Anda di halaman 1dari 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND

TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017


DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown at drip pans below CD prior to SD

SYS NO
DISCIPLINE
SCHEDULE

SISO

Onshore

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

PIPING

LOCATION

CD

Commissioning

Decommissioning

Early Start

Late Start

Actual Start

Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

N/A

Standart PPE

Pre Shutdown

SYS DESC

Personal H2S Monitor

SIPROD
SIPCOM

XXX

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

TEMPERORY REMOVE GRATING AND WASHDOWN AT DRIP PANS BELOW CD

TOOLS / EQUIPMENTS / MATERIAL HANDLING

REINSTATE GRATING AND HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

4.00

0.55

2.20

MW

PAX

2.20

0.75

1.65

RG

PAX

4.00

2.15

8.58

MW

PAX

8.58

0.75

6.44

RG

PAX

8.58

0.75

6.44

MW

PAX

6.44

0.75

4.83

RG

PAX

2.00

1.375

2.75

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

12.9113

19.965

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-001

Job Constraints /
Hold Points
Page 1 of 104

Special Services
Requirement

SD-GEN-001

Job Constraints /
Hold Points

Page 2 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-001

Page 3 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-001

Page 4 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
32.88
Total
0.00
32.88

SD-GEN-001

Page 5 of 104

SD-GEN-001

Page 6 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-001

Page 7 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-001

Page 8 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown at drip pans below MD prior to SD

SYS NO
DISCIPLINE
SCHEDULE

SISO

Onshore

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

PIPING

LOCATION

MD

Commissioning

Decommissioning

Early Start

Late Start

Actual Start

Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

N/A

Standart PPE

Pre Shutdown

SYS DESC

Personal H2S Monitor

SIPROD
SIPCOM

XXX

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

TEMPERORY REMOVE GRATING AND WASHDOWN AT DRIP PANS BELOW MD

TOOLS / EQUIPMENTS / MATERIAL HANDLING

REINSTATE GRATING AND HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

4.00

0.55

2.20

MW

PAX

2.20

0.75

1.65

RG

PAX

6.00

2.15

12.87

MW

PAX

12.87

0.75

9.65

RG

PAX

12.87

0.75

9.65

MW

PAX

9.65

0.75

7.24

RG

PAX

2.00

1.375

2.75

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

18.5419

27.4725

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-002

Job Constraints /
Hold Points
Page 9 of 104

Special Services
Requirement

SD-GEN-002

Job Constraints /
Hold Points

Page 10 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-002

Page 11 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-002

Page 12 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
46.01
Total
0.00
46.01

SD-GEN-002

Page 13 of 104

SD-GEN-002

Page 14 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-002

Page 15 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-002

Page 16 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown open drain header prior to SD

SYS NO
DISCIPLINE
SCHEDULE

SISO

Onshore

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

PIPING

LOCATION

ALL

Commissioning

Decommissioning

Early Start

Late Start

Actual Start

Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

N/A

Standart PPE

Pre Shutdown

SYS DESC

Personal H2S Monitor

SIPROD
SIPCOM

XXX

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

TEMPERORY REMOVE BLIND/FLANGE AND WASHDOWN OPEN DRAIN HEADER

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

3.00

0.55

1.65

MW

PAX

1.65

0.75

1.24

RG

PAX

4.00

3.52

14.08

MW

PAX

14.08

0.75

10.56

RG

PAX

14.08

0.75

10.56

MW

PAX

10.56

0.75

7.92

RG

PAX

2.00

2.475

4.95

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

19.7175

31.24

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-003

Job Constraints /
Hold Points
Page 17 of 104

Special Services
Requirement

SD-GEN-003

Job Constraints /
Hold Points

Page 18 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-003

Page 19 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-003

Page 20 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
50.96
Total
0.00
50.96

SD-GEN-003

Page 21 of 104

SD-GEN-003

Page 22 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-003

Page 23 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-003

Page 24 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown closed drain header

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

SUMP

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

WASHDOWN CLOSED DRAIN HEADER

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

RG

NOS

4.00

3.52

14.08

MW

PAX

14.08

0.75

10.56

RG

NOS

14.08

0.75

10.56

MW

PAX

10.56

0.75

7.92

RG

PAX

2.00

0.825

1.65

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

19.305

27.39

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-004

Job Constraints /
Hold Points
Page 25 of 104

Special Services
Requirement

SD-GEN-004

Job Constraints /
Hold Points

Page 26 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-004

Page 27 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-004

Page 28 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
46.70
Total
0.00
46.70

