankments be needed to protect against flooding?
Yes
No
16. What is the water supply at the site?
None
I-74
Pond
Pumping well
Piped supply from off site
17. How many existing latrines at the site?
0
18. Foundation soils: what kind of soil will the health facility be constructed on?
* Kind of soil: gravel, silty sand, micaceous sand, lateritic sand, clayey sand, loams,
clayey silts, organic silts, micaceous silts, sandy clays, silty clays, organic clays, sandy;
silty or clayey peats.
Number
of trial pit
1
X of
GPS
304015
Y of
GPS
1528220
Depth (m)
Type of soil
group of soil
0.15
1.5
organic
silt
silty sands
2.0
gravel
Fine grained,
cohesive
course grained, noncohesive
course grained, noncohesive
X of GPS
304015
304000
304030
Y of GPS
1528220
1528222
1528218
1050112
1050114
Description
boundary
fence
wooden gate
Quantity
Advice
120m
I-75
1100102
four latrines
1030511
rainwater
collection and
storage tank
1030201
well
I-76
Project location enter the GPS coordinates of the proposed output, if it is a linear
project such as a covered drain enter the start and finish coordinates, if it is a point
project such as school laterine, enter a coordinate of the laterine.
Quantity of proposed outputs enter the number or length of the proposed outputs
chosen above.
hydraulic design of channel drain if the output is a channel drain Applet T101
calculates the size of the drain. There is an option to accept or override the preceding
capacity calculation (but do not enter a lower capacity). Enter the bed levels and length
of the drain, bed width, side slope and Mannings n using the guidance on the form.
The calculation is iterative. A water depth is entered: if it is too small the Applet instructs
to Increase depth; if it is too large the form instructs to Decrease depth; if the depth is
correct (within a band of tolerance) the form prints Depth OK. The Applet then outputs
the: minimum height of banks above bed level; width between tops of bank; and velocity
of design flow. After that you need to copy all of these results to the generator.
Hydraulic design of pipe drain (once for each drain) enter the depth of the bottom of
the pipe below ground and the length of drain. You then calculate the maximum
hydraulic gradient. Use the tables on the form to select the minimum pipe diameter, it is
permitted to go a size or more up to a larger diameter. There are different tables for
plastics and concrete pipes.
Example
The example is for covered channel drains both sides of road through a village center, each
about 100 m in length, including a connecting pipe beneath the road to outfall.
For this example the attachments generated by the Project Generator will be:
1. Template drawing(s) when available for chosen output code(s) (See Part 3 of this
Technical Manual).
I-77
2. Quantities table to allow calculation of cost estimate will be produced by the project
generator (See Part 4 of this Technical Manual).
3. Specification (see Part 6 of this Technical Manual).
4. Construction check lists (see Part 7 of this Technical Manual).
The flow chart and example Project Generator output follow below.
I-78
Flowchart for
Technical Form T101
Sanitation
Create
output?
General
information?
Location?
Quantity of
proposed
outputs?
Calculation in the
form
Applet calculates advise
size of pipe
Pipe chart.xls
Capacity of
drain(s)?
Applet calculates
size of channel
Size of
drain(s)?
T101 Channel
design.xls
x Drawings
x Quantities
I-79
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
1. Location: where is the sanitation and drainage located within the Sangkat/commune?
Describe the location
The box drain locates in the centre of Phsar Leu village.
2. Provide de coordinate of GPS.
* if it is a point, fill only the first row. First row is the starting point and the second row is
the ending point.
X of GPS
Y of GPS
304010
1528230
305100
1528250
3. Description of requirements: give a brief description about the project.
Build covered channel drains both sides of road through Phsar Leu, each about
100 m in length, include pipe from north to south side of road to outfall.
4. List the number or length of the proposed outputs.
* provide the number for the latrines and length for the drain.
Output
Box drain
Number or length
200
5. Drainage capacity: give drain a name; area of land drained, flow rate (m3/s/ha), flow
capacity and external catchment.
* in peri-urban or village can allow for 50m wide strip from road centerline for drains each
side of road. Recommended flow rate is 3.5l/s/ha, but you choose another value. The
required flow capacity of drain = flow rate x drained area. Will the drain collect water from
catchments beyond the drain, e.g. a stream flow into the head of the drain from a small
catchment or drain system? Write down Collect or Does not collect.
I-80
Name of drain
Box drain,
north of
Phsar Leu
Box drain,
south of
Phsar Leu
6. Remark
Drained area
(ha)
0.5
Flow rate
(l/s.ha)
0.5
Flow capacity
(l/s)
2.5
External
catchment
Collect
0.5
0.5
2.5
Does not
collect
Description
There is irrigation area of 30ha flows in
the north Phsar Leu box drain
8. Give a name of drain collecting water from external catchment, area of external
catchment, flow rate (l/s/ha) and extra flow capacity.
* if catchment area > 1.0Km2, flow from this catchment will be too big for a culvert or a
drain, so let think about the flow conveyance or a special advice.
* Recommended drain flow capacity is 3.5l/s.ha, but you can choose another one.
* flow capacity extra = catchment area (ha) x flow rate (l/s.ha).
Name of drain
External catchment
area (ha)
30
* Total design flow capacity = drain flow capacity (l/s) + extra flow capacity of external
catchment (l/s)
Name of drain
Box drain north of Phsar Leu
Box drain south of Phsar Leu
I-81
Name of drain
Required flow
capacity (l/s)
107.5
Box drain
north of
Phsar Leu
Box drain
2.5
south of
Phsar Leu
12. Design of pipe drain: remark
0.49
Width of box
drain (m)
0.6
Design velocity
(m/s)
0.46
0.19
0.15
0.18
Required
flow
capacity
(l/s)
Pipe
drain
depth
(m)
Pipe
length
(m)
Efficient
hydraulic
gradient
Type of
pipe
Minimum
diameter
(m)
Chosen
diameter
(m)
14. Remark
Upload the Applets youve used to get the result as above.
I-82
District : Sreisanthor
S/C:Roseisrok
Code of S/C : 31411
1. Location: where is the sanitation and drainage located within the Sangkat/commune?
Describe the location.
At the Phsar Leu village centre
2. Provide de coordinate of GPS.
* if it is a point, fill only the first row. First row is the starting point and the second row is
the ending point.
X of GPS
304500
304530
Y of GPS
1528240
1528260
Number or length
100
5. Drainage capacity: give drain a name; area of land drained, flow rate (m3/s/ha), flow
capacity and external catchment.
* in peri-urban or village can allow for 50m wide strip from road centerline for drains each
side of road. Recommended flow rate is 3.5l/s.ha, but you choose another value. The
required flow capacity of drain = flow rate x drained area. Will the drain collect water from
catchments beyond the drain, e.g. a stream flow into the head of the drain from a small
catchment or drain system? Write down Collect or Does not collect.
Name of drain
Pipe drain,
downstream of
Phsar Leu
Drained area
(ha)
0.5
Flow rate
(l/s.ha)
5
Flow capacity
(l/s)
2.5
External
catchment
Collect
6. Remark
I-83
Description
With 30ha of irrigation area, flow to
the north of road
8. Give a name of drain collecting water from external catchment, area of external
catchment, flow rate (l/s.ha) and extra flow capacity.
* if catchment area > 1.0Km2, flow from this catchment will be too big for a culvert or a
drain, so let think about the flow conveyance or a special advice.
* Recommended drain flow capacity is 3.5l/s.ha, but you can choose another one.
* flow capacity extra = catchment area (ha) x flow rate (l/s.ha).
Name of drain
Pipe drain
downstream of
Phsar Leu
External catchment
area (ha)
30
9. Calculate the total design flow capacity for box culvert (l/s).
* Total design flow capacity = drain flow capacity (l/s) + extra flow capacity of external
catchment (l/s)
Name of drain
Pipe drain downstream of Phsar Leu
Required flow
capacity (l/s)
Width of box
drain (m)
Design velocity
(m/s)
I-84
13. Result of the design of pipe drain from Applet Pipe Chart
* Skip it if you dont design the pipe drain.
* calculate the flow capacity, see the suitable pipe and copy the answer from Applet Pipe
Chart that you used.
Name of
drain
Pipe drain
downstream
of Phsar
Leu
Required
flow
capacity
(l/s)
107.5
Pipe
drain
depth
(m)
1
Pipe
Efficient Type of
length hydraulic pipe
(m)
gradient
100
0.008
Minimum Chosen
diameter diameter
(m)
(m)
Concrete 0.8
0.8
14. Remark
Upload the Applet you used to get the result as above.
I-85
PART 3:
TEMPLATE DESIGNS FOR
LOCAL INFRASTRUCTURE
I-86
I-87
settings. This will ensure the A4 prints can be read, particularly if copied successively on a
photocopier because each round of photocopying looses quality.
3.4.3 Dimensions
All of the dimensions needed to construct the output are shown on the drawings. If a dimension
is missing, resolve the matter locally or by seeking advice from supervisors. In every case
advise the supervisor who should ensure that the drawing is amended to show the missing
dimension (see 3.4.4).
Most dimensions are in millimeters. Some dimensions are in meters, but this is always shown
on the drawing. So, 2000 means 2000 millimeters, or 2 meters; 2 m means 2 meters.
3.4.4 Revisions
Each drawing sheet includes a revision table above the title block. This is to be filled whenever
a template drawing is changed so that there is a history of the change. The amended design
must be reloaded to the Project Generator; amending also the quantity tables if necessary (see
Part 5).
The box should also be filled if a template is changed to fit the requirements of a particular
project. This can be done in hand on hard copy issued to the contractor. Senior advisors
should be consulted to confirm such change and can decide if this change should apply only for
the project or for wider use of the Template.
3.4.6 How to read the steel details and the steel schedule
For most outputs with reinforced concrete elements, separate reinforcement drawings are
included, with separate bar schedules. For some small outputs (e.g. width restriction posts) the
reinforcement requirement and schedule is included on the drawing.
On a design drawing, reinforcement is usually divided into position sets of bars. Each set is
labeled by a number (e.g. f), the number of bars used, the diameter of bar and the spacing.
Following construction industry convention and the software settings (see below) bars the
description of bars may be in several ways.
Bar call-up type and arrangement
Description
f1010@200
1010@200f
f10@200
10f
When bar schedules have been produced these have been generated using SofiCAD, which is
a proprietary add-in software for AutoCAD (see section 3.5). It is not essential to use SofiCAD
for producing future template designs. However the use of software makes drawing production
easier and reduces mistakes so it is advisable to use software for more complicated drawings.
Using SofiCAD will ensure consistency with existing Templates.
I-88
Whenever there is an output that has a bar schedule this is loaded and output by the Project
Generator together with the drawing.
An example of a bar schedule is shown below. The schedule shows the output number and
steel grade for the bars.
Pos:
No:
d:
diameter in millimeters.
Length:
Dbr ds:
Not used.
Type:
Shape code: A diagram showing the shape and dimensions of a bent bar, where
dimensions vary because of a tapering shape, a table is included to show
the dimensions of each bent bar. Dimension of figures are centimeters.
Total length:
Total length of steel used for all the bars at that position (e.g. for position
f total length 26 x 1.9 = 49.4 meters).
Weight:
I-89
Templates. It is desirable that any additional templates also follow the same standard
AutoCAD format. The remainder of this sub-section specifies the AutoCAD format.
All drawing prepared using the AutoCAD software should comply with these instructions in order
to facilitate data exchange and uniformity of layout.
The drawing unit for the MODEL space shall be meters. Drawing dimensions are in
millimeters.
Type: Decimal
Precision: 0.0000
Type: Decimal degrees
Precision: 0.000
Unit to scale inserted content: meter
The drawing frame, title block and scale bars and legends have to be in LAYOUT space. All
other objects shall be in MODEL space.
Regardless of the version of AutoCAD with which the drawings are produced, all drawings
files are to be saved in AutoCAD 2004 format. Set software as follows:
Menu > TOOLS > OPTIONS > tab Open and Save > Save as: AutoCAD 2004 (*.dwg)
I-90
Margins
Left
ISO A3
Right
Above
Below
420 x 297
No. of Color
Color
Pen Color
Red (1)
Black (7)
0.18
Yellow (2)
Black (7)
0.25
Green (3)
Black (7)
0.35
Cyan (4)
Black (7)
0.5
Blue (5)
Black (7)
0.7
Magenta (6)
Black (7)
1.0
White/Black (7)
Black (7)
0.10
Black (7)
0.05
0.05
NCDD.ctb
Description
1-AXIS
1-DIM
1-HATCH
1-HELP-OFF
Help lines
1-INV
1-CUT-LINE
1-TEXT
Z-FRAME
Frame
Z-VIEWPORT
Z-VIEWPORT-OFF
TITLEBLOCK
Color
Line Type
White
Centre2
Red
Cont.
Cont.
Magenta
Cont.
Red /White
Hidden
Green
Centre
Red
Cont.
Yellow
Cont.
Cont.
Magenta
Cont.
Yellow
Cont.
