Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
Equitable risks allocation of projects inside China: analyses from Delphi survey studies
Yongjian Ke ShouQing Wang Albert P.C. Chan
Article information:
To cite this document:
Yongjian Ke ShouQing Wang Albert P.C. Chan, (2011),"Equitable risks allocation of projects inside China:
analyses from Delphi survey studies", Chinese Management Studies, Vol. 5 Iss 3 pp. 298 - 310
Permanent link to this document:
http://dx.doi.org/10.1108/17506141111163372
Downloaded on: 23 May 2015, At: 03:41 (PT)
References: this document contains references to 24 other documents.
To copy this document: permissions@emeraldinsight.com
The fulltext of this document has been downloaded 413 times since 2011*
Access to this document was granted through an Emerald subscription provided by 534288 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald for
Authors service information about how to choose which publication to write for and submission guidelines
are available for all. Please visit www.emeraldinsight.com/authors for more information.
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
The current issue and full text archive of this journal is available at
www.emeraldinsight.com/1750-614X.htm
CMS
5,3
298
Yongjian Ke
Department of Building, National University of Singapore, Singapore
ShouQing Wang
Department of Construction Management, Tsinghua University,
Beijing, China, and
1. Introduction
Public-private partnership (PPP) has been identified as an innovative tool for
financing major infrastructure projects and has huge potential for the near future.
The work described in this paper was fully supported by a joint grant from the National Natural
Science Foundation of China (Project No. 70731160634) and the Research Grants Council of the
Hong Kong Special Administrative Region, China (RGC Project N_PolyU514/07). Special gratitude
is extended to those industrial practitioners who have kindly participated in the interviews
reported in this paper. This paper forms part of the research project entitled Developing an
equitable risk-sharing mechanism for public-private partnership projects in the Peoples Republic
of China, from which other deliverables have been produced with different objectives/scope but
sharing common background and methodology. The authors also wish to acknowledge the
contributions of other team members including Dr Patrick T.I. Lam, Dr Daniel W.M. Chan,
Dr Edmond W.M. Lam, Dr John F.Y. Yeung, Dr Esther Cheung, Yelin Xu, Wendy Wen, Tony Peng
and Calvin C.P. Yu.
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
On 9 November 2008, the Chinese Government announced that China would relax
credit conditions, reduce taxes and embark on a massive infrastructure spending
program in a wide-ranging effort to offset adverse global economic conditions by
boosting domestic demand (Chinese Governments Official Web Portal, 2008). With the
four trillion RMB stimulus plan as announced by the Chinese Government, only
1.18 trillion came from the central government, the rest was topped up by the local
government, and/or the private sector (State Development and Reform Commission,
2009). Since most of the local governments are still subject to severe budgetary
pressure, there is a heavy reliance on the private sector investment. It is also worth
noting that Several opinions of the State Council on encouraging and guiding the
healthy development of private investment issued in May 2010 further widen the field
and scope of private investment, which include railway, water conservancy, petroleum
gas, telecommunication, land control, exploration and development of mineral
resources, policy-related housing, medical industry, education, social warfare service
and the national defense science and technology industry (State Council, 2010). These
might provide a great opportunity for private investors to get more involved in
infrastructure development via the PPP model.
However, PPP is not a panacea or a quick fix solution to deliver project financing and
realization (European Commission, 2003). The adoption of PPP may enable private
investors to charge a high tariff on the services provided, which used to be free in the
traditional procurement method (Wang, 2006); PPP projects often have high costs and take
up a long time in contract negotiation, which may not represent good value to all parties.
As a result, the deal may not materialize in the beginning or may falter in the end (Chan
et al., 2010). More importantly, the introduction of PPP has exerted much pressure on the
legal framework. In China, the PPP regulatory systems such as cost auditing, tariff
regulation, responsibility scope and boundary of regulatory agencies have not been fully
developed. These subsequently lead to a great deal of resistance from the conservative
wing, and are already slowing down some key reform projects (Zhang, 2009).
