Short Name:

OMV Refining Standard


Sub-Document

3700_002_Q_v091001
Description:

Split of Work List


Construction Main Group Q (Online Analytics)
Activities
1.
1.1
1.2
1.3
1.4
1.5
1.6
1.7

Basic Planning
Compilation of analyses list (laboratory and on-line)
Generation of specification sheets
Defining the sampling and return points
Insertion in the process and P&I schematics
Device selection
Setting out the concept for the measurement point arrangement
Positioning in the plant
Determination of utilities required (electrical power, steam, carrier
1.8
gas etc.)
1.9
Clarification of interfaces on-site/off-site
1.10 Approval of the basic planning principles
2.
2.1
2.2
2.3
2.4
2.5
2.6
2.7

Construction Planning
Analyzer house incl. building engineering
Electrical power supply
M & C engineering
Sample conditioning
Measured value transmission to, and integration in, the PCS
Erection documents
Approval of the detail planning

3.
3.1
3.2
3.3
3.4
3.5

Procurement
Generation of inquiry specifications
Comparison of tenders
Contract award recommendation
Equipment acceptance at the manufacturer
Taking in charge of equipment deliveries

CO

CU

X
X
X
X
X
X
X

Remarks

X
X
X

X
X
X
X
X
X
X

X
X
X
X
X

X
X

Note.
Hardcopies of this document may not represent the current applicable standard. Check for latest document on the Refining Regulation
Platform

Author

MRS-TQO
Department

Ernst Seidl

Responsible
for Contents

MRS-TQO
Department

Ernst Seidl

RefStd_3700_002_Q_v091001_EN_Online-Analyzers-Split-of-Work.doc
Split of Work List
Page
Valid as of: 100101
1 of 2
Version: v091001
OMV Refining and Marketing GmbH all rights reserved

Activities
4.
4.1
4.2
4.3
4.4
4.5
4.6

Erection
Construction supervision
Loop-checks and functional tests
Insulation and loop resistance measurements
Leakage tests
Instigation of the required TV inspections
Mechanical acceptance

5.
5.1
5.2
5.3
5.4

Commissioning
Start-up of the measurement equipment
Integration into the VISTA-NET
Performance verification
Acceptance test of the Measurement equipment

6.
6.1

Documentation
Documentation of the inspections carried out
Generation of all drawings in CAD (Promis,ICEM) and integration
into the existing inventory
Compilation of the instruction manual in accordance with QMV 1102
as an independent section for MRS-TQ
Allocation of the entire documentation to the existing inventory
(EDMS)
Documentation acceptance (as built)

6.2
6.3
6.4
6.5
7.

Handover of the measurment equipment, complete with


documentation and performance verification

CO

CU

Remarks

X
X
X
X
X
X

X
X

Not for MRB

X
X

X
X
X
X
X
X

RefStd_3700_002_Q_v091001_EN_Online-Analyzers-Split-of-Work.doc
Split of Work List
Page
Valid as of: 100101
2 of 2
Version: v091001
OMV Refining and Marketing GmbH all rights reserved