RESEARCH PROGRAM
INDIANA DEPARTMENT OF TRANSPORTATION
AND PURDUE UNIVERSITY
STRUCTURAL IMPACT
OF CONSTRUCTION LOADS
Daniel McPheron
Graduate Research Assistant
School of Civil Engineering
Purdue University
Bob McCullouch
Research Scientist
School of Civil Engineering
Purdue University
Corresponding Author
Mark D. Bowman
Professor of Civil Engineering
and Director of Bowen Laboratory
School of Civil Engineering
Purdue University
SPR-3514
Report Number: FHWA/IN/JTRP-2012/18
DOI: 10.5703/1288284314980
RECOMMENDED CITATION
McPheron, D., B. McCullouch, and M. D. Bowman. Structural Impact of Construction Loads. Publication FHWA/IN/JTRP2012/18. Joint Transportation Research Program, Indiana Department of Transportation and Purdue University, West Lafayette,
Indiana, 2012. doi: 10.5703/1288284314980.
CORRESPONDING AUTHOR
Bob McCullouch
School of Civil Engineering
Purdue University
(765) 494-0643
bgm@purdue.edu
JOINT TRANSPORTATION RESEARCH PROGRAM
The Joint Transportation Research Program serves as a vehicle for INDOT collaboration with higher education institutions
and industry in Indiana to facilitate innovation that results in continuous improvement in the planning, design, construction,
operation, management and economic efficiency of the Indiana transportation infrastructure.
https://engineering.purdue.edu/JTRP/index_html
Published reports of the Joint Transportation Research Program are available at: http://docs.lib.purdue.edu/jtrp/
NOTICE
The contents of this report reflect the views of the authors, who are responsible for the facts and the accuracy of the
data presented herein. The contents do not necessarily reflect the official views and policies of the Indiana Department of
Transportation or the Federal Highway Administration. The report does not constitute a standard, specification or regulation.
FHWA/IN/JTRP-2012/18
4. Title and Subtitle
5. Report Date
August 2012
6. Performing Organization Code
7. Author(s)
FHWA/IN/JTRP-2012/18
SPR-3514
12. Sponsoring Agency Name and Address
Final Report
Prepared in cooperation with the Indiana Department of Transportation and Federal Highway Administration.
16. Abstract
Numerous bridge construction accidents have occurred across the country because of construction loadings, which are an underemphasized topic in many DOT specifications and design manuals. Bridge girders are least stable when they are subjected to construction
loads, so it is important for design engineers and contractors to understand and design for these loads. The Indiana Department of
Transportations current Standard Specifications does not contain many construction load provisions, so this study was performed to
identify and implement new requirements to proactively prevent accidents from occurring in Indiana.
Various documents were examined in this study, including AASHTO and ASCE standards in addition to several other states DOT Standard
Specifications and Design Manuals. Based on these documents, new falsework and formwork design loads, including horizontal loads,
impact loads, and wind load, were developed and proposed to INDOT, which currently only specifys a dead load and live load. A set of
drawings showing proposed minimum lateral bracing requirements was also developed to help ensure the stability of prestressed
concrete and steel girders during construction.
Unclassified
Form DOT F 1700.7 (8-69)
Unclassified
41
22. Price
EXECUTIVE SUMMARY
STRUCTURAL IMPACT OF
CONSTRUCTION LOADS
Introduction
Numerous bridge construction accidents have occurred because
of construction loadings, which are an underemphasized topic in
many specifications and design manuals. Bridge girders are least
stable during the construction phase, so it is important for bridge
designers and contractors to understand and design for conditions
during this phase. The Indiana Department of Transportations
current Standard Specifications contain limited construction load
provisions and temporary bracing requirements; therefore this
study was performed to identify and implement new requirements
to proactively prevent construction accidents from occurring in
Indiana.
