Chapter1: Introduction
1.1 Project Description:
The project is structural analysis and design of a proposed new
building for Nablus Municipality. First a preliminary analysis and design using
1D and 2D models are made, then the analysis and design are done using 3D
model using SAP2000 program.
The building is composed of 3 stories above the ground, and an
underground parking. The area of each story is about 1580m2, and its height
is 4m.
The project has 2 structural joints which divide the building into three
parts: A,B, and C from left to right. It is composed of both reinforced concrete
and steel parts. The large dome over part B is made of steel and the vault
over the entrance is made of steel arches. The rest of the structure which
includes the two domes over the stair roofs over part B, and the dome over
minaret are made of reinforced concrete. All these descriptions are illustrated
on fig.1.1.
1.3 Materials
1. Concrete
Concrete strength for all concrete parts is B350f'c=280 Kg/cm
Modulus of elasticity equals 2.5*105 Kg/cm2.
Unit weight is 2.5 ton/m 3.
2. Steel:
Modulus of elasticity equals 2.04*106 Kg/cm2.
Steel yield strength:
For steel reinforcement, is 4200 kg/cm2.
For rolled steel, is 2750 kg/cm2.
3. The unit weights of the main materials used are shown in table1.1:
Density(ton/m3)
Reinforced concrete
2.5
Bricks
1.2
Filler
1.5
Masonry
2.7
Tiles
2.5
Mortar
2.3
plastering
2.3
1.9
base coarse)
Polycarbonate
0.04
1.4 Loads:
1. Dead Loads:
Dead loads are composed of own weight of the slabs, beams, columns, walls,
Domes, and superimposed dead loads from the partitions and tiles.
o The super imposed dead loads are composed of:
Bricks, mortar and filling as shown below
S3 is a factor that takes into account of the degree of security and the
period of time in years during which there will be exposure to wind ,
normally wind loads on complete structure and buildings should be
calculated at S3 = 1 with the following exceptions :
o Temporary structures.
o Structures where a shorter period of exposure to the wind
may be expected
o Structures where a longer period of exposure to the wind
may be required
o Structure where greater than normal safety is required
Since our building is not one of those exception then S3 = 1
k = 0.613 in SI units (N/m2 and m/s) " British code page 145".
Table1.2. Ground Roughness, building size and height above ground, factor S2
Class
Class
Class
(m)
*
Class
A
3 or
less
0.83
0.78
0.73
0.72
0.67
0.63
0.64
0.6
0.55
0.56
0.52
0.47
0.88
0.83
0.78
0.79
0.74
0.7
0.7
0.65
0.6
0.6
0.55
0.5
10
0.95
0.9
0.93
0.88
0.83
0.78
0.74
0.69
0.67
0.62
0.58
15
1.03
0.99
0.94
0.95
0.91
0.88
0.83
0.78
0.74
0.69
0.64
20
1.06
1.01
0.96
1.03
0.98
0.94
0.95
0.9
0.85
0.79
0.75
0.7
30
1.09
1.05
1.07
1.03
0.98
1.01
0.97
0.92
0.9
0.85
0.79
40
1.12
1.08
1.03
1.1
1.06
1.01
1.05
1.01
0.96
0.97
0.93
0.89
50
1.14
1.1
1.06
1.12
1.08
1.04
1.08
1.04
1.02
0.98
0.94
60
1.15
1.12
1.08
1.14
1.1
1.06
1.1
1.06
1.02
1.05
1.02
0.98
80
1.18
1.15
1.11
1.17
1.13
1.09
1.13
1.1
1.06
1.1
1.07
1.03
100
1.2
1.17
1.13
1.19
1.16
1.12
1.16
1.12
1.09
1.13
1.1
1.07
120
1.22
1.19
1.15
1.21
1.18
1.14
1.18
1.15
1.11
1.15
1.13
1.1
140
1.24
1.2
1.17
1.22
1.19
1.16
1.2
1.17
1.13
1.17
1.15
1.12
160
1.25
1.22
1.19
1.24
1.21
1.18
1.21
1.18
1.15
1.19
1.17
1.14
180
1.26
1.23
1.2
1.25
1.22
1.19
1.23
1.2
1.17
1.2
1.19
1.16
200
1.27
1.24
1.21
1.26
1.24
1.21
1.24
1.21
1.18
1.22
1.21
1.18
Class A. All units of cladding, glazing and roofing and their immediate fixings
and individual members of unclad structures, class B. All buildings and
structures where neither the greatest horizontal dimension nor the greatest
vertical dimension exceeds 50m,
This building will be considered case 4, classC.
The external pressure coefficient " Cpe" will be taken from the table 1.3.
Table 1.3 Pressure coefficients Cpe for pitch roofs of rectangular clad buildings
Pressure coefficients Cpe for pitch roofs
wind angle =0
degree
building
height* ratio
h/w 0.5
roof angle
Wind
ward
face
Leeward
face
Wind
ward
face
Leeward
face
-0.8
-0.4
-0.8
-0.4
-0.9
-0.4
-0.8
-0.4
10
-1.2
-0.4
-0.8
-0.6
20
-0.4
-0.4
-0.7
-0.6
30
-0.4
-0.7
-0.6
45
0.3
-0.5
-0.7
-0.6
60
0.7
-0.6
-0.7
-0.6
-0.8
-0.6
-1
-0.6
-0.9
-0.6
-0.9
-0.6
10
-1.1
-0.6
-0.8
-0.6
20
-0.7
-0.5
-0.8
-0.6
30
-0.2
-0.5
-0.8
-0.8
45
0.2
-0.5
-0.8
-0.8
60
0.6
-0.5
-0.8
-0.8
-0.7
-0.6
-0.9
-0.7
-0.7
-0.6
-0.8
-0.8
10
-0.7
-0.6
-0.8
-0.8
20
-0.8
-0.6
-0.8
-0.8
30
-1
-0.5
-0.8
-0.7
40
-0.2
-0.5
-0.8
-0.7
50
0.2
-0.5
-0.8
-0.7
60
0.5
-0.5
-0.8
-0.7
The dome will be divided into 4 areas, marked by points shown on Fig.1.1.
Each area will take approximately the same wind load on these points.
Table1.4 gives wind pressure values using the equation below:
P = (V *S1 *S2 *S3) *k *(Cpe Cpi )
Pressure
(N/m)
Cpe
point
no.
elevation
(m)
S2
17.32
0.668
70
0.7
135
-0.6
-66.1
19
0.688
60
0.7
143.3
-0.6
-43
20.25
0.702
40
0.2
74.57
-0.433
-19.8
20.91
0.708
10
1.2
-163.54
-0.4
-15.2
angle of
inclination
Pressure
(N/m)
(win ward
face)
at the wind
ward face
(leeward
face)
at the leeward
face
point Elevation
no.
(m)
S2
Cpe at
Angle of
windward
Inclination
face
pressure
(N/m) at
windward
face
Cpe at
leeward
face
pressure
(N/m) at
leeward
face
12
0.645
50
0.433
92.29
-0.533
-29.34
13
0.668
37.6
0.355
88.46
-0.45
-20.26
13.75
0.688
25
-0.2
14.33
-0.4
-14.33
14.21
0.702
18.06
-0.555
-38.03
-0.4
-14.91
14.37
0.708
-0.8
-75.86
-0.4
-15.17
1.5
Loads combinations:
10
11
k1
k2
k3
0.5
0.5
10
0.505
-0.48
5.3
20
0.516
-0.425
1.37
30
0.537
-0.33
0.64
40
0.566
-0.2
0.38
50
0.608
-0.034
0.27
51.48
0.618
0.26
60
0.667
0.167
0.21
70
0.747
0.402
0.18
80
0.838
0.68
0.16
90
0.16
1. Minaret Dome:
Concrete dome with ring beam below.
Dimensions:
Radius (R)=3 m, Rise = 2.22 m, c = 75
Thickness(d)= 10 cm (range 7.5cm
15cm).
