Anda di halaman 1dari 182

Controlling is used for internal reporting

Controlling Area is the highest hierarchy.


Areas to be covered:
1.
2.
3.
4.
5.
6.

Cost element Accounting


Cost centre accounting
Internal orders
Profit centre accounting
Product costing
Profitability analysis

1. Cost element Accounting: To update controlling records you have to create cost
elements
Cost elements are:
a. Primary cost elements
b. Secondary cost elements
2. Cost centre Accounts: To view department wise cost
3. Internal orders: To view costs for a specific tasks
4. Profit Centre Accounting: To view profitability, product wise, product group wise
(or) location wise if business area is not activated in FI
5. Product Costing: valuation of inventories like finished goods and work in process.
6. Profitability analysis: To view profitability for number of parameters at a time like
Customer wise, product wise, sales organization wise, plant wise, sale order wise
This is called data cube
It is a reporting tool
Basic settings for controlling:
FI organization structure
Company

Company code

Business Areas

Co. organization structure


Controlling

Cost centre

Scenario 1

Company

Company code
= Controlling Area

Business Area
Cost Centre
Controlling area at company code level, cost element is assigned to Business
Area.
Scenario 2
Company
=

Company code

Business Area

Controlling area

Cost Centre

(Controlling area at company level)


Scenario (2) is more flexible, because in this scenario when we want to view number of
cost centers data for different company codes, we have to go for 2nd scenario.
Also we want view No. of cost centers data for a particular company code we get
in 2nd scenario by creating cost center group.
Maintain controlling area:
Path: SPRO Controlling General controlling Organization Maintain
controlling area
Double click on maintain controlling area (T. Code OKKP)
Select new entries button
Controlling area:
1st scenario: company code: AML
2nd scenario: Any no. (Or) name (Max 4)
Give controlling area: AML
Name: Controlling area for AML
Company code Controlling Area: select controlling area same as company code
Currency type: select 10 (company code currency)

Once we select 10, your currency field, chart of accounts field, fiscal year variant field
updated automatically
Cost centre standard hierarchy: AMLHIER (AML Hierarchy)
Select save button (or) (ctrl + s)
Select yes button for the message, system to create as a standard hierarchy
Select create request button
Short description: Co. Customization for AML
Press enter
Press enter once again to saving the request
Double click on Activate components/control indicators folder
Select new entries button
Fiscal year: 2006
For the field cost centre: select component active
Select activate type check box
Order management: select component active
Select profit center check box
Select save button (or) (ctrl + s)
Ignore the message, press enter
Double click on assignment of company codes folder
Select new entries button
Select the company code: AML
Select save button (or) (ctrl + s)
Maintain Number ranges for controlling documents
Same path: (T. Code KANK)

1. Co. documents through posting from FI document: Controlling through posting of


accounts in FI Module i.e. called COIN
In FI you have to give the details like

SA
Co: Automatically generated number range intervals

1 100000
2. Report Co. line items (RKU3)
Posting through FI document
Ex:

Wages Dr
Dept A 100000
Wages Dr
Dept B 200000
Wages Dr
Dept C 300000
To Bank

(COIN)
600000

2) Wages A/C
Dr
600000
To Bank
600000
At the time of posting which department we are posting is dont know
After Posting (repost to CO items) (RKU3)
We transfer 600000 to various cost centers (or) dept.
600000: 1) Dept A 100000
2) Dept B 200000
3) Dept C 300000
(Transfer line item wise/document wise)
Here 1 FI document and 2 CO. documents are generated
3. Repost costs (RKU1): Incase split the department (or) wrong cost centre postings.
Example:
Dept A
Dept Z
Salaries
April
100000
20000
May
200000
50000
(Repost to cost line items)
June
200000
July
200000
August
100000
Wages:
200000
-----------Total
1000000
Here 200000 Salaries & Wages belongs to dept Z & 800000 belongs to dept A

How we shown the total transaction amount transferred to department wise


Here NO FI documents
Only Co. document
Dept A

Dept B

Salaries A/C
1
2
3
4
5
Total

100000
200000
300000
50000
150000
---------800000

20000
50000 (Repost cost line items

-------70000 (Repost Cost)

4) Planning Primary Costs (RKP1) (Budgeting)


Maintain Number Ranges for controlling document (same path)
(Transaction Code KANK)
Give the controlling area: AML
Select Maintain groups button
From the Menu select group Insert
Text: Co. document No. range intervals for AML
From No: 1 to 100000
Enter
Double click on COIN (Co. through postings from FI)
Double click on RKU3 (Repost Co. line items)
Double click on RKU1 (Reposts costs)
Double click on RKP1 (Planning Primary cost)
Select Co. document no. range intervals for AML check box
From the menu select edit Assign element group
Save (or) (ctrl + s)
Maintain versions:
(Versions are nothing but budgets)

- Planning for whole year (original Budget) 0


- Revised Budget 1
- Re revised Budget 2
Here actual are compared with original/revised (or) re revised budgets
Path: Same Path
Select version 0
Double click on settings for each fiscal year
Give your controlling area: AML
Enter
Once the planning is complete select version locked check box so that no one change
planned figures
Save
Cost element Accounting:
To update Co. records we require cost elements
Cost elements are 2 types
1. Primary cost elements
2. Secondary cost element
1. Primary cost elements: These are nothing but G/L expenditure/ revenue
Account.
Posting to primary cost elements are possible.
2. Secondary cost elements:
- Other than your G/L Account
- Postings are not possible
- Support for allocation/settlement in Co.

Cost element categories:

Primary cost element categories:


1. Primary costs/cost reducing revenues used for expenditure account
3. Accrual/deferral per surcharge used for Month end provisions in co
11. Revenues used for sales and other income accounts
12. Sales deductions used for expenditure like trade discount/sales conversion etc.
22. External settlement: Allocation from Co to G/L (or) Assets.
Secondary cost element categories:
21. Internal settlement Allocation from Co to Co
31. Order/project results analysis (used for work in process calculation in product
costing)
41. Over head rates used for raw material over head/production overhead
calculation in product costing.
42. Assessment used for allocation of service department cost to production
departments.
43. Internal activity allocation (This is used for calculation of activity like machine
hour rate/labor rate in product costing.

Cost Centre Accounting


This is used to view department wise costs.
a) Creation of primary cost element
May created in FI Area
- Co Area
- Automatic creation of cost element
b) Creation of field status group making cost center mandatory.
c) Assign new field status group in G/L expenditure accounts.
d) Creation of cost centers
e) Creation of cost centre groups
f) Creation of cost element groups
g) Posting of transaction is FI
h) To view cost center wise report
a) Creation of primary cost element at FI Area:
Use the transaction code: FS00
Select your G/L Account No: 400001
Company code: AML
Enter
Select edit cost element button
Give valid from 01.04.2006 to date 31.12.9999
Enter
Cost element category: select 1 (Primary cost/cost reducing revenues)
Save
Creation of primary cost element at Co. area: (T. Code FS00)
Path: Accounting Controlling Cost element accounting Master data cost
element Individual processing create primary (T. Code KA01)
Cost element 400100
Valid from 01.04.2006 to 31.12.9999
Enter
Co. element category 1
Save

Automatic creation of primary cost element


There are 3 steps in this area
1st step make default settings.
SPRO Controlling cost element accounting master data cost element
automatic creation of primary and secondary cost elements make default setting
(T. Code OKB2)
Chart of Accounts AML
Enter
Accounts from: 400101 to 499999
Save & save in your request
Create batch input session:
SPRO Controlling cost element accounting Master data Cost element
Automatic creation of primary and secondary cost elements make default setting
Create batch input session (T. Code OKB3)
Controlling area: AML
Valid from: 01.04.2006 valid to 31.12.9999
Session name: AML
Batch input user: sap user
Execute (F8)
Execute batch input session:
Path: SPRO Controlling Cost element accounting Master data cost element
Automatic creation of primary and secondary cost element Execute batch input
sessions (T. Code SM35)
Select the session name: AML
Select process button
Select display errors only radio button
Select process button
You get message processing of batch Input sessions completed
Select exit batch input button (F12)
9

To view the cost elements created


Path: Accounting Controlling Cost element accounting Master data cost
element Individual processing Display (T. Code KA03)
Select the drop down button beside cost element
Give the controlling area: AML, enter
Creation of field status group making cost centre mandatory:
Path: (T. Code: OBC4)
Select field status variant: AML
Double click on field status group folder
Double click on G004
Double click on general data
Text make it required entry field
Select next group button
Cost centre make it required entry field
Save (or) (ctrl + s)
Save in your request
Assign new field status group G/L expenditure:
Use the transaction code: FS00
`
G/L account: 400100 (Salaries)
Company code: AML
From menu G/L Account Change
Select create/bank/interest tab
Field status group: G004
Save

10

G/L Account: 400300 (Rent A/C)


Company code: AML
From menu G/L Account change
Select create/bank/interest tab
Field status group: G004
Save
Creation of cost centre:
Path: Accounting Controlling Cost centre accounting Master data Cost
centre Individual processing Create (T. Code KS01)
Cost centre: Dept A
Valid from: 01.04.2006 to 31.12.9999
Enter
Name: Dept A
Depart Cost centre: Department A
Person responsible: A
Cost centre category: 1 (Production)
Hierarchy area: AMLHIER
Business area: AMH
Currency: INR
Save (or) (Ctrl + s)
Ignore the warning message, press enter

11

Cost centre: Dept B


Valid from: 01.04.2006 to 31.12.9999
Reference cost centre: Dept A
Controlling area: AML
Enter
Name: Department B
Description: Cost centre department B
Basic data
Person responsible: B
Save (or) (ctrl + s)
Ignore the warning message, press enter
Cost centre: Dept C
Valid from: 01.04.2006 to 31.12.9999
Reference cost centre: Dept A
Controlling area: AML
Enter
Name: Department C
Description: Cost centre department C
Basic data
Person responsible: C
Save (or) (ctrl +s)
Ignore the warning message, press enter

12

Creation of Cost centre group:


Path: Accounting controlling Cost centre Accounting Master data Cost
centre group Create (T. Code KSH1)
Cost centre group: AMLProdu
Enter
AMLProdu Production department for Co. area AML
Select insert cost centre button (Shift + F4)
Give the cost centre: Dept A, Dept B
Save
Creation of cost element group:
Path: Accounting controlling Cost centre accounting Master data Cost
element group Create (T. Code KAH1)
Cost element group: AMLADMIN
Enter
AMLADMIN Administration expenses for AML
Select insert cost element button (Shift + F4)
400300 to 400399
Enter & save

13

Posting of transaction in FI
T. Code: F 02
Document date: 23.10.2006
Type: SA
Company code: AML
Posting: 40
Account no: 400100 (Salaries)
Enter
Amount: 200000
Cost centre: Dept A
Text: Salary payment
Posting: 40 (one more debit)
Account No: 400300 (Rent account)
Enter
Amount: 50000
Cost centre: Dept A
Text: Rent payment
Posting key: 50
Account No: 200101 (IDBI Current Account)
Enter
Amount: *
Business area: AMH
Text: Expenditure for October
Document Simulate and save

14

To view cost centre wise report:


Path: Accounting Controlling Cost centre accounting Information system
report for cost centre accounting line items cost centers actual line items (KSB1).
Cost centre: select dept A
Execute
Keep the cursor on first line item
Select doc. Button (Shift + F2)
Select back arrow
Select change layout button (Ctrl + F8)
Select ref doc. No. under column set
Select value in reporting currency under columns.
Select left arrow (or) show selected field button
Select reference document number under column set
Select document number under columns
Select left arrow (or) show selected fields button
Select business transaction under column set
Select reference document number under column
Select left arrow (or) show selected fields button
Enter

15

Repost Co. line items (RKU3)


No FI document
Only Co. document

400100
400300

Dept A

Dept B

Dept C

200000
50000

75000

25000

Transfer document wise/line item wise


Report Co. line item: Accounting Controlling Cost centre accounting actual
postings report line items enter (T. Code KB61)
Select accounting document number: 33
Company code: AML
Fiscal year: 2006
Execute (F8)
Double click on 200000 (First line item)
New accounts assignment
Amount: 75000
Cost centre: B
Select next item button (Ctrl + F11)
Select next button
New account assignment
Amount: 25000
Cost centre: Dept C
Save
Go and see the cost centre report (KSB1)

16

Cost centre: dept A


Execute (F8)
To view cost element wise totals
Select cost element column
Select sub total button (Ctrl + Shift + F6)
Repost cost: (RK01)
Split department/wrong postings to cost centre
Transfer amount wise/cost element wise
No FI document only Co. document
25000 dept C No FI document
10000 Dept C Only Co document
Repost cost:
Path: Accounting Controlling Cost centre accounting Actual postings
Manual re postings of costs (T. Code: KB11N)
Ccts (old) Dept A
Cost element: 400100 (Salaries)
Amount: 25000
Ccts (New): Dept C
Ccts (old): Dept A
Cost element: 400300 (Rent)
Amount: 10000
Ccts (new): Dept C
Save

17

Planning cost centre wise:


Path: Accounting controlling cost centre accounting planning cost and
activity inputs change (T. Code KP06)
Version: 0
From period: 1
To period: 12
Fiscal year: 2006
Cost center group: AMLHIER
Select next page (or) page down button
Cost element: 400000 to 499999
Select form based radio button
Free centers to choose cost
element from drop down
menu and plan

Form based enter cost element list


is available on screen plan against
cost element

Select over view screen button (F5)


Cost element: 400100
Enter plan fixed cost: 600000
Distribution key: 0 (Equal distribution)
Select cost element: 400100
From menu go to period screen F6
Select back arrow
For cost element: 400300
Plan fixed cost: 540000
Distribution key: 1
To plan for department: B
Select combination button (Ctrl + F12)
To go to department: A
Select previous combination button (Ctrl + F1)
Select save button (or) (ctrl + s)
18

To view various reports cost centre wise accounting


Path: controlling cost centre accounting information system reports for cost
centre accounting plan/actual comparison cost centre actual/plan/variance (T. Code
S _ ALR _ 87013611)
Controlling area: AML
Fiscal year: 2006
From period: 7
To period: 7
Plan version: 0
Cost centre (or) values Dept A
Execute
To go to transactional level
Keep the cursor on salaries A/C and costs
Select call up report button (F7)
Double click on cost centre actual line items
Keep the cursor on first line item
Select document button
How to set up controlling area
Path: Accounting Controlling Cost centre accounting environment set
controlling area (T. Code OKKS)
Controlling area: AML
Period lock:
Path: Accounting Controlling Cost centre accounting environment period
lock change (T. Code OKP1)
Controlling area: AML1
Fiscal year: 2006

19

Selected button (FS)

FI

CO

a) Transaction
effect FI and CO (COIN)

b) Transaction
Affect only Co (RKU1/RKU3)
c) Transaction
effect only FI balance sheet

No

No

Keep the cursor on 01


Select lock period button (F5)
Save

20

Reconciliation Ledger
Reconciliation used when
When number of company codes having one controlling area 2nd scenario
It generates documents only in FI
It can be run at controlling area
AML controlling area
Company code
AML

Dept a

Dept B

Company code
ASL
Dept C

Dept X

Dept Y

If salaries paid and posted FI at (F 02)


Salaries A/C
100000
Out of 100000/- salaries 20000 belongs to company code ASL (Dept x) balance
80000/- belongs to company code AML
If we use the reconciliation account at cost centre level and the 20000/- is transferred to
company code ASL (Dept x) it passes the entry in Financial automatically
Here
Reports at No FI records
Co. area
In AML Books
ASL Dr
20000
To Salaries A/C
20000
In ASL Books
Salaries A/C Dr 20000
To AML A/C
20000