To ensure success for PPP projects in China, risk allocation should be clearly
communicated and understood between the collaborating parties. Both public and private
sectors therefore must pay particular attention to the procurement process to ensure
equitable risk allocation. The aim of this paper is to develop an equitable risk allocation
scheme for PPP implementations in China. The research findings are believed to be useful
for organizations which intend to invest in infrastructure construction in China.
2. Literature review
An equitable risk allocation and management is important to the project success of a
PPP project within a rather long concession period (Zhang, 2005; Li et al., 2005a).
Governments would state their preference as to how the project risks should be shared
in the invitation of tendering, while private investors would assess their capability of
taking these risks and then propose a bidding price. The contract negotiation would
thereafter probably focus on the risk allocation scheme. A general principle is that each
risk should be allocated to the party best able to manage it and at the least cost
(Cooper et al., 2005). In other words, an optimal risk allocation is not to pass all risks to
the private sector, but to seek a solution minimizing both the total management costs
of the public and private sectors. Unfortunately, this criterion often causes contrasting
results in the risk allocation context. Sometimes, the partner from which the risk
Equitable risks
allocation
299
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
CMS
5,3
300
emanates and thus who is considered to be best able to control it, may not actually be
able to control the risk in the most efficient way and at the lowest cost (Medda, 2007).
A number of academic researchers have provided solutions to achieve equitable risk
allocation schemes. Among them, a questionnaire survey is the most common research
technique used. For instance, Li et al. (2005b) developed a preferred risk allocation
scheme for PPP projects in the UK and Roumboutsos and Anagnostopoulos (2008) and
Ke et al. (2010a) conducted a similar survey using the same questionnaire in Greece and
China, respectively, and then compared the findings to those in the UK. A case study is
another popular technique for exploring a suitable risk allocation scheme for PPP
projects, such as Abednego and Ogunlana (2006) and Ng and Loosemore (2007). Recent
researchers have developed more complicated and vigorous methods in the risk
allocation arena, such as game theory (Medda, 2007), the fuzzy synthetic allocation
model (Xu et al., 2010; Jin and Doloi, 2009), theoretical framework based on transaction
cost economics ( Jin and Doloi, 2008; Jin, 2010a) and the neuro-fuzzy decision support
system ( Jin, 2010b), etc.
3. Knowledge gap
It is easy to understand that risk allocation lessons learnt from past cases may not be
directly suitable for the future projects, as each project has its own characteristics.
Preferred allocations from experts via questionnaire surveys would be subjective and the
accuracy highly depends on the hand-on experiences of experts selected. There are also
pitfalls for the vigorous models developed recently. For example, the allocation models by
Xu et al. (2010), Jin and Doloi (2009) and Jin (2010b) mentioned hereinbefore could only deal
with one risk at one round of the complicated process. Moreover, given the observation
from previous research (Lyons and Skitmore, 2004) that there is an absence of risk
management culture and a lack of experts who are familiar with the risk management
tools in many construction companies, the potential application possibilities of these
vigorous models may not be as wide in scope as they should have been. A knowledge gap
therefore exists to develop an equitable risk allocation scheme that could be also applicable
in China. This study aims to fill the gap by furthering a previous published study (Ke et al.,
2010b), in which a two-round Delphi survey was conducted in Mainland China to analyze
the risks and their preferred allocations for PPP projects in China from the perspectives of
46 experts with in-depth knowledge and sound experience of risk management.
4. Research methodology
As mentioned above, the previous Delphi survey with experienced practitioners aimed
to seek for the preference of risk allocation in Chinas PPP projects based on their own
perceptions and understandings. The findings may not be applicable for all PPP
projects at this stage. A series of face-to-face interviews were therefore subsequently
carried out from March to May 2009 to collect actual risk allocations in some recently
completed PPP projects in China. By comparing the preferred and actual allocations
and discovering the reasons behind the differences, an equitable risk allocation scheme
for PPP projects in different sectors could be then obtained.
Instead of collecting pieces of project information and analyzing the risk allocation,
the authors requested the selected experts to provide their understandings on the
actual risk allocation in one of their successful PPP projects. Because the risk register
adopted in the previous research included 37 different risks (as presented in Table I),
ID Risk factor
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
1 Corruption
2 Governments intervention
3 Expropriation and
nationalization
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Definition
Equitable risks
allocation
301
Table I.