Various documents were examined in this study, including
AASHTO and ASCE standards and the standard specifications
and design manuals of other departments of transportation. Based
on these documents, new falsework and formwork design loads,
including horizontal loads, impact loads, and wind load, were
developed and proposed. INDOT currently specifies only
construction dead load and live loads. A set of drawings showing
proposed minimum lateral bracing requirements was also created
to help ensure the stability of prestressed concrete and steel girders
during construction.
Findings
To develop new proposed falsework and formwork design
loads, the results of the literature review were studied and then
discussed with a committee consisting of INDOT bridge
engineers, consulting engineers, and Indiana contractors in a
series of meetings. For various construction load types, appropriate specification language was developed, and if needed,
analysis performed. For some of the design loads, it was agreed
to simply adopt the corresponding provision in the AASHTO
Guide Design Specifications for Bridge Temporary Works.
N
N
N
N
N
N
Implementation
N
N
CONTENTS
1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2. DESIGN LOAD RECOMMENDATIONS
2.1 Introduction . . . . . . . . . . . . . . . . . . . .
2.2 Dead Load . . . . . . . . . . . . . . . . . . . . .
2.3 Live Load. . . . . . . . . . . . . . . . . . . . . .
2.4 Combined Dead and Live Load . . . . . .
2.5 Impact Load . . . . . . . . . . . . . . . . . . . .
2.6 Horizontal Load . . . . . . . . . . . . . . . . .
2.7 Wind Load . . . . . . . . . . . . . . . . . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
2
2
2
2
3
3
3
4
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
4
4
5
5
6
9
12
15
15
18
18
21
18
32
LIST OF TABLES
Table
Page
Table A.2 Comparison of Design Checks with Current and Proposed Live Loads
11
12
13
13
Table B.4 Wind Pressure Values for Design of Falsework and Formwork
13
13
LIST OF FIGURES
Figure
Page
10
10
10
11
14
14
15
16
16
17
18
19
20
32
33
1. INTRODUCTION
In the past few decades, there have been several
significant bridge construction accidents across the
country caused by construction loads. Bridges are
designed to carry a full design vehicle loading when
they are completed, but not enough attention is given to
their strength and stability during construction.
Gaining a better understanding of the construction
loads that act on a structure could help prevent future
accidents. Many past failures have been caused by
inadequately designed falsework, formwork, or bracing
systems, and some departments of transportation have
reacted by reviewing the construction requirements in
their standard specifications, construction manuals and
other related documents.
In Maryland in 1989, a Route 198 bridge under
construction collapsed during deck placement, spilling
wet concrete onto the road below. The failure was later
attributed to inadequate shoring towers (1). Shortly
after the accident, the Federal Highway Administration
(FHWA) began studying ways to improve specifications used in designing temporary shoring in bridge
construction. The American Association of State
Highway and Transportation Officials (AASHTO)
later used some of the FHWAs results in developing
the Guide Design Specifications for Bridge Temporary
Works (1).
In Colorado, during a construction project on a C470 overpass in 2004, insufficient temporary bracing
allowed a steel girder to crash down onto I-70. The fall,
caused by a gust of wind, crushed a vehicle travelling on
I-70 and killed a family of three (2). Figure 1.1 shows
the collapsed girder and the remains of the vehicle.
Another accident occurred in 2005 in Lansing, Illinois,
Figure 1.1
Figure 1.2
N
N
N
For members subject to impact during placement operations, the design dead load must be increased by at least 30
percent of the weight of the material being placed.
For members subject to impact during lifting operations,
the static load due to the payload must be increased by at
least 30 percent.
It is recommended that INDOT adopt this requirement from AASHTO. Accounting for an increased
design load to include impact is consistent with the
large number of failures that occur during concrete
placement. As stated in the Introduction, the 1986
study Analysis of Causes of Falsework Failures in
Concrete Structures considered over 85 failures related
to falsework, and found that 49% of them occurred
during the concrete placement phase (4).