21

Dept Z

Customization at finance:
Copy company code AML customization including accounting to
Path: SPRO enterprises structure definition financial accounting edit, copy,
delete, check company code
Double click on copy, delete, check company code (T. Code EC01)
From the menu select organization object copy organization object
From company code: AML
To company code: ASL
Enter
Select yes for the message (For copy the G/L Accounts)
Select No button to allocate a different local currency
Ignore the message press enter
Select create request button
Short description, customization for Aravind Steels limited
Press enter
Enter once again to saving the request
Go on press enter till you got the message company code AML copied to ASL with out 75
number range objects.
Ignore the message press enter
Select back arrow
Double click on edit company code data
Select position button
Give the company code: ASL
Enter
Select company code: ASL
Select details button
Change the company name to: Aravind Steels limited
Save & Save in your request

22

Assign company code to company


Path: SPRO enterprises structure Assignment Financial Accounting Assign
Company code to company
For company code: ASL
Assign company AVG then select
Save button (or) (ctrl + s)
Save in your request
Document type SA should allow inter company posting
Use the transaction code: OBA7
Select position button
Document type: SA
Enter
Select the document type: SA
Select details button
Select inter company posting check box
Save
Creation of 2 G/L Accounts
AML Books
a) FI/CO reconciliation A/C
400150 A/C (Expenses A/C
with out cost element)

ASL Books
a) FI/CO reconciliation Accounts
( 400150)

b) ASL A/C 0 200160

b) AML A/C No: 200161

23

Use the transaction code:FS00


Give the G/L account No: 400150
Company code: AML
Select with template button
Give the G/L account: 400100 (salaries account)
Company code: AML
Enter
Change short & long text: FI/CO reconciliation account
Select create/bank/interest tab
Field status group: select ICCF (Co FI reconciliation posting)
Save
Give the G/L Account NO: 400150
Company code: ASL
Select with template button
Give the G/L account No: 400150
Company code: AML
Enter & save
G/L Account No: 200160
Company code: AML
Select with template button
Give the G/L account No: 200120 (Inventory raw material)
Company code: AML
Enter

24

Change short & long text to: Aravind steels limited


Select create/bank/interest tab
Field status group: G067
Save
G/L Account No: 200161
Company code: ASL
Select with template button
Give the G/L Account No: 200160
Company code: AML
Enter
Change the short text & long text to: Aravind mills limited
Save
Prepare cross company code transactions
SPRO financial accounting general ledger accounting business transaction
prepare cross company code transactions
FI Customization (T. Code OBYA)
Give the company code 1: AML
Company code 2: ASL
Enter
Posted in AML
Cleared against ASL
Debit posting key: 40
Account debit: 200160
Credit posting key: 50
Account credit: 200160

25

Company code: 2
Posted in: ASL
Cleared against: AML
Debit posting key: 40
Account debit: 200161
Credit posting key: 50
Account credit: 200161
Save (or) (ctrl + s)
Save in your request
Co. Customization:
Assign company code ASL to controlling area AML:
Use the transaction code: OKKP
Select controlling area: AML
Select details button
Company code to controlling area select cross company code cost accounting
Document type: SA
Save
Save in your request
Double click on assignment of company codes folder:
Select company code: AML
Select copy as button
Change the company code to: ASL
Enter & save

26

Define adjustment accounts for reconciliation posting:


Path: SPRO controlling cost element accounting reconciliation ledger define
adjustment accounts for reconciliation postings
Double click define accounts for automatic postings
From the menu select extras select controlling area
Give your controlling area: AML
Enter
Select change account determination button
Save
Give the account No: 400150 (FI/CO reconciliation account)
Save & save in your request
Specify document no. range for reconciliation posting:
Same path: (T. code: OK13)
Give the controlling area: AML
Select change intervals button
Select interval button
Give the No. range: 01
From No: 1 to 100000
Enter & save
Creation of cost centre (path: KS01)
Give the cost centre: Dept X
Valid from: 01.04.2006 to31.12.9999
Reference cost centre: dept A
Controlling area: AML

27

Enter
Change the name to dept X
Description, cost centre dept X
Person responsible: X
Company code: change to ASL
Save (or) (ctrl + s)
Ignore the message, press enter
Posting of salaries in company code AML (F -02)
Document date: 01.11.2006
Type: SA

Company code: AML

Posting key: 40

Account No: 400100 (Salaries)

Enter
Amount: 100000
Cost centre: Dept A
Text: salary payment
Posting key: 50
Account No: 200105 (SBI current account)
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & save

28

Go and see the G/L account: (FS10N)


Give the G/L account No: 400100 (Salaries)
Company code: AML
Fiscal year: 2006
Execute
Select back arrow
Give the company code: ASL
Execute
Go and see the cost centre report (KSB1)
Cost centre: Dept A to Dept C
Execute
Select back arrow
Give the cost centre: Dept x
Execute
Reposts costs: (KB11N)
Give the cost centre old: (Dept A)
Cost element: 400100 (Salaries)
Amount: 20000
Cost center new (Dept x)
Save
Go and see the G/L Account: (FS10N)
Give the G/L account No: 400100 (salaries)
Company code: AML

29

Fiscal year: 2006


Execute
Select back arrow
Give the company code: ASL
Execute
Go and see the cost centre report (KSB 1)
Cost centre: Dept A to Dept C
Execute
Select back arrow
Give the cost centre: Dept x
Execute
Reconciliation ledger run:
Path: accounting Controlling Cost element accounting Actual postings
Reconciliation with FI (T. code: KALC)
Select controlling area radio button
Give the controlling area: AML
Period: 8
Fiscal year: 2006
Deselect test run check box
Execute
Select reference document No: 1
Select back arrow
Select reference document No: 2

30

Cross company code postings in FI


If outstanding expenses paid by ASL on behalf of AML Entries
In AML

- Outstanding expenses A/C Dr


To ASL

In ASL Books -

AML Dr
To Bank

Use the transaction code: (F-02)


Give the document date: 01.11.2006
Type: SA
Company code: ASL
Posting key: 50
Account No: 200105 (SBI Current Account)
Enter
Give the amount: 5000
Business area: AMH
Text: Out standing expenses payment on behalf of AML
Posting key: 40
Account No: 100500 (Outstanding expenses)
New company code: AML
Enter
Amount: *
Business area: AMH
Text: +
Document Simulates & Save (or) (ctrl + s)

31

Double click on 3rd line item


Give the business area: AMH
Text: +
Select next item button
Business area: AMH
Text: +
Save (or) (ctrl + s)
Select continue button
Accrual orders: (Inputed cost calculations)
- This is used for month and provisions in Co
- It generates only document in CO
- Cost element category 03 Accrual/deferred per surcharge
- For irregular expenditure we use this accrual orders
If the provision made only in year end in FI records.
For the last month the cost of the product is high. Hence provision is made in Co regards
for every month to reduce the product cost
In this scenario
1st Scenario
30/11/06

Bonus A/C
Dr (Dept A)
To Outstanding A/C

01/12/06

Outstanding A/C
To Bonus A/C

Dr

2nd Scenario (open item management)


30/11/06

Bonus A/C
Dr (Dept A)
To Outstanding A/C
(Make entry every month)

3rd Scenario (Made provision for Bonus (in Co. Records)


Salaries A/C Dr
To 10% Bonus

100000 (Dept A)
10000

32

If bonus paid year ending


Bonus A/C
Dr (Dummy A/C)
To Outstanding expenses A/C

120000
120000

Creation of G/L account of bonus fund (FS00)


Give the G/L account No: 400110
Company code: AML
Select with template button
Give the G/L account No;: 400100 (Salaries A/C)
Company code: AML
Enter
Change short text & G/L account long text: Bonus account
Save
Select edit cost element button
Give valid from date: 01.04.2006 to 31.12.9999
Enter
Cost element category: select 3 (Accrual/deferred per surcharge)
Save (or) (ctrl + s)
Creation of dummy cost centre: (KS01)
Give the cost centre name: Depart W
Valid from 01.04.2006 to 31.12.9999
Give the reference cost centre: Dept A
Controlling area: AML
Enter

33

Change the name to: Dept W


Change the description: Cost cost centre dept W
Save (or) (ctrl + s)
Ignore the message, press enter
Maintain overhead structure:
SPRO controlling cost element accounting Accrual calculation percentage
method maintain overhead structure (T. Code: KSAZ)
Select create overhead structure button (F7)
Overhead structure: AML1
Description: Bonus calculation for AML
Select save button
Give the Row 10: Base: AML 1
Enter
Give the name: Salaries
Select create button
Row 20: overhead rate: AML2
Enter
Give the name: Bonus
Dependency: select KRS1 (Controlling Area)
Select create button
Give from to: 10 to 10
Credit: AML
Enter
Select create button

34

Save
Ignore the message, press enter
Keep the cursor on overhead structure: on AML1
Select assignments button
Give the controlling area: AML
Select: Actual accrual radio button
Select continue button
Valid from: 01 2006 valid to 12 2006
Overhead structure: AML1
Save
Double click on overhead structure on AML
Keep the cursor on actual accrual
From menu select environment Bases
Double click on AML1 (Salaries)
Give from cost element: 400100 (Salaries A/C)
Save
Select back arrow
Keep the cursor on actual accrual
From the menu select environment Overhead rates
Double click on AML2 (Bonus)
Valid from: 01 2006 valid to 12 2006
Actual overhead rate: 10%
Save

35

Select back arrow


Keep the cursor on actual accrual
From the menu select environment Credits
Double click on AML bonus
Company code: AML
Business area: AMH
Valid to 12 2006
Cost element: 400110
Cost centre: Dept W
Save
Assign Co. number range interval for the process (KAZI)
i.e. Actual cost centre accrual
Use the transaction code: KANK
Give the controlling area: AML
Select maintain groups button
Double click on KAZI
Select: Co document No. range interval for AML check box
From the menu select edit Assign element group
Save

36

Salaries posting in cost centre in dept B (F 02)


Give the document date: 03.11.2006
Type: SA
Company code: AML
Posting key: 40
Account No: 400100(Salaries A/C)
Enter
Give the amount: 100000
Cost centre: Dept B
Text: salaries posting
Posting key: 50
Account No: 200105 (SBI current A/C)
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & save
Accrual calculation
Accounting controlling cost element accounting Actual postings accrual
calculation (KSA3)
Select cost centre radio button
Give the cost centre: Dept B
Period: 8
Fiscal year: 2006

37

Deselect: test run check box


Select: Details list check box
Execute
Select next list level button
Go and see the cost centre report (KSB1)
Give the cost centre: Dept B
Execute
Select back arrow
Give the cost centre: Dept dummy
Execute
Bonus provision on 31.03.2007 (F -02)
Document date & posting date: 31.03.2007
Type: SA
Company code: AML
Posting key: 40
Account: 400110 (Bonus A/C)
Enter
Ignore the warning messages, press enter
Give the amount: 10000/Give the cost centre: dept dummy
Text: Bonus provision
Posting key: 50
Account No: 100500 (Outstanding expenses)

38

Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & save
Bonus in the cost centre report (KSB1)
Give the cost centre: Dept Dummy
Posting date: 01.04.2006 to 31.12.2007
Execute
Period and closing:
Service cost
Enter

Production cost
enter

While posting service cost, we dont know to which production centre it is


applied. Only month ending transfer cost from one cot centre to other cost centers.
Method: 1: (Here we transfer primary cost as well as secondary cost)
- Receiving cost centre can not track the original cost elements
- Co. document No. range intervals RKIU
Method: 2 (Distribution):
-

Transfer only primary cost


Receiving cost centre can track the original cost
element
Sender should be only cost centre
Co. document No. range interval RKIV

Method: 3 (Periodic posting):


-

Transfer only primary cost


Receiving cost centre can track original cost element
Sender can be any cost object Cost centre/orders
Co. document No. range intervals RKIB

39

Method: 4 (Indirect actual allocation):


-

Transfer quantities and values


Co. document member range intervals RKIL

Example:
Service dept: C
Salaries 100000
Wages - 200000
Rent 50000
---------350000

Dept A: 90% (315000)


Dept B: 10% (35000)

Cycle: If allocation of cost elements are in different ways. We have to create No. of
segments of No. of cycles.
If service dept:
Salaries 100000
Rent 20000

Production Dept
A
B
75%
25%

Here we have 2 methods:


1. One cycle No. of segments
XYZ

Seg1

Seg2

2nd Method:
XYZ

Seg1

XYZ

Seg2

Here to better follow 1st method because of you can make any no. of segments
automatically.
In second method we can create up to 10 methods.
Statistically key figures: (S. K. F)
- Statistical figures are used to allocation of costs from one cost centre to other costs
centers.

40

Example: No. of employees, sq. meter area etc.


- It can be fixed or total
- If you select category fixed, the values are common till the year end, if we dont change
in between No. of employees.
- If we select category of total, the values are to be entered each month Ex: No. of
electrical units consumed, no. of telephone calls.
- Here it generates co document (Number ranges for the process (RKS (Actual
statistical key figures)
Assessment:
Cost centre
Service Dept C

Production
Dept A

Production
Dept B

(Key Figure)
Salaries (No. of employees)
Rent (Percentage basis)
Creation of statistical key figure employee
Path: Accounting Controlling Cost centre accounting master data statistical
key figures individual processing create (KK01)
Give the statistical key figure: Emp
Enter
Give the name: Employee
Statistical figure unit measurement: Select PER (Persons)
Key figure category: select fixed values
Save
Assign Co No. range interval for the process of RKS (Use the Transaction code:
KANK)
Co. Area: AML
Select maintain groups button
Double click on the process RKS (Enter statistical figures)
Select Co. document No. range interval for AML check box
From the menu select edit Assign element group

41

Save (or) (ctrl + s)


Enter statistical key figures:
Path: Accounting controlling cost centre accounting actual postings
statistical key figures enter (KB31N)
Give the receiving cost centre: Dept A
Statistical key figure: Emp (Employee)
Give the total quantity: 75
Cost centre: Dept B
Statistical key figure: Emp
Total quantity: 25
Save
Note: enter the document date & posting date: 06.10.2006
Creation of secondary cost element
Path: Accounting Controlling Cost centre accounting master data cost
element individual processing create secondary (T. Code: KA06)
Give the cost element No: 1000000
Valid from: 01.04.2006 to 31.12.9999
Enter
Give the name: Assessment cost element
Description: Assessment cost element
Cost element category: select 42 (Assessment)
Save

42

Creation of assessment cycle


Path: Accounting controlling cost centre accounting period end closing
current settings define assessment (S _ALR _ 87005742)
Double click on create actual assessment
The final T. Code is (KSU1)
Cycle: AML1
Start date: 01.04.2006
Enter
Text: Cost allocation using assessment
Select: interactive check box
Purpose of interactive check box:
Example:
Service dept C (Rs. 100000):
It allocated to

Product A 80% - 80000


Prod Dept B 10% - 10000
Service Dept X 10% - 10000
(Here it will become 0 (Zero)
Service Dept X:
200000
10000 (From service dept C)
--------210000
It allocated to
Prod Dept H - 60% - 126000
Prod Dept I - 20% - 42000
Prod Dept C- 20% - 42000
+

42000/- allocated to service dept c will be again reallocate to various dept. up to it will
becomes zero (0)
If you select interactive check box it will allocate the costs up to zero
automatically.
Select save button (or) (ctrl + s)