Plot
Yes/No
no
no
I-91
Description
Color
CON-SEC
Concrete sections
CON-VIEW
Concrete view
Furniture and decoration
(cars, people, etc.)
FURNITURE
GEOTEX
Line Type
Green
/Red
Yellow
Cont.
White
Cont.
Cyan
ACAD_IS
O10W100
Red
Cont.
Yellow
Cont.
Cont.
variable
Geo-textile
Cont.
MASONRY-VIEW
Geo-technical information,
boreholes, DCP, etc.
Masonry, Brick wall
MASONRY-SEC
OPENING
OTHER
Miscellaneous Objects
Green
Red
/White
variable
REBARS
Yellow
Cont.
ROAD-VIEW
Yellow
Cont.
ROAD-SEC
Road section
Green
Cont.
STEEL-VIEW
Steel structure
Yellow
Cont.
STEEL-SEC
Steel structure
Green
Cont.
TIMBER-VIEW
Wood structure
Yellow
Cont.
TIMBER-SEC
Wood structure
Ground section line and
vegetation
Green
Cont.
Green
Cont.
GEOTECH
TREE
Plot
Yes/No
Cont.
NOTE: If additional layers are required, please inform the project manager.
If you come across layers with similar names but different spelling eliminate the
incorrect layer from the drawing.
Text Style
Color
Height
In Layout
1:1000
1:500
1:100
1:50
Headings
Arial Narrow
Green
4mm
0.4
0.2
Sub headings
Arial Narrow
Yellow
3mm
1.5
0.3
0.15
Common text/labels
Notes, dimensions,
elevations,
inscriptions, legend
Axis labels
Arial Narrow
Red
2mm
0.2
0.1
Arial Narrow
Red
2mm
0.2
0.1
Arial Narrow
Yellow
4mm
0.4
0.2
Description
I-92
CONTINUOUS
HIDDEN
CENTER
DOT
PHANTOM
continuous
hidden
center
center
Recommended Use
Line Color
green
0.35
yellow
0.25
red
0.18
yellow
0.25
green
0.35
white
0.1
yellow
0.25
axes
structural elements in front or above of
cutting plane
dot
Line Width
3.5.10
Hatch
Note:
x Do not explode hatch lines.
x
Do not delete hatch boundary line but put them on a help layer.
Description
Hatch Name
Angle
Line Type
Masonry
ANSI31
By layer
Concrete, reinforced
ANSI33
By layer
BETONUB
By layer
EARTH
45
By layer
AR-CONC
By layer
3.5.11
Dimensions
Use the dimension style provided in the model drawing file (NCDD 50, NCDD 100, etc.). Do not
change the settings of these styles. If you need to create a dim style for another drawing scale
ask for permission.
Note that the drawing unit in MODEL space is metre. However, dimensions are in mm. (The
scale factor for measurement is set to 1000.)
I-93
STYLE NAME
DIM 100
DIM 50
DIM 25
DIM 10
1:100
1:50
1:25
1:10
Overall scale
1000
500
250
100
The height of dimension text is 1.5 mm in Layout. Dimension lines should have equal spacing.
Do not overwrite dimension texts (No cheating).
3.5.12
Blocks
The use of blocks is recommended for objects that are repeatedly used in drawings or projects.
Block shall be created on Layer 0.
Purge unreferenced blocks before sending drawing files to design team members.
3.5.13
The use of external references is useful especially for Mechanical and Electrical design.
When attaching (or overlaying) external references use the Relative Path not the Full Path.
Bind the x-reference; do not insert them.
When exchanging drawings that make use of drawings from other design team members via xref, the reference drawings do not have to be exchanged.
3.5.14
Viewports
Viewport frames can be visible or invisible. Visible viewport frames are created on layer Zviewport. Invisible are created on layer Z-viewport-off
Viewport zoom scales:
Drawing Unit m
3.5.15
Drawing Scale
Zoom Scale
1:1
1000xp
1:2
500xp
1:5
200xp
1:10
100xp
1:20
50xp
1:25
40xp
1:50
20xp
1:100
10xp
1:200
5xp
1:250
4xp
Plotting
Use color-depended plot style table files NCDD.ctb for all plots
I-94
PART 4:
MATERIALS, QUANTITIES
AND COSTS
I-95
labor to construct the formwork and to mix and place the concrete; and
For another example, in Table 5 the unit quantity for steel bars is:
x
(1.0) tonne, but the quantity of steel used is 1.1 tonne which allows 0.1 tonne or 10% for
waste;
in addition 10 kg of binding wire is allowed for fixing each 1.0 tonne unit quantity of steel;
Net: remaining after all deductions (for waste and not permanently used).
Gross: before any deductions (everything used).
I-96
(e.g. cement, sand and stone for concrete) and adding the temporary costs (e.g. the labor and
the materials used in formwork for concrete). The cost estimate is then obtained by multiplying
the gross quantities by unit costs for the current cost database. The flow chart below illustrates
the process.
Hence it is clear that it is necessary to first determine the Net quantities.
Net
quantities
Tables of
quantities
and labor
Gross
quantities
Cost
estimate
Cost
database
The net quantities must be calculated from the output drawings. This is a standard construction
industry task for infrastructure engineering and building work. It is usually done by the designer
for the bidding documents so that the contractors have an accurate indication of quantities, and
so that the project owner can have an estimate of the cost before proceeding. It is done a
second time by the contractor (by the contractors staff with responsibility for quantity surveying
and purchasing) so that the purchase and delivery of materials to site can be organized. It will
commonly be done a third time as final measurement for payment3.
For C/S Fund projects two situations exist:
1. Where a template design has been prepared for an output and loaded into the Project
Generator, the quantity calculations have already been made and also loaded into the
Project Generator. The cost estimate is produced automatically by the software
accessing the current cost database and the Detailed Cost Estimation Form for
Construction Output is output for C/S Chief approval.
2. Where no template design has been prepared for an output, or where a one-off output
requires special or unique design drawings, then the Net quantities will have to be
calculated. The cost estimate can then be prepared following the steps in the flow chart
and procedures required by the PIM.
When new template designs are prepared quantities should also be calculated and loaded to
the Project Generator as for existing templates.
The following section gives further explanation and example of how the tables of quantities are
applied and how the cost estimate is prepared using the Project Generator.
It is conventional for the designers and final quantities to be measured Net, but the contractor
obviously needs the Gross quantities otherwise there will be shortfalls of materials delivered to site.
NCDD (and Seila previously) is different in that the Designers quantities in the bidding documents are
Gross. The reasons for this are outlined in the PIM; the designers estimate is given to contractors as
an aid to inexperienced small contractors to correctly make due allowance for all costs and profit when
preparing a bid.
I-97
Length (m)
width (m)
Dimension
Thickness (m)
Surface (m)
Volume (m)
5.50
-6.00
2.50
-0.40
0.05
0.05
0.40
1
2
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
2
0.8
6
1
0.5
30
Description
Number
1
2
1
11.00
Total
Concrete (1:2:4)
wing wall 1 (Rectangular)
wing wall 2 (Trapezoidal)
slab under pipes
slab at sides of pipes
cut off 1 (outside)
cut off 2 (inside)
head of wall
4
4
1
2
2
2
2
0.60
1.10
5.50
-7.50
2.50
2.50
0.50
2.90
2.50
-0.70
0.40
1.80
Formwork
slab under pipes
slab at sides of pipes
wing wall
wing wall
head wall
cut off
cut off
1
2
8
4
2
2
2
16.04
14.74
1.10
0.60
5.54
15.44
5.54
0.10
0.20
2.90
1.22
1.80
0.50
0.30
0.20
0.20
0.10
0.20
0.20
0.20
0.25
Total
4
Gabion mattress
2.00
1.00
7.78
-0.79
Total
Total
5
Geotextile filter
8.60
2.30
Total
Soil Excavation
From actual road EL to base slab
slab under pipes
Slab at sides of pipes
cut off 1 (outside)
cut off 2 (inside)
Gabion
Slopes at both end of pipes
1
1
2
2
2
8
2
6.00
6.00
-7.50
2.50
2.00
4.50
2.50
2.50
-0.70
0.30
1.00
--
1.80
0.20
0.20
0.20
0.25
0.30
--
Soil Backfill
Pipes
5.50
2.50
0.50
Item
Pipes
7
8
Item/Diameter
Smooth bar (235 MPa)
Deformed bar 400MPa
9
10
Number
12
Diameter
0.80
Length(m)
1.00
D6
43.64
D8
298.46
0.69
1.10
0.96
2.75
m
m
m
m
0.24
2.55
1.38
3.11
2.10
0.40
1.86
11.63
m
m
m
m
m
m
m
m
1.60
5.90
25.52
2.93
19.94
15.44
3.32
74.66
0.30
Units
m
m
m
m
m
m
m
m
4.80
4.80
19.78
19.78
m
m
m
2.43
Total
27.00
3.00
3.11
2.10
0.38
4.80
21.87
62.26
m
m
m
m
m
m
m
m
Total
6.88
6.88
m
m
7.78
Total
12.00
D10
D12
Total
342.10
411.20
268.41
142.79
kg
kg
Wire
7.53
kg
Nail
8.96
kg
All the spreadsheets follow the same principles although their appearance is different. The
spreadsheets automatically make calculations using embedded formula and links between cells
and spreadsheets. Each spreadsheet is different and an understanding of embedded formula is
necessary to make changes or prepare new spreadsheets.
In many cases a single spreadsheet is used for similar outputs. This is the case for the pipe
culvert example which can be used for 0.6 m, 0.8 m, 1.0 m diameter and single, double or triple
pipe culverts4. The required output code is selected from a drop down selection Detailed
4
For pipe culverts the range of options has been limited to ensure a logical progressive increase in
hydraulic capacity; see Part 6 for further explanation. In terms of the quantity spreadsheet there is no
I-98
Calculation Cell A2. This the fills Cell B2 with the description Double pipe culvert 0.8m
diameter; Cell C5 with the number of rows 2; Cell C6 with the diameter 0.8.
Drop down options are used for Cell C7, number of culvert rings per row 6, Cell C9 cover 0.5,
and Cell C10 distance from market to site 30 (used to calculate transport costs).
The remainder of the Detailed Calculation worksheet contains the dimensions taken from the
drawings and the calculations and summation of Net quantities for each work item, e.g. blinding
concrete, concrete (1:2:4), etc.
The Transport and Labor cost spreadsheet takes the Net quantities and factors these by the
appropriate values extracted from the quantity and labor tables. The Material Transport Cost
and its distance are read from the cost database and entered at Cell D2 on the Detailed
Calculation spreadsheet C10. These are used to calculate the transport related costs in the
spreadsheet.
The Output Data spreadsheet provides the Detailed Cost Estimate Form for Construction
Output. It provides a summary of quantities of material, labor and transport costs by item.
Transport and Labor cost Spreadsheet
A
1
2
3
4
5
6
Weight/Unit
(kg)
Total Weight
(kg)
Transport Cost
(Riels)
Unskilled Labor
(days/Unit)
Semi-skilled Labor
(days/Unit)
Skilled Labor
(days/Unit)
66
13
No
Description
Unit
Quantity
Cement
bag
88.26
50
4413.07
106,000
10.01
1700
17009.35
408,300
2.47
1700
4203.68
100,900
10
Sand
6.24
1700
10606.51
254,600
11
Formwork
74.66
10
746.56
18,000
19
12
Gabion mattress
4.80
--
00
13
Geotextile Filter
19.78
--
00
14
Number
12.00
250
3000.00
72,000
24
15
10
kg
376.31
376.31
9,100
16
11
kg
452.32
452.32
10,900
17
12
Wire
kg
7.53
7.53
200
18
13
Nail
kg
8.96
8.96
300
19
14
Soil Excavation
62.26
--
00
20
15
Soil Backfill
6.88
--
00
40.82
980,300
100
34
10
21
Total
limit on additional pipe sizes or combination which may be added (e.g. if ISO standard 0.9 m or 1.2 m
diameter pipes are imported and used).
Study and Design Guidelines
I-99
1
2 C/S Project
3 Detailed Cost Estimation Form for Construction Output
Province:
District:
4
Project Name:
5
Description of Output:
Village:
Commune:
C/S Code:
1010305
6
7 Cost Estimation for 1 Unit of Output
N
Unit
Quantity
Price/Unit(R)
Total (R)
Cement
bag
88.26
19,600
1,730,000
11 1.2
10.01
100,000
1,000,600
12 1.3
2.47
52,000
128,600
13 1.4
Sand
6.24
23,200
144,800
14 1.5
Formwork
74.66
16,650
1,243,100
15 1.6
Gabion mattress
4.80
200,000
960,000
16 1.7
Geotextile Filter
19.78
20,000
395,600
17 1.8
Number
12
95,000
1,140,000
Description
9 1
Construction Materials
10 1.1
18 1.9
kg
376.31
3,120
1,174,100
19 1.10
kg
452.32
2,930
1,325,300
20 1.11
Wire
kg
7.53
8,600
64,800
21 1.12
Nail
kg
8.96
5,300
47,500
572,800
22 1.13
Soil Excavation
62.26
9,200
23 1.14
Soil Backfill
8.94
10,000
89,400
10,016,600
25
26 2
27
28
2.1
2.2
Tonne
40.82
24,000
979,800
Tonne
3.27
24,000
78,400
29 2.3
Unskilled labor
day
100
15,000
1,500,000
30 2.4
Semi-skilled labor
day
34
20,000
680,000
31 2.5
Skilled labor
day
10
25,000
250,000
32 2.6
3%
72,900
3,561,100
34
35 Sub-Total (Direct Cost) (1+2)
13,577,700
10%
37 Total Cost
38
1,357,800
14,935,500
Unit
Quantity
Price/Unit
Total (R)
14,935,500
14,935,500
43
44
45
Date:..
