Presentedby
MagA.Risk,P.E.
Principal
p
Youmaydownloadthis
p
presentationfromthe
followingwebsite:
htt //
http://www.conrisk.com/seminar_presentations.asp
i k
/
i
t ti
Thepresentationwillbeavailableuntil12/31/08
p
/3 /
Typesofdelay
yp
y
1. Critical orNonCritical
2. Excusable orNonExcusable
3. Concurrent
C
orNonConcurrent
N C
4 Compensable orNon
4.
orNon
Compensable
p
TypesofDelay
NonCriticalDelays:
Impactaportionoftheworkwithavailablefloat
timeallowingtheprojecttobecompletedontime
CriticalDelays:
Impactaportionoftheworkexceedingfloattime
availableanddelayingtheproject
CriticalDelays
ExcusableDelay
Adelaybeyondthecontrol orfaultofacontractor
orowner(e.g.ForceMajeurecausesincluding
weather fire flood&actofGod)
weather,fire,flood&actofGod)
NonExcusableDelay
N E
bl D l
Thecontractorsfault
Excusable Delay
NonCompensable:
Contractorentitled toatimeextension butnot to
delaydamages
Delaydueto:
Weatherdelay
h d l
Strikes
ActsofGod
contractorandcouldhavepotentiallybeenavoided
hadthecontractorexercisedcare
Excusable/Compensable
/
p
ProofofDelay
Contractormustproofthatdelayscausedbythe
compensabledelay
10
FormalRequests
Requestsforatimeextensionand/oradded
compensationmustbemadeformally:
ComplywithContractNoticeRequirements
Providesupportingdocumentation:
P id
ti d
t ti
AFragnet
AF
d i i
depictingtotaldaysofimpacttothe
ld fi
h
criticalpath
Adetailedcostbreakdown
Ad t il d tb kd
11
Exampleofa
FormalRequest
12
December 1, 2006
Mr. Owner
1000 Any Road
New York, NY 01000
Subject:
Reference:
Contract Agreement
Completion Date
October 19, 2006
May 7, 2007
July 9, 2007
The current completion date of July 9, 2007, for building H incorporates the current design delivery dates received
from the Architect on 6/29/06 reflecting the following:
Building
Design Review
Committee
Approval
7/24
Shell to
Consultants
8/4
Early Steel,
Concrete &
Brick
8/25
Foundation
Permit
Drawings
8/28
100% CD
9/29
p
drawings,
g , we are unable to incorporate
p
sufficient detail for the steel
Due to the lack of detailed completed
sequencing and erection for building H into the attached progress schedule.
Once the completed drawings become available, we shall incorporate such detail and notify you of any additional
requirements and/or impacts to the completion dates. We shall also have the ability to notify you of any additional
requirements to perform work in winter conditions due to the slippage directly attributable to the delay in the
delivery of completed design documents.
The current
c rrent design for building
b ilding H is still in conceptual
concept al form.
form We reserve
reser e our
o r right to additional req
requests
ests for time
extensions based on the actual design, delivery dates, detailing of the sequencing and erection of steel activities for
building H, as may be applicable.
13
14
ManagingRisk
Theprocessofmeasuring,orassessing risk and
developingstrategies tomanageit.
tomanageit
TypesofRisk
11. Contractual
2. Construction
15
ContractualRisk
16
ContractualRisk
1. NoDamageForDelay
Contractor'ssoleremedyfordelay,lossof
productivity,impactdamagesorother
productivity
impactdamagesorother
similarclaimsshallbeanextensionoftime
i hi ht
inwhichtocompletethework.Innoevent
l t th
k I
t
shallContractorbeentitledtoadditional
compensationordamages fordelay."