43

Save in your request


Select attach segment button:
Give the segment name: segment 1
Name: salary allocation
Assessment cost element: select 1000000
Sender rule: selected posted amounts
Share in percentage: 100%
Select actual value origin radio button
Receiver rule: select variable portions
Variable portion type: select actual statistical key figures
Select senders/receivers tab
Sender cost centre: Dept X
Cost element: 400100 (salaries)
Receiver cost centre group: select AML prod
Select receiving tracing factor tab
Statistical key figure: Emp
Select receiver weighing factor tab
Save
Save in your request
Select attach segment button
Segment name: segment 2 (Rent allocation)
Assessment cost element: select 1000000
Sender rule: Posted amount
Sharing percentage: 1001

44

Select origin value radio button


Receiver rule: Fixed percentages
Select senders/receivers tab
Sender cost centre: Dept C
Cost element: 400300 (Rent)
Receiver cost centre group: AML Prod
Select receiver tracing factor tab
Statistical key figure: Dept A 40%
Dept B 60%
Save
Save in your request
Assign Co number range interval for the process (RKIU) (Use the transaction code
KANK)
Controlling area: AML
Select maintain groups button
Double click on RKIU (Actual overhead assessment)
Select Co. document number range intervals for AML check box
From the menu select edit Assign element group
Save (or) (ctrl + s)
Go and see the cost centre report (KSB1)
Give the cost centre: Dept C
Give the period: 01.10.2006 to 31.10.2006
Execute

45

Assessment Run:
Path: Accounting Controlling cost centre accounting period end closing
single functions allocations Assessment (KSU5)
Period: 7
Fiscal year: 2006
Deselect: Test run check box
Select the cycle: AML 1
Execute
Select receiver button
Go and see the cost centre report (KSB1)
Give the cost centre: Dept A
Posting date: 01.10.2006 to 31.10.2006
Execute
Internal orders:
Internal orders are used & decision making purpose
-

To view costs for a specific task


Vehicle wise costs/ - Based on petrol expenses & repair
and maintenance
Telephone wise costs/exhibition costs/production order
costs

-Orders are of 2 types


1. Real orders
2. Statistical orders
1. Real orders:
- Settlement possible
- Settlement possible in cost centre,
G/L Account & Asset

2. Statistical orders:
- Not possible
- Only for information/decision making

- Settlement to cost centre Internal settlement (With in Co)

46

- Settlement to G/L account External settlement


STATISTICAL ORDERS:
Example: Telephone orders:
FI posting G/L account no 100000
Cost centre administration 100000
Order Telephone 100000
(We did not allocate the total amount to cost centre. Only 100000 is allocated
because one is real and another is statistical)
a) When we post to 2 cost objects only. One object will be real and others will be
statistical.
b) At the time of creation of order, there is a check box for statistical order.
a) Select statistical order check box

Order
Statistical

b) Deselect statistical order check box

Real

Cost centre
Real
Statistical

In the month ending cost centers cost will be apportioned to product.


i. Real Orders:
Vehicle orders:

(Allocation from order to cost centre)

Order Red
FI posting G/L Account
Petrol expenses
Order Vehicle No: 1234
Settlement: It allocated to Dept A, Dept B & Dept C.
(Allocation may be percentage/ratio/amount basis)
ii. Statistical order (allocation from cost centre to cost centers)
FI posting G/L account
-

Cost centre: Administration (Red)


Order vehicle 1234 statistical
Cost centre admin: Dept A, Dept B & Dept C
(Assessment)

47

1st Scenario (Statistical orders)


Define order type:
SPRO Controlling Internal orders order master data define order types (T.
Code: K0T2 _ FUNCAREA)
Select new entries button
Order category: 01 (Internal order (Controlling))
Enter
Give the order type: AMLT
Description: Telephone orders for AML
Planning profile: 000001 (General budget/plan profile)
Object class: Select overhead costs
Select release immediately check box
Save
It gives the message No. range not processed
Ignore the message, press enter
Save in your request
Select Assign/change intervals button beside No. range intervals
Double click on AMLT
Select Motor pool A ZZZZZZZZZZZZ (External check box)
From the menu select edit Assign element group
Save (or) (ctrl + s)

48

Creation of field status group making cost centre and internal order mandatory:
(T. code: OBC4)
Select field status variant (AML)
Double click on field status groups folder
Select G004 cost Accounts
Select copy as button
Change the field status group to G002
Change text to: Cost Accounts (CC & IO) required
CC. cost centre & IO (Internal order)
Enter & Save
Save in your request
Select G002 and double click
Double click on additional account assignments
Select CO/PP order: required entry field
Save
Creation of G/L Account Telephone expenses: (FS00)
Give the G/L Account No: 400305
Company code: AML
Select with template button
Give the G/L Account No: 400300 (Rent A/C)
Company code: AML
Enter
Change the short text & long text to telephone expenses

49

Select create/bank/interest tab


Change the field status group to: G002
Save
Select edit cost element button
Valid from 01.04.2006 to 31.12.9999
Enter
Cost element category: 1
Save
Creation of Internal order:
Path: Accounting Controlling Internal orders master data Special functions
order Create (KO01)
Give the order type: AMLT
Enter
Order: TEL 66626246 (Telephone No)
Short text: Telephone No: 66626246
Company code: AML
Business area: AMH
Select control data tab
Select statistical order check box
Save
One more order type: AMLT
Enter
Give the order: TEL 66626247
Company code: AML
Business area: AMH
Select control data tab
Select statistical order check box

50

Save
Creation of order group:
Path: Accounting Controlling Internal orders Master data Order group
create (KOH1)
Give the order group name: AML HYD TEL
Enter
Give the description: Hyderabad Telephones for AML
Select insert order button
Select: TEL 66626246 & TEL 66626247
Save
Posting of transaction in FI: (F 02)
Give the document date: 13.11.2006
Type: SA
Company code: AML
Posting key: 40
Account No: 400305 (Telephone expenses)
Enter
Give the amount: 25000
Select cost centre: Dept A
Give the order No: TEL 66626246
Text telephone expenses
Posting key: 50
Account No: 200105 (SBI Current Account)
Enter
Amount: *
Business area: AMH
Text: +

51

Document Simulate & Save


To view order wise report:
Accounting Controlling Internal orders information system Reports for
Internal orders line items Orders: Actual time items (KOB1)
Give the order No: TEL 66626246
Execute
Select the line items
Select document button
Planning order wise:
Accounting Controlling Internal orders Planning Cost and activity inputs
Change (KPF6)
Give the version: 0
From period: 8
To period: 8
Fiscal year: 2006
Order: TEL 66626246
Cost element: 400305 (Telephone expenses)
Select from based radio button
Select overview screen button
Total plan cost: Enter20000
Save (or) (Ctrl + s)

52

To variance report order wise:


Path: Accounting Controlling Internal orders Information systems Reports
for internal orders Plan/actual comparisons orders: Actual/plan/variance
(S _ ALR _ 87012993)
Give the controlling area: AML
Fiscal year: 2006
From period: 8
To period: 8
Plan version: 0
Give the order value: TEL 66626246
Execute
Real orders:
Creation of secondary cost element called settlement cost element (T. Code: KA06)
Give the cost element: 1000001
Valid from: 01.04.2006 to 31.12.9999
Enter
Give the name: Settlement cost element
Give the description: settlement cost element
Cost element category: select 21 (Internal Settlement)
Save

53

Creation of field status group making order required


Use the transaction code: OBC4
Select field status variant: AML
Double click on field status groups button
Select G002 (Cost Account CC & IO required)
Select copy as button
Change the field status group to: G010
Change the text: cost accounts IO required
Enter & Save
Save in your request
Select G010 and double click
Double click on additional account assignments
Cost centre: make it optional entry
Save
Creation of G/L Account: Petrol expenses (FS00)
Give the G/L Account No: 400306
Company code: AML
Select with template button
Give the G/L Account No: 400300
Company code: AML
Enter
Change short text & Long text to: Petrol expenses
Select: Create/bank/interest tab
Field status group: Select G010
Save
Select edit cost element button
Enter
Cost element category: 1

54

Save
Maintain allocation structures:
Path: SPRO Controlling Internal orders Actual postings settlement
Maintain allocation structures.
Select new entries button
Allocation structure: A5
Text: Co allocation structure for AML
Save, save in your request
Select: A5
Double click on assignments folder
Select: New entries button
Give the assignment: AML
Text: Vehicle order settlement
Save
Select: AML
Double click on source folder
From cost element: 400306
Save
Double click on settlement cost elements folder
Select new entries button
Receiver new entries button
Receiver category: Select CTR (Cost centre)
Settlement cost element: Select 1000001
Save

55

Maintain settlement profiles:


Same path
Double click on maintain settlement profiles
Select: New entries button
Give the settlement profile name: AML
Description: settlement profile for AML
Select: To be settled in full radio button
Allocation structure: A5
Default object type: CTR (Cost centre)
Select: % settlement check box
Select: equalance No. check box
Select: Amount settlement check box
Under valid receivers
For cost centre: Select settlement required
Max No. of dist trials: 999
Residence time: 12
Save & Save in your request
Maintain number ranges for settlement documents
Same path: (T. Code: SNUM)
Select maintain groups button
Double click on AML
Select standard accounting document check box
From the menu select edit Assign element group

56

Save (or) (ctrl + s)


Define order type: (T. code: KOT2 _ FUNCAREA)
Select new entries button
Order category: select 01 (Internal order controlling)
Enter
Give the order type: AMLV (Vehicle order type for AML)
Settlement profile: Select AML
Budget profile: 000001 (General budget profile)
Object class: Select over head costs
Select release immediately check box
Save (or) (ctrl + s)
It gives the message No. range not processed
Ignore the message, press enter
Save in your request
Select Assign/change intervals button
Double click on AMLV
Select Motor pool A ZZZZZZZZZZZZ check box
From the menu select edit Assign element group
Save (or) (ctrl + s)
Assign Co. number range interval for the process KOAO (Actual settlement)
Use the T. Code: KANK)
Give the controlling area: AML
Select maintain groups button
Double click on KOAO (Actual settlement)
Select Co. document No. range intervals for AML check box
From the menu select edit Assign element group

57

Save
Creation of vehicle order: (T. Code KOO1)
Give the order type: AMLV
Enter
Give the order: AP9A1234
Short text: Vehicle No: AP9A1234
Give the company code: AML
Business area: AMH
Select control data tab
Deselect statistical order check box
Select settlement rule button
Category: Select CTR (Cost centre)
Settlement receiver: Dept A Percentage: 70%
Category: CTR (Cost centre)
Settlement receiver: Dept B Percentage: 30%
Save
Ignore the warning message, press enter
Posting of transaction in FI (F 02)
Give the document date: 15.11.2006
Type: SA
Company code: AML
Posting key: 40
Give the G/L Account No: 400306 (Petrol expenses)
Enter

58

Give the amount: 100000


Give the order: AP9A1234
Text: Petrol expenses
Posting key: 50
Account No: 200105 (SBI current account)
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & Save
Settlement of internal order to cost centers:
Path: Accounting Controlling Internal orders period end closing Single
functions Settlement Individual processing (K088)
Give the order No: AP9A1234
Settlement period: 8
Fiscal year: 2006
Deselect test run check box
Select check transaction data check box
Execute
Select details list button

59

Budgeting and availability control


SAP given 2 types of Budget
Plan
1. Plan period wise

Budget
1. Budget for year wise

2. We can plan each element


wise
3. Micro level

2. Budget for the whole order


3. Macro level
4. Called availability control

When you posting actual


1. If the budget cross more than 90% of budget
a. It gives warning message (or)
b. It gives warning message and inform to budget lead (or)
c. Give error message
Number range interval: 04 (Hot coded)
Number range is at client level (Client wise)
Define number range intervals for budgeting
SPRO Controlling Internal orders Budgeting & Availability control Maintain
No. ranges for budgeting (T. Code: OK11)
Select change intervals button
Select intervals button: No: 04
From: 4000000000 to 4999999999
Enter
Define tolerance limits for availability control
Same path
Select new entries button
Give the controlling area: AML

60

Profile: 000001 (General budget profile)


Transaction group: Select ++ (All activity groups)
Action: select 2 (warning with maid to person responsible)
Give the usage: 90%
Save (or) (ctrl + s)
Save in your request
Specify exempt cost element from availability control
(Exempted cost elements from budget)
Same path:
Select new entries button
Give the controlling area: AML
Give the C/C No: 400100 (Salaries A/C)
Save in your request
Maintain budget manager
Same path:
Select new entries button
Give the controlling area: AML
Order type: AMLV
Object class: Select OCOST (over head)
Give the user ID: SAPUSER
Save (or) (ctrl + s)
Save in your request

61

Budgeting:
Accounting Controlling Internal orders Budgeting Original budget
Change (KO22)
Give the order No: AP9A1234
Select original budget button
Give the budget amount: 200000
Enter
From the menu select extras Availability control Activate
Save
Posting of Transaction in FI (F 02)
Give the document date: 15.11.2006
Type: SA
Company code: AML
Posting key: 40
Give the A/C No: 400306 (petrol expenses)
Enter
Give the amount: 90000
Give the order No: AP9A1234
Text: Petrol expenses
Posting key: 50
Account No: 200105
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & Save

62

Ignore the message, press enter


To view the inbox of the budget head
SAP menu Office Work place (T. code SBWP)
Select inbox folder
Double click on the message
It gives the message
Capital work in progress line item settlement CWIP _ M/L
Freight charges
Installation charges
Define settlement profile
SPRO Financial accounting Asset accounting Transactions Capitalization of
assets under construction define/assign settlement profile
Double click on define settlement profile
The transaction code is (OK07)
Select settlement profile A1 (settlement assets under construction)
Select details button
Select to be settled in full radio button
Allocation stock: A1 Co. allocation structure
Default object type asset type: FXA
Select percentage settlement check box
Select equalance Nos check box
Select amount settlement check box
Under valued receivers for fixed assets
Select settlement required
Document type: AA

63

Max No. of distribution rules: 999


Residence time: 12
Save
Select back arrow 2 times
Double click of assign settlement profile to company code
Select for company code: AML assign settlement profile A1
Enter & Save
Save in your request
Creation of capital work in progress (Asset master) (T. Code: AS01)
Give asset class: AML 4000 (Capital work in progress)
Company code: AML
Enter
Description: C. W. P general
Capitalization: 15.06.2006
Select time dependant tab
Business area: AMH
Select depreciation area tab
Dep. Key: 0000
Save

64

Machinery purchase postings: (T. Code (F 90)


Give document date: 01.08.2006
Posting date: 01.08.2006
Type: KR
Company code: AML
Posting key: 31
Vendor No: 8700001
Enter
Ignore the warning message, press enter
Give the amount: 200000
Business area: AMH
Text: Machinery purchase posting
Posting key: 70
Account No: 500000 0
Transaction type: 100
Enter
Remove TDS codes
Enter
Amount: *
Text: +
Document Simulate & save

65

Fright payment: (F -02)


Document date: 10.09.2006
Posting date: 10.09.2006
Type: SA
Company code: AML
Posting key: 70
Account: 500001 0
Transaction type: 100
Enter
Ignore the warning message, press enter
Give amount: 25000
Text: Fright payment
Posting key: 50
A/C No: 200105 (SBI Current A/C)
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & save

66

Creation of machinery asset master (AS01)


Give asset class: AML 2000(Dept A)
Company code: AML
Enter
Give description: Machine No: 40
Capitalized on: 14.11.2006
Select time depended tab
Business area: AMH
Select description area tab
Give description key: AML1
Useful life: 20 years
Period: 4
Ordinary depreciation start: 17.11.2006
Save
Settlement of capital work in progress to Asset
Path: Accounting Financial accounting Fixed assets Capitalized asset under
construction Distribute (T. Code: AIAB)
Give company code: AML
Asset: 500001
Sub no: 0 Execute
From the menu select edit Select Select all
Select enter button
Category select: FXA Asset

67

Settlement receiver: 200004 0


Give percentage: 100
Select back arrow
Save
Select settlement button
Give the asset value dated: 17.11.2006
Text: asset settlement
Deselect test run check box
Execute
Go and see the document FB03
Enter
Profit Centre Accounting
- To view profitability product group wise/product wise/location wise/
If business area is not used in FI
1) One location No. of product groups
|
Cement

Hyderabad
|
Steels

|
Pharma

In that case you can get profitability.