Date:..
C/S Chief
Technical Assistant
46
I-100
0.01
m2
m3
Pipe bedding
Sub-foundation gravel
Mortar
0.01
7.0
0.5
0.5
1.1
1.0
1.1
m2
0.55
0.5
Formwork
3.0
4.8
m3
Concrete (1:5:10)
m3
1.0
m3
40 x 60
Concrete(1:3:6)
0.9
1.0
1.0
10
m3
m3
1.0
20 x 40
10 x 20
Wood
Class 3
0.55
0.5
0.5
0.5
Sand
Stone
6.2
6.7
m3
6.7
m3
6.7
Bags
Cement
Unit
Description
Construction Task
Table 1
0.12
0.12
kg
Nail
0.2
0.1
0.0
0.0
0.5
0.1
0.1
0.1
Skilled
1.0
0.3
0.25
0.5
0.5
0.5
1.0
1.0
1.0
Labor
Semiskilled
0.5
0.5
3.0
0.1
0.05
2.0
3.0
4.0
4.0
4.0
5.0
Unskilled
I-101
m2
m2
fibro roof
m2
Zinc roof
Tile piece
Unit
Description
Square tiles
Construction Task
16
Roof Materials
70
Tile piece
Fish scale
roof tile
2.5
Sheet
0.55 x 1.2 m
Fibro
0.9
Sheet
0.5 x 3 m
Zinc
Table 2
0.05
0.1
0.1
Skilled
0.05
0.05
0.1
0.1
Semi-skilled
Labor
0.05
0.05
0.1
0.1
Unskilled
I-102
105
m2
m2
Paint walls
floor tile
Masonry
1.05
0.05
m2
Plaster(1:6)
3
0.14
0.1
2.2
0.34
m2
210
Plaster(1:2)
0.17
0.0017
0.2
0.1
0.002
bag
Cement
m2
1.1
Stone
105
1.05
Floor tile
Air
brick
piece
52.5
m2
Solid brick
1.05
piece
Hollow brick
piece
piece
Construction task
Unit
Solid
brick
Hollow
brick
Description
Table 3
0.015
0.33
0.011
0.011
0.053
0.026
0.0003
0.032
0.016
0.0003
m3
Sand
0.25
kg
Whitewash
0.05
1.5
0.07
0.07
0.6
0.3
0.003
0.3
0.15
0.003
Skilled
0.02
1.0
0.4
0.2
0.002
0.2
0.1
0.002
Semiskilled
Labor
0.01
0.15
3.2
0.15
0.15
1.0
0.5
0.006
0.64
0.32
0.006
Unskilled
I-103
piece
Unit
Ring
Ring
Ring
Ring
Ring
Ring
Ring
Ring
Description
Well ring 1 m x 1 m
Note:
Labor quantities include for excavation of earth and backfilling.
Cement and sand quantities are for mortar for sealing joins
Ring
0.2
0.084
0.14
0.17
0.14
0.1
0.09
0.17
bags
Cement
0.03
0.012
0.021
0.026
0.021
0.016
0.013
0.026
m3
Sand
Construction Task
Table 4
0.5
0.5
0.4
0.25
Skilled
0.5
0.5
0.4
0.25
0.16
0.12
0.1
0.02
Semi-skilled
Labor
0.5
0.5
0.4
0.25
Unskilled
I-104
Wood Class 3
Wood Class 2
1.1
m3
Wood Class 1
1.1
tonne
Structural steel
1.1
1.1
1.1
Unit
Unit
tonne
Steel bars
Quantity
kg
Wire
kg
Nail
Structural Materials
Description
Construction Task
Table 5
1.8
1.8
14
Skilled
3.4
3.4
20
Semi-skilled
Labor
4.5
4.5
2.4
Unskilled
I-105
10
m3
m3
Filter sand
Grass
Notes
For tasks carried out by machine, standard price = Cost/Unit x Compaction factor
For tasks carried out by labor, standard price is calculated:
m3
Filter gravel
m x km
m3 x km
m3 x km
m x km
m3
m3
Excavate Laterite
Compact Laterite
m3
Compact earth
m x km
Transport earth
Units/day
Description
Unit
Labor norm
0.15
0.09
0.10
0.11
0.12
0.60
0.60
0.36
0.30
0.12
0.50
Riel/unit
Earthwork tasks
Table 6
1.3
1.3
1.1
1.3
1.3
1.3
1.3
1.3
1.3
1.3
Compaction Factor
0.15
0.12
0.13
0.14
0.16
0.60
0.60
0.47
0.30
0.16
0.65
Riel/unit
Standard price
I-106
I-107
m2
m
m
m
m
m
m
m
Piece
Piece
Student desks
White board
Piece
Number
Set
Teacher desk
VN No 6 pump
Quantity
m2
Latrine
Quantity
Quantity
Quantity
Column base
Set
Unit
Bolt
Description
Afridev Pump
Construction task
Table 7
0.1
Skilled
0.1
0.4
Semiskilled
2
Labor
Unskilled
I-108
PART 5:
STUDY AND DESIGN GUIDELINES
I-109
5.1.1 Limitations
Infrastructure design can be very complex. It is very difficult to reduce design to a few simple
rules and guidelines. There is always a risk that the conditions at the site are outside the
simplifying assumptions made for the guidelines. Yet it is equally difficult to instruct a nonspecialist to spot these situations.
The problem in the past under the Seila Program and similar work by The Social Fund, NGOs
and others is that the complexities of design have been too daunting for the people on the
ground. Consequently they often ignored even basic and essential design procedures, took a
chance and unquestioningly built whatever the community asked for. Not every time but more
often than not the infrastructure variously did not work as intended or broke very soon after it
was built, often because bad design choices meant it required maintenance and repair beyond
the means of the community.
In fact for all the caution expressed above about the limitations of simple guidelines, in the
majority of cases for simple infrastructure these guidelines, used correctly, will provide a safe
and sustainable design. Most importantly the guidelines should avoid most of the big mistakes
made by not carrying out design at all.
About 90% of the projects are for simple infrastructure. It is for this 90% that the guidelines
have been carefully chosen. The other 10% of projects are typically outside the guidelines
because they are unusual, have some complex issues, or are components of a larger project
that needs a full design process; in such cases specialist advice and/or assistance should be
obtained. Overall the objective of this approach is to improve the success rate of C/S Fund
infrastructure projects.
I-110
You will only get the design guidance if you answer the questions, and the
guidance will only be correct if the answers are honest do not invent the
answers.
The basis of the guidance is explained. When the guidance is based on recommendations in
an external reference this is listed as a footnote. Often these references are available from the
Internet. This allows the user to find out more about the guidance, they may do this to improve
their knowledge. There will also be occasions where it essential to use the references, e.g. if
the project requires something beyond the coverage of an original template design.
Form T11 incorporates the advice for road earthworks and surface options.
Form T12 incorporates the advice for structures, particularly the selection of the correct
structure type and size for drainage of rivers and streams across the road.
Sub-Tertiary 1
Sub-Tertiary 2
Sub-Tertiary 3
MRD applies two design standards for tertiary/sub-tertiary roads based on traffic (traffic is
measured as ADT, see the explanation of ADT below).
Type A
Type B
ADT = 0 to 200
The MRD standards for Type A and Type B are given in Table 5.1.
Sub-tertiary roads in rural areas will mostly have ADT less than 200 for existing traffic so will
initially be Type B, but could become Type A if ADT increases above 200, as can happen after
a good road is built. If existing ADT is almost 200, if the road will join two busy centres or if it
provides access to growing businesses such as a plantation or factory this is a reason to design
to Type A standards.
Interim Rural Roads Standards for Tertiary and Sub-Tertiary Roads, Ministry of Rural Development
2006.
I-111
Designation
Composition of traffic (ADT)
Type A
201 ~ 2,000+
Type B
0 ~ 200
2
3
4
Design Period
Design speed (Km/hr)
Assumed ESA of commercial
vehicle (6 tyres or more)
Minimum radius of curvature
(metres) Unpaved surface
Minimum radius of curvature
(metres) Paved surface
Vertical alignment maximum (%)
Earth Road
Vertical alignment maximum (%)
Gravel Road
15 years
70 / 60 / 50
1.0
10 years
60 / 50 / 40
0.4
190 / 125 / 80
125 / 80 / 40
130 / 85 / 60
85 / 60 / 30
4%
6%
6%
6%
15%
20%
85 / 65 / 50
65 / 50 / 35
7%
7%
0.5 metre
0.5 metre
Normally 3 4% is
appropriate
If radius of curvature <100 m
7% / 3%
7% / 3%
1.0 metre
1.0 metre
Width of
earth/gravel/Laterite/paved
surface carriageway (minimum)
Initial constructed thickness of
Laterite / gravel surface
(millimetres)
5.0 metres
3.5 metres
200 mm
compacted
150 ~ 200 mm
compacted
17
18
19
Depends on
requirements
500 mm above
the HFWL
150 mm (each)
horizontal layer
Depends on
requirements
500 mm above
the HFWL
150 mm (each)
horizontal layer
Can be reduced in
mountainous areas with
provision of passing bays on
single lane roads. Minimum
Type B roadway = 5.5 m
These are minima. If
resources allow, wider
carriageway may be justified
Use technical design
guidelines. The suitability of
gravel is adequately covered
in the Rationale.
Use technical design
guidelines
Sub-grade formation level
20
1:2 ~ 1:3
1:2 ~ 1:3
21
See technical
guidelines
See technical
guidelines
22
15
15
7.0 metres
5.5 metres
3.5 metres
3.0 metres
2.0 metres
2.0 metres
Recommended minimum
5
6
7
8
9
10
11
12
13
14
15
16
23
24
25
Notes
Design Period Max flow in
PCU
Depends on compaction
equipment used. All
earthworks must be
compacted.
(Vertical : Horizontal). Turfed
finishing
Trapezoidal shape, turfed.
Scour checks or lined if
gradient >4%
Recommended
I-112
6.0 m
Sub-Tertiary 1
6.0 m
Sub-Tertiary 2
5.0 m
Sub-Tertiary 3
4.0 m
Sub-Tertiary 3
4.0 m
These widths are in some cases wider than the minimum in Table 5.1 but wider carriageways
are permitted by the MRD standards.
The design of the road depends on its location and alignment plus two key pieces of data.
x
Type of Vehicle
Passenger Car
1.0
Motorcycle
0.4
Motorcycle-trailer
0.6
Bicycle
0.3
Animal Cart
0.4
1.0
Koyun
1.5
2.0
2.5
2.25
Mini-bus (4 tyres)
1.1
By completing the Road Traffic (traffic count) boxes on Applet Form T11 the PCU
values are automatically calculated and totalled. The required road design
standard Type A or Type B is then shown, and need to be taken to filled into the
Form.
Remember, the ADT calculated from the traffic count is for existing traffic, you
must decide whether to allow for future increase in traffic.
There are some further questions on Form T11 to help make the decision about future traffic.
Study and Design Guidelines
I-113
I-114
The basis of the design guidance incorporated into Form T11 for road types used by the C/S
Fund is as follows.
1010101 Earth road
Suitable for ADT 20 ADT of which no more than 2 heavy trucks, buses or
mini buses.
Pavement: No guidance for DCP test results but > 15 mm/blow indicates the ground is
too weak for at grade road construction, either the ground must be excavated
and compacted or the road must be on compacted fill embankment.
Type:
Traffic:
I-115
PIARC, TRL & Intech Associates. Rural Road Surfacing: Surface Options Gravel, Ref: RR Surface
3h, June 2003. (Note: Pavement thicknesses adopted are for high rainfall more than 1,500 mm/year
with long dry season).
Gourley Dr C et al. Low Cost Road Surfacing (LCS) Project, LCS Working Paper No12 Paving the
Way for Rural Development & Poverty, CSIR, TRL, Intech Associates, September 2002.
Azam A I et al. Low Cost Road Surfacing (LCS) Project, LCS Working Paper No7 Bamboo
Reinforced Concrete Pavement Road Construction in Cambodia, ILO, Intech Associates, June 2002.
I-116
Thickness 50 mm
Thickness 300 mm
Gourley Dr C et al. Low Cost Road Surfacing (LCS) Project, LCS Working Paper No12 Paving the
Way for Rural Development & Poverty, CSIR, TRL, Intech Associates, September 2002.