17
NoDamageForDelay
Theownershallnot
Th
h ll t beliablein
b li bl i
monetarydamages
y
g forthecostof
delayswhicharisefromactsor
omissionsforwhichtheowner
i i f hi hth
i
is
responsible
p
18
ContractualRisk
2. LimitedDelayDamages
TheContractorssoleremedyforanydelayinthe
commencement,prosecution,orcompletionoftheWork,
orforhindrancetotheperformanceoftheWork,lossof
productivity orothersimilarclaims shallbeanincreasein
productivity,orothersimilarclaims,shallbeanincreasein
theContractTime unlesscausedbyactsconstituting
intentionalinterferencebytheOwner.TheContractorshall
beentitledtoanincreaseintheGeneralConditions ifthe
f
ContractorsGeneralConditionshaveactuallybeen
increased asaresultofadelaytothecriticalpathofthe
ProjectSchedule causedbytheimproperactsoromissions
oftheOwner.
19
Reduce/EliminateContractualRisk
3. DelayDamages
D l D
"IntheeventthatContractor's
IntheeventthatContractor s
performanceisdelayedorhindered,
throughnofaultofitsown Contractor
throughnofaultofitsown,Contractor
shallbeentitledan extensionoftime
co espo d g to t e u be o days ts
correspondingtothenumberofdaysits
performancewasdelayed,andshallbe
entitledtoadditionalcosts relatedtosuch
delayorhindrance."
20
SubcontractorsRecoveryofDelayDamages
fromGeneralContractor
4 ConditionalRecovery
4.
21
"Subcontractoragreesthatitshallnotbeentitledtonor
Subcontractoragreesthatitshallnotbeentitledtonor
claimanycostreimbursementordamagesforanydelay,
obstruction,hindranceorinterferencetotheWork,
,
,
excepttotheextentthatGeneralContractorisentitled to
correspondingcostreimbursement,compensationor
d
damagesfromtheOwner
f
h O
undertheContractDocuments
d h C
D
andthenonlytotheextent oramount,ifany,which
GeneralContractoronbehalfofSubcontractoractually
receivesfromtheOwner onaccountofsuchdelay,
obstruction,hindranceorinterference."
,
The Fundamentals of Construction Contracts, Peabody, MA 12/11/08
ConditionalRecovery
Subcontractorsrecoveryofdelaydamagesis
y
y
g
contingent uponthecontractorprevailing inits
claimfordelaydamagesagainsttheowner
22
AIAGeneralConditionsoftheContractfor
Construction
Delays&ExtensionsofTime
8.3.1IftheContractorisdelayedatanytimeinthecommencementorprogressof
theworkbyanactorneglectoftheOwnerorArchitect,orofanemployeeof
either,orofaseparatecontractoremployedbytheOwner,orbychangesordered
intheWork,orbylabordisputes,fire,unusualdelayindeliveries,unavoidable
casualtiesorothercausesbeyondtheContractorscontrol,orbydelayauthorized
bytheOwnerpendingmediationandarbitration,orbyothercauseswhichthe
Architectdeterminesmayjustifydelay,thentheContractTimeshallbeextended
h
d
f d l
h
h
h ll b
d d
byChangeOrderforsuchreasonabletimeastheArchitectmaydetermine.
8.3.2Claimsrelatedtotimeshallbemadeinaccordancewiththeapplicable
provisionsofParagraph4.3
8.3.3Thisparagraph8.3doesnotprecluderecoveryofdamagesfordelay
by e t e pa ty u de ot e p o s o s o t e Co t act ocu e ts
byeitherpartyunderotherprovisionsoftheContractDocuments
23
OwnersRemedytoRecoverDamagesfor
Delay
5. LiquidatedDamages
Anagreeduponamountperdayfor
delaysencounteredontheprojectwhich
arecausedbythecontractor
db th
t t
24
OwnersRemedytoRecoverDamagesfor
Delay
6. ConsequentialDamages
7 ReverseLiquidatedDamages
7.