Checklist of PPP project
risk factors
CMS
5,3
ID Risk factor
Definition
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
302
29
30
31
32
33
34
35
36
37
Table I.
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
Experts only with direct involvement in one or more PPP projects were selected as
target interviewees. A total of 38 managers agreed to be interviewed after much
persuasion and follow-up telephone calls. They were requested to choose the most
successful PPP project they have participated in. The definition of successful in this
study is that by the time of interview the project achieves the triple-project goals,
i.e. completed on or ahead of time, within budget at an acceptable level of quality and
runs well with little conflict among the parties during the operation period. Table II
shows the respondents information and their roles in the past projects that the
interviewees reported as their PPP case studies. As presented in Table II, the selected
interviewees are middle-/high-level managers in their project and have rich experience
in PPP projects.
5. Results
The interview feedback concerning the preferred and actual risk allocations is collated
and summarized in Table III. The preferred allocation as presented in Table III shows
that the public sector would take the majority of responsibility for 13 risks related to
government or government officials and their actions. A total of 14 risks that neither the
public nor private sector could be dealt with alone are preferred to be shared equally. The
private sector would take the majority of responsibility for ten risks that are at the
project level.
This paper focuses on the reasons behind the differences and discusses whether the
actual allocation would be more appropriate for PPP projects in China. In line with the
previous study (Ke et al., 2010b), the risk allocation options are presented as mean
values of participants responses. Three risk allocation categories are identified
according to the half-adjusting principle:
(1) Risks with a mean score smaller than 2.5 that should be allocated to the public
sector.
(2) Risks with a mean score greater than or equal to 2.5 and smaller than 3.5 that
should be equally shared by both parties.
(3) Risks with a mean score greater than or equal to 3.5 that should be allocated to
the private sector.
As shown in Table III, there are nine risks of which actual allocations were different
with preferred allocations.
However, as mentioned above, differences in allocations would only be considered
if the t-test returns a significant result in mean values between two sets of
allocations. The correlation coefficient of the rankings on the preferred and actual
allocations was 0.953, which is much greater than the critical value of 0.275 at a 0.05
level. This result reinforces the rationale of the preferred allocation published in the
previous paper (Ke et al., 2010b). Furthermore, the independent two-sample t-test was
undertaken to examine if there was any significant difference in mean value
responses between the two groups of allocations for each of the 37 risks discussed.
There are five risks which had different actual allocations and fell below the
significance level of 0.05, i.e. public/political opposition, foreign exchange and
convertibility, supporting utilities risk, organization and coordination risk and
tax regulation changes.
Equitable risks
allocation
303
CMS
5,3
No. Title
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
1
2
304
3
4
5
6
7
8
9
10
11
No. of PPP
involved
Project type
Investment
(billion RMB)
More than 20
4
More than 6
30
Power
Power
5.6
0.3
Power
Less than 5
5
More than 20
Less than 5
Less than 5
6-10
11-15
1-3
2
More than 6
1-3
1-3
1-3
More than 6
Power
Power
Power
Power
Power
Transport
Transport
0.07
0.8
0.65
0.14
5.6
Less than 5
1-3
Transport
0.4
Project role
Project company
Government
agency
Project company
Consultant
Project company
Project company
Project company
Consultant
Contractor
Designer and
contractor
Supervisor
4
6-10
10
1-3
Transport
Transport
1.77
0.6
14
15
16
Contract
manager
Vice manager
Contract
manager
Director
Project manager
Project manager
6-10
Less than 5
3
1-3
1-3
4
0.3
0.23
17
Chief engineer
6-10
1-3
0.59
Project company
18
Consultant
Less than 5
1-3
0.6
Consultant
19
20
21
22
23
Chief engineer
Project manager
Vice president
Manager
Deputy director
6-10
Less than 5
6-10
5
7
1-3
1-3
1-3
10
2
Transport
Transport
Waste
treatment
Waste
treatment
Waste
treatment
Water
Water
Water
Water
Water
Consultant
Government
agency
Supervisor
Consultant
Lender
0.84
0.3
0.1
0.4
0.03
24
25
26
27
28
Lawyer
Consultant
Consultant
Project manager
Project manager
8
4
3
Less than 5
Less than 5
3
11
12
1-3
1-3
Water
Water
Water
Water
Water
0.07
0.4
0.65
0.3
0.1
29
Legal counsel
Water
0.645
30
31
32
33
34
35
36
2
Less than 5
Less than 5
6-10
5
8
8
5
1-3
1-3
1-3
1
40
5
Water
Water
Water
Water
Stadium
Hospital
Housing
0.043
0.06
0.103
0.84
3.465
0.046
0.3
37
Consultant
Manager
Consultant
Dean
Legal manager
General manager
Vice general
manager
Project manager
Project company
Project company
Project company
Consultant
Government
agency
Project company
Consultant
Consultant
Contractor
Government
agency
Government
agency
Consultant
Project company
Consultant
Consultant
Project company
Consultant
Consultant
Less than 5
1-3
Housing
0.16
38
Director
Less than 5
1-3
Housing
12
13
Table II.
