BORED PILING METHOD STATEMENT.

WORK PROCEDURE
PROJECT:
SECTION:
FOUNDATIONS
SUBJECT:
BORED PILING

1.

Ref No. FOUN/04


PAGE 1 OF 2
DATE OF ISSUE
Dec 2012
BY:
QA/QC ENGINEER
APPROVED BY:
QEHS MANAGER
ACTION
VERIFY

SCOPE
The scope of this procedure covers the control of
installation of Bored Cast-in-Situ Concrete piles
executed by a sub-contractor.

2.

PROCEDURE

.1

Method Statement:
A method statement shall be submitted by the piling
Sub-contractor for approval which shall include:

Project
Manager

Method
Statement

i)
ii)
iii)
iv)

Construction procedure.
Pile design with calculations.
Testing procedure.
Documentation to be maintained during the
execution of work.
v)
Mix design for concrete.
vi)
Specification for reinforcement steel and
bentonite clay.
vii) Any other information required by the
specification.
.2

.3

.4

Construction Programme:
SubThe sub-contractor shall submit a programme for contracto
approval based on the Contract Programme. The r
subcontractor shall also indicate the mobilisation
time of plant, equipment, materials and work force.
Project
Piling Sequence:
Manager
Approval of piling sequence will be given prior to
commencement of piling by the Subcontractor.
Setting-Out:
HEE will execute pre-piling setting out and offer for
cross-checking by Subcontractors Surveyor and
Consultants Representative.

Subcon/
FCC
Surveyor

Approved
Constructi
on
Programm
e
Approval

Field Book

WORK PROCEDURE
PROJECT:
SECTION:
FOUNDATIONS
SUBJECT:
BORED PILING

.5

Ref No. FOUN/04


PAGE 2 OF 2
DATE OF ISSUE
Dec 2012
BY:
QA/QC ENGINEER
APPROVED BY:
QHSE MANAGER
ACTION
VERIFY

Source Certificates:
Reinforcement steel and Bentonite test certificates if Project
required shall be obtained from the Subcontractor Engineer
and, submitted for approval by the Consultant.

.6

Concrete Cube Testing:


Project
Cube results will be assessed and retained. The cube Engineer/
test reports shall be clearly identified with the Labtech.
location of pour by reference to the checksheet.

.7

Subcon.

Pile testing
record

Inspection of Work/Checksheet:
The work shall be inspected using the attached
checksheet as Appendix FOUN/04/A which shall be QA/QC
completed as verification and record of compliance.

.9

Test result,
FOUN/04/A

Testing of Piles:
The Subcontractor shall carry out a load test and
integrity test as specified in the Contract.

.8

Source
certificate

Checkshee
t

Non-Conformity:
Non-conforming workmanship shall be notified to
the Subcontractor as Appendix 7/3/6/A and QA/QC
corrective action taken in accordance with good
working practice and Consultants approval.

NonConformity
Report

PROJECT:

SITE NO.:
CHECK SHEET FOR BORED PILING

SUBCONTRACTOR:

Sheet No.

FATAYERJI

SECTION OF WORK ____________________________LOCATION _________________


STAGE
PREPARATION

INSTALLATION

ITEM

Check
ed
by

1. Subcontractors method statement


approved.

PE

2. Materials approved by the consultant.

PE

3. Cross-check location of Pile.

SU

APPROVAL TO PROCEED
4. Check borehole to be filled with
Bentonite
slurry at all times.

QA/QC

5. Check cleaning of bottom of borehole.

GF

6. Check reinforcement cage.


7. Check minimum cover while lowering
cage into the borehole.

SE

8. Check slump of concrete.

Lab

9. Check cut-off level + location.

SU

APPROVAL TO PROCEED WITH PILE


CAP.

CM

DATE

GF

GF

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE - Project Engineer,


SE Site Engineer, GF General Foreman, SU - Surveyor, Lab - Laboratory Technician