I-117
There must be one T12 form for each road structure. The form will attach with it an
Applet T12 used to obtain advice on structures to be chosen before creating a
project. If catchment area can be defined, it is a must to use the applet.
Note:Explanation on questions to be answered in the applet can be found from the Hydrology
and hydraulic capacity section below.
Design standards
Template designs for culverts provide a minimum unobstructed width of 5.5 m between the
backs of culvert headwalls at road surface level. This complies with the MRD Design Standards
for Type B roads (Table 5.1). For Type A roads the width should be 7.0 m. Pipe culverts can
be made wider by adding extra pipes. For box culverts width between headwalls of the box
section walls and slabs will have to be increased and will require more concrete and reinforcing
steel. Extra width will also be needed for a high embankment because the bottom of the slopes
is farther apart.
Template designs for concrete bridges provide an unobstructed width of 4.5 m which is
consistent with contemporary MRD road projects. A wider roadway will require a modified
design which will require the assistance of a qualified structural engineer. The particular
concern is the hanging beams which support the bridge; these also provide the bridge parapets.
The beam reinforcement would have to be increased for a wider roadway. Also the abutment
walls and deck slab will have to be increased in width and will require more concrete and
reinforcing steel, as well as extra piles for piled foundations.
Concrete bridges are designed for AASHTO HS 20-44 20 tonne loading.
The wooden bridge template design is unchanged from the Seila Template and has a notional
5 tonne loading.
Steel bridges including Bailey Bridges are not covered by this design guidance and specialist
advice should be sought on an as-needed basis.
Road classification
The road classification, standard and width are entered manually, but if Form T12
has been generated by a Form T11 then the information is entered the same as
the road form.
If the project is for an isolated road structure then the road classification, road standard and
road width questions will have to be answered. It is not necessary to conduct a traffic count to
determine the road standard; judgement can be used to answer this question.
Scope of works
The questions relating to the scope of works focus on the description, sizes, condition and
causes of damage to existing structures. It is important to complete this information in order to
understand the problems at the site, e.g. a culvert that collapsed due to scour is a very definite
indication that the structure was too small for the flow, and/or that the new structure requires
scour protection.
Pay attention to the questions asked and think about the causes of the problems.
Material available for construction
These questions indicate whether there will be problems complying with the Specification, e.g. if
gravel will come from a river then it will be rounded and unsuitable for concrete.
Soils and Dynamic Cone Penetration Test (DCP)
Information on soils and DCP tests is needed to consider whether the foundations will be strong
enough to support the structure, also whether they will be particularly vulnerable to erosion and
scour.
Study and Design Guidelines
I-118
The DCP results are used in the same way as described for road projects. One test may be
sufficient for a small culvert but for large culverts and bridges it is recommended to check each
bank and the water channel, as many times as necessary.
For concrete bridges it is recommended to have an investigation borehole at each abutment. It
is recognised that this adds to the cost but a bridge is a big investment. If the bridge is on piled
foundations the risk of not sinking an investigation borehole is reduced.
The template designs for concrete bridges are for single spans and do not require an
intermediate pier. However, if multiple spans are required then investigation boreholes should
also be sunk in the river bed as close as practical to each pier location.
Hydrology and hydraulic capacity
The size of a bridge, culvert or low level crossing and any protection works must be chosen for
the flow and flood conditions at the site. Deciding flow and flood conditions can be difficult
where the land is very flat and/or where the natural drainage has been altered by roads,
embankments and irrigation systems.
Two situations occur:
x
the structure is in a flat and/or flood area where water can come from distant and large
catchments.
The design guidance is focused on being able to define the catchment and its characteristics.
This is described first below. The guidance that applies for large flat and flood areas follows.
By answering a few simple questions about the catchment on Applet Form T12
you will automatically be told the estimated peak flood flow, advised on the most
suitable size of structure, and told the exit velocity for flow from the structure.
Water divide
Catchment area
A = 5.8 km2
Culvert
I-119
Catchment boundaries cannot cross a stream. Every plot of land must be in the catchment of
one stream or another, if you draw the catchment divides between several streams and have
any area of land left over where you do not know where the water flows, it means you have
made a mistake and need to correct the boundaries.
Overland flow
Road
Culvert
Low-level road
Road on embankment
Flow
Flow
I-120
Rational method
SWAT Model.
The Rational Method is intended for urban catchments and because of the simplifying
assumptions that apply only for these conditions it should not be used for rural catchment
more than 0.8 km2 area otherwise it grossly overestimates flow11. Because the method is so
simple to use it is used mistakenly by many people. The GTFM can be used for small
catchments so there is no need to consider the Rational Method.
The US SCS Method is quite complicated to use correctly and requires catchment data not
generally available directly from maps. Since it is no more reliable than the GTFM it has not
been used.
The SWAT model is a river basin, or catchment, scale model developed for the United States
Department of Agriculture Agricultural Research Service and used by the Mekong River
Commission. It is intended for water resource planning rather than peak flow prediction,
requiring the software and knowledge how to use it. These factors make it unsuitable for
road structure design.
The next few sections give the basic theory for using the GTFM, it is good to
understand these but it is not essential provided the questions on Form T12 are
answered correctly.
Rainfall
All the methods of flow estimation discussed above including the GTFM are known as rainfallrunoff models, that means a design rainfall is assumed for the catchment and the models take
into account the factors that determine what percentage of the rain will appear as runoff at the
structure, what percentage stays in the catchment in the soils, or is used by vegetation, etc, and
also the timing and size of the peak flow at the structure.
For road structure design it is necessary to know the rainfall intensity in mm/hr over different
durations between 5 minutes and 24 hours, and for different return periods. This information
can be obtained by measuring rainfall with a continuously recording rain gauge over a period of
not less than 10 years. In Cambodia such a record only exists for Phnom Penh International
Airport (Pochentong) for a period of 16 years, although the national coverage of rain gauges
and records is fairly good these are all daily (24 hour) rain gauges. This is overcome by using
the method of Rainfall Ratios and converting the 24 hour rainfall to shorter duration by applying
indices derived by back analyses of the record at Pochentong. This technique is described in
10
Watkins L H and Fiddes D. Highway and Urban Hydrology in the Tropics, Pentech Press, London,
92-100 (1984).
11
Chow V T. Handbook of Applied Hydrology, McGraw-Hill Co, London (1964).
Study and Design Guidelines
I-121
Watkins and Fiddes12. The indices vary from region to region according to rainfall
characteristics but the rainfall at Phnom Penh is representative of that for lowland Cambodia.
To avoid the need to obtain rainfall records and use different rainfall charts for each location the
design guidance is based on long term rainfall records at 21 locations covering the most
populace areas of the country. The 80 percentile values for these data are shown in Figure 5.4
and Figure 5.5 as rainfall rainfall-intensity-duration and total rainfall curves respectively for
return periods 1 in 2.3313, 5, 10, 25, 50 and 100 years.
By default the design guidance applied by T12 uses these rainfall curves for design because
they are appropriate for most places in Cambodia. However, the form has the option to apply
33% greater rainfall in known high rainfall areas.
Return period
The larger and more expensive structures are designed for a longer return period rainfall/flow
than the smaller ones; the logic is that it is easier and cheaper to replace a small structure than
a large one. This approach is used in all countries and is applied by MRD for road structures.
This design guidance applies the following standards.
Table 5.3 Road structure design return period for peak flow
Structure type
Bridge 10m
Small bridge <10m
Large box
Small box
Low level crossing
Pipe
GTFM
The advice on use of the GTFM that follows is applied automatically by answering
all the questions on T12. This is explained in Design procedures below.
The Generalised Tropical Flood Model is expressed by the formula:
QR
Where
QR :
R:
CA :
P:
A:
F:
ARF :
TB :
12
13
C A u P u A u F u ARF
360 u TB
Watkins L H and Fiddes D. Highway and Urban Hydrology in the Tropics, Pentech Press, London,
92-100 (1984)
A return period of 1 in 2.33 years is the mean annual peak rainfall.
I-122
80 Percentile Rainfall-Duration-Intensity
Intensity (mm/hour)
1000
100
1 in 2.33 Year
1 in 5 Year
1 in 10 Year
1 in 25 Year
1 in 50 Year
1 in 100 Year
10
0.01
0.10
1
1.00
10.00
100.00
Duration (hours)
200
1 in 2.33 Year
150
1 in 5 Year
1 in 10 Year
1 in 25 Year
100
1 in 50 Year
1 in 100 Year
50
0
0.00
3.00
6.00
9.00
12.00
15.00
18.00
21.00
24.00
I-123
The peak flow QR is the flow used to select the structure type and size. The hydraulic capacity
is chosen to pass this flow.
The return period R is selected for the proposed structure (Table 5.3). If the structure required
is different to that originally proposed it may be necessary to restart the calculation (by changing
the proposed structure at the beginning of the form) until the return period is correct for the
structure type and size.
The percentage runoff coefficient CA is express by the formula:
CA
Where
CS :
CW :
CL :
C S u CW u C L
Description
Rock surface
Paved urban, village centre
Clay soils with high swelling potential; shallow soils
over largely impermeable layer, very high water
table.
Mostly flooded paddy in wet season
Impeded drainage and areas of flooded paddy in wet
season
Drainage slightly impeded when soil fully wetted.
Deep soils but areas of flooded paddy in wet season
Deep soils of relatively high infiltration rate when
wetted.
Soils with very high infiltration rates such as sands,
gravels and aggregated clays.
1
1
2
2
2.5
3
3.5
4
5
Slope is measured along the path taken by the water, therefore this must be along the length of
the stream or flow path, not the straight line distance but the distance allowing for twists and
turns of the stream, or the valley if there is no stream. Slope must also be representative for the
catchment. For this reason it is measured between two point 10% and 85% distance up the
catchment measured from the structure. This eliminates error due to a steep rise at the top of
the catchment, a situation which is common in many places in Cambodia where steep
mountains are beside flat plains. Hence slope is calculated from the formula.
Slope
Where
Elv85:
Elv10:
L:
100:
Elv85 Elv10
u 100
0.75 u L
I-124
30
25
20
15
10
5
0
1
Having determined the soil class S and slope class I the standard value of contributing runoff
coefficient CS is calculated from the following formula. Values for CS are also shown in Table
5.5.
CS
Where
CS:
I:
S:
53 12 I 8S
13
21
29
37
45
53
1
9
17
25
33
41
I-125
Catchment type
Urban or village centre
Largely bare soil
Intensive cultivation
Grass cover
Dense vegetation (particularly in valleys)
Forest: (a) shallow impermeable soils
Forest: (b) very steep (S5, S6) permeable
soils
Forest: (c) deep soils and gentle slopes
CL
1.00
1.50
1.50
1.00
0.50
1.00
0.67
0.33
The design rainfall P is obtained from Figure 5.5 for the calculated value of TB (see below) and
the selected return period.
If you have reason to think the structure is in a high rainfall area then it is recommended that P
be increased by 33%. This is done automatically by selecting the high rainfall option on Form
T12.
The catchment area A is measured from the map.
The peak flow factor F converts the average flow generated by the model to peak flow, F=2.5 is
a suitable peak flow factor for structures in Cambodia.
The area reduction factor ARF is introduced to take into account that rainfall at any given instant
varies over the catchment. In simple terms, the average rainfall intensity at any instant for a
catchment will be less than the rainfall measured at a single point in the catchment, and the
difference increases with increasing size of catchment. Therefore, this is not significant for
small catchments but becomes so as catchment size increases. The relationship adopted for
ARF is suitable for the convective rainfall14 that occurs in Cambodia:
ARF
Where
T:
A:
This equation applies for storms of up to 8 hours duration. For longer durations on large
catchments the value calculated for T = 8 hours is used.
The hydrograph base time TB can be thought of as being made up of three components: the
storm duration, the time taken for the surface runoff to drain into the stream system; and the
flow time down to the structure.
Base time TB is expressed by the formula:
TB
Where
14
C:
A:
S:
TS :
C u A 0.5
TS
S2
Convective rainfall occurs where there is low pressure and air movement is mostly vertical.
Evaporation is high early in the day and moisture is carried high by vertical currents. Rainfall occurs
usually in the afternoon or early evening.
I-126
Catchment type
Arid zone
Poor pasture / scrub (large bare soil patches)
Good pasture
Cultivated land (down to river bank)
Forest (a) shallow impermeable soils
(b) very steep (S5, S6) permeable soils
(c) other
Swamp filled valleys
TS (h)
0.0
0.0
1.0
2.0
2.0
2.0
12.0
20.0
The GTFM equation assumes a catchment of average shape with length to width ratios (L/W) of
between 2 and 6. For fan-shaped catchments (L/W = 1) the design flood is increased by 50%.
For very long catchments (L/W = 20) it is halved.
As is shown by Figure 5.3 raising a road embankment can block flood flow;
whereas water can freely flow over a road at about ground level, a road embank
creates a dam which forces all the flow through the road structures. You must
think whether building the road and structures will make flooding worse or whether
it will cause damage to the new road and structures; if you think it will you must
change the design and may need specially advice and help.