25
Ratherthanprohibitdelaydamages,thepartiesmay
agreethattheownersliabilitytothecontractorshall
th tth
li bilit t th t t h ll
belimitedtoanagreeduponamountperdayfor
delaysencounteredwhicharecausedbytheowner.
delaysencounteredwhicharecausedbytheowner
RiskAllocation
Generally,acontractormayrecoverdamages
Generally
acontractormayrecoverdamages
arisingfromdelay&disruptionifitcanprove:
Thecontractorsworkwasdelayed ordisrupted
Thecontractorsuffered damagesasaresult
Theownerand/oritsagentsareresponsible
g
p
forthe
actsoromissionswhichcausedthedelayor
disruption
4. Thelanguageofthecontractallows thecontractor
torecoverdamagesfordelayordisruption
1.
2.
33.
26
RiskAllocation
Partiestoaconstructioncontractmayelectto
prohibitorlimitcompensabledelayclaims:
Contractualclausesgoverningtherights&liabilities
forprojectdelaysallocate risk
Reviewtheprovisionsofyourcontractpriorto
executiontounderstandhowthesubstantial
risksassociatedwithprojectdelayshavebeen
allocated
27
ChangesintheWork
28
ChangeOrders
Awrittenorder issuedafter acontracthasbeen
29
AChangeOrdercouldbeIssuedbyanOwner
asaResultof:
Unforeseenorunanticipatedfieldconditions
Unforeseenor
nanticipatedfieldconditions
2. Correctionofdesigndiscrepancies,orerrorsor
omissionsinthecontractdocuments
3. Ownerrequestedchangestoenhancethe
g
presentdesign
4. Changesinthecompletiondate
5. Changesinbuildingcodeinterpretations
6 Changesinavailabilityofexistingornew
6.
Ch
i il bilit f i ti
materialandproducts
1.
30
ChangeCategories
1. DirectedChanges
Areacknowledgedchangesbytheownertoa
contractedscopeofwork
Examples
Architectmodifiescontractedscopeofwork
h
df
d
f
k
Ownerwishestomakebettermentsand/or
substitutionsofproducts
b tit ti f d t
31
ChangeCategories
2. ConstructiveChanges
Arenot readilyacknowledgedbytheownertoa
contractedscopeofwork
Examples
Performingworkoutofnormalsequence
f
k
f
l
Actualjobconditionsaredifferentthanthey
appearedattimeofbid
d tti fbid
Requestingtimeextensions
32
ChangeCategories
3. CardinalChange
Takeaprojectbeyond theoriginalscopeofwork
thatwascontracted
Entitlementisnotassertedby
EntitlementisnotassertedbyContract
Contract
adjustmentprocedures
Examples
Ifyouwerecontractedtobuildagarageandthe
ownerdecidestoaddahousetotheproject
33
ClaimsAndDisputes
p
34
CausesofConstructionClaims
1. ProjectDelay
Delaysinconstructionprojectsareexpensive
because:
thereisusuallyaconstructionloaninvolved
whichchargesinterest
g
managementstaffdedicatedtotheproject
whosecostsaretimedependentand
p
ongoinginflationinwageandmaterialprices
35
CausesofConstructionClaims
2. Acceleration tomeetContractMilestoneDates:
Remedies:
36
ContractDateshavenotbeenextended
ContractorsobligationresultsinConstructive
Acceleration
Progresstheschedulebiweeklyormonthly
Progresstheschedulebi
weeklyormonthly
Determinepercentcomplete relativetoBaseline
Id tif d l d
Identifydelaysandresponsibility
ibilit
DevelopRecovery plans
The Fundamentals of Construction Contracts, Peabody, MA 12/11/08
CausesofConstructionClaims
3. LackofCoordinationbyOwnerorCM
TypeofContractdictatesresponsibilities(Multi
PrimeContractingvs.Single)
LackofManagement:considertheenormous
LackofManagement considertheenormous
effortrequiredtocoordinatetheactivitiesof1500
tradesmenonaprojectduringpeakperiods
ExcessiveManagement:considerthe
inefficienciesassociatedwithmicromanagement
37
CausesofConstructionClaims
4. ChangesintheWork
ChangesinWorkSequence
ToomanyChangeOrders (turnedouttobe
Design/Build)
9 Remedies:
38
Analyzeimpact:insertproposedchangeorder
intoprogressschedule
CausesofConstructionClaims
5. WorkRestrictions&Limitationsof
Operations
Accessrestrictionstocontractorswork
Workhoursrestrictions
W kh
t i ti
Noiserestrictions
9 Remedies:
39
Includeallrestrictionsandlimitationof
operationsinthecontract.