Information of
the respondents and
selected projects
Director
Vice general
manager
Investment
manager
Consultant
Deputy dean
Director
Director
Consultant
Project manager
Director
Year of PPP
experience
Government
agency
Government
agency
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
ID
Risk factor
DM
PA
IM
AA
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
Corruption
Governments intervention
Expropriation and nationalization
Governments reliability
Third-party reliability
Public/political opposition
Immature juristic system
Change in law
Interest rate
Foreign exchange and convertibility
Inflation
Poor political decision making
Land acquisition
Approval and permit
Improper contracts
Financial risk
Construction/operation changes
Construction completion
Delay in supply
Technology risk
Ground/weather conditions
Operation cost overrun
Competition (exclusive right)
Market demand change
Tariff change
Payment risk
Supporting utilities risk
Residual assets risk
Uncompetitive tender
Consortium inability
Force majeure
Organization and coordination risk
Tax regulation changes
Environmental protection
Private investor change
Subjective evaluation
Insufficient financial audit
2.11
1.70
1.28
1.65
3.39
2.54
2.43
2.33
3.39
3.26
3.22
1.83
2.00
2.11
3.15
4.07
3.52
4.02
3.96
4.37
3.33
4.20
2.30
3.37
2.87
3.00
2.26
3.52
2.28
3.78
2.91
3.65
2.35
3.02
3.85
3.13
3.04
Public
Public
Public
Public
Share
Share
Public
Public
Share
Share
Share
Public
Public
Public
Share
Private
Private
Private
Private
Private
Share
Private
Public
Share
Share
Share
Public
Private
Public
Private
Share
Private
Public
Share
Private
Share
Share
2.05
1.52
1.41
1.67
3.16
2.32
2.53
2.54
3.60
3.57
3.41
2.04
2.04
2.24
3.29
4.19
3.46
4.16
4.03
4.63
3.21
4.23
2.47
3.12
2.99
3.28
2.55
3.56
2.41
4.25
2.88
3.33
2.61
2.97
4.12
3.30
3.28
Public
Public
Public
Public
Share
Public
Share
Share
Private
Private
Share
Public
Public
Public
Share
Private
Share
Private
Private
Private
Share
Private
Public
Share
Share
Share
Share
Private
Public
Private
Share
Share
Share
Share
Private
Share
Share
Sig.
0.449
1.410
2 1.413
2 0.145
2.525
2.794
2 0.727
2 1.724
2 1.609
2 2.343
2 2.312
2 1.694
2 0.352
2 1.089
2 1.947
2 1.052
0.575
2 1.370
2 0.636
2 2.195
1.273
2 0.285
2 1.201
2.068
2 1.109
2 2.337
2 2.414
2 0.339
2 1.033
2 2.926
0.833
2.856
2 2.390
0.397
2 2.542
2 1.510
2 1.942
0.656
0.165
0.164
0.885
0.015 *
0.008 *
0.471
0.092
0.115
0.024 *
0.025 *
0.097
0.726
0.282
0.058
0.298
0.568
0.178
0.528
0.033 *
0.210
0.777
0.236
0.044 *
0.274
0.024 *
0.020 *
0.736
0.307
0.005 *
0.409
0.006 *
0.021 *
0.693
0.015 *
0.138
0.058
Diff.