Design procedure
You can complete all the above design simply by filling correct answers on the
Applet T12.
I-127
Form T12 incorporates applet T12 that completes the recommended hydrological and hydraulic
calculations. You need to answer a series of questions in the applet, then you need to copy the
necessary responses and recommendations directly to the form.
The questions are listed below together with explanation of the reason for the
questions and advice on how to answer.
What type of structure is envisaged?
Choose the type of structure you expect to
provide.
Can catchment be defined?
This question decides whether the flow to
the structure is from a large flat flood area
or a catchment that can be measured.
I-128
15
Bodhaine GL. 1968, Measurement of Peak Discharge at Culverts by Indirect Methods: U.S. Geol.
Survey Techniques Water-Resources Inv., book 3, chap. A3, 60 p, 1968.
I-129
Design flow
capacity
(m3/s)
0.50
1.03
1.80
2.07
3.61
5.41
8.23
14.00
16.47
32.95
41.20
49.42
61.80
82.40
Flow type
A
A
A
A
A
A
E
E
E
E
E
E
E
E
Design
velocity
(m/s)
2.42
2.80
3.13
2.80
3.13
3.13
3.93
4.06
4.25
4.25
4.84
4.25
4.84
4.84
Flow type
F
F
F
F
F
F
F
F
F
F
F
F
F
F
Low-level crossings
Similarly Form T12 does not specifically recommend low-level crossings. This is because they
are only suitable in special circumstances. They have frequently been used in unsuitable
locations in Cambodia and without a rational consideration of design criteria or the benefits.
Some brief guidance on the correct use of low-level crossings is given below.
Template designs are provided for two types of low-level crossing:
x
A Drift crosses a watercourse at bed level; whenever there is flow or standing water in
the watercourse there will be water on the drift roadway.
A Vented Causeway has culverts beneath the low-level crossing roadway such that the
roadway is higher than the stream bed but usually lower than the approach roads. This
allows the roadway to remain dry when there is a normal flow or standing water in the
watercourse but also for the roadway to be submerged for short periods during a flood.
Drifts are suitable for hilly areas where there is no flow or a trickle of water for most of the time
but where the stream flows full for a short time following heavy rainfall. Drifts are not suitable
for crossing areas where flood water may stand several weeks or months a year, as occurs in
many locations in lowland Cambodia.
Vented causeways can be used in lowland areas provided the roadway is above standing flood
level. They can provide extra capacity to pass large flood flows. However providing sufficient
length of causeway and protection against damage can make a vented causeway more
expensive than box culverts or a small bridge. The criteria that should be used are as follows.
x
The vent culverts can be assumed to have the capacity listed in Table 5.8.
The safe depth of flowing water on the roadway is 150 mm. If the water is deeper than
this cars and light 4-wheel drive vehicles can float, this has been the cause of many
deaths by drowning worldwide.
At this flow depth the flow per metre length of causeway is 0.18 m3/s. Therefore a 91 m
long roadway and protected slopes is required to provide the same capacity as a single
3.0 mW x 2.0 mH box culvert. It is obvious that in most locations the box culvert is a
better solution.
Think very carefully about your reasons for choosing a drift or vented causeway, a
conventional culvert will often be a better technical and cheaper solution.
I-130
Drifts and vented causeways can be used as spillways for small irrigation
reservoirs, provided proper consideration is given to erosion protection
downstream, seek specialist advice.
Form T21 gathers general information about the irrigation system, estimates the
irrigation water requirements and lists the canals and structures that may be needed.
Form T22 is used for the design of earthworks which includes canals and drains, dams
and dykes.
Form T23 is used for all irrigation structures including headworks and distribution system
structures.
International Commission for Irrigation and Drainage. Checklist to Assist Preparation of SmallScale Irrigation Projects in Sub-Saharan Africa, via Department for International Development, London,
England, 1998.
I-131
answered because the information is used to calculate irrigation water requirements later in the
form.
There are also questions about water shortage.
Flooding
The questions on floods have two purposes:
x
Find out if the fields are flooded for part of the year, if this is the case then the system
should manage the water levels for the maximum benefit to the cropping.
Find out if flooding is a significant constraint to cropping, either because it will damage a
standing crop or it will dictate the time a crop is planted.
I-132
It is necessary to enter the catchment area. The applet then uses the irrigated area and the
rainfall data previously entered. It is also necessary to enter the planting date for rice. The
applet then outputs the water requirement each month as the total quantity of water in m3, as
the flow rate in m3/s if water is pumped 8 hours each day, and as the flow rate in m3/s if water is
delivered over 24 hours by gravity. An approximate water balance is also made to estimate the
storage volume required of a reservoir.
Dependable rainfall
The rainfall records are converted to dependable rain. Dependable rain is the monthly rainfall
having an 80% probability of exceedance17 (i.e. that is likely to occur in the particular month
under consideration in four years out of five). The dependable rainfall is calculated with the
following formula:
Pdep = 0.6Ptot - 10 (for Ptot < 70 mm/month)
Pdep = 0.8Ptot - 24 (for Ptot > 70 mm/month)
where Pdep and Ptot are respectively monthly mean dependable rainfall and monthly mean
measured rainfall in millimetres.
Once you have entered the monthly rainfall record, the applet calculates
dependable rainfall on a monthly basis.
Planting month
The planting month can be varied. You should try different planting months to see how this
affects water requirements and reservoir volume. It is probable that farmers will have to change
their usual planting date to get the maximum benefit from irrigation. These issues should be
discussed with the Commune (or FWUC if one exists or will be established).
FAO Irrigation and Drainage Papers No 25 "Effective Rainfall" and No 46 "CROPWAT: A Computer
Program for Irrigation Planning and Management"
I-133
The applet calculates the net irrigation water requirement for the chosen month of
planting taking into account the contribution from dependable rainfall.
Work proposed for irrigation project
Form T21 is finished by filling the requirement for earthworks and structures, stating whether
these are new or repairs, and the expected sizes. This generates Forms T22 and T23 for each
separate output required.
I-134
I-135
The required capacity of the canal depending on the answers given to the
questions on Form T22. It is the factor between area supplied and supply rate.
You must enter the area supplied by the canal. The default supply rate advised by the form for
calculation is 2 l/s/h but you can enter another flow rate. You answer whether the supply is by
gravity or pumping. When it is by pumping you must decide how long the pumps will run each
day. Then you need to calculate the capacity of the canal for the selected method of delivery
and fill into the form as advised in the Project Generator itself.
Capacity of drain
Only rarely will purpose built irrigation drains be provided under the C/S fund. However, it is
common for rehabilitated canals to function as both a canal and drain, particularly Khmer Rouge
built systems. The capacity required for a drain is greater than that for a canal. Therefore,
wherever a canal may operate as a drain it is important to check the design as a drain.
When no drain is provided the form requires explanation of how the irrigation system is drained,
e.g. water may drain into a river.
Form T22 requires the calculation of required capacity including taking into
account an external catchment also served by the drain which needs to be
calculated by using Applet T22 Extenal Catchment Flow.
Drains should be designed to convey not less than 3.5 l/s/h from the fields drained. The default
drainage rate used by the form for calculation is 3.5 l/s/h but the form allows you to choose
another flow rate.
Often a drain will also collect runoff from other fields or have a catchment upstream. When this
is the case you must answer so on the form and enter the catchment area. If this area is
1.0 km2 then it assumes these are fields and you need to calculate the extra flow based on
3.5 l/s/h (or whatever other value you have entered on the form). If it is larger than 1.0 km2 the
form needs the additional flow result form applet T22 External Catchment Flow. The Applet T22
applies the GTFM as described for Applet T12, except that it designs for the mean annual flood
(about 5 year return period) and only outputs the flow.
Hydraulic design of canal or drain
Once you know the flow in the canal or drain you must calculate the channel size. This is the
hydraulic design.
Form T22 uses applet T22-Design of canal or drain to calculate the channel size
for the flow calculated as described above. All you need to do is select a few
design criteria and the Applet includes advice on how to choose these.
Mannings formula
The simplest way to design a channel is to use Mannings formula but first it is necessary to
understand the Continuity Equation.
The continuity equation describes the fact that flow rate can be calculated by multiplying the
cross sectional area of flow by velocity of flow, it is written:
Q
Where: Q =
A=
V=
A uV
I-136
Once the size of flow has been decided, the size of the canal can be calculated using Mannings
formula. Mannings formula calculates flow velocity. In some books use of Mannings Formula
is referred to as the Slope Area Method.
Where: V :
A:
P:
s:
n:
1 A
nP
2/3
s1 / 2
velocity (m/s)
cross-sectional area of the flow (m2)
length of wetted bed at the cross-section (m)
gradient of water surface or bed slope
Mannings n representing the channel roughness, see Table 5.9.
Channel surface
Earth (Primary and Secondary canals)
Earth (Tertiary and Quaternary canals)
Earth (Drain)
Concrete (and plastered masonry)
Masonry
Gabions
Mannings n
0.025
0.030
0.035
0.015
0.020
0.025
Mannings formula is also used to calculate flow, simply by using the continuity
equation Q A u V , which means we only have to multiply the velocity V calculated by
Mannings formula by the flow cross-sectional area.
Where: Q :
A:
P:
s:
n:
The
A A
n P
2/3
s1 / 2
A
expression in Mannings formula is sometimes written as R which is called the
P
A
P
Design calculation
Hand calculation for channel design using Mannings formula is a trial and error process
because you first must select the channel dimensions, make the calculation and compare that
with the required capacity. Therefore designers tend to use charts or spreadsheets to quickly
complete the design. Form T22 calls-up Applet T22-Design canal or drain which will do the
calculation.
I-137
I-138
Code
1020201
1020202
1020203
1020204
1020211
1020212
1020213
1020221
xxxxxxx
xxxxxxx
1020251
1020251
Description
Medium size water gate (2.0 mW)
Single pipe culvert 0.6 m diameter with gate
Single pipe culvert 0.8 m diameter with gate
Single pipe culvert 1.0 m diameter with gate
Double pipe culvert 0.6 m diameter with gate
Double pipe culvert 0.8 m diameter with gate
Double pipe culvert 1.0 m diameter with gate
Triple pipe culvert 1.0 m diameter with gate
Single cell box culvert with gate (2.0 mW x 1.0 mH)
Double cell box culvert with gate (2No 2.0 mW x 1.0 mH)
Pipe head regulator 0.3 m diameter
Pipe head regulator 0.6 m diameter
Capacity
m3/s
5.5
0.5
1.0
1.8
1.0
2.0
3.6
5.4
5.5
11.0
0.1
0.5
I-139
1020251
1020251
1020252
1.0
1.8
Varies
Wells
Ponds
I-140
Rainwater storage
Pipe sizing and hydraulic design for piped and pumped water supply systems.
Form T31 is used. The form is designed for a water supply project, but there must be one form
for each output. If a project comprises several outputs such as pumped wells, water tanks and
a pipe distribution system, it is required one Form T31 for the pumped wells, another for the
water tanks, and the other one for the pipe water system. It is because one form can only
provide one set of associated templates drawings and quantity table.
Quantity of proposed outputs
The proposed outputs you have chosen need to be quantified in number or size before
proceeding to complete the form.
Purpose of water supply
These questions establish whether the water supply is for a community (domestic), a school,
health or other facility. School and health projects often include water supply and if the projects
include the water supply, the Project Generator will require a Form T31 to be completed.
Information about the number of users
This indicates the number of people who will benefit. It is also an indication of the potential
demand on the water supply.
The questions establish the population of the village(s) and the number of households in the
villages benefiting from the water supply. It also asks how many households will use the water
supply. For schools it asks the number of pupils.
Water demand
Form T31 does not calculate the water demand but you should still consider this. The World
Health Organization recommends 30 l/head/day for domestic use. Consumption is also
influenced by the distance from a well or water point if water has to be carried.
Table 5.11 - Water consumption and distance to water source (well or water point)
Distance to source
500 to 1000 m
12
20 to 30
40
You can use these figures to make a side calculation to check whether the proposed project
can supply enough water. Remember that children at school or visitors to a community
facility such as a health post get only part of their daily requirement there. However, it is
quite common for a well in a school grounds to be used by nearby residents so you must
consider if the project can satisfy such an additional demand.
Existing water supply
These questions are designed to establish the existing sources of water supply by type, number
of users and where relevant distance from the household to the source.
I-141
Will the new water supply replace the water supply or will it be additional to the
original supply? Will the existing and new systems compete for the same water?
Information about site of proposed facility
These questions establish ownership of the land, if the land is not in public ownership there may
be disputes about access in the future.
Political considerations may influence accessibility. There may be pressure to put the well near
the dwelling of an influential member of the community. A compromise may be necessary.
There are also questions about flooding. There is a risk of contamination of the supply if the
land floods; a well provides a path for pollution to reach the groundwater which can be
permanently contaminated making it unusable for water supply. It may be necessary to
construct the water supply, e.g. a well head, on a mound or platform so that it is accessible and
protected against contamination when there is a flood.
