onstructing
Mechanically
Technical
Aerated
lagoons
A mechanically
aerated
lagoon is
similar
to a stabilization
pond except
that it is equipped
with one or more
electrically
powered aerators
that
treat
effluent
by mixing
it with air.
Constructing
a mechanically
aerated
lagoon requires
the services
or an
engineer
or construction
foreman
experienced
with these systems.
Construction
involves
assembling
materials,
tools,
and labor;
preparing
the site;
staking
the lagoon,
embankment, and pipe locations;
excavating
the lagoon;
building
embankments;
lining
the lagoon;
laying
pipes;
finishing
embankments;
and installing
aerators.
\
Branch sewer line
Main sewer line
Mechanically
This technical
note describes
how to
construct
a mechanically
aerated
lagoon.
Most of the steps are identical
to those described
in
"Constructing
Stabilization
Ponds,"
SAN.2.C.5.
Read the entire
technical
note before beginning
construction.
aerated
Maturation
pond /II
Useful Definition
- Settled
sewage.
Table 1. Sample Materials List for Aerated Lagoon
Materials
Needed
Before construction
project
designer
must
can begin,
provide:
1) Location
map, or master
to Figure
1.
map, similar
2) Design drawings,
Figure
2 and 3.
3) Materials
1 the
tion
list,
similar
similar
the
sewer
to
to Table
sample.
4) Aerator
Manufacturer's
and specification
sheet.
instruc-
You will
also need the technical
note "Constructing
Stabilization
Ponds,"
SAN.2.C.5.
Construction
Steps
Depending
on local
conditions,
availability
of materials,
skills
of
and so on, some construction
workers,
Embankmentr
p
3
will
then have an Idea of when specific
and tools
must be
workmen, materials,
available
during
the construction
proDraw up a work schedule
to Table
cess.
2, showing construction
steps.
Preparing
I
Distances for
aerator placemer
I
the Site
See "Constructing
Ponds,"
SAN.2.C.5.
Aerated lagoon-
Staking
Lagoon,
Locations
Embankment,
See "Constructing
Ponds,"
SAN.2.C.5.
Excavating
Maturation
Building
laying
steps will
take only a few hours,
while
Read
others
may require
a day or more.
the construciton
steps and make a rough
estimate
of the time required
for each
You
step based on local
conditions.
\
Top View
Stablization
Stabilization
Pipes
See "Constructing
Ponds,"
SAN.2.C.5.
Lining
Stabilization
Embankments
See "Constructing
SAN.2.C.5.
Ponds,"
and Pipe
the lagoon
See 'lConstructing
Ponds,"
SAN.2.C.5.
pond
Stabilization
Stabilization
the Lagoon
1 Eyelet for
mooring line
edbankment
---
-.,^-----r------crC
Inside of
embankment
Side View
Electrical
hook-up
;-
Mortar between;/
rocks
Eyelet for
mooring line
Bottom of lagoon
covered with 50mm sand
Propeller
Figure 3. Aerator
..I
day
1% days
Task
Day
l-2
Personnel
Maps, drawings,
surlng tape
mea-
6 workers
Axes, machetes,
cart
site
Scrape topsoil
and
pile for finishing
embankment
6 workers,
operator
1 day
1 surveyor,
1 day
5-8
Picks, shovels,
1OOmm
diameter sewer pipe,
pipe valves,
mortar
6 workers,
1 worker
skilled
with mortar
Sand, flat
stones,
chipping
hammers,
safety goggles, mortar
1 loader
Loader, shovels,
soil,
sod
14-15
Finish
16-17
Transit,
level,
level
rod, steel measuring
tape, stakes
6 workers,
1 worker
skilled
with mortar
2 days
l%- days
l&2-
3 workers
loader,
Dig pipe
lay pipe
Line
16
Front-end
shovels
6 workers
10-13
10-13
day
1 loader
4 days
ti
Materials/Tools
Engineer or experienced
foreman (always pre2 workers
sent),
Mark lagoon
1 day
4 days
an Aerated Lagoon.
trenches
the lagoon
embankment
and
1 loader
6 workers
operator,
I
operator,
Set securing
posts
4 workers
Lay electric
cable
1 electrician,
4 workers
Finishing
Front-end
shovels,
Posts,
Electric
I tricians
els
Installing
shovels
cable,
tools,
I
elecshov-
Stabilization
Aerators
Floating
aerators
are
electric
cables and held
mooring
lines
attached
to
posts on the embankment.
3. Pour concrete
mortar
between the
stones and smooth with a trowel.
The
mortar
should be 1 part cement, 2-3
parts
sand, and enough water to make a
very wet, pourable
mix.
top-
Embankment
See ffConstructing
Ponds,"
SAN.2.C.5.
2. Stones
used must be at least
25mm
thick.
Fit
them as close together
as
possible.
Use a stonemason's
chipping
hammer to Improve the fit
between the
stones and wear protective
goggles.
loader,
picks,
carts
connected
to
In place by
securing
See Figure
5.
1. String
electric
cable from the
power source to the lagoon site.
Cables should be suspended
overhead
or
buried
underground,
and they should be
3
protected
from damage caused
ment maintenance.
by embanklop View
Securing
3. The aerators
cannot be positioned
until
the lagoon is filled
to its
design depth with effluent.
See
"Operating
and Maintaining
Mechanically
Aerated Lagoons,"
SAN.2.0.7.
post
Outdoor electrical
enclosure
Side View
Outdoor electrical
Bonom of
Buried electric
cable
Figure 5. Positionlng
TechnicsI Notea
are part of a set of Water for the World materials produced under contract to the U.S. Agency for International Development by National
Demonstration Water Project, Institute for Rural Water, and National Environmental Health Association. Artwork was done by Redwing Art Service. Technical Notes are
intended to provide assistance to a broad range of people with field responsibility for village water supply and sanitation projects in the developing nations. For more
detail on the purpose, organization and suggestions for use of Technical Notes, see the introductory Note in the series, titled Using Water for the World Technical
Notes. Other parts of the Water for the World series include a comprehensive
Program Manual and several Policy Perspectives. Further information on these
materials may be obtained from the Development Information Center, Agency for International Development, Washington, D.C.. 20523. U.S.A.