Geotechnical
I
Investigation
ti ti and
d
Design for Piling
Works
Chris Haberfield
Outline
Client Moments
You get what you pay for
Benefits of Doing More
Case Studies
Closing Remarks
Client Moments
Just do a basic investigation the piling contractors can take the risk
A
A primary risk to my project involves the in-ground
in ground construction
construction
Can you guys help us out as we have a problem with our foundations ...
we have a geotechnical report .. but.....?
but.....?
The piling contractor cant install the piles to the design depth in the way
I want them to install them
Geotechnical advice during construction is an expense I dont need
the investigation, analysis and design have all been done I dont need
construction advice
The piling contractor is claiming latent conditions can you help
I must have bored piles on this project, and you cant use bentonite or
polymer to install them
3
Client Moments
You pay for geotechnical advice/investigation one way or another
I am taking
t ki a conservative
ti approach....so
h
I can go cheap
h
on my
geotechnical advice/investigation
It
It worked down the road so it will work here
here
I want to spend as little money as I can on the foundations as we never
see them what we can
cantt see wont
won t hurt us .... and if it does I can always
go and get decent geotechnical advice/investigation later on
Your
Your proposal for the geotechnical investigation is too expensive I can
get one from Joe for half the price
We
We have to take the cheapest price I know we will pay for it in the end
but that is the policy
With g
geotechnical advice/investigation
g
y
you get
g what yyou p
pay
y for
4
Platinum
Gold
Silver
Bronze
Ground
Investigation
Geotechnical
Engineer
Design
g
Parameters
Silver
boreholes>toedepthof
boreholes
toe depth of
piles
shallowboreholes
SPTtesting
notestingand/orsampling
Indextesting
Gold
Silver+moreboreholes,
Design
Foundations
Risk
Cost
Gold+comprehensive
Limitedexperience
Nonexpert
Experienced
Limitedinexpertise
Experienced
Expert
Experienced
Expert
G
Guessed
d
G
Generic
i
Si
Sitespecific
ifi
E h
Enhancedsitespecific
d i
ifi
Silver+simple
Analysis
Platinum
None
Empirical
Rulesofthumb(overly
conservative)
Usuallyoverdesigned
May be impractical
Maybeimpractical
Maybeunsafe
High
Empirical,Loadbased,
standardindustry
Low
theoreticalorbasic
numerical modelling
numericalmodelling
Improved
Serviceabilitybased
Partiallyoptimiseddesign
Practical to build
Practicaltobuild
Safe
VeryLow
$50k
$80k
$120k
Usuallyoverdesigned
Safe
Gold+advanced
numericalmodelling
Optimised
Serviceabiltybased
Optimiseddesign
Practical to build
Practicaltobuild
Safe
VeryLow
$250k
Hypothetical Example 1
10
11
12
Hypothetical Example 2
13
Risks
Optimised retention
Excavation
system
G
Groundwater/dewatering
d
/d
i
Optimised pile lengths
Pile founding levels
e g piles founding at
e.g.
Socket lengths
Si ifi- dykest opportunities
Significant
tdifferent
iti levels
for
f in
Differential
settlement/tilt
reducing
foundation
costs,
basalt/bedrock
Longer piles
Alternative
construction time
and riskfooting
Construction difficulties
systems
Delays
Shorter construction time
Latent conditions
14
Case Studies
15
GARSP - as
constructed
t t d
10
EW - MW
Siltstone/Sandstone
Depth (m)
Traditional
approach
20
Saving of 9.5 m
25
Benefits - savings
950 m3 concrete
t
1400 m3 spoil
$$ + 42 days
Additional Cost for
P
Pressuremeter
t testing,
t ti
UCS
testing, analysis
on-site presence
30
GARSP - as
constructed
35
Depth (m)
settlement : 1 % dia
40
HW - SW
Siltstone /
Sandstone
45
FE analysis
l i
50
55
60
Traditional
approach
1000 m3 concrete
1500 m3 spoil
$$ + 40 days
Additional Cost for
on-site presence
Saving of up to 17 m
19
Upper basalt
Lower basalt
Siltstone
Upper basalt
25m
Lower basalt
35 m
Siltstone
Limits of basalt
Upper Basalt
L
Lower
B
Basalt
lt
(50)
The original
Th
i i l Sil
Silver llevell iinvestigation
ti ti was nott
sufficient for alternative design options. Gold
level
investigation
allowed
alternative
footing
time savings
27
Initial investigation
Boreholes to 60 m,, one borehole to 120 m
lower standard of drilling, laboratory testing only (disturbed samples)
Preliminary recommendations piles possibly in excess of 120 m
d th (t
depth
(to lilimit
it settlements)
ttl
t )
Settlement estimate of about 500 mm risk of tilt
Subsequent
q
Investigation
g
Boreholes to 300 m, triple tube coring
Extensive laboratory testing for strength, stiffness and constitutive
behaviour
Extensive insitu testing including pressuremeter, crosshole seismic,
full scale pile load tests and construction trials
Extensive 3D finite element analysis
y
p
plus others
Settlement estimate of about 80 mm
Basement retention no anchors
The Pl
Th
Platinum
ti
llevell iinvestigation
ti ti
gave everyone the confidence that
this could be done
30
Footing Layout
Barrette toe levels
-55 m DMD
-60 m DMD
-79 m DMD
Barrette sizes
1.5
15mx2
2.8
8m
1.2m x 2.8 m
Raft thicknesses
2.5 m
4.0 m
6.0 m to 8.0 m
32
Concluding Comments