Mould oils will alleviate these defects. Mould oils are designed to
overcome these problem specially using steel forms by encouraging
the trapped air to slide up the surface of the formwork.
Care to be taken since some oils cause some retardation of the
setting time of the cement causing the defect Dusting.
Emulsions are easy to apply but may promote rusting in steel forms.
Oils and emulsions are release agents and it is essential they are
only applied to the form work and not to the reinforcement since
this may cause a reduction of bond.
Spacing of ties and clamps are depend on the actual concrete
pressure at the location. Pressure will vary according to
Rate of placing
Type of mix richer will be the grater
Method of placing if vibrators are used pressures can
be increased up to 50% over hand placing.
Air temperature lower temperature the slower is the
hydration and consequently higher pressures.
1. Preliminary preparations/Pre planning
Reference of latest drawing
Shop drawing to be prepared
Surrounding area to be cleaned
Level and lines to be obtained
Idea about the sizes of columns, beams, slab thickness and wall
thickness and heights also their locations and elevations etc.
Organize required materials plywood, nails, nut and bolts, form oil,
timber, frames, How many?
Required accessories - props, pipes, tie rods, soldiers, P- cones,
threaded bars, wing nuts, rapid clamps
Priority areas to be identified
Identify the sizes and locations of openings, drops, ducts etc.
Kickers to be checked with the setting out
Co-ordination with R/F, Concrete, M&E parties etc.
Check whether there any built-in parts in the concrete.
2. Pre-Concrete works
Verticality to be checked (Columns, walls, beams sides)
Levels to be checked.( Columns, walls, slabs, beams etc)
Method of concrete to be pre determined (to plan the scaffolding
etc)
Props to be checked
Joints, holes and connections to be checked properly.
Cleanliness in the formworks Column heads, beam bottoms
specially.
Keep cleaning provisions in the form work specially in the columns.
3. Post concrete inspections
Verticality to be checked
System Formwork
Systematic / Methodical / Easy to erect
Quality finish
Virtually zero fabrication
No fabrication debris
Speedy construction
Less indirect works for construction gangs
Easy / Clear planning
Easy to monitor and control
(-) ves
High initial capital cost / High maintenance cost
Make up panels for missing and lost ones
Zero sharing
Strict material planning and management required
Accessories are costly and liable to get lost
Well trained technical support
High welding and fab. Cost
Zero changes/ alterations
Noise during errection
Consistent labour gangs / Labour disputes
Work specialization
Theft
Climbing Shutters