A vehicle impact provision is contained in some
states specifications. It applies to the design of any
falsework potentially subjected to collision, and lists
minimum design requirements for any such members.
Designs adhering to this section would help ensure the
stability of falsework over or adjacent to traffic,
reducing the potential for collapse should vehicular
impact occur. It is recommended that Indiana adopt the
following language:
Falsework over or adjacent to roadways or railroads which
are open to traffic shall be designed and constructed so that
the falsework will be stable if subjected to impact by
vehicles. Falsework posts which support members that
cross over a roadway or railroad shall be considered as
adjacent to roadways or railroads. Other falsework posts
shall be considered as adjacent to roadways or railroads
only if they are located in the row of falsework posts
nearest to the roadway or railroad, and the horizontal
distance from the traffic side of the falsework to the edge of
pavement or to a point 10 feet from the centerline of track
is less than the total height of the falsework and forms.
Falsework shall not be considered adjacent to roadways or
railroads if it is protected from traffic by an approved
barrier. If not properly protected, the appropriate loads are
as follows:
N
2.5 Impact Load
Some states specifications require an impact load,
which helps ensure a bridges stability should an
accident occur during construction. There were two
types of impact loads found in the literature search a
design provision in AASHTO Bridge Temporary Works
(23,24) accounting for lifting and placement operations,
and a requirement in a few states specifications for
vehicular impact on falsework.
AASHTO Bridge Temporary Works (23,24) requires
an increased design load for any members subject to
placement or lifting operations. It states:
TABLE 2.1
Design Wind Pressure Values
Wind Pressure (psf)
Height Above
Ground (ft)
Typical
Falsework
Falsework over or
Adjacent to Traffic Openings
025
2550
5075
30
35
40
35
40
45
TABLE 2.2
Design Wind Pressure Reduction Factor
Construction Period
0.57
0.64
0.73
0.81
N
N
2.
3.
TABLE 3.1
Results of Unbraced Length Analysis
Beam Type
AASHTO II
AASHTO III
AASHTO IV
AASHTO V
AASHTO VI
Height (in)
# PS Strands
PS force (kips)
PS cg (in)
yb (in)
Eccentricity (in)
Span (ft)
# Braces
Unbraced Length (ft)
Stress - Placement
Stress - Braced
Stress - Deck
Stability - Braced
Stability - Deck
36
22
740
13.2
15.8
2.6
50
0
50
OK
OK
OK
OK
OK
45
32
990
13.6
20.3
6.7
50
0
50
OK
OK
OK
OK
OK
54
54
1670
16.0
24.7
8.7
100
1
50
OK
OK
OK
OK
OK
63
60
1860
15.7
32.0
16.3
100
1
50
OK
OK
OK
OK
OK
72
64
1980
19.0
36.4
17.4
100
1
50
OK
OK
OK
OK
OK
N
N
N
N
N
29. Texas Department of Transportation (TxDOT). Minimum Erection and Bracing Requirements. Austin, Texas,
2006.
30. Florida Department of Transportation (FDOT). FDOT
Structures Manual: Volume 1 Structures Design
Guidelines. Tallahassee, Florida, 2011.
31. Florida Department of Transportation (FDOT).
Structures Design Bulletin C10-01. Tallahassee, Florida,
2010.
Figure A.1
TABLE A.1
Given Overhang Bracket Information
Overhang Bracket Spacing
3600
1087
1080
50
88
1218
Feet
lbs
lbs
lbs
lbs
lbs
lbs
(per
(per
(per
(per
(per
bracket)
bracket)
bracket)
bracket)
bracket)
Source: (1).
Figure A.2
Figure A.4
Figure A.3
10
APPENDIX A REFERENCE
1. Kansas Department of Transportation (KDOT). Design
Manual. Topeka, Kansas, 2009.