SupportingConstructionClaims
TimelyNotices
ComplywithNoticerequirementsinthecontract
Reserveyourrights
SupportingDocumentation:
pp
g
CostImpact
ScheduleImpact(Fragnets)
40
TypesofContractorDelayDamages
11. DirectCosts
2. IndirectorConsequentialDamages
41
DirectCosts
a) Mobilization/Demobilizationcosts
b) Costsofstandbytime/idleequipment
c) Extendedgeneralconditions&fieldoffice
g
overhead
d)) Extendedhomeofficeoverheadduringdelay
g
y
period
e) Increasedlabor&materialcosts
f) Lossofproductivityduetodelaysandhavingto
altermethodsofperformance
42
ReserveYourRights
SubmitformalNoticeofDelaytimely
Sometimesyouareunabletoascertainimpact
earlyon:
Acknowledgeimpactcannotbedeterminedatthis
time
Reserveyourrightstofuturerequests
43
Languageto
ReserveYourRightstoFuture
Requests
Weherebyreserveourrightstosubmitrequests
foradditionalunforeseenconditions.Additional
requestsshallinclude butnotbelimitedto time
requestsshallinclude,butnotbelimitedto,time
extensions and/oraddedcosts tocompensateus
toperformadditionaloutofscope work.
work
44
DevelopingStrategies
t M
toManageRisk
Ri k
45
FactorsContributingto
g
ConstructionRisk
IncompleteDesign
Ambiguousplans
CoordinationoftheWorkbyOwnerorCM
Interferences/Unanticipatedconditions
ChangesintheSequenceoftheWork
ExcessiveChangeOrders
LackofProgressbyOtherTrades
46
ProjectRiskPlanning
Projectplanning isamust
CommonPitfalls
Thechallengesonemightencounterinan
organizationthatfeelsaprojectplanning
methodologyisnotneeded.
methodologyisnotneeded
47
ProjectPlanning
IspartoftheProjectManager'sarmourythat
mustbeinplacetoensurethateffective
controloftimeandbudgetovertime is
managedwithintheprojectenvironment
managedwithintheprojectenvironment.
TodothisaWorkBreakdownStructure (WBS)
mustbeidentifiedandactivitiesassociated
witheachelementofit.
48
ManagingRisk
DevelopChangeManagementSystem
ManageDelay
DevelopBaseline
Progressschedulebiweekly
Analyzedelay,changes
DevelopRecoveryPlans
DevelopFragnets
Requesttimeextensions&addedcompensation
49
AnalyzeScheduleImpact
ImpactduetoChanges:
InsertaproposedChangeOrder intotheprogress
scheduletoanalyzeimpacttoprojectcompletion
milestonedates
AnalyzeimpactduetochangesinWorkSequence
DevelopFragnet
D l F
t tosupportTimeExtension
t
tTi E t i
Requests
IdentifyAdditionalResources
Id tif Additi
lR
&C t requiredto
&Cost
i dt
performadditionalwork
50
ChangeManagementSystem
DevelopaChangeManagementSystem to
expeditetheissuanceofFormalChange
Orders:
ProvidetimelyNotice
P id ti l N ti
IdentifyScope ofchange
Identifylabor&materialcosts
ProvidesupportingDocumentation
Desiredresults:Performextraworkafterissuance
ofFormalChangeOrdertoexpeditePayment
g
p
y
51
52