SURVEY DURING CONSTRUCTION

SURVEYS DURING CONSTRUCTON


CONSTRUCTION
structural strength of every ship to which these
Rules apply and the number and disposition of
transverse watertight bulkheads shall be
adequate for the service for which the ship is
intended.
Watertight doors:
1.(1) In every ship to which these Rules apply
in which a watertight door is provided to
maintain the watertight integrity of a bulkhead,
every such watertight door shall be made of
suitable material and shall be efficiently
constructed for its intended duty.
(2) (a) Every watertight door of the sliding type
shall be capable of being operated by efficient
hand operated gear both at the door itself and
from an accessible position above the bulkhead
deck.
(b) The operating gear for operating from above
the bulkhead deck any sliding watertight door
fitted in the bulkhead of a machinery space
shall be situated outside the machinery space
unless such a position is inconsistent with the
efficient arrangement of the necessary gearing.

(3) Where there is access from the lower part of


a machinery space to a watertight shaft tunnel
the access opening shall be provided with a
sliding watertight door which shall be capable of
being operated locally on both sides of the door.
(4) Means shall be provided at remote operating
positions to indicate when a sliding door is
closed.
(5) Watertight doors shall be capable of being
operated when the ship is listed up to 15
degrees either way.
Anchors and chain cables:
Every ship to which these Rules apply shall be
provided with such anchors and chain cables as
are sufficient in number, weight and strength,
having regard to the size and intended service
of the ship.
Means of escape:
(1) In every ship to which these Rules apply
stairways and ladderways shall be arranged so
as to provide ready means of escape to the
lifeboat embarkation deck from all crew spaces,
passenger spaces and other spaces in which the
crew are normally employed.
(2) Subject to paragraph

(3), in every ship to which these Rules apply


there shall be provided from each engine room,
shaft tunnel and boiler room two means of
escape as widely separated as practicable, one
of which may be a watertight door if such a door
is available as a means of escape. Where no
such watertight door is available, the two means
of escape shall consist of two sets of steel
ladders leading to separate doors in the casing
or elsewhere from which there is access to the
lifeboat or liferaft embarkation deck or decks.

(3) The Minister may exempt any such ship of


less than 2,000 tons

SURVEYS
Surveys before issue of cargo ship safety
construction certificates:
39.(1) The owner of every ship to which these
Rules apply shall cause the same to be
surveyed by a surveyor appointed by a
certifying authority and any application for a
survey shall be accompanied by such
information relating to the ship as the certifying
authority may require.
(2) A certifying authority shall upon receipt of an
application for survey and any fee payable on

such application cause the ship to be certified


by a qualified surveyor.
(3) The surveyor shall survey the ship and shall
satisfy himself that the arrangements, materials
and scantlings of the structure, boilers and
other pressure vessels and their appurtenances
(other than domestic boilers having a heating
surface of 50 square feet or less and a working
pressure of 50 lb. per square inch or less and
other domestic pressure vessels having such a
working pressure), main and auxiliary
machinery, electrical installations and other
equipment comply with the requirements of Part
II and are in all respects satisfactory for the
service for which the ship is intended, having
regard to the period for which a cargo ship
safety construction certificate in respect of the
ship is to be issued.

general: 41.(1) The certifying authority shall,


on receipt of the application and of any fee
payable on such application, cause the ship to
be surveyed by a qualified surveyor.
(2) The surveyor shall survey the ship with a
view to satisfying himself

(a) that such of the parts of the ship and its


equipment specified in Rule 40 (2) as are the
subject of the application for survey remain
efficient, and
(b) so far as practicable, that no material
alterations have been made in the hull,
machinery or equipment of the ship to which
the cargo ship safety construction certificate
relates without the approval of the certifying
authority.
(3) On the completion of the survey in
accordance with the requirements of paragraph
(2), the surveyor shall forward a report on the
survey to the certifying authority.
SURVEY DURING CONSTRUCTION :
The classification survey procedure begins with
the approval of drawings. At that stage,

Bureau Veritas is
frequently consulted by shipyards; as the
development of the drawings progresses,
further discussions may be held. Meanwhile, BV
conducts a detailed analysis to determine the

structural and mechanical compliance of the


ship design to its published classification rules.

By this analysis, the classification society fulfils


an important technical task: to verify that the
submitted plans adhere to accepted technical
requirements as embodied in its rules. An
official request for classification is signed by the
shipyard for the society's services to survey a
new construction with regard to classification.
The design checking process is traditionally
divided into three main phases.
At the preliminary stage, when the main
characteristics and dimensions of the future
ship are determined, subdivision and
preliminary stability booklet may be checked.
Second, scantlings are checked for local
elements and the primary structure. This is used
to check the capacity of the structure, in other
words its ability to withstand the loads
prescribed in the rules.
The final phase consists of a review of the
structural details, machinery diagrams and
outfit falling within the scope of classification,
e.g. electrical equipment, fire-fighting
equipment and final stability booklet.

During the ship's construction the classification


surveyor role is to verify that construction is
preceding according to the classification rules
requirements, that materials and equipment are
approved and that approved classification plans
are used and that all the classification rules
requirements are observed. In addition, the
surveyor participates in the trials.
During his intervention he conducts an overall
examination of the parts of the ship covered by
the classification rules, he examines the

construction
methods and procedures, he checks selected
items covered by the rule requirements and
he attends tests and trials where applicable and
deemed necessary.
Inspection of site, builders qualification or
expertise
Keel voids prior to closing off, or mould
preparation for FRP construction
Approximately 20% hull completion including
reinforcement layers of FRP

Approximately 80% hull completion including


framing of FRP hulls
Hull thickness testing for FRP
Fuel tank pressure testing
Propeller shafting and components
Rudder stock and components
Engine and thrust seatings
Accommodation spaces prior to lining
Machinery, propulsion system, piping and
electrical systems
ADDITIONAL INSPECTIONS:
Witnessing by MAST(Marine and Safety
Tasmania) of the appropriate stability test.
Witnessing by MAST of operational trials
Inspection by MAST of fire safety and
safety equipment
Installation certificate for fixed fire fighting
and detection system to be supplied by
the installer on vessels where such
systems are fitted.
Certificate of compliance with Australian
Standards to be supplied by the installer
on vessels where LPG or 240/415V
supplies are fitted.

If foam buoyancy is to be fitted, the


builder or designer is to complete and
submit to MAST an appropriate installation
form.
Communication system survey report by accredited
surveyor.
Compass adjustment report for all A, B & C vessels.
Relevant test and installation certificates may be
required by MAST for various items of equipment or
machinery.
CERTIFICATE OF SURVEY :
Following satisfactory completion of plan approval,
stability approval and inspections, a vessel will be
issued with a Marine and Safety Tasmania Certificate
of Survey, valid in most cases for 12 months. The
certificate is issued within a nationally recognised
format as detailed in Section 14 of the Uniform
Shipping Laws Code.

LOAD LINE & OIL POLLUTION PREVENTION


CERTIFICATES :
Subject to design approval and vessel compliance,
MAST will issue:
Load line certificates to class 1 & 2 vessels exceeding
24 metres.
Oil Pollution Prevention certificates to vessels
exceeding 400 gross registered tonnage.