Equitable risks
allocation
305
p
p
Notes: *t-test of preferred and actual allocations for the risk returns a significant result,
the significance threshold is 0.05; DM, Delphi mean; PA, preferred allocation; IM, interview mean;
AA, actual allocation
6. Discussion
6.1 Public/political opposition
Public/political opposition risk is preferred to be shared between the public and
private sectors, but was actually allocated to the government in some PPP projects.
Interviewee from case 26 asserted that:
According to the current infrastructure project management framework, the requirements for
the bidding of a PPP project include the approvals of project feasibility, preliminary planning,
etc. In addition, the environment impact assessment report and other relevant information
Table III.
Comparative analysis
of preferred and actual
risk allocation
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
CMS
5,3
306
are provided to the general public. There is no doubt about its legal validity. The cause of this
risk event is therefore the default of local government of not fulfilling its functions, and then it
is reasonable to allocate it to the government.
However, the interviewee from case 25 shared several exceptional examples of public
opposition in wastewater treatment projects, i.e. environment pollution caused by the
illegal wastewater discharge by project company, air pollution due to the improper
odor treatment, the conflict on the value deduction of near properties, etc. It is
understandable that the government should be exempt from all liability in these
mentioned matters. This paper hence recommends public/political opposition risk to
be shared between public and private sectors. More specifically, the project company
would be responsible for the communication and settlement of a conflict with the
support of local government. If the occurrence of this risk is caused by the project
companys fault, no compensation towards the loss will be provided; if it is a result of
the local governments fault, the concession agreement should include provisions
requiring the project company to be restored to the same economics position; and if the
opposition results from force majeure or other factors beyond the control of both public
and private sectors, a reasonable compensation would be negotiated according to
specific project situations. It is strongly suggested that the provisions on compensation
mechanism including preconditions and procedure in the concession agreement should
be clearly stated in order to avoid potential disputes.
6.2 Foreign exchange and convertibility
The risk of foreign exchange and convertibility is preferred to be shared. However,
it was not clearly described in many past cases. Owing to the unequal positions, this
risk was actually considered to be undertaken by the private sector. As indicated by
the interviewee in case 2:
It is useless to force local governments to be responsible for the risk of foreign exchange, as
they do not have much authority concerning this issue under the current foreign exchange
regulation framework.
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
This study therefore recommends to list the past project experience and coordination
capability of a private consortium as one of the criteria of tendering evaluation and allow
the private consortium to deal with this issue alone. The private sector also suggests that
the timing and process of the governments involvement should be clearly defined so as
to avoid the risk of the governments unreasonable intervention.
6.5 Tax regulation changes
Instead of being allocated to the public sector in the perspectives of experts in the
Delphi study, the risk of tax regulation changes was actually shared in the past
projects. An interviewee in case 26 explained:
According to the law on the administration of tax collection in China (i.e. No. 49 Order of
the President of the Peoples Republic of China), no governmental entities or individuals
may be permitted without authorization to make decisions regarding the tax reduction,
Equitable risks
allocation
307
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
CMS
5,3
exemption or refund of tax. In other words, the national tax regulation change is out of the
control of local governments. It is hence unpractical to assign the risk to local governments
alone.
308
In light of the mentioned reason, this study therefore recommends this risk to be
shared. In particular, local governments shall promise to use their best efforts to ensure
that the private consortium would be entitled to enjoy tax incentives according to the
laws and regulations of China, especially for the exemption of local income tax. It is also
recommended to set up a threshold of change of tax rate. Once the change is greater
than the prescribed threshold, the government shall be responsible for part of the loss.
6.6 Equitable risk allocations
According to the above analysis and Table III, the equitable risk allocation scheme
suggested in this paper is as follows:
.
A total of 12 risks to be mostly allocated to the public sector as depicted in Table III are:
expropriation and nationalization, governments reliability, governments
intervention, poor political decision making, land acquisition, approval and
permit, corruption, supporting facilities risk, uncompetitive tender,
competition (exclusive right), change in law and immature juristic system.