Loads :
Dead load(w) =own weight=1*1*0.1*2.5=0.25 t/m
Live and snow loads(q) =0.15 t/m (on projected area).
Super imposed load, concentrated(W) =0.05 t.
Angle of super imposed load = 10 degree.
Applying Eqs. A to d, the stresses on the dome are given in Table 2.2.
12
-4.50
C live and
snow
(ton/m2)
-2.25
live and
snow
(ton/m2)
-2.25
4.55
4.32
-2.25
20
4.10
2.96
30
4.13
40
C dead
(ton/m2)
dead
(ton/m2)
4.50
10
C total
total
(ton/m2) (ton/m2)
2.25
-6.75
-0.92
2.30
3.40
-2.25
1.50
1.85
4.46
2.37
-2.25
2.14
1.88
4.51
4.31
1.44
-2.25
0.25
2.06
1.69
50
4.61
0.21
-2.25
-1.94
2.36
-1.73
51.48
4.68
-0.04
-2.25
1.70
2.43
1.66
60
5.04
-1.29
-2.25
-1.83
2.79
-3.12
70
75
5.63
6.59
-3.05
-4.58
-2.25
-2.25
0.45
1.32
3.38
4.34
-2.60
-3.26
All tension and compression stresses are much less than concrete
capacity, where concrete compression capacity is 2800 ton/m 2, and the
tension concrete capacity is approximately equal to 280 ton/m2.
Thus only shrinkage steel is needed for both directions(meridian and
hoop).
As =0.2%*10*100 =2 cm2 use 4 8mm/m.
Loads :
Dead load = only its own weight (w)=1*1*0.1*2.5=0.25 t/m.
Live and snow loads (q) =0.15 t/m (on the projected area).
Applying Eqs. A to d, the stresses on the dome are given in table 2.2.
13
Table2.3. Meridian and Hoop Stresses for domes over stair roofs
-2.25
C live and
snow
(ton/m2)
-1.35
live and
snow
(ton/m2)
-1.35
2.27
2.16
-1.35
20
2.32
1.91
30
2.42
40
C dead
(ton/m2)
dead
(ton/m2)
2.25
10
C total
total
(ton/m2) (ton/m2)
-1.35
-1.35
-0.55
0.92
1.61
-1.35
0.90
0.97
2.81
1.49
-1.35
1.29
1.07
2.77
2.55
0.90
-1.35
0.15
1.20
1.05
50
2.74
0.15
-1.35
-1.16
1.39
-1.01
51.48
2.78
0.00
-1.35
1.02
1.43
1.02
58
3.00
-0.75
-1.35
-1.10
1.65
-1.85
All tension and compression stresses are much less than concrete
capacity, where concrete compression capacity is 2800 ton/m2, and the
tension concrete capacity is approximately equal to 280 ton/m2.
Thus only shrinkage steel is needed for both directions(meridian and
hoop).
As =0.2%*10*100 =2 cm2 use 4 8mm/m.
14
Table 2.4: minimum thickness of one way solid slabs and beams
Minimum thickness, h
Member
One end
continuous
Two ends
continuous
simply
supported
Cantilever
One way
solid slab
ln
24
ln
28
ln
20
ln
10
Beams
ln
18.5
ln
21
ln
16
ln
8
Max. shear at distance d =20 cm from the face of column= 1.910.79*(0.15+0.2)=1.633 ton.
(Assumed columns dimensions are 30*70 cm.)
Nominal shear=1.633/0.75=2.178 ton
Vc= 0.53*
-3
f c *b*d*1.1=0.53* 280 *12*20*1.1*10 =2.34ton>Vu no need for
shear reinforcement.
Max. neg. moment= 1.34 ton.m/rib
0.85 * 280
2.61*105 *1.34
* (1 1
.0079
4200
12 * 20 2 * 280
min .
14
0.0033 <.0079ok
Fy
16
0.85 * 280
2.61 * 105 * 1.19
* (1 1
.007
4200
12 * 202 * 280
As =1.675 cm2
2 12 /rib
So use 212 top steel for all spans except the exterior ends of the exterior
spans
Max. +ve moment= 0.99 ton.m/rib
0.85 * 280
2.61*105 * 0.99
* (1 1
) 0.0012
4200
52 * 20 2 * 280
1.57 * 4200
AS * fY
=
=0.53cm<8cm ok the compression area
0.85 * f c * b 0.85 * 280 * 52
Max. shear at distance d =20 cm from the face of column= 1.930.79*(0.2+0.15)=1.653 ton.
(Assumed columns dimensions to be 30*70 cm.)
Nominal shear=1.653/0.75=2.2 ton
Vc= 0.53*
-3
f c *b*d*1.1=0.53* 280 *12*20*1.1*10 =2.34ton>Vu no need for
shear reinforcement.
Max. neg. moment= 1.34 ton.m/rib
0.85 * 280
2.61*105 *1.34
* (1 1
.0079
4200
12 * 20 2 * 280
min .
14
0.0033 <.0079ok
Fy
* fy
1.7 * f c
) *b * d 2
0.0033 * 4200
) *12 * 202 *105 0.58ton.m
1.7 * 280
0.85 * 280
2.61*105 *1.02
* (1 1
) 0.0013
4200
52 * 20 2 * 280
1.57 * 4200
AS * fY
=
=0.53cm<8cm ok.the compression area
0.85 * f c * b 0.85 * 280 * 52
19
Max. shear at distance d =20 cm from the face of column= 2.320.79(0.2+0.15)=2 ton
(Assumed columns dimensions to be 30*70 cm.)
Ultimate shear=2/0.75=2.67 ton
Vc= 0.53*
-3
f c *b*d*1.1=0.53* 280 *12*20*1.1*10 =2.34ton<Vu need for
shear reinforcement.
Vs = Vu-Vn =2.67- 2.34 =0.33 ton
AV
V
S
S Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(10, 60 cm)=10cm
AV 0.33 *1000
=0.004
S
4200 * 20
(
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
AV
) min . max .of (0.01,0.0096) 0.01 >0.004use 0.01 reinforcement.
S
AV
=0.01, Using 8mm stirrups AV=1cm2
S
S=
1
=100cm>10cm use 1 8mm stirrup/10 cm.
0.01
20
0.85 * 280
2.61 *10 5 *1.73
* (1 1
.01
4200
12 * 20 2 * 280
min .
14
0.0033 <.01ok
Fy
* fy
1.7 * f c
) *b * d 2
0.0033 * 4200
) *12 * 202 *105 0.58ton.m
1.7 * 280
0.85 * 280
2.61 *10 5 *1.1
* (1 1
.0064
4200
12 * 20 2 * 280
min .
14
0.0033 <.0064ok
Fy
* fy
1.7 * f c
) *b * d 2
0.0033 * 4200
) *12 * 202 *105 0.58ton.m
1.7 * 280
0.85 * 280
2.61 *10 5 *1.68
* (1 1
) 0.0022
4200
52 * 20 2 * 280
0.85 * 280
2.61 *10 5 * 0.71
* (1 1
) 0.0009
4200
52 * 20 2 * 280
2.26 * 4200
AS * fY
=
=0.77cm<8cm ok.the compression area
0.85 * f c * b 0.85 * 280 * 52
22
Max. shear at distance d =20 cm from the face of column= 1.420.79*(0.2+0.15)= 1.143 ton
(Assumed columns dimensions to be 30*70 cm.)
Ultimate shear=1.243/0.75=1.524 ton
Vc= 0.53*
-3
f c *b*d*1.1=0.53* 280 *12*20*1.1*10 =2.34ton>Vu no need for
shear reinforcement.
0.85 * 280
2.61 *10 5 *1.05
* (1 1
.0061
4200
12 * 20 2 * 280
min .