Existing wells
Information on existing wells is very
useful for designing a new well. The
primary objective when sinking a
new well is to sink it where ground
water is likely to be found. Existing
wells are the best indication of the
presence of ground water. The
history of the old well will provide
information on seasonal changes in
the water tab1e, which may indicate
that the new well should be deeper
than the old one. The questions ask
about the type of well and its use,
the depth of water particularly during
the dry season, the soil and rock
that the well is sunk in. The
questions about the colour, taste
and smell of the water are good
indicators of the water quality18.
Useful Definitions
Aquifer
Bacteria
Contaminate
Drawdown
Ground Water
Impermeable
Permeability
These questions are the same as used on the RGC National Water Well Log Sheet.
I-142
Drawdown
When water is pumped or lifted
out of a well, the water level in
the well falls below the original
level, called the initial or static
water level, until it stabilises at
a new level, called the pumped
level. The distance between
the static level and the
pumped level is the drawdown.
The water table surrounding a
wells curves down to the
pumped level, forming a cone
of depression as shown by
Figure 5.7. If the cones of
depression of two wells
overlap, the pumped level in
one or both wells will be
lowered and the yield will be
decreased.
Local Geography
Drawdown
Cone of depression
(Pumped level)
Well casing
Aquifer
Well Screen
Impermeable layer
I-143
indicators, because they come and go with the seasons. The dry season is probably the
best time to survey vegetation for indications of ground water.
Aquifer
1,900-3,800
1,900
Fractured sandstone
1,900
Limestone
38 or less
As a general guide during the dry season drilled wells should be able to sustain yields of at least
1,000 l/h for 8 h/day. For dug wells for a standing water depth at least 3 m should have a
minimum yield of 10 l/minute, or 2.5 m of water and 15 l/minute, or 2.0 m of water and
20 l/minute.
If the quantity of ground water is insufficient, another or additional well sites or even alternative
sources will have to be found.
Safe distance
50 m
30 m
30 m
30 m
15 m
7m
50 m
Study and Design Guidelines
Source of contamination
Seepage pit or cesspool;
Sub-surface absorption system;
Pit latrine;
Animal pens, sheds, or silos;
Septic tank;
Drain, ditch, or house foundation.
Petro-chemical or agri-chemical store;
I-144
Flooding
The well site should not be subject to flooding during the wet season or any other time. This will
be of greatest concern where the well is in a low area or near a river that yearly overflows its
banks. The site can be protected from flooding by raising the well head above maximum flood
levels; building small dams or ditches to prevent flooding is an unreliable solution. If the well
cannot be protected against flooding, another site should be considered.
Record all possible sources of contamination using MangoMap.
Accessibility to Users
The well site should be as close as possible to the users. As the distance between the well and
the user increases, the per capita water consumption decreases. The typical effect is shown in
Table 5.11.
Construction method
Unsuitable Soil
Hand Dug
Driven
Jetted
Bored
Cable Tool
None
VN No 6
Tara
Afridev
13
30
1,200
1,000
1,000
35
250
500
These days standardization is not followed anymore and mostly the VN No6 hand pump is used
for low lifts and the Afridev for medium lifts. The locally manufactured Rovai Pump (also called
the Rope Pump) is used for all lifts in both hand dug wells and drilled wells.
I-145
More advice on pump selection can be found in: UNICEF A Water Handbook19.
For medium lift 30 to 50 m. UNICEF include Afridev amongst recommended pumps but
generally in Cambodia they are not used at this depth. Such deep wells are not usually
provided under the C/S Fund but if one is required it is advisable to seek specialist advice.
Ponds
The questions for ponds are similar in concept to wells except that the pond will usually be
shallower and will cover a large area. Information on the soils will decide the suitability of the
ground as well as the stable side slopes. The questions ask where the water to fill the pond will
come from and whether there are potential sources of contamination nearby.
Table 5.15 Recommend maximum slopes for dug water supply ponds
Soils type
Clay group
Sandy group
Silty soils
Dispersive clays20
A pond in sandy soil will probably filled by shallow groundwater flow during the wet season but
water will quickly drain away once the groundwater levels drop in the dry season. A pond in a
clay soil will retain water much better but groundwater inflow will be small and to fill it will have
to rely on direct rainfall or captured runoff from surrounding land. You should consider the
possibility of low bunds and channels in situations where this will increase the capture of runoff.
Water quality
The Royal Government of Cambodia has established a comprehensive policy on National
Water Supply and Sanitation, covering both urban and rural water supplies. Based on this policy
and to ensure access to safe drinking water to all people, it required the Drinking Water Quality
Standard (DWS) for Cambodia21. These standards were developed by an inter-ministerial
process initiated by Ministry of Industry, Mines and Energy and concerned ministries with
support from the World Health Organization in 2004.
Drinking water should be clean and clear with pleasant taste and odor. The public will assess
drinking water quality using these aesthetic indicators but actually the safety of water is
determined by microbiological, physical, and chemical quality. It should be safe so that it does
not contain suspended matter, harmful chemical substances, and disease-causing
microorganisms. Microbiological quality is most important and is a priority for monitoring.
Tables
The associated templates drawings and quantity table can then be called up by the Project
Generator. For some outputs there may be no Template design. In these cases a design and
quantities will have to be provided.
All water supply systems should be tested for water quality parameters set out in Tables 1
through 4 prior to commissioning to ensure compliance with DWS. Small water supply systems
(those serving less than 100 people or delivering less than 10 m3/day) should be tested for
priority parameters set out in Table 5.20
Priority parameters in small water supplies
Table 5.16
Bacteriological quality for drinking water
Parameter
Maximum Value
0 per 100 mL
a) Thermotolerant (Fecal) Coliforms
or E. coli
b) Total coliforms
0 per 100 mL
19
UNICEF. Towards Better Programming - A Water Handbook, Water, Environment and Sanitation
Technical Guidelines Series - No. 2, United Nations Childrens Fund, 1999.
20
Clays which dissolve in contact with water.
21
MRD, Drinking Water Quality Standards for Cambodia, January 2004
Study and Design Guidelines
I-146
Parameter
Taste
Odor
Color
Turbidity
Residual chlorine
pH
Aluminum
Ammonia
Study and Design Guidelines
Chloride
Copper
Hardness*
Hydrogen Sulfide
Iron
Manganese
Sodium
Sulfate
Total dissolved solids**
Zinc
*
**
250
1
300
0.05
0.3
0.1
200
250
800
3
Table 5.20
Priority parameters in small water supplies
Parameter*
Maximum Value
pH
6.5-8.5
Turbidity
5 NTU
Arsenic
0.05 mg/L
Iron
0.3 mg/L
Total Dissolved Solids (TDS)
800 mg/L
Thermotolerant Coliforms or E. coli
0 per 100 mL
* Additional parameters such as conductivity can be monitored but these are the
minimum requirements.
I-148
For a site specific output such as a fence the quantity will have to be measured.
For some outputs such as higher floor levels there may be no Template design. In these cases
a design and quantities will have to be provided.
I-149
trained staff and who will provide these staff. The answers should be considered for
appropriateness of the project and its sustainability. The responsibility for operation and
maintenance of Health Facilities is normally passed to the line agency, the Provincial
Department of Health.
Physical characteristics of the site
There are questions to establish whether the site floods, and whether this is seasonal deep
water flooding, or due to slow drainage after heavy rainfall. Essentially if there is a flood
problem the decision has to be made whether this can be dealt with by drainage ditches or
other means.
There are a series of questions intended to confirm suitability of the site. These include whether
it is free of UXO, the status of land title, boundary demarcation and whether the site is of
sufficient size. The existing water supply and sanitation provision should be determined
because water supply and sanitation outputs may be needed.
Foundation soils
Form T51 provides for ground investigation by trial pit and DCP, as many pits and tests as are
needed.
Form T51 creates in advance the trial pit log; you enter the soil type and the
depths at which the soil types change. The 20 percentile value for DCP needs to
be calculated and filled into the form. You can use Ms. Excel for the calculation.
Form T51 automatically calls-up the correct quantities within the project generator
according to the outputs chosen.
For a site specific output such as a fence the quantity will have to be measured.
Latrines
Waste water
I-150
5.11.1
Latrines
In the case of schools there should be two latrines for every 5 classrooms; template designs are
available for two and four latrines. Health posts should be provided with a two room latrine
building, one room provides a toilet, the second room provides a shower.
5.11.2
There is no design guidance for waste water treatment and solid waste management; specialist
advice should be sought for these outputs.
Waste water
Waste water is a mixture of toilet waste (excreta) and sullage. Sullage is household waste
which has been used for washing, cooking or cleaning purposes, it is sometimes known as
grey water. Modern practice is to provide separate drainage systems for wastewater and
surface water runoff. If a wastewater system is provided it will be under sub-group 11002.
However more often, and especially in villages and peri-urban areas, only surface water
drainage will be provided. As discussed at section 5.11.3 below in these circumstances the
drains will also remove sullage.
5.11.3
Drainage
The objective of drainage is to remove unwanted water from settlements in a controlled and
hygienic manner in order to minimise public health hazards, inconvenience to residents and
deterioration of other infrastructure. This requires:
x
the removal of surface water, that is, water which runs off the land and buildings as a
result of rainfall; and
the removal of sullage, that is, household wastewater which has been used for washing,
cooking or cleaning purposes but which does not contain excreta.
Sullage increases the potential of pollution by the drainage system. The risk is greatest when
the proportion of sullage water is high, as occurs during the dry season.
If drains convey sullage, pay attention to the location of wells and water supply
sources. It may be necessary to protect these by extending the length of piped or
lined drain to outfall a safe distance away. The safe distances quoted on Table
5.13 should be applied.
Under no circumstances allow toilet waste and excreta into the surface water
drainage system because it will create a serious health risk. Promote the use of
latrines.
Capacity of drain
In order to calculate the required capacity of the drain it is necessary to establish the catchment
for a drain. In a peri-urban or village centre location there are building frontages and roofs
discharging to the strip of land beside the road. If a roadside drain is proposed it is
recommended to allow for drainage of a strip extending 50 m back from the road. In such
locations it is normal to provide a drain both sides of the road, if a drain is only provided one
side of the road consider whether it will capture some water from both sides of the road and
adjust the area accordingly.
Form T101 uses a default value of 3.5 l/s/ha to estimate the runoff from land beside the drain.
This is the same as used for irrigation drainage. This figure comes from an analysis typical
rainfall in Cambodia that is only exceeded by very heavy storms that occur occasionally,
perhaps several times in one year, not at all in others. Therefore if drainage is provided for this
runoff, there may be local flooding for short periods on a few occasions but most of the time the
drains will be large enough. This is a compromise to reduce the cost of the drains. The form
Study and Design Guidelines
I-151
allows another value to be entered. The required capacity is then calculated manually and
enter to the form.
Form T101 asks if the drain collects water from beyond the immediate area, e.g. a small area of
paddy. If it does you are asked to describe how the drain is affected, e.g. you may find that the
water from the paddy must be added to the runoff within the village. It is also necessary to
enter the extra area of catchment. If the area is 1 km2 then the form will calculate the extra
flow based on 3.5 l/s/ha (or whatever other flow rate you enter) and adds it to the runoff from
beside the drain. If the area is >1.0 km2 then the form advises the flow is probably too large for
the drain and should be directed to flow another way.
Hydraulic design of channel
Different procedures apply for the hydraulic design of channels compared to pipes. The advice
on pipes follows below.
The theory for design of channels is the same as irrigation canals and drains.
Form T101 calls-up Applet T101 Channel drain that will choose the channel size
provided you answer a few questions. You then need to fill the results into the
generator.
You have to enter the level of the bed at the upstream and downstream ends plus the length of
the drain so that the Applet can calculate the gradient. You choose a bank slope, the Template
for a concrete or brick drain has vertical sides. You select a bed width. You also chose a
freeboard, 0.1 m is recommended as the minimum freeboard but you can choose a larger
freeboard. You enter Mannings n for channel roughness, the form lists recommended values
for earth, concrete and masonry. You then need to enter the required capacity previously
calculated manually and write into the form to the Appet T101 but you may enter another flow if
you chose.
Applet T101 then prints the required depth of drain, the width between top of banks (which is
the same as the bed width except for trapezoidal drains), and the flow velocity. If the
recommended dimensions are not suitable then you can try changing the bed levels and the
bed widths to see if this will improve the design. Finally, copy those results to the form T101.
Hydraulic design of pipe drain
Pipe design is based on solution of the Colebrook-White formula. The full solution is too
complex to provide rapid solution for design so Universal design charts were developed by
Ackers22 to permit direct solution. These are now in their 8th Edition in tabular form23.
The relevant results have to be taken from the charts to fill into Form T101.
The results used by Form T110 are show in Table 5.21 and Table 5.22 for concrete and plastics
pipes respectively. The form allows you to choose between these two pipe materials. The
difference is the pipe roughness (friction) expressed as the Colebrook-White coefficient k (see
tables). Plastic pipes are smoother so have a marginally greater capacity.