SD-GEN-004

Page 29 of 104

SD-GEN-004

Page 30 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-004

Page 31 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-004

Page 32 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown & purge Line 250-PL-101-6101X (TP-003/004)

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

CD

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

Washdown 250-PL-101-6101X (TP-003/004)

RG

NOS

3.00

5.39

16.17

Purge 250-PL-101-6101X (TP-003/004)

RG

MTR

13.86

0.55

7.62

MW

PAX

23.79

0.75

17.84

RG

NOS

23.79

0.75

17.84

MW

PAX

17.84

0.75

13.38

RG

PAX

2.00

0.825

1.65

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown & purge Line 250-PL-101-6101X (TP-003/004)

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

32.0533

44.3878

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-005

Job Constraints /
Hold Points
Page 33 of 104

Special Services
Requirement

SD-GEN-005

Job Constraints /
Hold Points

Page 34 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-005

Page 35 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-005

Page 36 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
76.44
Total
0.00
76.44

SD-GEN-005

Page 37 of 104

SD-GEN-005

Page 38 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-005

Page 39 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-005

Page 40 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown & purge Line 200-PL-011-1101X (TP-011/012)

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

MD

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

Washdown 200-PL-011-1101X (TP-011/012)

RG

NOS

3.00

4.18

12.54

Purge 200-PL-011-1101X (TP-011/012)

RG

MTR

5.19

0.55

2.85

MW

PAX

15.39

0.75

11.55

RG

NOS

15.39

0.75

11.55

MW

PAX

11.55

0.75

8.66

RG

PAX

2.00

0.825

1.65

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown & purge Line 200-PL-011-1101X (TP-011/012)

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

21.0303

29.6904

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-006

Job Constraints /
Hold Points
Page 41 of 104

Special Services
Requirement

SD-GEN-006

Job Constraints /
Hold Points

Page 42 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-006

Page 43 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-006

Page 44 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
50.72
Total
0.00
50.72

SD-GEN-006

Page 45 of 104

SD-GEN-006

Page 46 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-006

Page 47 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-006

Page 48 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Purge Line 50-V-002-1101 (TP-001/002)

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

CD

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Purge Line 50-V-002-1101 (TP-001/002)

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

RG

MTR

6.00

0.55

3.30

MW

PAX

3.30

0.75

2.48

RG

NOS

3.30

0.75

2.48

MW

PAX

2.48

0.75

1.86

RG

PAX

2.00

0.825

1.65

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

5.15625

8.525

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-007

Job Constraints /
Hold Points
Page 49 of 104

Special Services
Requirement

SD-GEN-007

Job Constraints /
Hold Points

Page 50 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-007

Page 51 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-007

Page 52 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
13.68
Total
0.00
13.68

SD-GEN-007

Page 53 of 104

SD-GEN-007

Page 54 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-007

Page 55 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-007

Page 56 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown & purge Line 80-DD-001-11430 (TP-013/014)

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

CD

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

Washdown 80-DD-001-11430 (TP-013/014)

RG

NOS

3.00

2.75

8.25

Purge 80-DD-001-11430 (TP-013/014)

RG

MTR

11.29

0.55

6.21

MW

PAX

14.46

0.75

10.84

RG

NOS

14.46

0.75

10.84

MW

PAX

10.84

0.75

8.13

RG

PAX

2.00

0.825

1.65

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown & purge Line 80-DD-001-11430 (TP-013/014)

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

19.8031

28.0541

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-008

Job Constraints /
Hold Points
Page 57 of 104

Special Services
Requirement

SD-GEN-008

Job Constraints /
Hold Points

Page 58 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-008

Page 59 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-008

Page 60 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
47.86
Total
0.00
47.86

SD-GEN-008

Page 61 of 104

SD-GEN-008

Page 62 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-008

Page 63 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-008

Page 64 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown & purge Line 80-DD-001-11430 (TP-013/014)

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

CD

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

Washdown 80-DD-001-11430 (TP-013/014)

RG

NOS

3.00

2.75

8.25

Purge 80-DD-001-11430 (TP-013/014)

RG

MTR

13.81

0.55

7.60

MW

PAX

15.85

0.75

11.88

RG

NOS

15.85

0.75

11.88

MW

PAX

11.88

0.75

8.91

RG

PAX

2.00

0.825

1.65

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown & purge Line 80-DD-001-11430 (TP-013/014)