Figure A.5
TABLE A.2
Comparison of Design Checks with Current and Proposed Live Loads
Calculation
Difference (%)
3130
3025
7562
4426
2860
2721
6803
4045
28.6
210.0
210.0
28.6
11
Eq:2
Table B.1 shows the value selected for each of the constants,
along with the corresponding sections in ASCE 7-10. Kzt and Kd
can be conservatively estimated as 1.0. Cp, the external pressure
coefficient, was determined from ASCE 7-10, Table 27.4-1. For
this study, Cp was considered to include both the windward and
leeward walls, with the wind pressure to be applied only on the
windward face, to simplify design. The Cp value was estimated at
1.15, the average value between the maximum (1.30) and minimum
(1.00) possible sums of the windward and leeward pressures.
The gust effect factor, G, is dependent on whether the structure
under consideration is rigid. A rigid structure is defined as having
a natural frequency no less than 1 cycle per second. For rigid
structures, G can be taken as 0.85. For non-rigid structures, it
must be calculated with a series of formulas provided in ASCE 710. An analysis was performed with a SAP2000 model in order to
confirm that typical falsework structures are considered rigid.
Dimensions of a falsework system set up on campus were
measured, and a model using similar elements was created. A steel
pipe with an outer diameter of 2 inches and a thickness of 1/80 was
used as a typical falsework member. The vertical members were
considered continuous, with the horizontal and diagonal members
pinned at all joints. The falsework was modeled as a series of bays
measuring 6 feet wide and 6 feet 8 inches high, with diagonal
members bracing each bay. Three models were constructed; each
measured 12 feet wide by 42 feet long and topped with an 8-inch
concrete slab, and the height was varied among the models from
20 feet to 40 feet to 60 feet. Figure B.1 shows side and end
elevation views of the 60-foot model.
The models were analyzed for their natural frequencies, and
were confirmed to be rigid structures. The 20-foot model had a
natural frequency of 4.20 Hz, the 40-foot model 2.15 Hz, and the
60-foot model 2.02 Hz. It was concluded that typical falsework
structures are rigid and can be assigned a gust effect factor of 0.85.
The exposure coefficient Kz varies with height. Table B.2 shows
the value for each height zone from Table 27.3-1 of ASCE 7-10,
the velocity pressure calculated using Equation 2, and finally the
wind pressure calculated with Equation 1.
To simplify the wind pressure values for falsework and
formwork design, the values were then approximated into three
different height zones at intervals of 25 feet: 30 psf for falsework
between 0 and 25 off the ground, 35 psf from 2550 feet, and 40
psf from 5075 feet. Table B.3 compares the calculated wind
pressure with the approximated value.
It is suggested that, like in Californias and Washingtons
specifications (24) and AASHTO Bridge Temporary Works (5,6),
the wind load should be increased by 5 psf for falsework over or
adjacent to traffic openings to account for the importance of such
falsework. Table B.4 is the wind pressure requirement recommended for Indianas specifications.
Wind Pressure Reduction Factor:
As mentioned in the Literature Survey, ASCE 37-02 (7)
contains a provision for reducing the wind speed based on the
length of the construction period. The reduction is encouraged
because the basic wind speed prescribed in ASCE 7-10 (1) is the
50-year design wind speed; i.e., the highest speed which is expected
in a 50-year time frame. For building design, a 50-year design
wind is appropriate because the expected life span of a structure is
often more than 50 years, but for temporary structures, it is highly
unlikely that speed will be reached during short-term construction
periods. The design wind speed can be significantly reduced while
still maintaining a low probability of reaching the 50-year speed.
In this study, it was desired to produce a factor to reduce the wind
pressure, rather than the wind speed, in order to shorten the wind
load design process. Because Equations 1 and 2 show that wind
pressure varies with the square of wind speed, the wind speed
reduction factors in Table B.5 can simply be squared and applied
to the wind pressure instead. Table B.5 shows the results of this
calculation. The construction period is defined as the time between
the first and last use of falsework on the project.