2) Each location different product group
Hyderabad

Cement

Bangalore

Steel

Mumbai

Pharma

Profitability as well as balance sheet


The advantage of profit centre will be derived through derivation rules.
Example: expenditure Through cost centers

68

Revenues Automatic account assignment


In case of balance sheet items through business area
We have to create a dummy profit centre
-

Transfer to respective profit centre


We create derivation rules. Future transaction will not
go to dummy profit centre.

Set controlling area:


SPRO Controlling Profit centre accounting Basic settings Set Controlling
area
Give controlling area: AML
Enter
Maintain controlling area settings:
SPRO Controlling Profit centre accounting Basic settings controlling area
settings maintain controlling area settings (T. code: OKE5)
Standard hierarchy: AML
Select elimination of internal business volume check box
Profit centre local currency type
Select 20 (i.e. controlling area currency)
Select confirm button
Select store transactions currency check box
Save
Creation of dummy profit centre:
Path: SPRO controlling Profit centre accounting Master data Profit centre
create dummy profit centre (T. code: KE59)
Double click on create dummy profit centre
Give dummy profit centre: AML dummy

69

Select basic data button


Give the name: AML dummy
Description: Dummy profit centre for AML
Profit centre group: AML
Save
Set control parameters for actual data
Path: SPRO Controlling Profit centre accounting Basic settings controlling
area settings Activate direct postings set control parameters for Actual data
(T. Code: 1KEE)
Select new entries button
From year: 2006
Select line item check box
Select on line transfer check box
Save
Maintain plan versions
Path: SPRO Controlling Profit centre accounting basic settings controlling
area settings activate direct postings plan versions maintain plan versions
Select version: 0
Double click on settings for profit centre A/C folder
Select new entries button
Year: 2006
Select on line transfer check box
Select line item check box
ER (Exchange rate): Type: B (Bank setting)
Select save button

70

Save in your request


Define number ranges for local documents
Path: SPRO Controlling Profit centre accounting actual postings Basic
setting actual define number ranges for local documents (T. Code GB02)
Select maintain groups button
Select actual document from direct posting with GB01 check box
From the menu select intervals maintain
Give your company code: AML
Enter
Select interval button
Year: 2006
From No: 1 to 100000
Enter & Save
Select back arrow
Select planned document from direct posting with GB01 check box
From menu select interval maintain
Give your company code: AML
Enter
Select interval button
Year: 2006
From: 100001 to 200000
Enter & Save

71

Creation profit centre:


Path: Accounting Controlling Profit centre accounting Master data profit
centre individual processing create KE51
Give the profit centre: Cement
Select master data button
Analysis period 01.04.2006 to 31.12.9999
Give the name: Cement
Long text: Profit centre cement
Person response: A
Profit centre group: AML
Select activate button
Profit centre: STEEL
Select master data button
Name: Steel
Long text: profit centre steel
Person response: B
Profit centre group: AML
Select activate button
Assign profit centre in cost centre
Accounting Controlling Cost centre accounting Master data cost centre
Individual processing change (T. code: KS02)
Give the cost centre: Dept A
Enter
Assign the profit centre: Cement

72

Select save button


Ignore the warning message, press enter
Cost centre: Dept B
Enter
Give profit centre: Steel
Select save button
Ignore the warning message, press enter
Creation of revenue element (FS00)
G/L account No: 300000 (Sales account0
Company code: AML
Enter
Select edit cost element button
Enter
Cost element category: Select 11 (Revenues)
Save
Maintain automatic account assignment of revenue elements
Path: SPRO Controlling Profit centre accounting Actual postings Maintain
automatic assignment of revenue elements (T. Code: OKB9)
Select new entries button
Give the company code: AML
Cost element: 300000
Account assignment detail
Select business area is mandatory
Save, Save in your request

73

Select AML and then double click on detail per business area/select new entries button
(1)
Hyderabad
|
|
|
Cement
Steel
Pharma
300000 Sales cement
Hyd Cement
300001 Sales steels
Hyd Steels
300002 Sales Pharma
Hyd Pharma
(2)

Hyderabad

Cement

Bangalore

Steel

Mumbai

Pharma

300000 Sales
Hyderabad - cement
Bangalore Steel
Mumbai Pharma
Give the business area: AMH
Give the profit centre: Cement
Give the business area: AMB
Give the profit centre: Steel
Save
Choose additional balance sheet & Profit & Loss A/C
It is applicable only second scenario
Path: Same path
Select choose accounts
Transaction code: 3KEH
Select new entries button

74

Account from: 100000 to 299999


Default profit centre: Cement
Save & Save in your request
Select profit centre detail button
Select create step button
Give the step description: Profit centre derivation for item through Business area
Under define name: GSBER (Business area)
Save
Select maintain rule values button
Select source field interval on/off button
Note down A/C No: 100000 to A/C No: 299999
Business area: AMH
Give the up due profit centre: Cement
From A/C: 100000 to A/c: 299999
Business area: AMB
Profit centre: Steel
Creation of Accounts group
Path: Accounting Controlling Profit centre accounting Master data Account
group Create (T. Code KDH1)
Give the account group: PL items
Enter
Profit & Loss account for AML
Select insert accounts button
Give account 300000 499999
Save

75

Select back arrow


Next A/C group: BS items
Enter
Give the description: Balance sheet account for AML
Select insert account button
Give the range 100000 to 299999
Save
Planning profit centre wise for P&L items
Path: Accounting Controlling Profit centre Accounting planning
Cost/revenues Change (T. Code 7KE1)
Version: 0
From period: 8 to period: 8
Fiscal year: 2006
Company code: AML
Profit centre: Cement
Account group: PL items
Select from based radio button
Select overview screen button
For A/C No: 300000(Sales)
Profit centre reporting currency: 500000
For A/C No: 400100 (salaries)
Profit centre reporting currency: 400000
Save

76

Planning for Balance sheet Accounts profit centre wise


Path: Accounting Controlling Profit centre accounting Planning Balance
sheets accounts change (T. code: 7KE3)
Version: 0
From period: 8 to period: 8
Fiscal year: 2006
Company code: AML
Profit centre: Cement
A/C group: BS items
Select from based radio button
Select overview screen button
For A/C No: 100300 (SBI rupee term loan)
Plan: 100000
For account No: 200105
Plan: 100000
Save
Credit sales posting in FI (F 22)
Give document date: 20.11.2006
Type: DR
Company code: AML
Posting key: 01
Account No: 6200001
Enter

77

Give the amount: 450000


Business area: AMH
Text: Credit sales postings
Posting key: 50
Account No: 300000(Sales A/C)
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate
Ignore the warning message, press enter
Save (or) ctrl+s
Expenditure posting (F 02)
Document date: 20.11.2006
Document type: SA
Posting key: 40
Account No: 400100 (salaries A/C)
Enter
Give amount: 425000
Cost centre: Dept A
Text: Salary payment
Posting key: 50
Account No: 200105 (SBI Current account)
Enter
Amount: *
Business area: AMH
Text: +
Document Simulate & save

78

To view various reports profit centre wise for P&L items


Path: Accounting Controlling Profit centre accounting Information system
Reports for profit centre accounting Interactive reporting Profit centre group
plan/actual/variance
Transaction code: S _ ALR _ 87013326
From period: 8 to period: 8
Fiscal year: 2006
Plan version: 0
Profit centre values: Cement
Profit & Loss account group: PL items
Execute
To view variance report profit centre wise for Balance sheet accounts
Path: Same path
Transaction code: S _ ALR _ 87013336
From period: 8 to period: 8
Fiscal year: 2006
Plan version: 0
Profit centre values: Cement
Balance sheet account group: BS items
Execute

79

Transfer values from one profit centre to another profit centre


Path: Accounting Controlling Profit centre accounting Actual posting Profit
centre document enter (T. Code: 9KE0)
Select layout: 8A 001
Execute
Give the company code: AML
Select entry screen button
Give profit centre: Cement
Account No: 400100 (salaries A/C)
In profit centre local currency: 200000
Save

80

Integration
Organization structure
Company

In SD: combination of sales organization, distribution channel & division they call at as
one sales area.
Movement types: Posting keys in FI
101 Material receipt against purchase order/production
102 Reversal of 101
201 Issue to cost centre (stores of all departments)
202 Reversal of 201
261 Issue to orders (Raw material shows)
262 Reversal of 261
521 Material receipt with out production order
522 Reversal of 521
561 Opening stock taking

81

562 Reversal of 561


601 Delivery
602 Reversal of 601
Process key (Transaction key)
These are system defined keys
1) BSX Inventory postings
2) WRX GR/IR clearing (G.R Goods receipts)
(I.R Invoice receipts)
3) PRD Price difference/production order differences
4) GBB Offsetting entry for inventory posting
a) VBR consumption
b) VNG Scrapping
c) BSA Opening stocks taking
d) SUF Production receipt against production order
e) ZOF Production receipt with out production order
f) VAY Delivery where sales account is a revenue element
g) VAY - Delivery where sales account is not a revenue account
h) AUA Production order differences
GBBVBR Raw material consumption A/C Dr
BSX To Inventors raw material local A/C
Valuation class:
- Valuation class determines the G/L accounts to be posted automatically.
a) Raw material: 4 valuation classes
Local
- Imported
- Inter unit
- Inter company
b) Stores: 2 valuation classes
- Local
- Imported
b) Finished goods: 1 valuation class -Own goods

82

Valuation grouping code/valuation modification key/ valuation modifier

Chart of Accounts: AML

AML

Hyd

Bangalore

Rm1

Valuation area
(plant)

ASL

Hyd

Mumbai

Rm2

Hyderabad
Bangalore
Bangalore

Bangalore

Rm3

Bangalore

Rm1

Rm4

Chart of accounts

ALL

Company Code

AML
AML
AML

Mumbai

Rm2

Rm3

Valuation group
code

AML
AML
AML

X
X
X

Advantage is we need not create valuation group code each company code wise.
Material types

Price control

Purchase price

1. Raw material ROH V Moving average price - Available


2. Stores & Spares FRSA - V - Moving average price - Available
3. Packing material VERP - V - Moving average price - Available
4. Finished goods FERT S Standard price Raw material + overheads
5. Semi finished goods:
Purchased HALB - V Moving average price - Available
Produces HALB S Standard price
- Raw material + overheads
6. Traded goods HAWA -

V Moving average price

7. Services DIEN

83

Material types similar to account groups in G/L


In M.M we create material mater
-

Material master is to be created under material type


Material master to be created at plant level
When no. of plants are using same material it will be
extended to other plants
Material periods we can open 2 periods at a time
In G/L it is called as tabs, where as in MM it is called

Basic data
Purchase data
Sales data
MRP data
MRP data
Ware house
Quality
Accounting
Costing

No. of views like:

Why systems support inventory account, not purchase account:


Purchase order
Price 10
Qty 5
Taxes 8% Cenvat
4% VAT
Other expenses 2%
In normal accounting system
RM 1

If other expenses not taken

Opening stock
Add: Purchases

0
63
------63
Less: Closing stock 10

84

Consumption

-----X_

If invoice is not taken (Only Delivery challan copy is taken)


Opening stock 0
Purchases
----0
Closing stock 20
-----Consumption _X_

In SAP
Opening stock - 0
Purchases 5
-63
Consumption 3 37
-----Closing stock 2 26
(Here the price of the goods is taken from purchase order).
MM flow (Material management flow)
1. Material requisition: Production dept to stores called internals
If the material not available, stores department raised.
2. Purchase requisition stores to purchase dept
3. Purchase dept call for enquiry, quotations & price comparisons
4. Raising the purchase order by purchase dept
Purchase order contains Vendor, Material, plant, quality, rate, delivery terms
and payment terms
5. Release procedure Work flow
Up to 10000 Manager Purchases
6. Goods receipt (G.R)
G.R should be against purchase
Inventory Raw material local Dr Balance sheet current asset BSX
To GR/IR clearing raw material local Balance sheet current Liabilities WRX
7. Invoice verification Verification against GR (or)/Purchase orders

85

GR/IR clearing Raw material Dr Balance current Liabilities WRX


To party Sundry creditors Balance sheet current liabilities Feam po
8. Consumption:
Raw material consumption local Dr P&L debit GBBVBR
To Inventory raw material local B/S current assets - BSX
9. Wages payment:
Wages A/C Dr
To Bank A/C
10. Production receipt:
Inventory finished goods (At product cost) Dr Balance sheet current assets BSX
Increase/decreased stock finished goods P/L A/C credit GBBAUF (Production order)
GBBZOF (NO production order)

11. Delivery:
Increase/decrease in stock finished goods P&L credit: GBBVAY sales (At product)
GBBVAX Sales not revenue account
To Inventory finished goods Balance sheet current asset BSX
12. Sales billing:
Customer A/C Dr Sundry debtors Balance sheet current Asset From sale order
To sales P&L A/C credit ERL
Profit & Loss A/c
(8) Raw material
consumption
(9) Wages
Surplus in Profit & Loss

(10) Increase/decrease
100 in finished goods
10

(11) Increase/decrease
in finished goods

110
110 0

40
(12) Sales
150

150
150

86

Balance Sheet
(6) GR/IR

100

(6) Inventory Raw


material

(7) GR/IR

100

100

(7) Sundry Creditors

(8) Inventory Raw


100 material

100

Surplus in P&L A/C

40

(9) Bank
(10) Inventory finished
goods
11) Inventory finished
goods
(12) Sundry debtors

0
-10

110
110

140

0
150

140

Integration is based on 3 rules:


1. In material master we specially valuation class
2. For valuation class we assign G/L accounts based on the nature of
transaction.
3. Stores person when he received (or) issues material he will enter
movement type, material number and quantity. Accounts will be
updated automatically based on account assignment to valuation class
which is specified in material master.