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

21.6222

30.4796

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-009

Job Constraints /
Hold Points
Page 65 of 104

Special Services
Requirement

SD-GEN-009

Job Constraints /
Hold Points

Page 66 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-009

Page 67 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-009

Page 68 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
52.10
Total
0.00
52.10

SD-GEN-009

Page 69 of 104

SD-GEN-009

Page 70 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-009

Page 71 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-009

Page 72 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown & purge Line 50-P-13512-11432 (TP-021/022)

SYS NO

SYS DESC

DISCIPLINE
SCHEDULE

PIPING

LOCATION

CD

SISO

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

Commissioning

Decommissioning
Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

Actual Start

Standart PPE

Pre Shutdown

Late Start

Personal H2S Monitor

SIPROD
SIPCOM

Early Start

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

Onshore

TASK DESCRIPTION

WORK VOLUME

TRADE

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

2.00

0.55

1.10

MW

UNIT

1.10

0.75

0.83

Washdown 50-P-13512-11432 (TP-021/022)

RG

NOS

2.00

2.64

5.28

Purge 50-P-13512-11432 (TP-021/022)

RG

MTR

3.42

0.55

1.88

MW

PAX

7.16

0.75

5.37

RG

NOS

7.16

0.75

5.37

MW

PAX

5.37

0.75

4.03

RG

PAX

2.00

0.825

1.65

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown & purge Line 50-P-13512-11432 (TP-021/022)

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

10.2238

15.2818

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-010

Job Constraints /
Hold Points
Page 73 of 104

Special Services
Requirement

SD-GEN-010

Job Constraints /
Hold Points

Page 74 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-010

Page 75 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-010

Page 76 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
25.51
Total
0.00
25.51

SD-GEN-010

Page 77 of 104

SD-GEN-010

Page 78 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-010

Page 79 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-010

Page 80 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown at drip pans below CD prior to start-up

SYS NO
DISCIPLINE
SCHEDULE

SISO

Onshore

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

PIPING

LOCATION

CD

Commissioning

Decommissioning

Early Start

Late Start

Actual Start

Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

N/A

Standart PPE

Pre Shutdown

SYS DESC

Personal H2S Monitor

SIPROD
SIPCOM

XXX

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown at drip pans below CD prior to start-up

TOOLS / EQUIPMENTS / MATERIAL HANDLING

REINSTATE GRATING AND HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

4.00

0.55

2.20

MW

PAX

2.20

0.75

1.65

RG

PAX

4.00

2.15

8.58

MW

PAX

8.58

0.75

6.44

RG

PAX

8.58

0.75

6.44

MW

PAX

6.44

0.75

4.83

RG

PAX

2.00

1.375

2.75

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

12.9113

19.965

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-011

Job Constraints /
Hold Points
Page 81 of 104

Special Services
Requirement

SD-GEN-011

Job Constraints /
Hold Points

Page 82 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-011

Page 83 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-011

Page 84 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
32.88
Total
0.00
32.88

SD-GEN-011

Page 85 of 104

SD-GEN-011

Page 86 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-011

Page 87 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-011

Page 88 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown at drip pans below MD prior to start-up

SYS NO
DISCIPLINE
SCHEDULE

SISO

Onshore

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

PIPING

LOCATION

MD

Commissioning

Decommissioning

Early Start

Late Start

Actual Start

Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

N/A

Standart PPE

Pre Shutdown

SYS DESC

Personal H2S Monitor

SIPROD
SIPCOM

XXX

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown at drip pans below MD prior to start-up

TOOLS / EQUIPMENTS / MATERIAL HANDLING

REINSTATE GRATING AND HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

4.00

0.55

2.20

MW

PAX

2.20

0.75

1.65

RG

PAX

6.00

2.15

12.87

MW

PAX

12.87

0.75

9.65

RG

PAX

12.87

0.75

9.65

MW

PAX

9.65

0.75

7.24

RG

PAX

2.00

1.375

2.75

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

18.5419

27.4725

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-012

Job Constraints /
Hold Points
Page 89 of 104

Special Services
Requirement

SD-GEN-012

Job Constraints /
Hold Points

Page 90 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-012

Page 91 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-012

Page 92 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
46.01
Total
0.00
46.01

SD-GEN-012

Page 93 of 104

SD-GEN-012

Page 94 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-012

Page 95 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-012

Page 96 of 104

CHO/2012/DFHD/193 : PROVISION FOR HOOK-UP, COMMISSIONING AND


TOPSIDE MAJOR MAINTENANCE SERVICES FOR 2013-2017
DFHD/2014/042A/001 : PROVISION FOR HUC WORK
FOR TOPSIDE MODIFICATION FOR SKO PIPELINE
REJUVENATION PROJECT PL 381/210