.
There are 15 risks in the equally shared risk category option, i.e. third-party
reliability, public/political opposition, interest rate, foreign exchange and
convertibility, inflation, improper contracts, ground/weather conditions,
market demand change, tariff change, payment risk, force majeure, tax
regulation changes, environmental protection, subjective evaluation and
insufficient financial audit.
.
The survey results (Table III) indicate that ten risks out of 37 should be mostly
allocated to the private sector. These risks include: financial risk, construction
completion, construction/operation changes, delay in supply, technology
risk, operation cost overrun, residual assets risk, consortium inability,
organization and coordination risk and private investor change.
7. Conclusions
In the authors previous study (Ke et al., 2010b), a two-round Delphi survey was
conducted in Mainland China to analyze the risks and their preferred allocations for PPP
projects in China from the perspectives of 46 experts with in-depth knowledge and sound
experience of risk management. However, the risk allocation preferences derived may
not be equitable for all PPP projects at this stage. This paper hence attempts to validate
and elaborate on the preferred risk allocations by furthering the research.
A series of face-to-face interviews were subsequently carried out from March to
May 2009 to collect actual risk allocation in the past successful PPP projects.
By comparing the preferred and actual allocations and discovering the reasons behind
the differences, an equitable risk allocation scheme for different sectors was obtained.
There are five risks identified with significant different allocations, i.e. public/political
opposition, foreign exchange and convertibility, supporting utilities risk,
organization and coordination risk and tax regulation changes. After uncovering
the reasons behind the actual allocations of these five risks, only the risk of
tax regulation changes was recommended to be reallocated to the shared category.
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
In other words, the equitable allocations for the other 36 risks remain as the findings in
the previous study (Ke et al., 2010b). These interviews reinforce the rationale of the
preferred allocations from the Delphi study in Ke et al. (2010b), so that the re-allocation
for tax regulation changes risk and the preferred allocations for the other 36 risks in
Ke et al. (2010b) together would be considered as equitable for PPP projects in China as
described in Section 6.6.
The selected cases were regarded as the most successful project that the
interviewees were directly involved in. These projects were completed on or ahead of
time, within budget and to an acceptable level of quality, and run well with little
conflict among the parties during the operation period. But one limitation of this study
is that no successful transferred projects are available for the comparative analysis,
because PPP is a new financing modality in China.
References
Abednego, M.P. and Ogunlana, S.O. (2006), Good project governance for proper risk allocation
in public-private partnerships in Indonesia, International Journal of Project Management,
Vol. 24 No. 7, pp. 622-34.
Chan, A.P.C., Lam, P.T.I., Chan, D.W.M., Cheung, E. and Ke, Y.J. (2010), Potential obstacles to
successful implementation of public-private partnerships in Beijing and the Hong Kong Special
Administrative Region, Journal of Management in Engineering, Vol. 26 No. 1, pp. 30-40.
Chinese Governments Official Web Portal (2008), Chinas 4 trillion yuan stimulus to boost
economy, domestic demand, available at: www.gov.cn/english/2008-11/09/content_
1143763.htm (accessed 25 November 2008).
Cooper, D.F., Grey, S., Raymond, G. and Walker, P. (2005), Project Risk Management
Guidelines: Managing Risk in Large Projects and Complex Procurements, Wiley, Chichester.
European Commission (2003), Guidelines for Successful Public-private Partnerships, European
Commission, Brussels, version 1, January, p. 13.
Jin, X.H. (2010a), Determinants of efficient risk allocation in privately financed public
infrastructure projects in Australia, Journal of Construction Engineering and
Management, Vol. 136 No. 2, pp. 138-50.
Jin, X.H. (2010b), Neuro-fuzzy decision support system for efficient risk allocation in
public-private partnership infrastructure projects, Journal of Computing in Civil
Engineering, Vol. 24 No. 6, pp. 525-38.
Jin, X.H. and Doloi, H. (2008), Interpreting risk allocation mechanism in public-private
partnership projects: an empirical study in a transaction cost economics perspective,
Construction Management and Economics, Vol. 26 No. 7, pp. 707-21.