Material
No

Valuation
class

RM1

3000 RM
local

RM2

3001 RM
Imported

Inventory
Postings
(BSX)
200121
(Inventory
R.M.
local)

GR/IR
clearing
(WBX)
150000
(GR/IR
clearing RM
local

Consumption
GBRVBR

200122
(Inv. RM
imported)

150001
(GR/IR
clearing RM
Imported)

400001 (Imp. Material


consumption)

87

400000 (Raw material


consumption)

Example:
Po1

Po1

Move type 101

Raw material 1

Material No RM1

Qty: 100

Qty: 20 Kgs

Rate 5

Save

Vendor 1234

Movement type 101 Debit BSX 200121 Inventory raw materials Qty in GRX
Rate as per PO = 100
Credit WRX 150000 GR/IR clearing.
1st rule:
In material master we specify valuation class:
Here RM1 & RM2 (Material master) is specify the valuation
Class 3000 RM local & 3001 RM imported respectively.
(2) For valuation class we assign G/L accounts based on the nature of transaction.
Here valuation class (3000 RM local & 3001 RM Imported)
Assign G/L accounts Inv. Postings (BSX) ( 200121 Inventory raw material local, 20012
Inv. Raw material imported), GR/IR clearing. WRX (150000 GR/IR clearing),
150001 (GR/IR clearing raw material imported)

Price differences

Batch
Stocks fully available

Moving average

Stocks partly available

88

Stocks not available

Batch mode:
Batch:
1
2

Qty

Rate

Amount

100
200
------300
10

10
40

1000
8000
-------9000
100
------8900
+ 180
-------9080
--------

10

Receipt:
a) Inv. Raw material local A/C
Dr
1000 BSX
To GR/IR clearing raw material local
1000 WRX
Consumption:
b) Raw material consumption local Dr
To Raw material local
Price difference:

100 GBBVBR
100 BSX

Inv. Verification
GR/IR clearing raw material 1000
Inv. Raw material local
200
To party

Moving average:
Stock partly available
Qty
100
200
----300
Consumption 280
----20
Price difference
-----

Rate

Amount

10
40
----30
30

1000
8000
-------9000
8400
-------600
40
-------

89

1200

20
-----a) Receipt:

640
--------

Inv. Raw material local Dr 1000 BSX


To GR/IR clearing raw material 1000 WRX
b) Consumption:
Raw material consumption local Dr 8400 GBBVBR
To Inv. Raw material
8400 BSX
c) Inv. Verification:
GR/IR clearing raw material local
Price difference raw material
Inv. Raw material
To party

1000 WRX
160 Prd
40 (20*2) BSX
1200 (from P.O)

The difference between batch method and moving average method


In batch method it checks with material No and Batch Number only.
Moving average
Qty
100
200
-----300
Consumption 300

Stocks not available


Rate
Amount
10
1000
40
8000
----------30
9000
30
9000

a) Receipt:
Inv. Raw material load Dr 1000 BSX
To GR/IR clearing raw material 1000 WRX
b) Consumption:
Raw material consumption local Dr 9000 GBBVBR
To Inv. Raw material
9000 BSX
c) Inv. Verification:
GR/IR clearing raw material 1000 WRX
Price difference raw material 2000 PRD
To party

90

SD to FI
1. Enquiry and quotation
2. Sale order: Material, qty, plant, sales organization, rate, delivery terms,
payment.
3. delivery:
With out post goods issue (With out PGI) No transfer of ownership
With post goods issue (With PGI) Transfer of ownership
FOB(Free on Board):
Example:
Plant

Hyd

Port

Chennai

Customer

Delivery without PGI

Delivery with PGI

Only material
No FI document

Material document
FI document

Inv/Dec in stock finished goods Dr GBBVAY (Sales revenue element)


GBBVAX (Sales not revenue element)
To Inventory finished goods BSX
a) Billing: Billing should be with reference to delivery
Billing: In SD module there is a pricing procedure
Procedure:
i) From region Andhra Pradesh
To region - Andhra Pradesh
Customer - Taxable
Material
- Tax
Billing
Basic XXX
Excise XXX
VAT XXX
-------91

Bill amount

XXX

ii) From Region Andhra Pradesh


To Region Andhra Pradesh
Customer Non taxable
Material Non taxable
Here in this case the buyer is purchasing in local state and same is exported under
Form H
Billing is
Basic XXX
-------Bill amount XXX
iii) From region Andhra Pradesh
To Region Andhra Pradesh
Customer Taxable
Material Taxable
Billing is
Basic XXX
Excise XXX
CST XXX
-------Bill amount XXX_
iv) From Region Andhra Pradesh
To Region India
Customer Non taxable
Material Non taxable
Billing
Basic XXX
-------Bill amount XXX
Condition type: KOFI

92

Assignment of Accounts:
(1)
(2)
(3)
(4)
(5)
Application Condition Chart of Sales Account
area
type
accounts org
assignment
group for
customer
V Sales
&
distribution

KOFI

KOFI

AML
Hyd

01

AML

Hyd

01

KOFI

AML

Hyd

01

KOFI

AML

Hyd

01

(5)

Account assignment group for Customer

(6)

01 Domestic revenues
02 Foreign revenues
03 Affiliated company revenue
Account asset group for material

(7)

01 Trade goods
02 Services
03 Finished goods
Accounts key:
ERL Sales revenue
ERF Freight revenue

93

(6)
(7)
(8)
Account Accounts G/L
assets
key
accounts
group
for
materials
03
300001ERL
Sales
local
own
goods
01
ERL
300002
Sales
local
taxed
goods
03
ERF
400320

Freight
local
own
good
01
ERF
400321

Freight
local
traded
goods

ERB Rebate (Trade discount)


ERS Sales deduction (Commissions)

MM Integration step
1. Define plant
Path: SPRO Enterprises structure definition logistics general define,
copy, delete, check plant
Double click on define plant
Select new entries button
Give plant: AMLP
Assign factory calendar: A2 (AML Hyderabad factory calendar)
Save
Give the name: AML Hyderabad factory plant
Give the country: IN (India)
Enter
Select create request button
Give the short description: MM Customization for AML
Enter
Press enter to save in your request
Define copy, delete, check division:
Path: same path
Select define, copy, delete, check division
Double click on define division
Select new entries button
Division A1 Name: Cement division
Save

94

Save in your request


Maintain storage location:
Path: SPRO enterprises structure Definition Materials management
Maintain storage location
Give the plant: AMLP
Enter
Select new entries button
Give the storage location: Hyd
Give the description: Hyderabad storage location
Save
Save in your request
Maintain purchasing organization:
Path: same path
Select new entries button
Give the purchase organization: AMLR: Raw Material of purchase order
Save
Save in your request
Assign plant to company code:
Path: SPRO enterprises structure assignment Logistics general assign
plant to company code
Select find button
Give company code: AML
Enter
Select: AML

95

Select assign button


Select: AMLP check box
Enter
Save (or) (ctrl + s)
Save in your request
Assign business area to plant/valuation area and division:
Path: same path
Select plant/valuation area Division button
Select new entries button
Plant: AMLP
Division: A1
Give the business area: AMH
Select save (or) (ctrl + s)
Save in your request
Assign purchasing organization to company code:
SPRO enterprises structure assignment materials management assign
purchasing organization to company code
Select find button
Give the company code: AML
Enter
Select company code: AML
Select assign button
Select: AMLR check box
Enter

96

Save (or) (ctrl + s)


Save in your request
Creation of Material group:
Path: SPRO logistics general Material group create material group
Material group: CHEMICAL
Give the material group description: Chemicals
Save
Creation of purchasing group:
Path: SPRO materials management purchasing create purchasing groups
Select new entries button
Purchase group: AML
Description: Raw material purchase group
Save
Save in your request
Maintain company codes for materials management:
Path: SPRO logistics general material master basic settings maintain
company codes for materials management
Select position button
Give the company code: AML
Enter
For the company code: AML
Give the year: 2006
Give the period: 7
Select ABP check box
ABP Allow back period postings
Select save button (or) (ctrl + s)
Ignore the warning message

97

Press enter
Press enter to save in your request
Define attributes of material types:
SPRO logistics general material master basic settings material types
define attributes of material types
Select material type: ROH (Raw material)
Double click on qty/value updating folder
Select position button
Give the valuation area: AMLP
Enter
For AMLP: select qty updating check box & value updated check box
Save
Save in your request
Select back arrow
Select material type: FERT (Finished product)
Double click on qty/value updating folder
Select position button
Give the plant: AMLP
Enter
For AMLP: select qty updating check box & value updated check box
Save
Set tolerance groups for purchase orders:
Path: SPRO materials management purchasing purchase order set tolerance
limits for price variance.
Select: Tolerance key PE & Tolerance key: SE

98

For company code: 1000


Select copy as button
Change the company code: AML
Press enter
Once the company code to AML for SE
Enter & Save
Save in your request
Set tolerance limits for goods receipt:
Path: SPRO materials management inventory management & physical inventory
goods receipt set tolerance limits
Select tolerance key: B1, B2, &VP for company code 1000
Select copy as button
Change the company code to AML for B1
Enter
Change the company code: AML for B2
Enter
Change the company code: AML for VP
Enter & save
Save in your request
Plant parameters:
Path: Up to inventory management & physical inventory path is same
Plant parameters
Select plant: 1000
Select copy as button
Give the plant: AMLP

99

Enter & Save


Save in your request
Maintain default values for tax codes:
Path: SPRO materials management logistics invoice verification incoming
invoice maintain default values for tax codes
Select new entries button
Company code: AML
Select tax code: VO
Save (or) (ctrl + s)
Set Tolerance limits for invoice verification:
Path: SPRO materials management Logistics invoice verification invoice block
set tolerance limits.
Select tolerance key BD
Select tolerance key ST for company code 1000
Select copy as button
Change the company code: AML
Enter
Once again change the Co code to AML for ST
Enter & Save
Save in your request
Define automatic status change
Up to logistics invoice verification the path is same
Invoice verification in back ground Define automatic status
Change
Select new entries button
Give the company code: AML

100

Save
Save in your request
Creation of GL master (FS00)
1.
2.
3.
4.

Inventory raw material local under current assets, loans advance.


In
finished good under current assets, land & advances
GR/IR clearing raw material local under current liabilities & provisions
Increase/decrease finished goods under the group increase/decrease the
stocks
5. Raw material consumption local under raw material consumption group
Use the transaction code: FS00
Give the G/L account No: 200121
Company code: AML
Select with template button
Give the G/L account No: 200120 (Inv. Raw material)
Company code: AML
Enter
Change short text & long text to: Inventory raw material local
Select create/bank/interest tab
Field status group change to G006 (Material accounts)
Select post automatically only check box
Save (or) (ctrl + s)
2) G/L account No: 200122
Company code: AML
Select with template button
Give the G/L account No: 200121
Enter
Change short text & G/L long text to: Inventory finished goods

101

Save
3) G/L account No: 100510
Company code: AML
Select with template button
Give the G/L account No: 100500 (Out standing expenses)
Company code: AML
Enter
Change short text & G/L long text to: GR/IR clearing raw material local
Select control data tab
Tax category: * (All tax types allowed)
Select posting with out tax allowed check box
Select create/bank/interest tab
Field status group: G045
Save
4) G/L account No: 300200
Company code: AML
Select with template button
Give the G/L account No: 300100 (Exchange gain)
Company code: AML
Enter
Change the account group to: Increase/decrease in stocks
Change short text & G/L long text to: Increase/decrease in stocks finished goods
Select create/bank/interest tab

102

Field status group: G030 (Change in stock accounts)


Save
G/L account No: 400000
Company code: AML
Select with template button
Give the G/L account No: 400100 (Salaries account)
Enter
Change the account group to: Raw material consumption
Change short text & G/L long text to: Raw material consumption local
Select create/bank/interest tab
Field status group: G003
Save
Select edit cost element button
Valid from date: 01.04.2006 to 31.12.9999
Enter
Cost element category: 1
Save
Group together valuation areas:
Path: SPRO materials management valuation & account assignment account
determination account determination with out wizard group together valuation
areas
Select position button
Give the valuation area: AML1
Enter
For valuation area: AMLP valuation grouping code: X

103

Save
Save in your request
Define valuation classes:
Path: same path
Select valuation class button
Select valuation class 3000 raw material
Select copy as button
Change the valuation class, class to AML1
Change the description to Raw materials local
Enter
Select valuation class: 7920 (Finished product) check box
Select copy as button
Change the valuation class to AML2
Change the description: finished goods
Enter & save
Save in your request
Configure automatic postings:
Path: same path
Select cancel button
Select account assignment button
Transaction code: 0BYC
Double click on BSX (Inventory postings)
Give the chart of accounts: AML
Enter
Select valuation modifier check box

104

Select valuation class check box


Save
Valuation modifier: X
Valuation class: AML1
Give the account No: 200121 (Inventory raw material local)
Valuation modified: X
Valuation class: AML2
Account No: 200122
Save
Save in your request
Select back arrow
Double click on WRX (GR/IR clearing)
Select valuation modifier check box
Select valuation class check box
Save
Valuation modifier: X
Valuation class: AML1
Account No: 100510 (GR/IR raw material)
Save
Save in your request
Select back arrow
Double click on GBB (offsetting entry for Inventory postings)
Select general modification check box
Valuation modifier check box

105

Valuation class check box


Save
Valuation modifier: X
General modification: VBR
Valuation class: AML
Account No: 400000
Valuation modifier: X
General modification: AUF
Valuation class: AML2
Account No: 300200 (Increase/decrease in stock)
Valuation modifier: X
General modification: Z0F
Valuation class: AML2
Account No: 300200
Valuation modifier: X
General modification: VAY
Valuation class: AML2
Account No: 300200
Valuation modifier: X
General modification: VAX
Valuation class: AML2
Account No: 300200
Save
Save in your request

106

Document types & number ranges: (OBA7)


Select position button
Select document type: WE (Goods receipt)
Select details button
Note down the number range: 50
Select No. range information button
Give the company code: AML
Select change intervals button
Select interval button
No. range: 50;

year: 2006

From no: 800001 to 900000


Enter & Save
Select back arrow 3 times
Select type: WA (goods issue)
Select details button
Note down the number range: 49
Select No. range information button
Give the company code: AML
Select change intervals button
Select interval button
No. range: 49

year: 2006

From no: 900001 to 1000000

107

Enter & Save


Select back arrow 3 times
Select type: RE (Gross invoice receipt)
Select details button
Note down the number range: 51
Select No. range information button
Give the company code: AML
Select change intervals button
Select interval button
No. range: 51

year: 2006

From no: 1000001 to 1100000


Enter & Save
Creation of vendor master in MM (Path: XK01)
Give the company code: AML
Purchase organization: AMLR
Account group: AML2
Enter
Give the name of the vendor: Reliance industries
Country: In (India)
Select next screen button 3 times
Reconciliation account: 100501
Sort key: 012
Select next screen button
Payment terms: 0001
Select next screen button 3 times
Order currency: INR

108

Select GR based invoice verification check box


Save
Material master creation:
Path: Logistics materials management material master material create
(General) Immediately (MM01)
Give the material No: AMLRM!
Industry sector: Mechanical Engineering
Material type: Raw material
Press select views button
Select: Basic data 1
Select: purchasing
Select: General plan data/storage/ accounting1
Select organization levels button
Give the plant: AMLP
Storage location: Hyd
Enter
Give the description: Raw material 1
Base unit of measurement: Kg
Material group: Chem (Chemical)
Select purchasing tab
Purchasing group: AML (Raw material purchase group)
Select accounting 1 tab
Division: A1 (Cement division)
Valuation class: AML1 (Raw materials local)
Price control: V (Moving average price)
Moving price: 50/Total stock: 0

109

Total value: 0
Save
To open material periods:
Path: Logistics materials management Material master other Close period
(T. code: MMPV)
Give the from company code: AML
Period: 8
Fiscal year: 2006
Select check & close period radio button
Execute
Select back arrow
From company code: AML
Period: 9
Fiscal year: 2006
Select check & close period radio button
Execute
Purchase order creation:
Path: Logistics Materials management Purchasing Purchase order Create
Vendor/supplying plant known (T. Code: ME21N)
Give the vendor number: 6400001
Purchasing organization: AMLR
Company code: AML
Purchasing group: AML
Item: 10
Material: AMLRM1
P. O. quantity: 100
Net price: 75/Plant: AMLP

110

Save
Note down the P. O. No: 4500014522
Goods receipts:
Logistics materials management inventory management goods movement
Goods receipt for purchase order P. O. No known (T. Code: MIGO)
Give the purchase order No: 4500014522
Enter
Select quantity tab
Quantity in delivery note: 100 Kegs
Select item OK check box
Select where tab
Storage location: Hyd
Save
Display material document:
Path: Logistics materials management Inventory management Material
document Display (T. Code: MB03)
Enter
Select accounting documents button
Select accounting document number
Inventory RM local 7500 AMLRM1 AML1 (BSX0
To GR/IR RM local 7500 AMLRM1 AML1 (WRA)
Qty in GR * rate as per PO 100 * 75 = 7500

