Project: no.

AI 01313001
Preparation beech P19 for
transportation

AIRCRAFT GENERAL
Aviation Maintenance Technician school, BONAIRE

Name/Group:
Type:
(Research, practical ...etc)

Any Equipments chosen


Aircraft, sub syst. or part

..............................................
..............................................
..............................................
..............................................
...
...

(All the above must be filled in)

Period or date: 04 March 30 March 2015


Resources
Description
1. A/P mechanics general handbook
2. Aircraft inspection and repair
3. A/P mechanics engine handbook
4. Beech P19 Maintenance manual
5. Beech P19 Illustrated parts catalog
6. Beech P19 Structural repair manual
7. AC 143.1B
8. Jeppesen Airframe handbook
9.
10. www.faa.gov
11. amtsktm30@hotmail.com

Remarks

For the AC (The


manuals)
For emailing
your project

Task
1. Reason/ goal
Give the students the chance during removal/installation the engines and wings from
the aircraft to become familiar with the construction of an aircraft.
Important note: The check list, the discrepancy list and the release statement has to
be filled in, in writing. Nice and readable. This will have its influence on your grade.
ALSO; YOU MUST USE ALL YOU HAVE LEARN IN JEPP CH 17 A&B

Prep. by: J. Frans


Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

2. Hypothesis
- The student must c/o a 100 hours inspection on the aircraft and log all
discrepancies found, after installation of wings, empennage and engines. The
student must write down the problem, the parts needed to fix the problem and the
maintenance manual reference.
- The student must by using the installation manual install the engine, wings and
empennage on the aircraft, carry out the necessary paperwork and prepare the
aircraft for flight.

3. Report on the project. (Brief description of the work)


We moesten voor school het Pj ray demonteren op Curacao en monteren
op Bonaire, maar voordat we dit konden doen moesten we eerst alles
netjes voorbereiden. Het voobereiden van het werk werd clasicaal gedaan.
We hebben de klas in 3 groepen verdeel, groep 1 moest het linker vluegel
demonteren groep 2 moest het rechter vluegel demonteren en als laast
groed 3 die moest de horizontale tab demonteren.
Nadat we het werk haden verdeel we hebben ook rekening gehouden met
verschillenden punten die waren als volg: veiligheid, gereedschapen lijst,
doeldatum, de maat van de container die we zal gebruiken en de volgorde
di we elk onderdeel gaan demonteren.
4. Job preparation (What to do in sequence)
Cabin floor and furniture removal
Horizontal stab removal
Left and right wing removal
Container filling
Container unloading
Left and right wing installation
Horizontal stab installation
Engine installation
Cabin assemble

Prep. by: J. Frans


Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

5. 50 inspection checklist
BEST AIRWAYS
50HRS INSPECTION CHECKLIST
Aircraft reg:

Hours: 260

Station.

Date:

Inspector:

Sign:

INSP.
DES.
PROPELLER

Cycles:

Lic. No.

ITEM

Spinner and spinner bulkhead


Blades
ENGINE COMPARTMENT
Engine oil, screen, filler cap, dipstick, drain plug and external filter
element
Induction air filter; clean inspect and replace as necessary
Engine Baffles
All lines and hoses
Intake and exhaust system
Engine control linkages
Engine cowling
FUEL SYSTEM
Fuel strainer, drain valve and controls
Fuel tanks, fuel lines, sump drains, filler caps and placards
Fuel selector valve and placards
LANDING GEARS
Main gears wheels and fairing
Nose gear wheel, torque links, steering rods, boots and fairings
Nose gear strut and shimmy dampener
Tires
Torque link lubrication
Park brake and toe brake (Operational check)
AIRFRAME
Aircraft exterior
Windows, windshields and doors
Instruments and markings
Battery, battery box and battery cables
CONTROL SYSTEM
Prep. by: J. Frans
Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

Trim control wheels, indicator, actuators and bungee


Flap control switch, flap rollers and tracks, and indicator
Elevator trim tab hinges, tips and control rods
Skin and structure of control surfaces and tabs

Prep. by: J. Frans


Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

6. Discrepancy list
BEST AIRWAYS
INSPECTION DISCREPANCY LIST
Aircraft reg: Pj- ray
Station.

280

Hours:

Cycles:

Date:

Inspector: Vandervock romelus


NO. DISCREPANCY.
1.
Airspeed indicator pipe is stuck in wing
Part: no 169-580001-67

Sign:

Lic. No. 0000


CORRECTIVE ACTION

Left-right side panel screw


Part:no
Bacon light screw are broken
Part:no 6-32
Fuel line pilot side broken
Part: no 169-920000-25
Pilot seat not in a good condition
Part:no 169-534012
Seat belt are damage
Part :no BE2003-6
Washer voor mixture control as require
Part:no -not given
Windshield scratch-crack
Part:no 169-420035-23
Rudder dorsal fairing
Part:no 169-40013-11
Flaps right bracket hinch broken
Part:no169-160005-11
Left tank cap assembly
Part:no 169-380024-1

Prep. by: J. Frans


Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

Date:

Technician:

sign:

Date:

Technician:

sign:

Date:

Technician:
MINTENANCE RELEASE

sign:
PARTS REPLACED
Part name:
Part number

NEXT INSPECTION DUE

Prep. by: J. Frans


Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

Prep. by: J. Frans


Date: 030315
Checked by:
Rev. original

AIRCRAFT GENERAL

Project: no. AI 01313001


Preparation beech P19 for
transportation

Aviation Maintenance Technician school, BONAIRE

7. Aircraft walk around (For reference)

8. Annexes (Copy of maintenance manual, illustrated parts, wiring


manual etc..)
Prep. by: J. Frans
Date: 030315
Checked by:
Rev. original