14
0.0033 <.0061 ok
Fy
* fy
1.7 * f c
) *b * d 2
0.0033 * 4200
) *12 * 202 *105 0.58ton.m
1.7 * 280
So use 2 12 / rib top steel for all spans except the end of the beams.
23
0.85 * 280
2.61 *10 5 * 0.22
* (1 1
) 0.00028
4200
52 * 20 2 * 280
1.57 * 4200
AS * fY
=
=0.53cm<8cm ok.the compression area
0.85 * f c * b 0.85 * 280 * 52
24
Flexure Design:
0.85 * 280
2.61*105 *13.28
* (1 1
) 0.0061 >0.0033
4200
30 * 452 * 280
As=0.0061*45*30=8.23cm24 18
+ve moment on span 3 =10.94 ton.m
0.85 * 280
2.61*105 *10.94
* (1 1
) 0.00497 >0.0033
4200
30 * 452 * 280
As=0.00497*45*30=6.7cm23 18
25
0.85 * 280
2.61*105 *13.53
* (1 1
) 0.0062 >0.0033
4200
30 * 452 * 280
As=0.0062*30*45=8.4 cm24 18
-ve. Moment on span2 = 10.75 ton.m
0.85 * 280
2.61*105 *10.75
* (1 1
) 0.00488 >0.0033
4200
30 * 452 * 280
As=0.00488*30*45=6.59 cm23 18
Shear Design
Span1:
Shear Force at distance d=45 cm from the face of the right support =
19.45- 7.05*(0.15+0.45)=15.22 ton.
Vn=
Vu
15.22
=20.29 ton
0.75
Vc= 0.53*
AV
V
S
S Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(22.5, 60 cm)=22.5cm
AV 8.32 *1000
=0.044
S
4200 * 45
(
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
AV
) min . max .of (0.025,0.024) 0.025 <0.044use 0.044 reinforcement.
S
26
AV
=0.044, Using 8mm stirrups AV=1cm2
S
S=
1
=22.7cm=22.5cm ok. use 1 8mm stirrup/20 cm c/c.
0.044
Shear Force at distance d=45 cm from the face of the left support of
span1 = 13.69- 7.05*(0.15+0.45)=9.46 ton
Vn=
Vu
9.46
=12.61 ton.
0.75
Vc= 0.53*
VS=Vn-VC= 12.61-11.97=0.64ton
AV
V
S
S Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(22.5, 60 cm)=22.5cm
AV 0.63 *1000
=0.0034
S
4200 * 45
(
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
A
( V ) min . max .of (0.025,0.024) 0.025 >0.0034use min. shear
S
reinforcement.
max. spacing =min. of(d/2, 60 cm)= min. of(22.5, 60 cm)=22.5cm
AV
=0.025, Using 8mm stirrups AV=1cm2
S
S=
1
=40cm>22.5cm ok. use 1 8mm stirrup/20 cm c/c.
0.025
So at distance 1.3m to 2.6 m (measured from left end) use 1 8mm stirrup/40
cm.
Span2:
Use min. shear reinforcement at the ends(1 8mm stirrup/20 cm), and at
distance 1.3m to 2.6m measured from left end use 1 8mm stirrup/40 cm.
Span3:
Use min. shear reinforcement at the ends(1 8mm stirrup/20 cm), and at
distance 1.85m to 3.1m measured from left end use 1 8mm stirrup/40 cm.
1015 30
46.9cm H= 70cm, D= 65cm.
21
Width= 30cm.
Ultimate load on all spans =
3.41
1.2 * 2.5 * (0.7 0.25) * 0.3 6.96ton / m
0.52
28
Flexure Design:
0.85 * 280
2.61*105 * 21.11
* (1 1
) 0.0046 >0.0033
4200
30 * 652 * 280
As=0.0046*65*30=8.93cm24 18
+ve moment on span 2,4 =1.88 ton.m
0.85 * 280
2.61*105 *1.88
* (1 1
) 0.0003 <0.0033
4200
30 * 652 * 280
29
Asmin=0.0033*65*30=6.43cm23 18
+ve moment on span 3 =40 ton.m
0.85 * 280
2.61*105 * 40
* (1 1
) 0.00905 <0.0033
4200
30 * 652 * 280
Asmin=0.00905*65*30=17.66cm27 18
-ve. Moment on span1,5 = 20 ton.m
0.85 * 280
2.61*105 * 20
* (1 1
) 0.0043 >0.0033
4200
30 * 652 * 280
As=0.0043*30*65=8.44 cm24 18
-ve. Moment on span2,4 = 49.46 ton.m
0.85 * 280
2.61*105 * 49.46
* (1 1
) 0.011 >0.0033
4200
30 * 652 * 280
As=0.011*30*65=21.45 cm29 18
Shear Design
Max. shear at distance d=65 cm from the face of the support = 35.336.96*(0.15+0.65)=29.76 ton.
Vn=
Vu
29.76
= 39.68ton
0.75
Vc= 0.53*
AV
V
S
S Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(32.5, 60 cm)=32.5cm
AV 12.47 *1000
=0.0456
S
4200 * 65
(
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
30
AV
) min . max .of (0.025,0.024) 0.025 <0.0456use 0.0456 reinforcement.
S
S max. = 1/0.025 = 40 cm
AV
=0.0456, Using 8mm stirrups AV=1cm2
S
S=
1
=21.9cm<32.5cm ok. use 1 8mm stirrup/21 cm.
0.0456
F1 in roof #1:
The left circular part in part A will be analyzed and designed as a frame.
Analysis of slab 1:
Wu= 1.2*0.455+1.6*0.2=0.866 ton/m 2=0.45ton/m/rib
31
Beam F1:
Hmin.=
12.2 0.2
64.8cm H= 70cm, D= 65cm.
18.5
Width= 30cm.
Ultimate load=
1.99
1.2 * 2.5 * (0.7 0.25) * 0.3 4.23ton / m
0.52
32
33
0.85 * 280
2.61*105 * 49.82
* (1 1
) 0.0116 >0.0033 ok.
4200
30 * 652 * 280
As=0.0116*30*65=22.62 cm28 20
-ve moment on the left end=15.98ton.m
0.85 * 280
2.61 * 105 * 15.98
* (1 1
) 0.0034 >0.0033ok.
4200
30 * 652 * 280
As=0.0034*30*65=6.7 cm24 16
-ve moment on the right end=42.72ton.m.
0.85 * 280
2.61*105 * 42.72
* (1 1
) 0.0097 >0.0033ok.
4200
30 * 652 * 280
As=0.0097*30*65=19 cm210 16
34
Vu
19.6
=26.13 ton
0.75
Vc= 0.53*
f c
AV
V
S
S Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(32.5, 60 cm)=32.5cm
AV 8.83 *1000
=0.032.
S
4200 * 65
(
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
A
A
( V ) min . max .of (0.025,0.024) 0.025 <0.032 V 0.032 .
S
S
AV
=0.032, Using 8 mm stirrups AV=1cm2
S
S=
1
=31.25 cm<32.5cm use S=30cm.
0.032
Use 1 8 mm stirrup/30cm.
if Vc Vn Vc/2, use min. shear reinforcement.
Vc=17.3=23.62/0.75-4.23*X X=3.36m
Min. shear reinforcement=0.025, Smax.= min. of(d/2, 60 cm)= min. of(32.5, 60
cm)=32.5cm
Using 8 stirrups S =1/0.025=40cm>32.5cm Use 1 8 mm
stirrup/30cm.
35
Vu
24.4
=32.53 ton.
0.75
Vc= 0.53*
f c
AV
V
S
S Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(32.5, 60 cm)=32.5cm
AV 15.23 *1000
=0.056.
S
4200 * 65
(
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
A
A
( V ) min . max .of (0.025,0.024) 0.025 <0.056 V 0.056 .
S
S
Using 8 mm stirrups AV=1cm2
S=
1
=17.9 cm<32.5cm use S=18cm.