111

Invoice verification:
Path: logistics Materials management logistics Invoice verification
Document entry enter invoice (MIRO)
Invoice date: 25.11.2006
Reference party bill no: 5678
Amount: 7500/Text: Invoice verification
Select payment tab
Give the base line date: 02/12/2006
Payment terms: 0001
Give the purchase order No: 4500014522
Enter
Save
Ignore the warning message, enter
From the menu select invoice document display
Select follow on documents button
Double click on accounting document No:
Reliance industries A/C Dr 7500 (From purchase order)
To GR/IR clearing RM local
7500 AMLRM1 AML1 (WRX)

112

Goods issue for consumption:


Path: Logistics materials management inventory management goods movement
Goods issue (MB1A)
Give the movement type: 201
Plant: AMLP
Storage location: Hyd
Enter
Give the cost centre: Dept A
Material number: AMLRM1
Qty: 10 kegs
Save
From the menu select goods issue Display
Enter
Select accounting documents button
Select accounting document No
Inventory RM local 750 (AMLRM1 AML1 (BSX0
RM consumption 750 AMLRM1 AML1 GBBVBR
To view material ledger:
Logistics Materials management Inventory management environment stock
stock for posting date (MB5B)
Give the material No: AMLRM1
Company code: AML
Plant: AMLP
Select date: 01.04.2006 to 31.03.2007
113

Select: value added stock radio button


Execute

SD to FI Integration
Insert regions:
SPRO general settings set countries Insert regions
Select new entries button
Give the country: IN (India)
Region: AP;

Description: Andhra Pradesh

Save
Define sales organization
SPRO Enterprises structure Definition sales & distribution define, copy,
delete check sales organization
Double click on define sales organization
Select new entries button
Sales organization: AMLS
Description: Hyderabad sales organization
Statistics currency: INR
Save (or) (Ctrl + s)
Ignore the warning message, press enter
Name: Hyderabad sales organization
Country: IN (India)
Enter
Select create request button
Short description: SD Customization for AML
Enter
114

Press enter to saving the request


Define distribution channel
Same path
Double click on define distribution channel
Select new entries button
Distribution channel: AD
Description: Direct sales
Save
Save in your request
Define shipping point:
SPRO enterprises structure definition logistics execution define, copy, delete,
check shipping point.
Double click on define shipping point
Select new entries button
Give the shipping point: AMSH
Description: Hyderabad shipping point
Save
Give the name: Hyderabad shipping point
Country: IN (India)
Enter
Press enter to save in your request

115

Assign sales organization to company code


SPRO enterprises structure Assignment sales and distribution Assign sales
organization to company code
Select final button
Give the company code: AML
Enter
Select company code: AML
Select assign button
Select: AMLS check box
Enter
Save (or) (Ctrl + s)
Save in your request
Assign distribution channel to sales organization
Same path
Select find button
Give: AMLS
Enter
Select: AMLS
Select: Assign button
Select: AD check box (Direct sales)
Enter & Save
Save in your request

116

Assign division to sales organization


Same path
Select find button
Give: AMLS
Enter
Select: AMLS
Select: Assign button
Select: A1 (Cement division)
Enter & Save
Save in your request
Set up sales area:
Path: same path
Select find button
Give: AMLS
Enter
Select: AMLS
Select: Assign button
Select: AD check box (Direct sales)
Enter
Keep the cursor on AD
Select: assign button
Select: A1 (Cement division check box)

117

Enter & Save


Save in your request
Assign sales organization Distribution channel plant
Select find button
Give: AMLS
Enter
Select: AMLS
Select assign button
Select AMLP check box
Enter & Save
Save in your request
Define rules by sales area:
SPRO enterprises structure Assignment Sales and distribution Business area
account assignment define rules by sales area
Select position button
Give the sales organization: AMLS
Enter
For AMLS select rule 001 (Business area determination from plant/division
Save
Save in your request
Assign shipping point to plant
SPRO enterprises structure assignment logistics execution assign shipping
point to plant
Select find button
Give: AMLP

118

Enter
Select: AMLP
Select: Assign button
Select: AMSH (Hyderabad shipping point) check box
Enter & save
Define pricing procedure determination
SPRO sales & distribution Basic functions pricing pricing control define
& Assign pricing procedures
Double click on define pricing procedure determination
Select new entries button
Sales organization: AMLS
Distribution channel: AD (Direct sales)
Division: A1 (Cement division)
Document procedure: A (Standard)
Customer pricing procedure: Select 1 (Standard)
Pricing procedure: Select RVW01 (Standard)
Condition type: Select PRO0 (Price)
Save
Save in your request
Define tax determination rules:
SPRO Sales & distribution Basic functions Taxes define tax determination
rules
Select new entries button
Tax country: select IN (India);

sequence: 1

119

Tax category: Select MWST (Output tax)


Save
Creation of G/L master, sales local own goods (FS00)
Give the G/L account No: 300001
Company code: AML
Select with template button
G/L account No: 300000 (Sales account)
Company code: AML
Enter
Change short text & G/L account long text to: Sales local own goods
Select create/bank/interest tab
Field status group: G029 (Revenue accounts)
Save
Select edit cost element button
Valid from date: 01.04.2006 to 31.12.9999
Enter
Cost element category: 11 (Revenues)
Save
Assignment of accounts for automatic postings:
SPRO sales & distribution Basic functions accounts assignment/costing
Revenue account determination Assign G/L accounts (T. Code: VKOA)
Double click on table: 001
Select new entries button
Application area: Select V (Sales & distribution)
Condition type: Select KOFI

120

Chart of accounts: AML


Sales organization: AMLS
Account assignment group for customer: select 01 (Domestic revenues)
Account assignment group for materials: Select 03 (finished goods)
Account key: select ERL (Sales revenues)
G/L account No: 300001 (Sales local own goods)
Save
Save in your request
Set up partner determination:
4 types of partners:
SP Sold to party fixed Net modifiable
SH Ship to party
BP Bill to party
PY Payee
Path: SPRO sales & distribution Basic functions partner determination set
up partner determination
Double click on set up partner determination for customer master
Double click on partners function folder
Select: SP (Sold to party)
Double click on account groups function assignment folder
Select new entries button
Partner function: SP (Sold to party), enter: SH (AML); BP (AML2), PY (AML2)
Account group: AML2 (SD customers for AML)
Enter & Save
Save in your request

121

Double click on partners determination procedures folder


Select new entries button
Give the partner determination procedure: AML
Name: AML (Partner determination procedure)
Save
Ignore the message, press enter
Select: AML
Double click on partner functions in procedure folder
Select new entries button
Give the partner function: SP (Sold to party)
Select not modifiable check box
Select mandatory function check box
Partner function: SH (Ship to party)
Select mandatory function check box
Select: BP (Bill to party); select mandatory function check box
Select: PY (Payee); select mandatory function check box
Save (or) (ctrl + s)
Select back arrow 2 times
Select: AML
Double click on partner determination procedure assignment folder
Select position button
Account group: AML2
Enter
For AML2: Assign AML

122

Save
Assign shipping points:
SPRO logistics execution shipping Basic shipping functions shipping point
& goods receive point determination assign shipping points
Select new entries button
Shipping condition: 01 (As soon as possible)
Loading group: 0003 (Manual)
Plant: AMLP
Proposed shipping point: AMSH
Save, save in your request
Creation of customer master: (XD01)
Account group: Select SD customers for AML
Company code: AML
Sales organization: AMLS
Distribution channel: AD
Division: A1
Enter
Give the customer name: VBC Industries Ltd
Country: IN (India)
Region: AP
Select company code data button
Reconciliation A/C: 200110 (Sundry debtors)
Sort key: 031
Select payment transactions tab

123

Terms of payment: 0001


Select sales area button
Customer pricing procedure: Select 1 (standard)
Select: shipping tab
Delivery priory: Select 02 (Normal)
Shipping conditions: Select 01 (As soon as possible)
Select: Billing document tab
Select: Price determination check box
Inco terms: select EXW (From plant)
Account assignment group: Select 01 (Domestic revenues)
Output tax classification: select 1 (Liable for tax)
Save
Creation of finished goods material master: (MM01)
Give the material no: AMLFG
Industrial sector: Mechanical engineering
Material type: Finished product
Press: select views button
Select: Basic data
Select: Sales: sales Org data1
Select: sales: sales org data2
Select: Sales: general/plant data
Select: MRP
Select: General/plant/data/storage
Select: accounting 1

124

Select organization levels button


Give the plant: AMLP
Storage location: Hyd
Sales organization: AMLS
Distribution channel: AD
Enter
Give the description: Finished product
Base unit of measurement: Kg
Gross weight: 1000 Grams
Select: Sales: sales organization data1 tab
Division: A1
Tax classification: Select1 (Full tax)
Select: Sales: sales organization to tool tab
Account assignment: select 03 (Finished goods)
Select: sales: general/plant
Availability check: Select KP (No check)
Transportation group: 0003 (Container)
Loading group: 0003 (Manual)
Select: MRP1 tab
MRP Type: Select ND (No planning)
Select: accounting 1 tab
Valuation class: AML2 (Finished products)
Price control: Select S (Standard price)

125

Standard price: 400/Select save button (or) (Ctrl + s)


Creation of condition types:
Logistics sales & Distribution Master Data conditions select using condition
type Create (VK11)
Give the condition type: PR00 (Price)
Select: Key combination button
Select: Material with release status radio button
Enter
Give the material No: AMLFG
Amount: 500/Valid on: 01.04.2006 to 31.03.2007
Save (or) (ctrl +s)
Select back arrow
Give condition type: MWST (Output tax)
Select key combination button
Select domestic taxes radio button
Enter
Give the country: IN (India)
Valid on 01.04.2006 to 31.12.9999
Tax classification customer: 1 (Liable for Tax)
Tax classification for material: 1
Tax code: Select AO
Save
Ignore the message, press enter

126

Profitability analysis (CO PA)


Co Controlling
PA Profitability analysis
This is used to view profitability for number of parameters at a time.
If the client want to view profitability
Product wise/customer wise/sales order wise/plant wise/sales organization wise
-

This is called data cube


This is a reporting tool
Product costing is based on the based on data flown
from
MM, PP, FI, CO

Account based/costing based/both wise profitability


analysis
Here we create operating concern

equal to controlling area (or) above controlling area

Here we have

Operating concern can be

Controlling area can be equal to company code (or) above company code
Structure: company code = controlling area = operating concern
We are using called data structure
Data structure
|
Characteristics

Sales order
Customer
Product
Sales organization
Plant
Sales employee
Industry

|
value fields

Sales
Cost of goods sold
Net profit

Profitability segment:
127

In consist of system defaulted characteristics


Client required characteristics
Example of client required characteristics:
1. Sales employee wise profitability
2. Industry wise profitability
Data flow in profitability analysis
SD to FI
a) Enquiry & quotation
b) Sale order: customer, product plant, sales organization, quantity, price, delivery
terms & payment terms
c) Delivery: with out post goods issue/with post goods issue
d) Billing
Define operating concern:
SPRO controlling profitability analysis structures define operating concern
Maintain operating concern.
Operating concern: 1234 (It should be 4)
Select create button
Ignore the warning message, press enter
Give the description: Operating concern for AML
Select costing based check box, actual based check box
Select attributes tab
Give the operating concern currency: INR
Select company code currency check box
Fiscal year variant: V3
Save
Select data structure tab
Select create button under data structure

128

Select the characteristic: KNVTNR (Sales employee)


Select left arrow
Select value fields tab
Select: VV010 (Revenues)
Select: VV140 (Cost of goods sold)
Select left arrow
From the menu select data structure save
From the menu select data structure Activate
Select back arrow
Select yes button for the message to generate the operating concern environment.
Ignore the message, press enter
Define profitability segment characteristics: (In segment level characteristics)
Path: same path (T. Code: KUQ3)
Give the operating concern: 1234
Enter
For product & Customer
Select costing base & Account base radio butt
Save
Save in your request
Assign controlling area: to operating concern:
Path: SPRO enterprises structure assignment controlling assign controlling
area to operating concern
Select position button
Give the controlling area: AML
Enter: for controlling area: AML, assign operating concern: 1234

129

Save
Ignore the warning message, press enter
Define No. ranges for actual postings:
SPRO controlling profitability analysis flows of actual values initial steps
define number ranges for actual postings (T. Code: KEN1)
Give the operating concern: 1234
Select maintain groups button
Select generated groups check box
From the menu select interval maintain
Give the No from: 1 to 999999999
Save
Maintain assignment of SD conditions to Co PA value fields
Path: SPRO controlling profitability analysis flows of actual values transfer
of billing documents assign value fields
Double click on maintain assignment of SD conditions to CO-PA value fields (T. Code:
KE41)
Select new entries button
Open one more session & set operating concern idea
Path: SPRO controlling profitability analysis structures set operating
concern
Give the operating concern: IDEA
Enter
Use the transaction code: KE41
Come to the 1st session
Give the condition type: PR00 (Rice)
Select value fields VV010 (Revenues)
Select VPRS (Costs)

130

Select value fields VV140 (Cost of goods sols)


Save
Maintain PA (Profitability analysis) structure for direct postings:
SPRO controlling profitability analysis flows of actual values direct postings
from FI/MM maintain PA transfer structure for direct postings (T. code: KET2)
Select the structure: FI (Financial accounting to CO PA)
Double click on assignment lines folder
Select: 20 (Direct revenues from FI)
Double click on source folder
Give the cost element: from 300000 to 399999
Double click on value fields folder
Select new entries button
Qty/value select value field
Fixed variable select 1 (Fixed amounts)
Value fields select VV010 (Revenue)
Save
Save in your request
Double click on assignment lines folder
Select assignment: 10 (Direct costs from FI)
Give the cost element: from 400000 to 499999
Double click on value fields folder
Select new entries button
Qty/value select value field
Fixed variable select 1 (Fixed amounts)
Value fields select VV140 (Cost of goods sold)
131

Save
Activate profitability analysis:
Path: same path (T. Code: KEKE)
Select position button
Give the controlling area: AML
Enter
For controlling area: DRL Active status select a4 (Component active For both types of
profitability analysis)
Save
Save in your request
Sale order creation:
Path: Logistics sales & distribution sales order create (T. Code: VA01)
Give the sales organization: AMLH
Distribution channel: AD
Division: A1
Order type: OR (standard order)
Enter
Sold to party: VBC Industries Pvt. Ltd
Give the P. O. order: 5678
Required delivery date: 03.12.2006
Delivery plant: AMLP
Payment terms: 0001
Item: 10;
Material No: AMLFG

132

Order qty: 1 kg
Enter
Ignore the messages, press enter
Select item 10
From the menu select go to item condition
Select: Shipping tab
From the menu select edit Incompletion log
Save (or) (ctrl + s)
Note: Sales order No: 8209
Production receipt with out production order:
Path: Logistics Materials management Inventory management Goods
movement goods receipt Other (MB1C)
Give the movement type: 521
Plant: AMLP
Storage location: Hyd
Enter
Give the material type: AMLFG
Qty: 20 Kegs
Save
Ignore the warning message, press enter
From the menu select other goods receipts display
Enter
Select accounting documents button

133

Select accounting document No:


Account No

Description

INR

200122
300201

Inventory FG
10000 DRLFG1 DRL1 (BSX)
Inc/Dec in stock FG 10000 DRLFG1 DRL1 (GBBZAX)