At design capacity the pipes are intended to run full. For this condition the headwalls in the
intermediate chambers must be submerged. Hence the hydraulic gradient is calculated
assuming the water rises to 200 mm below ground level at the head of the drain and is the
depth of the drain at the outfall. The applet then enters the table for this gradient and reads off
the discharge and velocity for the chosen pipe size. If this does not match the required capacity
chose a different pipe size, or alter the drain depth to change the gradient until you are satisfied
the drain will be large enough.
22
23
Ackers P. Charts for Hydraulic Design of Channels and Pipes, Hydraulics Research Paper No2,
Hydraulics Research Station, Wallingford, Her Majestys Stationery Office, UK, First Edition, 1958.
Barr DIH. Tables for Hydraulic Design of Pipes, Sewers and Channels, Eighth Edition, Volume 1. HR
Wallingford, UK, March 2005.
I-152
The best pipe size is a compromise. Most of the time the drain will convey small
flows. Small flows will deposit sediment and rubbish, especially if the flow includes
sullage. The larger the drain, the more likely it is that sediment deposits will build
up. Some of the sediment will be washed away by storm flows if velocity is above
about 0.5 m/s. But an oversize drain will require frequent cleaning whereas a too
small drain will often overtop and cause localised flooding.
Discharge
(l/s)
Velocity
(m/s)
Discharge
(l/s)
Velocity
(m/s)
Discharge
(l/s)
Velocity
(m/s)
Discharge
(l/s)
Velocity
(m/s)
Discharge
(l/s)
Velocity
(m/s)
Discharge
(l/s)
Velocity
(m/s)
Pipe
diameter
1.0m
Hydraulic gradient
0.003
0.004
0.005
0.006
0.007
0.008
0.009
0.010
0.012
0.014
0.016
0.018
0.020
6
7
8
9
10
10
11
12
13
14
14
15
16
0.08
0.10
0.11
0.12
0.13
0.14
0.16
0.16
0.18
0.20
0.20
0.21
0.23
12
15
16
18
20
22
23
24
27
29
31
33
35
0.10
0.12
0.13
0.14
0.16
0.18
0.18
0.19
0.21
0.23
0.25
0.26
0.28
24
27
30
33
36
39
42
45
48
51
55
59
63
0.12
0.14
0.15
0.17
0.18
0.20
0.21
0.23
0.24
0.26
0.28
0.30
0.32
37
42
47
53
58
62
66
70
78
85
90
96
102
0.13
0.15
0.17
0.19
0.21
0.22
0.23
0.25
0.28
0.30
0.32
0.34
0.36
80
95
108
120
131
139
144
150
170
180
200
210
220
0.16
0.19
0.21
0.24
0.26
0.28
0.29
0.30
0.34
0.36
0.40
0.42
0.44
145
165
195
215
235
250
260
270
310
330
350
375
400
0.18
0.21
0.25
0.27
0.30
0.32
0.33
0.34
0.39
0.42
0.45
0.48
0.51
24
28
32
35
38
41
44
47
50
55
60
65
69
0.12
0.14
0.16
0.18
0.19
0.21
0.22
0.24
0.25
0.28
0.31
0.33
0.35
38
46
51
56
61
66
71
76
82
91
99
106
114
Discharge
(l/s)
Velocity
(m/s)
0.10
0.13
0.14
0.16
0.17
0.18
0.19
0.21
0.23
0.25
0.26
0.29
0.31
Velocity
(m/s)
Discharge
(l/s)
13
16
18
20
21
23
24
26
29
31
33
36
39
Discharge
(l/s)
Velocity
(m/s)
0.08
0.10
0.11
0.12
0.13
0.14
0.16
0.17
0.18
0.20
0.21
0.23
0.25
Velocity
(m/s)
Discharge
(l/s)
6
7
8
9
10
10
11
12
13
14
15
16
18
Pipe
diameter
1.0m
Discharge
(l/s)
Velocity
(m/s)
0.003
0.004
0.005
0.006
0.007
0.008
0.009
0.010
0.012
0.014
0.016
0.018
0.020
Hydraulic gradient
Table 5.22 - Pipe full flow and velocity for plastics pipes
0.13
0.16
0.18
0.20
0.22
0.23
0.25
0.27
0.29
0.32
0.35
0.37
0.40
88
102
117
126
136
146
154
160
175
200
215
230
250
0.18
0.20
0.23
0.25
0.27
0.29
0.31
0.32
0.35
0.40
0.43
0.46
0.50
160
180
200
220
240
260
280
300
330
360
390
420
450
0.20
0.23
0.25
0.28
0.31
0.33
0.36
0.38
0.42
0.46
0.50
0.53
0.57
I-153
ANNEX 1:
TECHNICAL FORMS
I-154
Province :
District :
Name of project :
Name of TSO :
S/C:
Code of S/C :
Yes
No
I-155
Bridge
culvert
drift
vented causeway
Yes
No
Yes
No
Flooding
Can meet specification for Type 3 material by mixing with imported material
Can meet specification for Type 1 material by mixing with imported material
I-156
Borrow pit
Stream bed
Borrow pit
Stream bed
quality
Limestone
Sandstone
Limestone
Sandstone
27. Road traffic: what are the proportion of the cars and trucks using the road?
*Write in percentage.
One place to another in
commune
28. the proportion of the cars and trucks using the road is:
* Put it into percentage.
Belong to people who live in the
commune
29. Foundation soils: what kind of soil the structure stand on?
Study and Design Guidelines
I-157
Normal clay
Sandy soils
Gravels
Other.
Horizontal
Horizontal
34. Fill with the thickness of the road pavement choosing above:
Road pavement
thickness
35. Road maintenance: Does the commune have a Commune Road Sub-Committee?
Yes
No
Sangkat/Commune
Others
37. Write the person who is responsible for road maintenance if you choose other
38. Remark:
You must upload Applet in which you entered your data to get the answers and the
advices about road pavement. If you chose the road pavement that is not suitable
less or more than recommendation from Applet T11, give your reason on Advice
Tab.
I-158
District :
S/C:
Name of project :
Code of S/C :
Name of TSO :
Y of GPS
Road standard
4. Scope of work: is the structure part of a road project to be carried out at the same
time or is the work for the structure only?
Structure only.
Yes
No
diameter (m)
Pipe material
Headwalls
Carriageway
width over
culvert
I-159
Number of
box
Width (m)
Height
Walls
Road slab
Carriage
width over
culvert
Width of
each
span
Height of
each span
Abutment
material
Piers
Deck
material
Deck
carriageway
width(m)
Number
of spans
Width of
each
span
Height of
each
span
Abutment
material
Piers
Deck
material
Deck
carriageway
width(m)
Width of
each
span
Height of
each span
Abutment
material
Piers
Deck
material
Deck
carriageway
width(m)
ramp slope
Difference in level
between road on
embankment and
crossing (m)
road material
carriageway
width (m)
ramp
slope
Difference in
level between
road on
embankment and
crossing (m)
road
material
carriageway
width (m)
Size of
opening
Width/Dia
Size of
opening
Height
I-160
source
distance
(km)
sand
source
of
sands
distance
(km)
gravel
source
of
gravel
distance
(km)
15. Part 2
* Source of stone: quarry or stream bed. Type of stone: hard metamorphic rocks
(granite, basalt, etc).
Stone
Source of
stone
type of
stone
distance
(km)
water
supply for
concrete
source
distance
(km)
Normal clay
Sandy soil
Gravel
Others
location
I-161
Yes
No
I-162
District :
S/C:
Code of S/C :
Yes
No
5. How many farmers (families) are members of the Community?
6. Have the farmers discussed together and agreed how they will pay the operation and
maintenance costs of the project?
Yes
No
7. Operation and maintenance responsibilities:
Who will be responsible to do the operation and maintenance?
* if the scheme dont need a pump, fill with No need.
Open and close
Collect
Organize
Solve disputes
Operate the
water gates?
water user
maintenance
between
pump (if the
fees?
work?
farmers about
scheme needs
the water?
a pump)?
8. Irrigation system requirement: what is the irrigated area in hectares?
* Remark: if the project will be a part of a big irrigation project, only describe the part
that will be affected by the project.
Wet season
dry season
9. What is the main type of crop that will be grown on the land?
wet season
dry season
10. How much of the land that has enough water every year already?
Wet season
number of families
dry season
number of families
11. How much of the land that has enough water some years?
Wet season
number of families
dry season
number of families
12. How much of the land never has enough water at present?
Wet season
number of families
dry season
number of families
I-163
dry season
number of families
14. Flooding: Do the fields flood for some days each year?
If Yes, answer the following questions, if No, skip to question 18.
Yes
No
15. How long are the fields flooded (days)?
16. What is the flood depth during these days (m)?
17. What is the flood path, does the water flow concentrate is some places, describe and
flow path(s) on map?
18. Existing irrigation system: is there and existing irrigation system?
If Yes, answer the following question. If No skip to question 28.
Yes
No
19. When was the irrigation system built?
If 1980 to 2000 or After 2000, answer the following questions. If not, skip one
question below.
French era
Sihanouk era
Khmer Rouge era
1980 to 2000
After 2000.
20. Under what program or which donor paid for the project?
21. Does the system work?
Working
Working 50%
Works a little
Not working
22. What are the main components of the system and what is their condition?
River intake
Reservoir
Dam
Spillways
Large water gates
Canals
I-164
condition
< 1 month
1 to 2 months
3 to 4 months
5 months
6 months
> 6 months
25. What do you judge as the main problem with the existing irrigation system?
26. How can a new irrigation project overcome these problems?
27. Do you have any other comments relevant to the proposed irrigation project?
28. Water resource: where will the water come from?
River
Reservoir
Flood lake
Canal
29. What is the water depth existing river, reservoir, lake or canal each month of the year
and is the water stationary or flowing (include largest river flowing into or out of an
existing reservoir)?
Month
depth (m)
flowing, not flowing
30. How will the water be delivered from the source to the distribution canals and fields?
By pumping
By gravity
31. What is the difference in between the lowest water level at the source and the level of
the fields (m)?
* It is recommended to measure the difference in level with a survey instrument.
32. Irrigation water requirement: remark
Use Applet T21 to get monthly water requirement for irrigation and gravity flow
capacity per second.
33. Works proposed for irrigation project: What are the main works items include size that
will be repaired or newly constructed for the Irrigation Project?
* For these following questions, answer only about situation and size of the structures
chosen in this question.
Reservoir
Dam
Spillways
River weir or gate
Head regulator
Secondary canal
I-165
Tertiary canal
Canal, water gate or regulator
Off-take
Culverts
34. Reservoir works
Repair or New
Area (ha)
Volume (m3)
I-166
District :
S/C:
Code of S/C :
Periodic maintenance
4. Traffic use of earthwork: Is the earthwork used as a public road or for farm access?
If Not used skip to question 11.
Public road
Farm access
Not used
5. Has the earthwork ever had Laterite or any other kind of improved surface in the
past?
Yes
No
6. Is there any Laterite or any other kind of surface on the earthwork now?
Yes
No
7. What is the largest vehicle that uses the earthwork?
Passenger car
People walking
Motorcycle
Motor-remorque
Bicycle
Animal cart
Light vehicle/van
Koyun
I-167
Mini-bus (4 tyres).
8. Approximately how many of these vehicles use the earthwork per day?
* In PCU units, you can use Applet T11 to help your calculation of the number of
vehicle.
9. According the traffic of vehicle above, what type of pavement is suitable for this
earthwork?
* if the number of vehicle is < 21 Earth surface is satisfactory.
* if the number of vehicle is < 25 Light Laterite surface is satisfactory
* If number of vehicles is <100 Medium Laterite surface is satisfactory
* If number of vehicles is >100 Too much traffic for Laterite surface consider other
option.
10. Condition of the existing dams or dykes and Canals or drains: describe the condition
of the existing earthwork.
11. What causes most damage to the earthwork?
* if Other, answer the question 12
Bank erosion
12. If Others mention them.
13. Soils: What kind of soil is at the project site, (a) for use as fill, (b) for excavating
canals and drains?
Clay group, stable slope: upstream 1:2.00, downstream 1:1.75, Canal and
drain 1:1.25
Sandy group, stable slope: upstream 1:2.50, downstream 1:2.00, Canal and
drain 1:1.50
Silty soil, stable slope: upstream not suitable, downstream not suitable,
Canal and drain 1:1.50
Dispersive clay, upstream not suitable, downstream not suitable, canal and
I-168
Organic soils, upstream not suitable, downstream not suitable, canal and
drain : Line canal.
14. Material for road construction: remark
Skip the materias which are not chosen for road construction.
15. Fill material from borrow beside earth works.
Not surfaced
Laterite
Others
28. Others, mention them.
29. If laterite, what is the thickness of laterite (mm) ?
30. What will be the upstream slope (see advice in question 13)?
31. What will be the downstream slope (see advice in question 13)?
32. What slope protect will be provided to the upstream slope?
* If not Rock riprap, skip the question 34 to 36.