0.056
Use 1 8 mm stirrup/18cm.
if Vc Vn Vc/2, use min. shear reinforcement.
Vc=17.3=27.99/0.75-4.23*X X=4.73m
Min. shear reinforcement: 1 8/30cm.
Secondary beams:
Beam12
36
Flexure Design:
Max +ve moment on span4 =1.08 ton.m
0.85 * 280
2.61*105 *1.08
* (1 1
) 0.00243 <0.0033
4200
30 * 20 2 * 280
37
0.85 * 280
2.61*105 *1.49
* (1 1
) 0.0034 >0.0033
4200
30 * 20 2 * 280
As=0.0034*30*20=2.04 cm23 10
Use 3 10 top steel for all spans.
Use minimum bottom and top steel(3 10) for all the secondary beams.
Shear Design
Max. shear at distance d=20 cm from the face of the support = 2.090.87*(0.15+0.2)=1.8 ton.
Vn=
Vu
1 .8
= 2.4ton
0.75
Vc= 0.53*
38
Let
M
k * lu
< 34 12 * 1b
M 2b
r
M 1b
=0
M 2b
k * lu 0.7 * 3.6
39
Sap 3D Model
40
3.1.2 Sections:
Ic=
52 * 83
12 *17 3
52 * 8 * 4.12
12 *17 * 8.4 2 28,518.9cm 4
12
12
52 * 8 3 / 12
=0.0078
28518.9
41
3.1.3 Loads:
Own weight: will be calculated by the program.
Loads other than own weight:
Loads on ground, first, and second floors:
Live load= 400 Kg/m2.
The difference in weight between ribbed and equivalent solid slab will
be added as super imposed dead load:
Ribbed slab weight= 0.455 ton/m 2
Solid slab weight = 2.5*1*0.1874=0.47 ton/m 2.
Total super imposed dead load =0.27+(0.455-0.47)=0.255 ton/m2.
Partitions loads are carried by secondary beams (0.6ton/m).
Loads on part roof #1:
Snow and live loads=0.2 ton/m 2.
Loads on Roofs #2 and #3:
Snow and live loads (=0.4 ton/m2.
Loads on concrete domes:
Snow and live loads= 0.15 ton/m 2.
Loads on steel domes, and steel arches:
Wind load: as calculated in section 1.4.
Live and snow loads: 0.15 ton/m 2.
The difference in live loads on these roofs is related to water tanks which
exist on roofs #2 and #3.
Dead loads on exterior walls from masonry and blocks=
0.06*2.7+0.1*1.2=0.282t/m2.
The wall cross section is shown on the following figure.
42
43
44
Dead loads
Beams load = length for each beam *area section *unit weight =
472 m*0.3*0.25*2.5 +1118.39m*0.3*0.45*2.5+ 165.71m*0.3*0.5*2.5=
824.67 ton
45
The moments obtained from SAP for this slab are shown on the
following figure:
46
The moments obtained from sap for this Beam are shown on the
following figures:
47
L
(from ACI 2003 "section 9.5.3.2)
360
Allowable deflection=
L 4850
=
=13.5mm>0.9mm ok.
360 360
L 10,000
=
=27.8mm>5.8mm ok.
360
360
48
Meridian stresses(F22):
Hoop stresses(F11):
49
Max. Hoop stress is 2.1 t/m (tension)=21 t/m 2, and the minimum is -10 t/m
(compression) = 100 t/m2.
Both tension and compression stresses are less than concrete capacity. Thus
only shrinkage steel is required (48/m).
Meridian stresses(F22):
Hoop stresses(F11):
50
51
3.4.2
check shear:
Ribbed slabs:
Ground Floor:
Second Floor:
52
53
For the max. shear force (at distance d=0.2m from the face of beam)=
2.7ton/m=1.4 ton/rib:
Solid Slabs:
Roof #3, and minaret roof:
54
55
Second Floor:
56
Roof #1:
Roof #2:
57
0.85 * 280
2.61*105 *1.04
* (1 1
0.006 min . 0.0033
4200
12 * 202 * 280
0.85 * 280
2.61*105 * 0.676
* (1 1
0.000865
4200
52 * 202 * 280
58
0.85 * 280
2.61 *105 * 2.42
* (1 1
0.0154 min . 0.0033
4200
12 * 20 2 * 280
0.85 * 280
2.61 *10 5 * 2.08
* (1 1
0.0134 min . 0.0033
4200
12 * 20 2 * 280
59
* (1 1
0.00245
4200
100 *16 2 * 280
0.85 * 280
2.61 *105 * 3
* (1 1
0.0032
4200
100 *16 2 * 280
Spacing=100/4=25 cm
Max. spacing= min. of(45cm, 5*h)=min. of(45cm, 100cm)=45cm>25cm ok.
61
Beam
number
Second digit
1,2,3,
M: Main
S: Secondary
B : Boundary
Analysis and design output was taken from SAP. Verification for
minimum steel was used as explained in chapter2.
Following tables and succeeding figures present a summary of
output results and typical details of beams.
1. Boundary beams: All boundary beams dimensions are 25*40cm
Part A, C
Parts A and C.
Beam
no 1
Floor GF
Beam type
boundary
stirrups (2leg 1 10mm)
span1
span 2
span 3
span4
span5
span 6
flexure
steel
top
top
top
bottom
top
bottom
top
bottom
top
bottom
top
bottom
top
torsion
steel
318
318
318
214
314
214
214
214
214
214
314
214
214
span 1
span 2
span 3
span 4
span 5
span 6
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
212
212
212
212
212
212
212
212
212
212
212
212
212
212
212
212
212
bottom
212
span 1
span 2
span 3
span 4
span 5
span 6
62
shear
torsion
total A/s
spacing
left
middle
right
left
middle
right
left
middle
right
left
middle
right
left
middle
right
left
middle
0
0
0
0.0018
0.0017
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.0209
0.022
0.023
0.025
0.02
0.021
0.022
0
0
0.011
0
0
0
0.014
0.01
0
0.023
0.024
0.044
0.046
0.05
0.0418
0.0437
0.0649
0.025
0.025
0.0429
0.025
0.025
0.025
0.0489
0.0409
0.025
0.0669
0.0689
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
right
0.0209
0.025
0.0709
20
63
Part A,
C
Floors P, 1, 2
Beam
no 2
flexure
steel
top
torsion
steel
Beam
type
boundary
stirrups (2leg 1 10mm)
314
span1
bottom
214
span 2
top
bottom
314
214
top
314
span 3
bottom
top
214
314
span4
bottom
214
span5
top
bottom
314
214
top
314
top
span 1
span 2
span 3
span 4
span 5
Part C
Floors
1, 2, GF
212
middle
212
bottom
top
212
212
middle
212
bottom
top
212
212
middle
212
bottom
top
212
212
middle
212
bottom
top
212
212
middle
212
bottom
212
span
1
span
2
span
3
span
4
span
5
shear
torsion
total A/s
spacing
left
0.027
0.054
20
middle
0.027
0.054
20
right
left
0
0.0209
0.025
0
0.05
0.025
20
20
middle
0.0209
0.025
20
right
left
0.0209
0.0209
0.013
0
0.0469
0.025
20
20
0.025
20
middle
right
left
0.0209
0.0209
0
0.015
0.025
0.0509
20
20
middle
0.0003
0.01
0.0203
20
right
left
0.0209
0
0
0.024
0.025
0.048
20
20
middle
0.025
0.05
20
right
0.025
0.05
20
Beam type
boundary
Beam
no 3
torsion
steel
318
top
214
top
214
top
span 1
212
middle
212
bottom
212
span
1
shear
torsion
left
0.0007
0.017
total
A/s
0.0347
middle
0.0005
0.017
0.0345
20
right
0.019
0.038
20
All the other boundary beams are numbered 4. Their steel reinforcement, at all
spans, are 214 for flexure top and bottom, 3 layers for torsion 212 top,
middle and bottom, and 110 stirrup/20 cm for shear and torsion.