Qty & standard price

Delivery:
Logistics sales & Distribution sales order subsequent functions outbound
delivery (VL01N)
Give the shipping point: AMLS
Give the sales order number: 8209 (What it is created in sales order)
Enter
Actual GI date (Goods issue date): 03.12.2006
Select item: 10
Select picking tab
Pick quantity: Enter 1
Select post goods issue button
From the Menu select out bound delivery display
Enter
From the Menu select environment Document flow
Keep the cursor on goods issue
Select display document button
Select accounting documents button
Select accounting document No:
200122
300201

Inventory FG
Inc/dec in stock FG

500 DRLFG1 DRL1 (BSX)


500 DRLFG1 DRL1 GBBVAY

134

Billing document:
Same path: (VF02)
Select the delivery document No: 11341
Enter
Save
From the menu select billing document display
Select accounting button
Select accounting document No
Report generation through report painter
Define forms
SPRO Controlling Profitability analysis information system report
components define forms define forms for profitability reports
Double click on create form
Give the form name: AML
Description: AML Form (T. Code: KE34)
Select two axes (Matrix) radio button
Select create button
Select operating concern currency radio button
Enter
Double click on: Row 1
Select value field with characteristics radio button
Enter
Value field select: VV01 (Revenue)

135

Select: Confirm button


Double click on: Row2
Select value field with characteristics radio button
Enter
Value field select: VV140 (Cost of goods sold)
Select: Confirm button
Double click on: Row3
Select formula radio button
Enter
Select Y001 (Revenue)
Select Minus (-) button
Select Y002 (Cost of goods sold button)
Enter
Short description: Net profit
Select copy short text button
Enter
Double click on column1
Select characteristics radio button
Enter
Select from the available characteristics plan/actual indicator
Select left arrow
For plant/actual indicator: Select 0 (Actual data)
Select confirm button

136

Save
From the menu select edit General data selection General data selection
From the available characteristics select record type, select period/year
Select left arrow
For record type: select from column B to column select F (Billing data)
For period/year
For from column: Select variable on/off check box
Local variable: enter1
Enter
For to column: Select variable on/off check box
Give the local variable: 2
Enter
Select confirm button
From the menu select extras Variables variables of definition
1- description: From period/year
2- description: To period/year
Enter & Save
Create profitability report:
Same path
Double click on create profitability report
Transaction code: KE31
Give the report name: AML Profit
Description: AML Profitability
Select: Report with form radio button

137

Give the form name: AML


Select create button
Select customer, product, plant, select sales organization from characteristics list
Select left arrow
Select output type tab
Select: Class drill down radio button
Select available on selection screen check box
Save
Select execute button
Give from period/year: 01.2006
To period/year: 12.2006
Execute
Ignore the message, select yes button
To view product wise:
From the menu select navigate switch drill down
Double click on product

138

Product costing
This is used for valuation of inventories like work in process & finished goods.
-

Data is flow from MM, PP, FI&CO modules


Product costing made easy- sap labs
When we will take production It will be standard cost
In the month ending we will knows the actual cost
The differences will be settle variances of accounts

Data flow in product costing:


Example: Product AMLFG1
Cost sheet

AML finished goods

Raw material
Raw material overheads
Production cost

XXX (Qty from BOM * Rate from material master


XXX (10% of raw material)
XXX (hours required * machine hour rate)
--------Cost of goods manufacturing XXX
(COGM)
Admn& selling& dist exp
XXX
-----Cost of goods sold
XXX
Sales budget Production budget
Sales budget: Make to order
Make to stock
Production budget: Material requirement plan
Overheads planning
MM
Material master
Accounting view
Raw material (AMLRM1) Moving average price 75/(AMLRM2) Moving average price 100/-

139

PP: Bill of material (BOM) required for production


AMLRM1 1kg
AMLRM2 1kg
Dept ADept B

Dept C
X

Dept D Work centre in PP


(Finished goods (AMLFG)

Finished product (AMLFG) process flow A C D (Routing)


Salaries 200000
Wages - 500000
Rent 20000
----------720000
Machines 100 Machines
Machine hours = 100 * 24 hours * 30 days = 72000 machine hours
Machine hour rate = 720000/72000 = 10/- per hour
To produce finished product AMLFG say 5 machine has = 5 * 10 = 50

Creation of secondary cost elements:


1. Overhead cost element
2. Activity cost element
Use the transaction code: KA06
Use the cost element: 1100000
Valid from: 01.04.2006 to 31.12.9999
Enter
Give the name: RM overhead rate
Description: RM overhead rate

140

Cost element category: select 41 (Overhead rate)


Save
One more cost element: 1200000
Valid from: 01.04.2006 to 31.12.9999
Enter
Give the name: Activity cost element
Description: Activity cost element
Cost element category: select 43 (Internal activity allocation)
Save
Creation o f activity type: (Called machine hour)
Accounting controlling cost centre accounting master data activity type
individual processing create (KL01)
Activity type: AML
Valid from: 01.04.2006 to 31.12.9999
Enter
Name: Machine hour
Description: Machine hour
Activity unit: Select H (Hour)
Cost centre categories: Select * (All cost centre categories)
Enter
Activity type category: select 1 (Manual entry, manual allocation)
Allocation cost element: select 1200000
Save

141

Creation of 2 cost centers: (KS01)


Give the cost centre: Dept G
Valid from: 01.04.2006 to 31.12.9999
Reference cost centre: Dept A
Controlling area: AML
Enter
Change the name to dept G
Description: Cost centre dept G
Other fields are common
Save (or) (ctrl + s)
One more cost centre: Dept H
Valid from: 01.04.2006 to 31.12.9999
Reference cost centre: Dept A
Controlling area: AML
Enter
Change the name to dept H
Cost centre: Dept H
Cost centre category: Select 9 (Allocation cost centre)
Save

142

Creation of cost centre group: (KSH1)


Give the cost centre group: AML Prod
Enter
Give the cost centre group: AML prod
Select insert cost centre button
Give the cost centre: Dept G
Select save button (or) (ctrl + s)
Define overhead keys:
SPRO Controlling product cost controlling basic settings for material costing
overhead define overhead keys
Select new entries button
Overhead key name: AML
Description: AML Overhead key
Save
Save in your request
Define overhead group:
Same path
Select new entries button
Valuation area: AMLP
Overhead group: AML
Overhead key: AML
Name of overhead group: Overhead group for AML

143

Save
Save in your request
Define calculation bases:
SPRO controlling product cost controlling product cost planning basic
settings for material costing overhead costing sheet components define
calculation bases
Select new entries button
Base: A1
Name: Raw materials
Save, Save in your request
Select: A1
Double click on details folder
Give the controlling area: AML
Enter
Select new entries button
From cost element: 400000 to 400099
Save
Select back arrow 3 times
Select: New entries button
Base: A2
Name: Production cost,
Save
Select: A2
Double click on details folder
Give the controlling area: AML
Enter
Select new entries button
From cost element: 400100 to 400299

144

: 400500
: 1200000
Save (or) (Ctrl + s)
Define percentage overhead rates:
Path: same path
Select: new entries button
Overhead rate: A3
Name: Raw material overhead rate
Dependency: Select DO10 (Overhead type/H key)
Save
Save in your request
Select: A3
Double click on details folder
Ignore the message, press enter
Select new entries button
Valid from: 01.04.2006 to 31.03.2007
Controlling area: AML
Overhead type: Select 2 (Planned overhead rate)
Overhead key: AML
Percentage: 15%
One more:
Valid from: 01.04.2006 to 31.03.2007
Controlling area: AML
Overhead type: Select 1 (Actual overhead rate)
Overhead key: AML

145

Percentage: 10%
Save
Save in your request
Define credits:
Same path
Select new entries button
Give the credit key: A4
Name: Raw Material credit key
Save
Save in your request
Select: A4
Double click on details folder
Give the controlling area: AML
Enter
Select new entries button
Valid to: 31.03.2007
Cost element: 1100000 (Raw material overhead rate)
Fixed percentage: 100%
Cost centre: Dept H
Save
Example:
RM1 Handling charges Dr - Dept H 3000
To Bank
3000
RM2 Handling charges Dr Dept H 7000
To Bank
7000
Dept H
Handling 10000 |
3000
Charges
|
7000
(7000 + 3000) |
------10000

146

Production 1
RM cost 30000
10% of cost 3000
Define costing sheet:

production2
RM Cost 70000
10% of cost 7000

SPRO Controlling product cost controlling basic settings for material costing
overhead define costing sheets
Select new entries button
Costing sheet: AML
Description: AML costing sheet
Select: AML
Double click on costing sheet rows folder
Select new entries button
Give Row: 10, Basic: A1 (Raw materials)
Row: 20, overhead rate: A3 (Raw material overhead rate)
From: 10 to Row 10: Credit: A4
Row: 30, Base: A2 (Production cost)
Row: 40, Description: Cost of goods manufacture
From Row 10 to Row 30
Save (or) (Ctrl + s)
Assign costing sheet to costing variant:
SPRO controlling Product cost controlling product cost planning material
cost estimate with quantity structure define costing variants
Transaction code: OKKN
Select costing variant: PPL1 (Standard cost estimate (Material))
Select details button
Select valuation variant button
Select create button (Beside valuation variant/plant)
Select new entries button

147

Give the plant: AMLP


Save, Save in your request
Select back arrow
Select valuation variant: 001 with plant: AMLP
Select details button
Select overhead tab
Give the costing sheet: AML costing sheet
The costing sheet: AML costing sheet
Save
Define cost component structure:
SPRO controlling product cost controlling product cost planning basic
settings for material costing define cost component structure
Select structure: 01
Double click on: Cost components with attributes folder
Select: cost component 10 (Raw materials)
Double click on assignment cost components cost element interval folder
Select new entries button
Cost component structure: 01
Chart of accounts: AML
From cost element: 400000 to 400099
Cost element: 010 (Raw materials)
Save, ignore the warning message, and enter
Save in your request
Double click on cost components with attributes folder
Select component: 80 (Material overhead)

148

Double click on assignment cost component cost element interval


Select: new entries button
Cost component structure: 01
Chart of accounts: AML
From cost element: 1100000 (Overhead rate)
Cost component: 080 (Material overhead)
Save
Double click on cost elements with attributes folder
Select cost component: 50 (Production machine)
Double click on assignment cost component cost element interval folder
Select new entries button
Cost component structure: 01
Chart of accounts: AML
From cost element: 400100 to 400299
Cost element structure: 050
One more
Cost component structure: 01
Chart of accounts: AML
From cost element: 400500
Cost element structure: 050
Cost component structure: 01
Chart of accounts: AML
From cost element: 1200000
Cost element structure: 050
Save

149

Double click on cost element structure folder


For 0 select activate check box
Save (or) (ctrl + s)
Determine person responsible for work centre:
Path: SPRO production Basic data work centre general data determine
person responsible
Select new entries button
Give the plant: AMLP
Person responsible: A
Give the responsible: Mr. A
Save
Save in your request
Define MRP controller: (MRP: Material requirement planning)
SPRO production material requirements planning master data define MRP
controllers
Select new entries button
Give the plant name: AMLP
MRP controller: B
Description: Mr. B
Save
Save in your request
Define floats (Scheduling margin key) (Floats: Cushion period)
Path: SPRO production materials requirement planning planning scheduling
& capacity parameters define floats (Schedule margin key)
Select new entries button
Give the plant name: AMLP

150

Schedule margin key: AML


Opening period: 2 days
Float before production: 2 days
Float after production: 2 days
Release period: 2 days
Save
Save in your request
Define production scheduler:
SPRO production shop floor control master data define production scheduler
Select new entries button
Plant: AMLP
Production scheduler: C
Production scheduler name: Mr. C
Save (or) (ctrl + s)
Planning cost centre wise (KP06)
Version: 0
From period: 9 to 9
Fiscal year: 2006
Cost centre: Dept G
Next page
Cost centre: 400100 (Salaries)
Select form based radio button
Select over view screen button

151

Give plan fixed cost: 720000


Save
Planning for machine hours:
Accounting controlling cost centre accounting planning activity ad put/prices
change (KP26)
Version: 0
From period: 9 to period: 9
Year: 2006
Cost centre: Dept G
Activity type: AML
Select form based radio button
Select overview screen button
Give plan activity 72000 (100 machines * 3 shifts * 30 days)
Save
Machine down rate calculation:
Accounting controlling cost centre accounting planning allocations price
calculation (KSPI)
Select cost centre group radio button
Give the cost centre: AMLPRODN
Version: 0
From period: 9 to period: 9
Fiscal year: 2006
Execute
Select save button (or) (ctrl + s)
Ignore the message, press enter

152

Creation of material master: (MM01)


Give the material number: AMLRM2
Industry sector: Mechanical engineering
Material type: Raw material
Press: select use button
Select: Basic data, purchasing, general plant data/storage one, accounting
Select organization levels button
Give the plant: AML
Storage location: Hyd
Enter
Give the description: Raw material
Basic unit of measurement: Kg
Material group: Chem
Select purchasing tab
Purchasing group: AML
Select: Accounting1 tab
Valuation class: AML1
Price control: V
Moving price: 100
Save

153

Creation of finished goods master (MM01):


Material No: AMLFG1
Industrial sector: Mechanical engineering
Material type: Finished product
Press select views button
Select: Basic data1, MRP1, MRP2, work scheduling, general plant data/storage1,
Accounting1, costing1.
Select organization levels button
Plant: AMLP
Storage location: Hyd
Enter
Give the description: Finished product1
Basic unit of measurement: Kg
Select: MRP1 tab
MRP type: select PD (MRP)
MRP controller: Select B (Mr. B)
Lot size: select Ex (Lot for lot order quantity)
Select MRP2 Tab
In house production: 0 days
Schedule margin key: AML
Select work schedule time tab
Ignore the warning message, enter

154

Production: Scheduler C
Select accounting1 tab
Valuation class: AML2
Price control: S (Standard)
Give the standard price: 300/Select costing1 tab
Overhead group: Select AML
Availability check: Select KP (No check)
Save
Creation of Bill of material:
Logistics production master data bills of material bill of material material
BOM Create (CS01)
Give the material No: AMLFG1
Plant: AMLP
BOM usage: Select 1 (Production)
Enter
Give the component
For item 10: AMLRM1;

Qty: 1 Kg

Item 20: AMLRM2;

Qty: 1

Save
Creation of work centre:
Logistics production master data work centers work centre create (CR01)
Work centre: Dept G
Work centre category: select 0001 (Machine)

155

Select basic data button


Give the description: Work centre Dept G
Person responsible: A
Usage, select 009 (All task lists types)
Standard value key: SAP1 (Normal production)
Select costing tab
Start date: 01.04.2006
Cost centre: Dept G
For activity machine: Give the activity type AML
Performance unit: H (Hour)
Formula key: SAP002 (Production machine types)
Save
Creation of routing:
Logistics Production master data routings routings standard routings
create (CA01)
Give the material No: AMLFG1
Plant: AMLP
Enter
Usage: select1 (Production)
Status: Select 4 (Release (General))
Select operation button
For operation at tab give the work centre: Dept G
Control key: Select PP01 (In house production)
Select operation: 10 and double click

156

Machine: standard values: 5


Unit: H (hours)
Save
Creation of cost estimate with quality structure:
Accounting controlling product cost controlling product cost planning
material costing cost estimate with quantity structure create (T. Code: CK11N)
Give the material: AMLFG
Plant: AMLP
Costing variant: PPC1 (Standard cost estimate)
Enter
Give the costing date from: 08.12.2006 Costing date to 31.12.9999
Qty structure date: 08.12.2006
Valuation date: 08.12.2006
Enter
Standard cost should be: 251.25
Cost sheet
RM AMLRM1 75
- AMLRM2 - 100
-----RM overhead 15%
Production costs
(5*10) machine hours

