To : Hensley Industrial
Dear Sir,
below during dismantle and packing process of the CVT equipment, and
1、 WASHING
(1)
It is very important that clean the matters which harm to the environment
including cutting matters, dirty oil, abolish, hydraulic liquid, and Freon before
packing.
(2)
All the equipments shall not be cleaned by water; it may cause the serious
pocking of the removable components such as the slid platform, trail, drive
(3)
To prevent water seepage, damp and other unnecessary loss, do not spray
water and other kind of liquid in the electrical boxes and operator panels
(4)
It is necessary to spray pickling oil in the surface of guide trail, drive crew,
(5)
Parallels and other sundries shall not be placed in any control panels and
the cabinets, and plug up the cable apertures before lock the door
1、 DISMANTLE
(1)
To ensure that all the marking labels are uniqueness, trace and inspect
the protecting work and match marking system timely. What’s more, it is
very important that the staff needs to note the defect and damage
Before dismantle, the entire guide trails, plunger pistons and other
removable surface should be wiped, put the power head and plunger
pistons into the muff. To prevent the unnecessary damage during the
and wood.
(3)
All the brass tags of the dismantled equipments including pipes and
how many main parts of the equipment divided into, what’s the name
and number of each parts, it is suggested that mark M1 for the 1st
equipment, then M1-1,M1-2…..for its main parts, then mark M1-1-1 for
its sub-main part. Besides, mark A1-1 for the 1st attachment of the 1st
equipment, and make sure how many pipes need to take back and how
many of these need to redistribution. Only in this way can ensure the
(4)
It is require that all the connecting screws, stoppers, allocation pins,
keys, removable fang bolts and parallels need to take back. It should
put these things into the electric box to prevent unnecessary damage;
(5)
The dismantled hydraulic pipes and other kind of pipe orifice, valve
prevent dust and sundries, besides, it is also needed to mark and sign
and the attachment of pipe needs to be taking back with the main
(6)
Beside the marking on the oil pipe, compressed air hose, and cooling
pipe, for the complexity of the pipeline system of testing line, assembly
large, it is needed that tight these pipes to bunches and put them on
such as power head and slid platform needs to be fixed in the bottom or
(2)
box, operator panel, and electric screen, it needs air-tight coating with
dryer and soft material package, especially the LCD panel and the
blanketing, and use foam and tape to tighten it up, loading and packing
(3)
which needs to fit into container should use wooden or metal skid underside.
transportation.
(4)
The attachment such as small parts, capsid, oil pipe, valve, cradle
firm carton. Small spare parts, cutting tools, circuit panel, electric
sorted package. Take the preparing work like greasing, damping, piling
1、 ATTENTION
(1)
(2)
(3)
(5)
The material which fit into wooden cart, carton and the skid shall be
record on list.
(6)
Forming the packing list and package document shall be exact and
true.
2009-12-14
Signature:________________
Signature:________________