64
spacing
20
Part B:
All boundary beams in this part have the same steel reinforcement at all spans:
214 top and bottom steel, 3 layers 212 top, middle and bottom torsion steel,
and 110/20 cm stirrups for shear and torsion reinforcement.
2. Secondary Beams :
All secondary beams dimensions are 30cm*25cm.
65
Part B:
Part B
Floors
1, 2
Beam
no 1
flexure
steel
top
bottom
top
bottom
top
bottom
top
bottom
top
bottom
top
torsion
steel
Beam type
secondary
stirrups (2leg 1 10mm)
span1
span 2
span 3
span4
span5
214
214
318
214
214
214
214
214
318
214
214
span 1
span 2
span 3
span 4
span 5
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
212
212
212
212
212
212
212
212
212
212
212
212
212
212
212
span 1
span 2
span 3
span 4
span 5
66
left
middle
right
left
middle
right
left
middle
right
left
middle
right
left
middle
right
shear
torsion
0
0
0
0.0038
0
0.0061
0
0
0
0
0
0
0
0
0
0
0
0
0.053
0.055
0.053
0
0
0
0.111
0.111
0.111
0.046
0.046
0.046
total
A/s
0.025
0.025
0.025
0.1098
0.11
0.1121
0.025
0.025
0.025
0.222
0.222
0.222
0.092
0.092
0.092
spacing
12
12
12
12
12
12
12
12
12
7
7
7
12
12
12
67
Part B
span1
3rd roof
Beam
no 2
flexure
steel
top
bottom
top
torsion
steel
314
214
214
span 1
Beam type
secondary
top
middle
bottom
214
214
214
span 1
For parts A and C all the secondary beams are numbered 1, they
have the same cross section as part B. Their steel reinforcement, at
all spans, are 314 for flexure top and 214 for flexure bottom, 3
layers for torsion 212 top, middle and bottom, and 110 stirrup/12
cm for shear and torsion.
68
spacing
12
12
12
69
Main Beams :
Part C
Part C
Floor s
1, 2, P,
GF
Beam
type
main
beam
Beam
no 1
span1
span 2
span 3
flexure
steel
top
bottom
top
bottom
top
bottom
top
torsion
steel
516
218
516
216
318
218
516
span 1
span 2
span 3
Part C
Floor1,
P, GF
Beam
no 2
flexure
steel
top
bottom
top
bottom
top
bottom
top
torsion
steel
top
middle
bottom
top
middle
bottom
top
middle
bottom
212
212
212
212
212
212
212
212
212
span 1
span 2
span 3
left
middle
right
left
middle
right
left
middle
right
shear
torsion
0.0256
0
0.0298
0.0251
0.0027
0.0251
0.0097
0
0.0186
0.07
0
0.077
0.043
0.013
0.043
0.055
0
0.045
total
A/s
0.1656
0.025
0.1838
0.1111
0.0287
0.1111
0.1197
0.025
0.1086
spacing
9
20
9
14
20
14
13
20
14
span1
span 2
span 3
318
216
318
216
318
216
318
span 1
span 2
span 3
top
middle
bottom
top
middle
bottom
top
middle
bottom
214
214
214
214
214
214
214
214
214
span 1
span 2
span 3
70
left
middle
right
left
middle
right
left
middle
right
shear
torsion
0.0256
0
0.0298
0.0303
0.0048
0.0174
0.0097
0
0.0186
0.07
0
0.077
0.06
0.017
0.059
0.055
0
0.045
total
A/s
0.1656
0.025
0.1838
0.1503
0.0388
0.1354
0.1197
0.025
0.1086
spacing
9
20
9
10
20
12
13
20
14
71
Part A:
Part
A
Floors
GF, 2,
1
Beam type
main beam
Beam
no 1
Part
A
torsion
steel
520
bottom
418
top
top
312
span
1
shear
torsion
left
0.087
0.018
total
A/s
0.123
middle
0.004
0.023
0.05
20
spacing
13
middle
312
620
bottom
312
right
0.088
0.019
0.126
12
bottom
218
top
312
left
0.05
0.018
0.086
18
top
320
middle
312
middle
0.025
20
bottom
312
right
0.05
0.018
0.086
18
span 1
span 2
Floor
2,3,4
Beam
no 2
flexure
steel
top
bottom
top
torsion
steel
318
316
420
bottom
216
top
220
span
2
span1
span
2
span 1
span 2
top
middle
bottom
216
216
216
top
216
middle
bottom
216
216
span 1
span 2
72
shear
torsion
left
middle
right
0
0.0047
0
0.097
0.023
0.103
total
A/s
0.194
0.0507
0.206
left
0.0189
0.07
0.1589
10
middle
right
0
0.0231
0
0.053
0.025
0.1291
20
12
spacing
8
20
8
73
Part B
Part B:
Floors
P, GF
Beam
no 1
flexure
steel
top
bottom
top
torsion
steel
318
318
516
bottom
318
top
516
bottom
318
top
bottom
top
bottom
top
516
318
516
318
318
Beam type
main beam
stirrups (2leg 1 10mm)
span1
span
2
span
3
span4
span5
span 1
span 2
span 3
span 4
span 5
top
middle
bottom
214
214
214
top
214
middle
214
bottom
214
top
middle
bottom
top
middle
bottom
top
middle
bottom
214
214
214
214
214
214
214
214
214
74
span 1
span 2
span 3
span 4
span 5
shear
torsion
left
middle
right
0.0251
0
0.0251
0
0
0
total
A/s
0.0251
0.025
0.0251
left
0.0251
0.011
0.0471
32
middle
0.025
32
right
0.0251
0.0251
32
left
middle
right
left
middle
right
left
middle
right
0.0251
0
0.0251
0.0251
0
0.0251
0.0251
0
0.0251
0.016
0
0.016
0
0
0
0
0
0
0.0571
0.025
0.0571
0.0251
0.025
0.0251
0.0251
0.025
0.0251
27
32
27
32
32
32
32
32
32
spacing
32
32
32
75
Part B
Floors
P, GF
Beam
no 2
flexure
steel
top
bottom
top
bottom
top
bottom
top
bottom
top
bottom
top
torsional
steel
span1
span 2
span 3
span4
span5
318
318
616
318
516
318
516
318
616
318
318
span 1
span 2
span 3
span 4
span 5
Part B
span1
span 2
span 3
span4
span5
320
318
320
318
720
518
720
318
320
318
320
span1
span 2
span 3
span 4
span 5
span 1
span 2
span 3
span 4
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
214
214
214
214
214
214
214
214
214
214
214
214
214
214
bottom
214
span 1
span 2
span 3
span 4
span 5
span 1
0.002
0
0.021
0.0391
0
0.025
0.03
0
0.03
0.0251
0
0.039
0.025
0
0.0251
0.034
0
0.037
0.029
0.018
0.04
0.073
0.014
0.037
0.04
0.018
0.029
0.038
0
0.037
total
A/s
0.07
0.025
0.095
0.0971
0.036
0.105
0.176
0.028
0.104
0.1051
0.036
0.097
0.101
0.025
0.0991
spacing
22
32
17
16
32
15
9
32
15
15
32
16
16
32
16
0.0251
0.016
0.0571
spacing
28
32
32
24
32
18
11
32
10
16
32
25
30
32
27
Beam type
main beam
torsion
steel
318
318
left
middle
right
left
middle
right
left
middle
right
left
middle
right
left
middle
right
torsion
Beam type
main beam
Beam
no 4
Floor P
flexure
steel
top
bottom
span 1
torsion
steel
span 5
Part B
216
216
216
216
216
216
216
216
216
216
216
216
216
216
216
Beam
no 3
Floor P
flexure
steel
top
bottom