175.00
26.25
50.00
--------251.25

From the menu select: Cost Display cost components


Select save button (or) (ctrl + s)
Enter

157

Marking & Releasing


Display material master:
Logistics materials management material master material display display
current (MM03)
Give the material number: AMLFG1
Press select views button
Select costings2, view
Select organization levels button
Give the plant: AMLP
Enter
Marking, updates future price 09.2006
Price 251.25
- 09.2006Price 251.25
Release updates current price 251.25
Use of marking & Releasing is for the next month if the product
Value is increased it is estimated in the current month and applicable in the next month
Path for Marking & Releasing:
Accounting controlling product cost controlling product cost planning
material costing price update (T. Code: CK24)
Give posting period/fiscal year: 9.2006
Company code: AML
Plant: AMLP
Material: AMLFG1
Select test run check box

158

Select marking allowance button


Select company code: AML
Give the costing variant: PPC1 (Standard cost estimate)
Save
Select back arrow
Deselect test run check box
Execute
Select: AMLFG1
Select costing2 tab
Select back arrow 2 times
Select release button
Executes
Select: AMLFG1
Select: costing 2 tab
Actual costing: (check costing variants for manufacturing orders)
SPRO controlling product cost controlling cost object controlling product
cost by order manufacturing orders check costing variants for manufacturing orders
(PP) (T. Code: OPL1)
Select costing variant: PPP1 (Production order plan)
Select details button
Select valuation variant button
Select create button beside valuation variant/plant
Select new entries button
In Plant: AMLP

159

Save
Save in your request
Select back arrow
Select valuation variant: 006 (with AMLP)
Select details button
Select overhead tab
Costing sheet: Assign AML costing sheet
Save
Select back arrow
Select: Costing variant: PPP2 (Production order actual)
Select details button
Select valuation variant button
Select create button beside valuation variant/plant
Select new entries button
In plant: Give AMLP
Select overhead tab
Save
Save in your request
Select back arrow
Select: 007 with AMLP
Select details button
Select: AML closing sheet
Save

160

Define goods received valuation for order delivery:


SPRO controlling product cost controlling cost object controlling product
cost by order define goods received valuation for order delivery
Select new entries button
Valuation area: AMLP
Valuation variant: 007 (Production order Actual)
Save
Save in your request
Define results analysis keys:
SPRO controlling product cost controlling cost object controlling product
cost by order period end closing work in process define results analysis keys (T.
Code: OKG1)
Result analysis key: FERT (WIP calculation for production orders)
Save
Define cost element for WIP calculation:
Same path
Double click on create cost element
Transaction code: KA06
Give the cost element: 1300000 (Secondary cost element)
Valid from: 01.04.2006 to 31.12.9999
Enter
Name: order/project result analysis
Description: order/project result analysis

161

Cost element category: 31 (Order/project results analysis)


Save
One more cost element: 1300001
Valid from: 01.04.2006 to 31.12.9999
Give the reference cost element: 1300000
Controlling area: AML
Enter & Save
One more cost element: 1300002
Valid from: 01.04.2006 to 31.12.9999
Give the reference cost element: 1300000
Controlling area: AML
Enter & Save
Cost element: 1300003
Valid from: 01.04.2006 to 31.12.9999
Give the reference cost element: 1300000
Controlling area: AML
Enter & Save
Cost element: 1300004
Valid from: 01.04.2006 to 31.12.9999
Give the reference cost element: 1300000
Controlling area: AML
Enter & Save

162

Creation of 2 G/L accounts: (FS00)


1. work in process under current assets, loans & advances
2. increase/decrease in stocks WIP under increase/decrease of stocks group
Transaction code: FS00
Give the G/L account No: 200123
Company code: AML
Select with template button
Give the G/L account No: 200121 (Inv. Raw material local)
Company code: AML
Enter
Change short text & long text to: work in process
Select create/bank/interest tab
Deselect post automatically check box
Save
Give the G/L account No: 300201
Company code: AML
Select with template button
Give the G/L account No: 300200 (Increase/decrease in stocks)
Company code: AML
Enter
Change short text & long text: Increase/decrease in stocks in WIP
Save

163

Define results analysis versions:


SPRO controlling product cost controlling cost object controlling product
cost by order period and closing work in process define results analysis versions
Select new entries button
Select: AML
Technical result analysis cost element: 1300000
Save
Save in your request
Define valuation method: (Actual Costs)
Same path
Select new entries button
Select actual costs button
Give the controlling area: AML
Result analysis version: 0
Result analysis key: FERT
Enter
Save
Save in your request
Define line IDs:
Same path
Select line ID: ABR, EK, EL, & FK for controlling area 1000
Select copy as button

164

Give your controlling area: AML for all the 4 items


Enter & Save
Save in your request
Define assignment:
Path: same path
Select EK (Direct costs) for controlling area: 1000
Select copy as button
Give the controlling area: AML
In the masked cost element enter: 00004000 + +
Enter & Save
Save in your request
Select: EL for controlling area: AML
Masked cost element: enter 00003 + + + +
Enter
Select line ID - EK (production costs) for controlling area: 1000
Select copy as button
Give the controlling area: AML
Masked cost element: enter 00004001 + +
Enter
Select the item what we are created
Select copy as button
Give the mask cost element: 00004002 + +
Enter
Select the both items what we are created
Select copy as button

165

For 1st one mark cost element give: 00004005 + +


For 2nd one give mask cost element give: 0001 + + + + + +
Enter & save
Define update:
Path: same path (T. Code: OKGA)
Select new entries button
Give the controlling area: AML
Version: 0
Result analysis key: FERT
Line ID: EF (Direct costs)
Category: Select K (Costs)
Work in process cost element: 1300001
Results: 1300002
Controlling area: AML
Version: 0
Result analysis key: FERT
Line ID: FK (Production costs)
Category: K (Costs)
WIP: 1300003
Results: 1300004
Controlling area: AML
Version: 0
Result analysis key: FERT
Line ID ABR
Category: A (Settled cost)

166

Save
Save in your request
Define posting rules: for settling work in process:
Path: same path (T. Code: OKG1)
Select new entries button
Controlling area: AML
Company code: AML
Result analysis version: 0
Result analysis category: WIPR (Work in process with requirement to capitalized)
P&L account: 300201 (Increase/decrease in stock WIP)
Balance sheet account: 200123 (Work in process balance sheet accounts)
Save
Save in your request
Define results analysis versions:
Path: same path (T. Code: OKG9)
Select controlling area: AML
Select details button
Select transfer to financial accounting check box
Select save button (or) (Ctrl + s)
Ignore the message, press enter
Save in your request
Define variance keys:
SPRO controlling product cost controlling cost object controlling product
cost by order period end closing variance calculation define variance keys (T.
Code: OKV1)
Select new entries button

167

Variance key name: AML


Description key: Variance key for AML
Save, save in your request
Define default variance keys for plants:
Same path
Select position button
Give the plant: AMLP
Enter
For AMLP plant assign variance key: AML
Save
Save in your request
Define target costs versions:
Path: same path
Select target cost version for controlling area: 1000
Select copy as button
Controlling area: AML
Description: Target cost version for AML
Enter & Save
Save in your request
Create allocation structure:
SPRO controlling product cost controlling cost object controlling product
cost by order period end closing settlement create allocation structure.
Select new entries button
Allocation structure: A4
Text: AML allocation structure for product costing

168

Save, save in your request


Select: A4 (What we are created)
Double click on assignments folder
Select new entries button
Give the assignment: AML
Text: overheads
Save
Select: AML
Double click on source folder
From cost element: 400000 to cost element 499999
Save
Double click on settlement cost elements folder
Select new entries button
Receiver category: select ord (order)
Settlement cost element: 1000001
Save
Create settlement profile:
Same path
Select new entries button
Settlement profile: AML1
Description: Settlement profile for AML
Select: To be settled radio button
Allocation structure: A4

169

Select % settlement check box


Select equivalence number check box
Select amount settlement check box
Under valid receivers for order settlement required
Maximum number of distribution: 999
Residence time 12 months
Save
Assign Co number range interval for the process
KZPI (Actual overhead periodic)
RKL (Actual activity allocation)
Transaction code: KANK
Give the controlling area: AML
Select maintain groups button
Double click on KZPI
Double click on RKL
Select co document No. range intervals for AML check box
From the menu select edit Assign element group
Save
Maintain exchange rate type for M & P for INR to EURO:
M Average rate
P Cost planning
Transaction code: OB08
Select new entries button
Exchange rate type: M

170

Valid from: 01.04.2006


From currency: INR
To currency: EURO
Direct quotation: 0.2
Save
Save in your request
Exchange rate: P
Valid date: 01.04.2006
From currency: INR to Currency: EURO
Direct quotation: 0-2
Save (or) (ctrl + s)
Creation of G/L account: (FS00)
Production order difference account
Give the G/L account No: 400201
Company code: AML
Select with template button
G/L account No: 400200 (Conversion charges)
Company code: AML
Enter
Change short text & G/L text to: production order differences
Select create/Bank/interest tab
Field status group: G014 (MM Adjustment Accounts)
Save

171

One more account


G/L Account No: 100599
Company code: AML
Select with template button
Give G/L account No: 100500 (Outstanding expenses)
Company code: AML
Enter
Change short text & G/L text to: stock taking account
Select create/Bank/interest tab
Field status group: G049 (Manufacturing costs account)
Select control data tab
Deselect open item management check box
Save
Select the G/L account: 300200 (Increase/decrease stock FG)
Company code: AML
Select create/bank/interest tab
Field status group change to: G036
Save
Select edit cost element button
Valid from: 01.04.2006 to 31.12.9999
Enter
Cost element category: select 22 (External settlement)

172

Save
Assignment of accounts for automatic postings:
Transaction code: OBYC
Double click on PRD (Cost price differences)
Give your chart of accounts: AML
Select valuation modifier check box
Save
Valuation modifier: X
Account Number: 400201
Save
Save in your request
Select back arrow
Double click on GBB
Valuation modifier: X
General modification: AUA
Valuation class AML2
Account No: 300200
Valuation modifier: X
General modification: BSA
Valuation class: AML1
Account: 100599 (Stock taking account)
Save
Save in your request

173

Define order type dependant parameters:


SPRO production shop floor control master data order define order type
dependant parameters (T. Code: OPL8)
Select order type: PP0K (For plant 1000)
Select copy as button
Give the plant: AMLP
Enter & Save
Define scheduling parameters for production orders:
Up to shop floor control the path is same
Operations scheduling define scheduling parameter for production orders (T.
Code: OPU3)
Select order type: PP01 (for plant 1000)
Select copy as button
Change the plant to AMLP
Enter & Save
Save in your request
Define checking control:
Up to shop floor control the path is same
Operations availability check defines checking control (T. Code: OPJK)
Select order type: PP02 (with business function) &
Order type: PP01 with business function 2 for plant 1000
Select copy as button
Give your plant: AML1
Enter

174

Once again give your plant: AMLP


Enter & Save
Save in your request
Define confirmation parameters:
Up to shop floor control the path is same
Operations confirmations Define confirmation parameters
Transaction code: OPK4
Select order type: PP010 (for plant 1000)
Select copy as button
Give the plant: AMLP
Enter & Save
Creation of production order:
Path: Logistics production production control orders create with material
(T. Code: COOK)
Give the material no: AMLFG1
Production plant: AMLP
Planning plant: AMLP
Order type: PP01 (Standard production order)
Enter
Total quantity 10kgs
Start date & Finished date: 10.12.2006
Select cost order button
Ignore the warning messages, enter
From the menu select go to analysis
Select back arrow
Select release order button
Save
Note down order No: 60002846
From the menu select order display
Transaction code: CO03

175

Enter
Select assignment tab
Note down the reservation number: 17516
AML Raw material to receipt by way of opening stock
Path: Logistics materials management Inventory management gods movement
goods receipt other (MB1C)
Give the movement type: 561
Plant: AMLP
Storage location: Hyd
Enter
Give the material No: AMLRM2
Give the qty: 100Kgs
Save
From the menu select other goods receipts display
Enter
Select accounting documents button
Select accounting document number
89 - 200121 Inventory RM local -10000 AMLRM2 AML BSX
91 100599 Stock taking A/C 10000 AMLRM2 AML AMLTGBB BSX
10000: Qty & rate as per material master
Goods issued for production order
Path: Logistics materials management inventory management goods movement
goods issue (T. Code: MB1A)
Select to reservation button
Give the reservation number: 17516
Enter

176

Give actual consumption AMLRM1 15kgs


AMLRM2 15kgs
Save
From the menu select goods issue display
Enter
Select accounting documents button
Select accounting document number
Work in process calculation:
Path: Accounting controlling product cost controlling cost object controlling
product cost by order period end closing single functions work in process
individual processing calculate (KKAX)
Give the order: 60002845
WIP to period: 9 (December)
Fiscal year: 2006
RA (Result analysis) version: select 0
Select test run check box
Execute
Select back arrow and deselect check run and execute
Settlement of work in process to accounts:
Up to period end closing the path is same
Single functions settlement individual processing (T. code: K088)
Give the order No: 60002845
Settlement period: 9
Fiscal year: 2006
Select test run check box

177

Execute
Select back arrow
Deselect test run check box
Execute
Select detail list button
Select accounting documents button
Select accounting document number
50 300201 Inc/Dec in stock WIP 2625 P & L A/C
40 200123 Work in process 2625 Balance sheet
Actual overhead calculation
Path: up to period end closing the path is same
Single functions overhead individual processing (KGI2)
Give the order No: 60002845
Period: 9
Fiscal year: 2006
Select test run check box
Select dialog display check box
Execute
Select back arrow
Deselect test run check box
Execute
Confirmation of production order:

178

Logistics production production control confirmation enter for operations


time ticket (CO11N)
Give the order number: 60002845
Operation: 10
Confirmation type: select final confirmation
Yield: 10kgs
For activity2: give the qty: 60
Unit of measurement: H
Save
Production receipt against production order
Logistics materials management inventory management goods movement
goods receipt for order (MB31)
Give the document date & posting date: 21.12.2006
Movement type: 101
Give order No: 60002845
Plant: AMLP
Storage location: Hyd
Enter, ignore the warning message and press enter
Save
From the menu select goods receipt display
Enter
Select accounting documents button
Select accounting document No
To make order technically complete (IECO)

179

Logistics production production control order change (CO02)


Give the order No: 60002845
Enter
To close the order from the menu select functions restrict processing technically
complete
Save
Assign variance key in material master (MM02)
Give the material No: AMLFG1
Select organization levels button
Plant: AMLP
Enter
Select costing 1 tab
Assign variance key: AML
Save
Calculation of variances:
Up to period end closing the path is same
Single functions Variances individual processing (KKS2)
Give the order: 60002845
Period: 9
Fiscal year: 2006
Select test run check box
Execute
Select back arrow
Deselect run check box
Execute
Open one more session with (T. Code: CO03) (Order display)

180

Give the order No: 60002845


Enter
From the menu select go to costs analysis
Calculation of work in process once again for December (KKAX)
Give the order number: 6002845
WIP period: 9
Fiscal year: 2006
RA version: 0
Select test run check box
Execute
Select back arrow
Deselect test run check box
Execute
Settlement of work in process of accounts (K088)
Give the order No: 6002845
Settlement period: 9
Fiscal year: 2006
Select test run check box
Execute
Select back arrow
Deselect test run check box
Execute
Select detailed list button
Select accounting documents button
Select accounting document no
91 300200 Inc/Dec in stock FG1 975 (AMLFG1 AML2 GBBAVA
83 400201 Prod. Order difference 975 AMLFG1 AML2 PRD

181

40 300201 Inc/Dec in stock WIP 2625


50 200123 work in process.
THE END