WORK PROCEDURE
PROJECT:
SECTION:
FOUNDATIONS
SUBJECT:
BORED PILING
1.
SCOPE
The scope of this procedure covers the control of
installation of Bored Cast-in-Situ Concrete piles
executed by a sub-contractor.
2.
PROCEDURE
.1
Method Statement:
A method statement shall be submitted by the piling
Sub-contractor for approval which shall include:
Project
Manager
Method
Statement
i)
ii)
iii)
iv)
Construction procedure.
Pile design with calculations.
Testing procedure.
Documentation to be maintained during the
execution of work.
v)
Mix design for concrete.
vi)
Specification for reinforcement steel and
bentonite clay.
vii) Any other information required by the
specification.
.2
.3
.4
Construction Programme:
SubThe sub-contractor shall submit a programme for contracto
approval based on the Contract Programme. The r
subcontractor shall also indicate the mobilisation
time of plant, equipment, materials and work force.
Project
Piling Sequence:
Manager
Approval of piling sequence will be given prior to
commencement of piling by the Subcontractor.
Setting-Out:
HEE will execute pre-piling setting out and offer for
cross-checking by Subcontractors Surveyor and
Consultants Representative.
Subcon/
FCC
Surveyor
Approved
Constructi
on
Programm
e
Approval
Field Book
WORK PROCEDURE
PROJECT:
SECTION:
FOUNDATIONS
SUBJECT:
BORED PILING
.5
Source Certificates:
Reinforcement steel and Bentonite test certificates if Project
required shall be obtained from the Subcontractor Engineer
and, submitted for approval by the Consultant.
.6
.7
Subcon.
Pile testing
record
Inspection of Work/Checksheet:
The work shall be inspected using the attached
checksheet as Appendix FOUN/04/A which shall be QA/QC
completed as verification and record of compliance.
.9
Test result,
FOUN/04/A
Testing of Piles:
The Subcontractor shall carry out a load test and
integrity test as specified in the Contract.
.8
Source
certificate
Checkshee
t
Non-Conformity:
Non-conforming workmanship shall be notified to
the Subcontractor as Appendix 7/3/6/A and QA/QC
corrective action taken in accordance with good
working practice and Consultants approval.
NonConformity
Report
PROJECT:
SITE NO.:
CHECK SHEET FOR BORED PILING
SUBCONTRACTOR:
Sheet No.
FATAYERJI
INSTALLATION
ITEM
Check
ed
by
PE
PE
SU
APPROVAL TO PROCEED
4. Check borehole to be filled with
Bentonite
slurry at all times.
QA/QC
GF
SE
Lab
SU
CM
DATE
GF
GF