top
bottom
top
bottom
top
bottom
top
bottom
top
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
shear
top
middle
214
214
76
span 1
spacing
32
32
span 2
span 3
span4
span5
top
bottom
top
bottom
top
bottom
top
bottom
top
318
318
920
520
720
318
318
318
318
span 2
span 3
span 4
span 5
Part B
Floor
P
Beam
no 5
flexure
steel
top
bottom
top
bottom
top
bottom
top
bottom
top
bottom
top
torsion
steel
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
214
214
214
214
214
214
214
214
214
214
214
214
214
span 2
span 3
span 4
span 5
right
left
middle
right
left
middle
right
left
middle
right
left
middle
right
0
0
0
0
0.0998
0
0.0844
0.072
0
0
0
0
0.0251
0.018
0.017
0
0.018
0.023
0
0.036
0.021
0
0.021
0.014
0.014
0
0.036
0.034
0.025
0.036
0.1458
0.025
0.1564
0.114
0.025
0.042
0.028
0.028
0.0251
32
32
32
32
11
32
10
14
32
32
32
32
32
Beam type
main beam
stirrups (2leg 1 10mm)
span1
span 2
span 3
span4
span5
318
318
318
318
818
518
818
318
318
318
318
span 1
span 2
span 3
span 4
span 5
Floor
GF
Beam
no 6
flexure
steel
top
torsion
steel
320
span1
bottom
318
span 2
top
bottom
320
318
top
620
bottom
top
318
620
Part B
span 3
span 1
span 2
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
top
middle
bottom
214
214
214
214
214
214
216
214
216
214
214
214
214
214
214
span 1
span 2
span 3
span 4
span 5
left
middle
right
left
middle
right
left
middle
right
left
middle
right
left
middle
right
shear
torsion
0.0251
0
0
0
0
0.0244
0.0622
0
0.0671
0.0346
0
0
0
0
0
0.015
0
0.02
0.042
0.014
0.025
0.057
0.011
0.058
0.024
0.013
0.087
0
0.024
0.021
total
A/s
0.0551
0.0251
0.04
0.084
0.028
0.0744
0.1762
0.022
0.1831
0.0826
0.026
0.174
0.025
0.048
0.042
spacing
28
32
32
19
32
21
9
32
9
19
32
9
32
32
32
Beam type
main beam
top
214
middle
214
bottom
top
214
214
middle
214
bottom
top
214
214
77
span
2
spacing
26
middle
0.025
32
right
left
0.0251
0.0272
0.015
0.02
0.0551
0.0672
28
23
middle
0.025
32
right
left
0.034
0.0481
0.026
0.016
0.086
0.0801
18
20
span4
bottom
318
span5
top
bottom
318
318
top
320
span 3
span 4
span 5
Part B
Floor
GF
Beam
no 7
flexure
steel
top
torsion
steel
middle
214
bottom
top
214
214
middle
214
bottom
top
214
214
middle
214
bottom
214
span
3
span
4
span
5
middle
0.0033
0.013
0.0293
32
right
left
0.0545
0.0382
0.022
0.025
0.0985
0.0882
16
18
middle
0.025
32
right
left
0.0251
0.0251
0.015
0
0.0551
0.0251
28
32
middle
0.025
32
right
0.0256
0.018
0.0616
25
Beam type
main beam
stirrups (2leg 1 10mm)
318
span1
bottom
318
span 2
top
bottom
318
318
top
818
span 3
bottom
top
318
618
span4
bottom
318
span5
top
bottom
318
318
top
318
top
span 1
span 2
span 3
span 4
span 5
Part
B
Floor
1
Beam
no 8
flexure
steel
top
torsion
steel
320
bottom
318
top
214
middle
214
bottom
top
214
214
middle
214
bottom
top
214
214
middle
214
bottom
top
214
214
middle
214
bottom
top
214
214
middle
214
bottom
214
span
1
span
2
span
3
span
4
span
5
shear
torsion
left
0.0251
total
A/s
0.0251
middle
0.0033
0.015
0.0333
30
right
left
0
0.003
0.021
0.018
0.042
0.039
24
26
middle
0.025
32
right
left
0.0018
0.064
0.026
0
0.0538
0.064
19
16
middle
0.0251
0.02
0.0651
15
right
left
0.0424
0.0283
0.024
0.015
0.0904
0.0583
11
17
middle
0.025
32
right
left
0.003
0.001
0.024
0.016
0.051
0.033
20
30
middle
0.0015
0.026
0.0535
19
right
0.0251
0.0251
32
spacing
32
Beam type
main beam
stirrups (2leg 1 10mm)
span1
span
2
shear
torsion
total A/s
spacing
left
0.0251
0.15
0.3251
10
middle
0.025
32
top
214
middle
214
320
bottom
214
right
0.0251
0.016
0.0571
27
bottom
318
top
214
left
0.0251
0.0251
32
top
520
middle
214
middle
0.0251
0.018
0.0611
26
span 1
span 2
span
1
span
2
78
span
3
bottom
318
bottom
214
top
520
top
span4
bottom
318
span5
top
bottom
320
318
top
320
span 3
span 4
span 5
Part
B
Floor
GF, 1
Beam
no 9
flexure
steel
top
torsion
steel
span
3
middle
bottom
top
0
214
middle
214
bottom
top
214
214
middle
214
bottom
214
span
4
span
5
right
0.0251
0.018
0.0611
26
left
0.0374
0.026
0.0894
18
middle
0.025
32
right
left
0.0426
0.0251
0.032
0.013
0.1066
0.0511
15
31
middle
0.0251
0.02
0.0651
24
right
left
0.0251
0.0251
0
0.017
0.0251
0.0591
32
27
middle
0.0251
0.0251
32
right
0.0251
0.016
0.0571
27
Beam type
main beam
stirrups (2leg 1 10mm)
span1
Part B
span1
span 2
418
bottom
418
top
418
Floors
1,2
flexure
steel
top
bottom
top
bottom
top
top
span 1
214
middle
214
bottom
214
span
1
shear
torsion
total A/s
left
0.033
0.066
24
middle
0.025
32
right
0.03
0.06
26
Beam no
10
torsion
steel
318
318
518
318
318
span 1
span 2
top
middle
bottom
top
middle
214
214
214
214
214
span 1
span 2
All other main beams in this part are numbered 11. They have the
same cross section. Their steel reinforcement, at all spans, are 318
for flexure top and bottom, 3 layers for torsion 212 top, middle and
bottom, and 110 stirrup/10 cm for shear and torsion near the support
and 110 stirrup /20 cm for shear and torsion at the middle of the
span.
79
21
25
15
20
25
Frames:
span1
flexure
steel
top
bottom
top
torsion
steel
318
318
318
span 1
left
middle
right
flexure
steel
top
420
bottom
322
top
622
318
318
318
span 1
torsion
steel
span 1
spacing
6
14
8
Beam type
main
Beam
no 2
Frames
span1
Beam type
main
Beam
no 1
Frames
left
312
middle
312
right
312
80
span
1
spacing
13
middle
0.022
0.044
32
right
0.029
0.058
27
81
Depth
width
min As
Av/s min
Smax
RB1
50
25
3.7
0.0208
22
RB2
50
25
3.7
0.0208
22
RB3
50
25
3.7
0.0208
22
RB4
60
30
5.44
0.025
30
RB5
50
25
3.7
0.0208
22
Ring
beam no.
top steel
bottom steel
RB1
316
216
S for shear
and
torsion
22
RB2
216
416
15
214
RB3
216
216
18
212
RB4
516
316
12
214
RB5
216
216
10/4 legs
316
torsion steel
for one layer
212
82
83
Column No.