Work Order No
& Title

JOBCARD ID NO

GENERAL
JOB DESCRIPTION

WORK CATEGORY

Washdown open drain header prior to start-up

SYS NO
DISCIPLINE
SCHEDULE

SISO

Onshore

Offshore

Prefabrication

Hook-Up

Hook-Up

Demolition

PIPING

LOCATION

ALL

Commissioning

Decommissioning

Early Start

Late Start

Actual Start

Plan Duration

Early Finish

Late Finish

Actual Finish

Actual Duration

Shutdown

Post Shutdown
Percent
Weight

HEALTH, SAFETY & ENVIRONMENT (HSE)


PERMIT TO WORK

JOB SAFETY ANALYSIS

Body Harness

Cold Work

Lifting

Hearing Protection

Chemical Protection

Others (specify below)

Hot Work

Radiation

Work Vest

Breathing Apparatus

_____________________

Electrical

QUALITY

TEST
REQUIREMENT

VI

UT

Hydrotest

Valve Leak Test

Cable Tests

Calibration

Function Test / Test Run

RT

MPI

Reinstatement

RV Pop Test

Tubing Leak Test

Loopcheck

Others

MANPOWER RESOURCES

TASK
NO

WORK
PHASE

N/A

Standart PPE

Pre Shutdown

SYS DESC

Personal H2S Monitor

SIPROD
SIPCOM

XXX

PERSONNEL PROTECTIVE EQUIPMENT

OPS MODE

TASK DESCRIPTION

WORK VOLUME

TRADE

TOOLS / EQUIPMENTS / MATERIAL PREPARATION

Washdown open drain header prior to start-up

TOOLS / EQUIPMENTS / MATERIAL HANDLING

HOUSEKEEPING

PLAN MHRS

Unit

Total

Unit

Total

RG

PAX

3.00

0.55

1.65

MW

PAX

1.65

0.75

1.24

RG

PAX

4.00

3.52

14.08

MW

PAX

14.08

0.75

10.56

RG

PAX

14.08

0.75

10.56

MW

PAX

10.56

0.75

7.92

RG

PAX

2.00

2.475

4.95

DIRECT MANHOURS SUMMARY

Contractor
Personnel

RS

PF

PWL

SF

SWL

FW

MW

IT

IF

ELE

BP

RG

19.7175

31.24

Third Party
Personnel

NDT

PT

BT

IS

CC

VR

WH

Total, Direct Manhours


Special Services
Requirement
SD-GEN-013

Job Constraints /
Hold Points
Page 97 of 104

Special Services
Requirement

SD-GEN-013

Job Constraints /
Hold Points

Page 98 of 104

TOOL & EQUIPMENT RESOURCES

Item No

Unit

Utility Requirements

Qty

Description

Utility Air

Instrument Air

MESC No

Material Type Codes P = Project Material

Qty

Potable Water

Description

Power

VAC

Others __________

Description

T = Temporary (construction) Material

Type

Unit

C = Consumable Material S = Commissioning Spares

REFERENCE DRAWINGS & DOCUMENTS


Dwg / Doc No

Service / Firewater

Unit

MATERIALS

Item No

Item No

Rev

Drawing / Document Title

NOTES

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR
Prepared By
Muhd Hasril Rahaman
Piping Engineer

Reviewed By

Agreed By

PCSB
Approved by

Workpack Team Leader

Project Manager

HUC Engineer

Signature
Date
SD-GEN-013

Page 99 of 104

JOBCARD
APPROVAL
Name
Designation

CONTRACTOR

PCSB

Presented By

Verified By

Confirmed By

Accepted By

Foreman / Supervisor

Construction Superintendent

Discipline Inspector

HUC Engineer

Signature
Date

SD-GEN-013

Page 100 of 104

SISO
SIPROD
SIPCOM
Pre Shutdown
Shutdown
Post Shutdown

JOB SAFETY ANALYSIS

Function Test / Test Run


Others

ACT
MHRS

ECT MANHOURS SUMMARY


Total
50.96
Total
0.00
50.96

SD-GEN-013

Page 101 of 104

SD-GEN-013

Page 102 of 104

Description

Others ___________

Qty

S = Commissioning Spares
Drawing / Document Title

PCSB
Approved by
HUC Engineer

SD-GEN-013

Page 103 of 104

PCSB
Accepted By
HUC Engineer

SD-GEN-013

Page 104 of 104

Anda mungkin juga menyukai