Wind Impact Area:
After the design wind pressure values and an appropriate
reduction factor were determined, the area over which the load
should be applied needed to be specified. For unenclosed
falsework, the wind load simply acts on the projected area of
the falsework perpendicular to the wind. For enclosed (wrapped)
falsework, the wind acts on the gross area of the falsework on the
face normal to the wind, and there is also an external pressure
effect that acts outward on the side faces of enclosed structures.
Table 27.4-1 of ASCE 7-10 lists a pressure coefficient Cp of 0.7
outward from side walls. However, since a Cp of 1.15 was already
factored into the pressure values for walls normal to the wind, 0.7
must be divided by 1.15 to produce a coefficient of 0.60 that
should be multiplied by the wind load to find the pressure acting
outward from the side walls. Figure B.2 illustrates where the wind
load, represented as W, shall be applied.
TABLE B.1
Wind Load Variables for ASCE 7-10 Calculation
Variable
Exposure Category
Wind Speed
Wind Directionality
Topographic Factor
Internal Pressure
External Pressure
Gust Effect
12
V
Kd
Kzt
GCpi
Cp
G
Value
Units
C
115
1.0
1.0
0
1.15
0.85
mph
26.7.3
26.5.1
26.6
26.8.2
26.11.1
27.4.1
26.9
TABLE B.2
Calculation of Wind Pressure Values
Exposure Coefficient, Kz
Height (ft)
Section 27.3.1
015
1520
2025
2530
3040
4050
5060
6070
7080
8090
90100
100120
Section 27.3.2
0.85
0.90
0.94
0.98
1.04
1.09
1.13
1.17
1.21
1.24
1.26
1.31
28.8
30.5
31.8
33.2
35.2
36.9
38.3
39.6
41.0
42.0
42.7
44.4
TABLE B.3
Approximation of Wind Pressure Values
Height (ft)
015
1520
2025
2530
3040
4050
5060
6070
7080
8090
90100
100120
28.1
29.8
31.1
32.4
34.4
36.1
37.4
38.7
40.0
41.0
41.7
43.4
30
30
30
35
35
35
40
40
40
N/A
N/A
N/A
TABLE B.4
Wind Pressure Values for Design of Falsework and Formwork
Wind Pressure (psf)
Height Above
Ground (ft)
Typical
Falsework
Falsework over
or Adjacent to
Traffic Openings
025
2550
5075
30
35
40
35
40
45
TABLE B.5
Wind Pressure Reduction Factor
Construction Period
Less than 6 weeks
6 weeks to 1 year
1 to 2 years
2 to 5 years
13
APPENDIX B REFERENCES
1. American Society of Civil Engineers (ASCE). ASCE 7-10:
Minimum Design Loads for Buildings and Other Structures.
Reston, Virginia, 2010.
2. California Department of Transportation (CALTRANS).
Standard Specifications. Sacramento, California, 2006.
3. Washington Department of Transportation (WSDOT).
Standard Specifications for Road, Bridge, and Municipal
Construction. Olympia, Washington, 2010.
4. California Department of Transportation (CALTRANS).
Falsework Manual. Sacramento, California, 1988.
5. American Association of State Highway and Transportation
Officials (AASHTO). Guide Design Specifications for Bridge
Temporary Works. Washington, D.C., 1995.
6. American Association of State Highway and Transportation
Officials (AASHTO). 2008 Interim Revisions to Guide Design
Specifications for Bridge Temporary Works. Washington,
D. C., 2008.
7. American Society of Civil Engineers (ASCE). ASCE 37-02:
Design Loads on Structures During Construction. Reston,
Virginia, 2003.
Figure B.1
Figure B.2
14
Figure C.1
15
Figure C.2
Figure C.3
16
Figure C.4
17
Figure D.1
18
Figure D.2
19
Figure D.3
20
21
22
23
24
25
26
27
28
29
30
31
Figure F.1
32
Figure F.2
33