Dimension
(cm)
C1
C2
C3
20*40
20*50
30*50
Longitudinal
reinforcement
(cm2)
Area of
# of
steel
Bars
(cm2)
8
6 14
10
6 16
15
6 18
84
Splicing 1
Distance
Shear reinforcing2
(cm2/cm)
30 cm
35 cm
35 cm
18/20cm
18/20cm
18/30cm
C4
30*60
22.43
6 22
45 cm
f y * db
0.0756 *
f c
Av
2. ( S ) min. =
1. If *Vc < 0.5*Vu:
A
( V ) min . max .of (3.5 * B / FY ,0.2 * Fc * B / FY )
S
Smax.=min. of( d/2, 60 cm)
2. If *Vc>Vu: No need for shear reinforcing
Smax.=min. of (16*db, 48 ds, least column dimensions)
85
18/30cm
part1:
PU=118 ton
Check if
M
k * lu
< 34 12 * 1b
M 2b
r
In direction1:
34 12 * (
0.26
) 35.9
1.62
r=
I
b * h3 / 12
=
= h 2 / 12 = 20 2 / 12 =
bh
A
5.77 cm.
k * lu 0.7 * 340
41.25 >35.9can be
r
5.77
considered as long column.
Mmax.=b*Mm
b =
Cm
P
1 u
Pc
No transverse loads
M
Cm=0.6+0.4* 1b 0.4
M 2b
Cm =0.6+0.4*
Pc
.26
=0.54
1.62
2
*Et * I
( K * lu ) 2
86
d =
1.2 * DL
1.2 * DL
=
1.2 * DL 1.6 * LL 1.2 * DL 1.6 * LL
Since the As is not known yet so the Is, we will take the second value then a
check will be made.
2. EI=
0.4 * Ec * I g
1 d
1.2 * DL
1.2 * 0.455
=0.63
1.2 * DL 1.6 * LL 1.2 * 0.455 1.6 * 0.2
EI=
0.54
=-0.24 b=1so the check to determine whether the first value
118
1
36
of EI is the larger is not necessary, because b must be equal or larger of 1.
b =
Mmax.= 1.62ton.m.
From the interaction diagram fig 3.3, the required steel ratio can be
determined.
87
Ka=
Pu
118 *103
=
=0.42
f c * Ag 280 * 50 * 20
In direction2:
34 12 * (
0.71
) 37.55
2.4
88
r=
I
b * h3 / 12
=
= h 2 / 12 = 50 2 / 12 =14.43cm.
bh
A
k * lu 0.7 * 340
part3:
PU=27 ton.
In direction1:
Check if
M
k * lu
< 34 12 * 1b
M 2b
r
34 12 * (
r=
0.05
) 37.64
0.165
I
b * h3 / 12
=
= h 2 / 12 = 20 2 / 12 =5.77 cm.
bh
A
k * lu 0.7 *1070
Cm
P
1 u
Pc
M 1b
0.4
M 2b
89
Cm =0.6+0.4*
Pc
0.05
=0.48
0.165
2
*Et * I
( K * lu ) 2
0.4 * Ec * I g
1 d
1.2 * DL
1.2 * 0.455
=0.63
1.2 * DL 1.6 * LL 1.2 * 0.455 1.6 * 0.2
EI=
b =
0.48
=1.92
27
1
36
90
Mu
0.32 *105
=
=0.0057.
f c * Ag * h 280 * 50 * 20 * 20
Ka=
Pu
27 *103
=
=0.1
f c * Ag 280 * 50 * 20
M
k * lu
< 34 12 * 1b
M 2b
r
91
34 12 * (
1.02
) 43.8
1.25
I
b * h3 / 12
=
= h 2 / 12 = 50 2 / 12 =14.43cm.
bh
A
r=
k * lu 0.7 *1070
Cm
P
1 u
Pc
0.6+0.4*
M 1b
0.4
M 2b
1.02
=0.27 Cm=0.4
1.25
2
*Et * I
Pc
2
( K * lu )
EI=
0.4 * Ec * I g
1 d
1.2 * DL
1.2 * 0.455
=0.63
1.2 * DL 1.6 * LL 1.2 * 0.455 1.6 * 0.2
92
Pc
2
9
*12.78 *10 =225 ton.
(0.7 *1070 ) 2
0 .4
=0.45 b=1so the check to determine whether the first value of
27
1
225
EI is the larger is not necessary, because b must be equal or larger of 1.
b =
Mmax.= Mm=1.25ton.m
From the interaction diagramfig.3.4 and fig.3.5, the required steel ratio can be
determined.
93
Where,
g =42/50=0.84
Rn=
Mu
1.25 *105
=
=0.009
f c * Ag * h 280 * 50 * 20 * 50
Ka=
Pu
27 *103
=
=0.1
f c * Ag 280 * 50 * 20
94
Vu
11
=14.7 ton/m.
0.75
Vc= 0.53*
95
Depending on the wall dimensions, the basement wall will behave either one
way or two ways.
Moments in direction
Max. -ve moment=3ton.m/m2, max. +ve moment=1.56ton.m/m2.
As shrinkage= 0.0018*100*30=5.4cm 2
0.85 * 280
2.61*105 * 3
* (1 1
0.0013
4200
100 * 252 * 280
As=.0013*100*25=3.2cm2< As shrinkage.
* (1 1
0.0019
4200
100 * 252 * 280
As=0.0019*100*25=4.78cm2< As shrinkage.
So shrinkage steel is required for both x and z directions(
negative and positive moments)
96
97
Loads on the landings: live load = 0.4 t/m2, Dead loads: own weight (
calculated by SAP ), super imposed dead load from tiles = 0.27 t/m2
Loads on the flights: live load = 0.4 t/m2, Dead loads: Own weight of the flight
slab (calculated by SAP), Weight of the stairs = 2.5 *(no.of stairs1)*0.3*0.16/2, Super imposed loads from tiles =(0.16+.3)*.27 *(no. of stairs -1)
The rise of the stair = 4-0.15*3= 3.55
for 0.17 m raise no. of stairs = 3.55/0.17 =20.88 not good
for 0.16 m raise no. of stairs = 3.55/0.16 = 22 stairs these 22 will be divided
7,8,7 in the flights.
99
100
0.85 * 280
2.61 * 10 5 * 0.311
* (1 1
0.00057
4200
100 * 12 2 * 280
As=0.00057*100*12=0.7 cm2/m.
101
As min.= 0.0018*100*15 =2.7 cm2/m>0.7 cm2/m 312/m top and bottom steel is required.
Design for M22 :
0.85 * 280
2.61 *105 * 0.4
* (1 1
0.00074
4200
100 *12 2 * 280
102
Check shear:
103
-3
f c *b*d=0.53* 280 *100*12*10 =10.64 ton>Vn, no need for shear
reinforcement.
Use a development length of ln/3 for the top steel = 1.57/3 = 0.53 m for the longest
landing
105
106
107
Single Footings:
All single footings are connected with ground beams in order to take the
moments, so these footings will be designed only for axial force from columns.
d=0.3 m
Use H= 45 cm d= 38 cm
ok.
Flexural design:
Mu = qu*l2/2= qu* (0.9)2/2 = 13.75 tom.m/m
min.=14/fy=14/4200=0.0033
0.85 * 280
2.61*105 *13.75
* (1 1
0.0026 0.0033
4200
100 * 38 2 * 280
Dowels reinforcement:
Bearing capacity of concrete is, Pc=*0.85* f c *A=0.7*0.85*280*20*40*2*10-3=266.56 t
Pu=172 t<Pc use min. area of dowels, 0.5% of column area
Area of dowel=0.5%*20*40*2=8cm2 812
109
f y * db
0.0756 *
f c
20cm
4200 *12
0.0756 *
280
23cm
Dowels splicing distance = max. of 22cm =23 cm.
20cm
The table shown below, represents the dimensions and reinforcement for all
single footings.
Longitudinal
Reinforcement
Footing dimensions
Footing
No.