Study and Design Guidelines
I-169
None
Grass
Rock riprap
Others
33. If Others, mention them.
34. If Rock riprap, What class of riprap (Class A suitable for small reservoirs)?
Class A
Class B
Class C
Class D
35. What thickness of riprap in millimeters (300 mm minimum for Class A)?
36. What filter will be placed below riprap?
150mm gravel
None
Grass
38. Capacity of canal: Will the canal be irrigated continuously (24 hours) by gravity or by
pumping?
If Gravity, answer the question 40, then skip the question 41. If Pumping, skip the
question 41, then answer the question 41.
Gravity
Pumping
39. Required flow capacity (gravity).
* the design peak flow rate : 2l/s/h or another higher flow rate.
* flow capacity (l/s) = irrigation area (ha) x flow rate (l/s/ha)
Flow rate (l/s/ha)
irrigation area (ha)
flow capacity (l/s)
40. Required flow capacity (pumping)
* Recommended flow rate is 2l/s/ha, or another higher flow rate.
* Pumping rate = flow rate / number of pumping hours x24hours
* flow capacity = irrigation area (ha) x flow rate (l/s.ha)
Flow rate (l/s/ha)
number of pumping hours
pumping rate (l.s.ha)
(hour)
41. Capacity of drain: How will the fields be drained?
If Irrigation canals provide drainage the canals must be sized (larger) top work as
drains. So you have to carry on the question about the drain. If No drain, explain the
following question, and then skip to question 48.
Separate drain
Canal as a drain
No drain
I-170
42. Explain how excess rainfall and flood water will be drained from the fields?
43. Drain capacity
* Recommended flow rate 3.5l/s/ha, or another higher flow rate.
* Flow capacity (m3/s) = area (ha) x flow rate (m3/s/ha)
Drainage area (ha)
flow rate (l/s/ha)
flow capacity (m3/s)
44. Will the drain collect water from catchments beyond the fields?
* E.g. a stream flows into the head of the drain from a small catchment or another
irrigation system? If Yes, answer the following questions, if No skip to question 48.
Yes
No
45. What is the catchment area in km2?
If the catchment < 1.00km2 , Add this area to the area of fields above and recalculate
new field drainage flow rate. If the catchment > 1.00km2, use Applet form T22, flow
external catchment or get help from engineer to calculate the total flow (with the flow
in the catchment above).
46. The flow rate of external catchment (m3/s) is:
Use Applet T22 external catchment then copy form column C32.
If the flow system of the external catchment is too complicate, you have to discuss
with the engineer to get the flow capacity of this catchment.
47. Total drain design flow (m3/s) is the flow from irrigated area + flow from external
catchment.
* Value of question 43 + value of question 46.
48. Hydraulic design of canal and drain: remark
Use Applet T22 Hydraulic design of canal and drain to calculate the minimum water
height, bottom width and design velocity.
49. Responsibility for operation and maintenance: is there a Farmer Water Use Comity
(FWUC) or similar group of people who are responsible for operation and
maintenance of the earthwork.
Yes
No
50. Who will take to operate and maintain the earthwork ?
51. Remark
Upload all of Applet T22 that you used into Project generator for engineer to
examine.
I-171
District :
S/C:
Code of S/C :
Yes
Study and Design Guidelines
I-172
No
13. Road classification:
District to district
District to commune
Commune to commune
Commune to village
Village to village
Farm acces
14. What is the largest vehicle that uses the earthwork?
Passenger car
People walking
Motorcycle
Motor-remorque
Bicycle
Animal cart
Light vehicle/van
Koyun
Medium truck (6 tyres)
Heavy truck (6 tyres)
Bus (>4 tyres)
Mini-bus (4 tyres).
15. Flow capacity: what is the design flow capacity (can be from T22), (m3/s)?
* Calculated from canal capacity. You can skip this question for spillways or river
intake. Generally, if the design structure is passed by the irrigation flow and drainage
flow, you must design the structure the drainage flow, because its value is always
higher.
16. What is the flow capacity at the structure (m3/s)?
* Calculated from canal capacity. You can copy skip question for spillways or river
intake. Generally, if the design structure is passed by the irrigation flow and drainage
flow, you must design the structure the drainage flow, because its value is always
higher.
17. Can this flow capacity be higher than design one?
If Can, answer the following questions, if Can not skip them.
Can
Can not
18. Describe the circumstance and consequence for the structure also what provision will
be provided to survive an extreme flow?
Using the design guidance spillways is sized for 1 in 50 year flow into the reservoir;
Study and Design Guidelines
I-173
the reservoir freeboard allows some of the flood to stay temporarily in the reservoir
until it call all pass over the spillways. A concrete stilling basin and erosion protection
will be provided downstream.
19. Did you use Applet to determine the design flow and length of structure? (Spillway
and diversion weirs)
* if you dont design the spillway or river intake, skip them.
Yes
No
20. Spillway and diversion weirs: is the structure for reservoir or river intake?
Reservoir
River intake
21. What is the design flow for spillway or river intake (m3/s) ?
* Copy from Applet T23, worksheet GTFM: C32.
22. What is the maximum safe water level at the upstream of structure? ( higher than this
level, it can be flooded, overtopped).
* Copy from Applet T23, worksheet GTFP: C33.
23. What is the proposed weirs crest level? ( it is a full water level of a reservoir or river
level intaking to the system).
* Copy from Applet T23, worksheet GTFM:C34.
24. Required weirs length (m):
* Copy from Applet T23, worksheet GTFM:C35.
25. Pumping capacity: provide the pumping capacity (m3/s).
* Answer if there is a pumping, see the irrigation project form T22.
26. Responsibility for operation and maintenance: is there a Farmer Water User Comity
(FWUC) or similar group of people who are willing to take responsibility to operate
and maintain the structure?
Yes
No
27. Who will operate and maintain the irrigation structure?
Commune council
28. Remark:
Dont forget to upload Applet that you used in your calculation.
I-174
District :
S/C:
Code of S/C :
Village
School
Health centre
5. Information about number of users: how many people use the water supply? In which
village do they live?
* Totalize the numbers above and write it down in the last row.
Name of village
people in village
number of family using
the water supply
6. Number of supplier in school and health post
* If you chose School in the answer above, write down only the number of rooms
and number of students. If you choose Health post write down only the number of
users in the health center.
Number of school rooms
number of students or health post
7. Maintenance: Who will maintain the water supply?
8. Existing water supply: how many families use the existing water supply?
* if the existing water supply is for school, write down only use for school.
9. Have the families who will use the supply agreed to form a Water Supply Committee?
Yes
No
10. Where does the domestic water used by these people come from now?
* Source: watercourse, natural pond, dug pond, rain water harvesting, spring, village
well, household will, water-point piped. Totalize the number of users, and then write it
down in the last row.
Source
number of users
distance to the centre of village
(km)
11. Information about proposed facility: Who owns the land where the new facility will be
constructed?
* if the land is in private ownership, answer the question 12.
Community
Study and Design Guidelines
I-175
Private
12. Does the landowner agree to construction and unrestricted use of the facility?
Yes
No
13. Does the location of the facility ever flood?
* if Yes, answer the questions 14 and 15.
Yes
No
14. What is the depth of flooding in meters ?
15. What type of flooding?
Dug well
Drilled well
Mixed well
17. Provide the coordinates of GPS
Type of well
X of GPS
Y of GPS
18. What is the distance (closest) from the existing well to the proposed well (km)?
19. Who owns this existing well?
20. Is the existing well used for domestic water or farming?
Domestic water
Framing
21. How old is the existing well?
22. How deep is the existing well?
23. What is the static water level in the dry seasons?
24. What is the static water level in the wet seasons?
2
25. How many families use the sell?
26. Does the existing well have enough water all year?
Enough
Not enough
27. What does water from the well taste like?
Note taste
Salty
Bitter
28. What is the color of the water in the existing well?
Clear
Study and Design Guidelines
I-176
Gray
Yellow
Brown
29. Does it smell?
Yes
No
30. Has the water from the existing well ever been tested for arsenic?
Yes, ever
No, never
31. What kind of soil or rock is the well sunk in?
From depth (m)
to depth (m)
32. How do you know about the information on the soil or rock?
33. How are the other well ?
Soak away
Watercourse
Pond
Other
42. If Other, list your answers.
43. Is there anything close to the well that could cause contamination of the well?
* If Other, answer the question 45.
None
Latrine
Animal pens
Cmetery
Study and Design Guidelines
I-177
Chemical store
Fuel store
Other
44. If other, list your answers.
45. if a potential cause of contamination is identified, write it down.
Consider another well location a safe distance from contamination source or explain
in the box below what measures will be taken to prevent contamination.
46. Suitable pump for well
I-178
Yes
No
9. Physical characteristics of the site: does the site ever flood in the wet season?
* if Ever, answer the two following questions.
Ever
Never
10. What is the maximum depth of flooding in meters?
11. What type of flooding?
Yes
No
13. Does land title exist for the site?
* If Yes, answer the following questions.
Yes
No
Study and Design Guidelines
I-179
Yes
No
16. Whom or what? (E.g. building, rice field and will compensation be
expected/demanded?)
17. Is the site presently walled or fenced?
Yes
No
18. Will land fill or embankments be needed to protect against flooding?
* If Yes, answer the question 19
Yes
No
19. If Yes, describe it.
20. Is there enough space for students to play sports?
Yes
No
21. Is there enough space to build more classrooms in the future?
Yes
No
22. What is the water supply at the site?
* If Pond or Pumping well, answer the following question
None
Pond
Pumping well
Piped supply from off site
23. Write down the dry season water level below ground (m)
24. How many existing latrines at the sites?
25. Foundation soils: (for school building construction, school fence and walls)
What kind of soil will the school be constructed on?
* Type of soil: gravel, silty sand, micaceous sand, lateritic sand, clayey sand, loams,
organic clays, lateritic clays, dandy, silty or clayey peats.
Number
X of
Y of
Depth (m)
Type of
group of soil
of trial pit
GPS
GPS
soil
26. DCP test (mm/blow)
DCP (mm/blow)
X of GPS
Y of GPS
27. 20 percentile of DCP (mm/blow)
I-180
District :
S/C:
Code of S/C :
Ever
Never
9. If Ever, what is the maximum depth of flooding in meters?
10. If Ever, what type of flooding?
Yes
No
12. Does land title exist for the site? If yes, at what stage is the documentation (district,
province)
13. Is the site presently occupied? If yes, list them.
* e.g. building, rice field will compensation be expected/demanded?
14. Is the site presently walled or fenced?
Yes
No
15. Will land fill or embankments be needed to protect against flooding?
Yes
No
16. What is the water supply at the site?
None
Pond
I-181
Pumping well
I-182
District :
S/C:
Code of S/C :
1. Location: where is the sanitation and drainage located within the Sangkat/commune?
Describe the location
2. Provide de coordinate of GPS.
* if it is a point, fill only the first row. First row is the starting point and the second row
is the ending point.
X of GPS
Y of GPS
3. Description of requirements: give a brief description about the project.
4. List the number or length of the proposed outputs.
* provide the number for the latrines and length for the drain.
Output
Number or length
5. Drainage capacity: give drain a name; area of land drained, flow rate (m3/s/ha), flow
capacity and external catchment.
* in peri-urban or village can allow for 50m wide strip from road centerline for drains
each side of road. Recommended flow rate is 3.5l/s/ha, but you choose another
value. The required flow capacity of drain = flow rate x drained area. Will the drain
collect water from catchments beyond the drain, e.g. a stream flow into the head of
the drain from a small catchment or drain system? Write down Collect or Does not
collect.
Name of drain Drained area
Flow rate
Flow capacity
External
(ha)
(l/s.ha)
(l/s)
catchment
6. Remark
* if you chose Collect, answer the two following questions.
7. Describe briefly how the extra catchment affects the requirements, e.g. it may only
affect a drain one side of the road.
Name of drain
Description
8. Give a name of drain collecting water from external catchment, area of external
catchment, flow rate (l/s/ha) and extra flow capacity.
* if catchment area > 1.0Km2, flow from this catchment will be too big for a culvert or a
drain, so let think about the flow conveyance or a special advice.
* Recommended drain flow capacity is 3.5l/s.ha, but you can choose another one.
* flow capacity extra = catchment area (ha) x flow rate (l/s.ha).
Name of drain
External catchment
Flow rate (l/s.ha)
Extra flow capacity
area (ha)
(l/s)
9. Calculate the total design flow capacity for box culvert (l/s).
* Total design flow capacity = drain flow capacity (l/s) + extra flow capacity of external
catchment (l/s)
Name of drain
Design flow capacity (l/s)
10. Design of box drain: remark
You must use Applet Form T101 Drain to determine the design flow, channel bed
level, bottom width and channel velocity.
11. Result of the design of box drain and drain from Applet T101.
* Skip it if you dont design the box drain. Copy the answer from Applet T101 that you
used to calculate.
I-183
Name of drain
I-184