Jin, X.H. and Doloi, H. (2009), Modelling risk allocation in privately financed infrastructure
projects using fuzzy logic, Computer-Aided Civil and Infrastructure Engineering, Vol. 24
No. 7, pp. 509-24.
Ke, Y.J., Wang, S.Q. and Chan, A.P.C. (2010a), Risk allocation in public-private partnership
infrastructure projects: comparative study, Journal of Infrastructure Systems, Vol. 16 No. 4,
pp. 343-51.
Ke, Y.J., Wang, S.Q., Chan, A.P.C. and Lam, P.T.I. (2010b), Preferred risk allocation in Chinas
public-private partnership (PPP) projects, International Journal of Project Management,
Vol. 28 No. 5, pp. 482-92.
Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005a), Perceptions of positive and
negative factors influencing the attractiveness of PPP/PFI procurement for construction
Equitable risks
allocation
309
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)
CMS
5,3
310
projects in the UK: findings from a questionnaire survey, Engineering, Construction and
Architectural Management, Vol. 12 No. 2, pp. 125-48.
Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005b), The allocation of risk in PPP/PFI
construction projects in the UK, International Journal of Project Management, Vol. 23
No. 1, pp. 25-35.
Lyons, T. and Skitmore, M. (2004), Project risk management in the Queensland engineering
construction industry: a survey, International Journal of Project Management, Vol. 22 No. 1,
pp. 51-61.
Medda, F. (2007), A game theory approach for the allocation of risks in transport public
private partnerships, International Journal of Project Management, Vol. 25 No. 3, pp. 213-18.
Ng, A. and Loosemore, M. (2007), Risk allocation in the private provision of public
infrastructure, International Journal of Project Management, Vol. 25 No. 1, pp. 66-76.
Roumboutsos, A. and Anagnostopoulos, K.P. (2008), Public-private partnership projects in
Greece: risk ranking and preferred risk allocation, Construction Management and
Economics, Vol. 26 No. 7, pp. 751-63.
State Council (2008), Regulation of the Peoples Republic of China on Foreign Exchange
Administration, Order of the State Council of the Peoples Republic of China, No. 532, August.
State Council (2010), Several opinions of the State Council on encouraging and guiding the
healthy development of private investment, No. 13 of the State Council, May.
State Development and Reform Commission (2009), More information about 4 trillion RMB
stimulus plan (in Chinese) available at: www.ndrc.gov.cn/xwfb/t20090309_265095.htm
(accessed 13 May 2009).
Wang, S.Q. (2006), Lessons learnt from the PPP practices in China, Keynote Speech, Asian
Infrastructure Congress 2006, Hong Kong, 9-30 November, organized by Terrapinn and
sponsored by IAPF.
Xu, Y.L., Chan, A.P.C. and Yeung, J.F.Y. (2010), Developing a fuzzy risk allocation model for
PPP projects in China, Journal of Construction Engineering and Management, Vol. 136
No. 8, pp. 894-903.
Zhang, L. (2009), Development of infrastructure sectors in China: status quo and trends (Seminar
Speech) Revamping PPPs: From Revisiting and Rethinking to Revamping and
Revitalising PPPs, The University of Hong Kong, Hong Kong, China, 28 February.
Zhang, X.Q. (2005), Critical success factors for public-private partnerships in infrastructure
development, Journal of Construction Engineering and Management, Vol. 131 No. 1,
pp. 631-44.
About the authors
Yongjian Ke is Research Fellow in the Department of Building, National University of Singapore,
Singapore and was formerly at the Department of Construction Management, Tsinghua
University, Beijing, China. Yongjian Ke is the corresponding author and can be contacted at:
bdgky@nus.edu.sg
ShouQing Wang is Professor in the Department of Construction Management, Tsinghua
University, Beijing, China.
Albert P.C. Chan is Professor and Associate Head in the Department of Building and Real
Estate, The Hong Kong Polytechnic University, Hung Hom, Kowloon, Hong Kong Special
Administrative Region, China.
To purchase reprints of this article please e-mail: reprints@emeraldinsight.com
Or visit our web site for further details: www.emeraldinsight.com/reprints
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 03:41 23 May 2015 (PT)