Dowels
Reinforcement
(m)
Width
(m)
Depth
(m)
Area of
steel
(cm2)
# of bars
in each
direction
# of
bars
Splicing
distance
2.3
2.2
0.45
12.54
518/m
812
23cm
2.7
0.45
12.54
518/m
812
23cm
1.8
1.6
0.4
10.98
518/m
412
23cm
2.1
1.8
0.4
10.98
518/m
412
23cm
1.7
1.4
0.3
7.59
514/m
412
23cm
2.4
2.2
0.5
14.19
618/m
412
23cm
1.7
0.35
9.24
614/m
412
23cm
Length
110
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
AV
) min . max .of (0.025,0.024) 0.025
S
AV
=0.025, Using 8mm stirrups AV=1cm2
S
S = 40 >22.5, 18 / 20 cm
111
144.3 * 2.65
=1.45m
120 144.4
152 184.4
=68.65 ton/m.
4.9
112
98.57-65.65*(d+0.25)= 133*d
d=42cm H=50cm, d=43cm.
0.85 * 280
2.61*105 *16.1
* (1 1
0.0012 <min.=0.0033
4200
200 * 432 * 280
0.85 * 280
2.61*105 * 54.87
* (1 1
0.004 >min.=0.0033
4200
200 * 432 * 280
* (1 1
0.0025 <min.=0.0033
4200
200 * 432 * 280
113
0.85 * 280
2.61*105 *19.31
* (1 1
0.0025 <min.=0.0033
4200
114 * 432 * 280
Dowels reinforcement:
Bearing capacity of concrete is, Pc=*0.85* f c *A=0.7*0.85*280*30*50*10-3=249.9 t
Pu=152 t<Pc only min. area of dowels is required, 0.5% of column area
Area of dowel=0.5%*30*50*2=7.5cm2 712
f y * db
0.0756 *
f c
20cm
23cm
Dowel splicing distance = max. of 22cm =23 cm.
20cm
Right column:
Band width=50+64=114cm
114
4200 *12
0.0756 *
280
0.85 * 280
2.61*105 * 25.93
* (1 1
0.00335 >min.=0.0033
4200
114 * 432 * 280
Dowels reinforcement:
Bearing capacity of concrete is, Pc=*0.85* f c *A=0.7*0.85*280*30*50*10-3=249.9 t
Pu=184.4 t<Pc only min. area of dowels is required, 0.5% of column area
Area of dowel=0.5%*30*50*2=7.5cm2 712
f y * db
0.0756 *
f c
20cm
23cm
Dowel splicing distance = max. of 22cm =23 cm
20cm
115
4200 *12
0.0756 *
280
116
0.85 * 280
2.61*10 5 * 3.925
* (1 1
0.002 .0033
4200
100 * 23 2 * 280
Use 514 /m
Steel in direction parallel with dtrap direction :
Use shrinkage steel =0.0018* 130*30 = 7.02 cm2
Use 514 /m
Strap design :
Let strap dimensions 30cm*60cm
117
Loads on strap
0.85 * 280
2.61 *105 * 22.1
* (1 1
) 0.00685 >0.0033
4200
30 * 55 2 * 280
As=0.00685*55*30=11.3cm26 16
+ve moment =20 ton.m
0.85 * 280
2.61 * 10 5 * 20
* (1 1
) 0.00615 >0.0033
4200
30 * 55 2 * 280
118
Shear Design
Shear Force at distance d from face of column=39.4ton.m
Vn=
Vu
21.7
=28.9 ton
0.75
Vc= 0.53*
VS=VN-VC= 28.9-14.63=14.27ton
AV
V
S
S
Fy * d
VS<2* VC max. spacing =min. of(d/2, 60 cm)= min. of(27.5, 60 cm)=27.5cm
AV 14.27 *1000
=0.076
S
4200 * 45
AV
) min . max .of (3.5 * Bw / FY ,0.2 * Fc * Bw / FY )
S
AV
) min . max .of (0.025,0.024) 0.025 <0.076
S
AV
=0.076, Using 10 mm stirrups AV=1.57cm2
S
S=
1.57
=22.7, use 1 10mm stirrup/22 cm.
0.076
Wall footings:
Footing #10:
Max. service and ultimate loads are 34.7 ton/m, 44.32ton/m respectively.
Footing width (B)=Ps/B.C=34.7/27.5= 1.3m.
Ultimate pressure(qu)= 44.32/1.3=34.1 ton/m2.
119
l= (1.3-0.25)=0.525m.
Ultimate shear force at distance d from the face of the wall(V u)= 34.1(l-d)=
34.1(0.525-d)
Vc=*0.53*
0.85 * 280
2.61*105 * 4.7
* (1 1
0.0024 <min.=0.0033
4200
100 * 232 * 280
As=0.0033*b*d=0.0033*100*23=7.59 cm 2 712/m
In other direction, shrinkage area of steel is required=
0.0018*b*h=0.0018*130*30=7.02cm2712.
Dowels reinforcement:
Bearing capacity of concrete is, Pc=*0.85* f c *A=0.7*0.85*280*25*100*10-3=416.5 t/m
Pu=44.32 ton/m<Pc only min. area of dowels is required, 0.5% of column area
Area of dowel=0.5%*25*100=12.5cm2 /m1212/m.
f y * db
0.0756 *
f c
20cm
120
4200 *12
0.0756 *
280
23cm
Dowel splicing distance = max. of 22cm =23 cm
20cm
The table shown below, represents the dimensions and reinforcement for all
wall footings.
Footing
dimensions
Footing
No.
Reinforcement
in short
direction
Area
Width Depth
of
(m)
(m)
steel
(cm2)
Shrinkage steel
in long direction
Dowels
Reinforcement
# of
bars
Area of
steel
(cm2/m)
712/m
7.02
712/m 1212/m
23cm
812/m 1212/m
23cm
10
1.3
0.3
7.59
11
2.7
0.5
16.86 916/m
121
# of
bars
# of
bars
Splicing
distance
Welded joints:
Max. hoop tension is 0.6 ton, and max. compression is 0.34 ton.
P = (0.7*S*Pw)
Where, P : weld capacity in N/mm.
Pw: weld strength =215 N/mm2.
S: weld leg length.
Using 4mm weld leg length, the weld capacity is 0.7*4*215= 602N/mm.
122
4 * t
Min. weld length= max.
TW
Where, t is the thickness of the thinner plate
TW is the minimum width of the two plates.
4 * 2 8mm
Min. weld length= max.
=30mm.
30mm
30/4+2*S=7.5+2*3=13.5mm.
So use 14mm weld length on each side, for all welded joints.
Base plates:
123
P 0.9 *10 4
=0.74 N/mm2.
A 110 *110
2.5 * w * (a 2 0.3 * b 2 )
Pyp
a=b=110-40=70 mm.
Pyp(plate design strength)=275N/mm 2 tmin4.8mm.
tmin arc thickness(=2mm)
plate thickness=5mm.
124
Arcs sections are UB 127*76*13. Bolts used for the upper joints (hinged joint),
and base plates are used to join arcs with concrete beams.
Pu
3.4 *10
=
=1.52 bolts.
capacity
23.2
P M *C
A
I
126
W=
3
150 * 200
(150 * 200 / 12)
Moment (M)=
Plate thickness(t)
6 * 2,437.2
6*M
=
=44.3mm.
1.2 * 275
1.2 * Py
Design of bolts:
Fs Ft
1.4
Ps Pt
Using 12mm bolt diameter, Ps= 31.8KN, and Pt= 37.9KN
.
Fs=2.72/no. of bolts(n).
Ft=1.42*42.6*200/n=12./n.
2.72 / n 12 / n
1.4 n=0.3
31.8
37.9
127
128
References:
ACI (American Concrete Institute), 2005, Building code
requirements for structural concrete (ACI 318-05),
Farmington Hills, Michigan.
BS 5950 Structural use of steel work in building: Part1. Code
of practice for design in simple and continuous construction:
hot rolled sections: 1985.
Computer Reference:
SAP2000 version 9, integrated soft ware for structural
analysis and design, computers and structures, Inc.
California, USA, 2006 .
129