Anda di halaman 1dari 8

DATA SHEET

(DATA-A)
Cost of 25 KVA Diesel Generator set with standard
accessories and acoustic enclosure (As per quotation).
Add
Concrete foundation with cc 1:2:4 and sand cushion
Towards Earth work.
Erection charge of generator, Fuel tank, etc.
31/2x25 sqmm PVC LTUG cable ( 3 mt) with laying under
ground (SD - 204) 385.20/- Mtr
31/2x25 sqmm cable gland and termination - 4 Nos
Rs.146.10/-Each (SD-235)

314669.00

20000.00
5000.00
10000.00
1155.60
584.40

First charging of 100litre fuel oil (MR)

6300.00

First charging of Lubricating oil - 10 Ltr (MR)

2000.00

Rate per set Rs. 359709.00/- Ea

359709.00

Page 3

ESTIMATE
Name of Work :Provision of 15 KVA Diesel Generator set for Fast Track Court at Palani in
Dindigul District.
Est.Rs.5.10 Lakhs
Sl.N
o.
1

Qty

Description of work

Rate

Per

Amount

1 Set Supply, Erection, Testing, commissioning and


handing over of 1 No 15 KVA Diesel
Generator set 0.8PF, 3 Phase, 415Volts 50c/s,
1500 RPM as deailed below
A.
ENGINE: "ASHOK LEYLAND" MODEL: 485
G1 HP 23.8, power generation type diesel
engine at 1500 RPM Complete with standard
accessories, Coolant cooled Radiator, Electric
start, Battery charging alternator, RPM meter
wit hour meter, Oil pressure Gauge with safety
system for LLOP, HWT, Battery Amps meter,oil
& fuel - filters. Air cleaner and initial filling of
oil.
B. Alternator: "STAMFORD" make
15KVA alternator at 1500 RPM, 50 cycles, 415
voltate, 0.8 PF.

C. Sound Proof Acoustics: "ASHOK


LEYLAND" Designed CPCB II approved
'ACOUSTIC ENCLOSURE'
D. CONTROL PANEL:
Standard control
panel with safety provisions for HWT & LLOP.
E. BATTERY: 1 No. 12Volt battery with leads
and terminals.
F. FUEL TANK: Floor mounted fuel tank
capacity of 75 ltrs, Diesel hose with necessary
arrangements.
Erection work including concrete foundation,
first charging of 100 ltrs fuel and necessary
lubricating oil. (DATA - A)
2

1 Set Supply and demonstration of the following


safety accessories.
a. 1 mtr x 1 mtr x inch 11KV rubber mat - 2
Nos
b. One set of 4 Nos. 9 litre fire buckets with
metal stand frame - 1 set
c. First aid box with medicines 1 No.
d. 11KV rubber hand gloves 2 Nos.

359709.00 Set

359709.00

Page 4

Sl.N
o.

Qty

Description of work

Rate

Per

Amount

e. 2 kg capacity dry powder type fire


extinguisher - 2 Nos
f. Hand operated pump to transfer fuel from
standard barrel to fuel tank 1 No
h. Battery water acidity tester 1 No.
(CER No.67/2006-07)
3

5 Nos Earthing as per the ISI specification with an


earth electrode of 2.1mt class 'B' GI pipe of
dia not less than 40mm, with copper earth
plate of size 125mm x 50mm x 6mm, with
necessary funneling arrangements with
necessary masonry work and with 38mm RCC
cover slab for the brick masonry.
(SD-233)
50 Mts Providing earth connection and inter
connection of earth pit by 1 x 1/8 copper flat
conductor.
(SD-76)

8500.00

Set

8500.00

1693.30

Each

8466.50

411.20

Mtr

20560.00

1 Job Preparation of site plan physical lay out


electrical line schematic diagram 10 sets
getting Drawing approval from CEIG
preparation of completion Report rectification
report etc arranging CEIG Inspection and
obtaining CEIG safety certificate payment of
CEIG Inspection fees if necessary and
preparation of one set of approved Drawing
and copy of safety certificate in a neat frame
work (MR)
20000.00 Job

1 Set

L.S

Supply of tools required for the maintenance


and operation of the Generator set as follows
1 No 15 Cutting plier
1 No 6 Screw driver
2 Nos 9 Screw driver
6 Nos Double end spanner
1 No Adjust table spanner
1 No spanner for removing engine oil plug
1 No line tester
1 No lb hammer (MR)
Towards seggregation of Light and power
loads including LTUG Cabling&change over
arangements

2000.00

1 set

20000.00

2000.00

80000.00
499235.50

Page 5

Sl.N
o.

Qty
LS

Description of work

Rate

PS & Contingencies Charges 2.5%


Total
(Rupees Five Lakhs and Ten Thousand only)

Per

Amount
10764.50
510000.00

Page 6

ESTIMATE
Name of Work :Provision of 15 KVA Diesel Generator set for District Munisif cum Judicial
Magistrate court at Aundipatti in Theni District
Sl.N
o.
1

Qty

Description of work

Est.Rs.

420000.00

Rate

Per

Amount

1 Set Supply, Erection, Testing, commissioning and


handing over of 1 No 15 KVA Diesel
Generator set 0.8PF, 3 Phase, 415Volts 50c/s,
1500 RPM as deailed below
A.
ENGINE: "ASHOK LEYLAND" MODEL: 485
G1 HP 23.8, power generation type diesel
engine at 1500 RPM Complete with standard
accessories, Coolant cooled Radiator, Electric
start, Battery charging alternator, RPM meter
wit hour meter, Oil pressure Gauge with safety
system for LLOP, HWT, Battery Amps meter,oil
& fuel - filters. Air cleaner and initial filling of
oil.
B. Alternator: "STAMFORD" make
15KVA alternator at 1500 RPM, 50 cycles, 415
voltate, 0.8 PF.

C. Sound Proof Acoustics: "ASHOK


LEYLAND" Designed CPCB II approved
'ACOUSTIC ENCLOSURE'
D. CONTROL PANEL:
Standard control
panel with safety provisions for HWT & LLOP.
E. BATTERY: 1 No. 12Volt battery with leads
and terminals.
F. FUEL TANK: Floor mounted fuel tank
capacity of 75 ltrs, Diesel hose with necessary
arrangements.
Erection work including concrete foundation,
first charging of 75 ltrs fuel and necessary
lubricating oil. (DATA - A)
2

351558.00

Set

351558.00

6000.00

Set

6000.00

1 Set Supply and demonstration of the following


safety accessories.
a. 1 mtr x 1 mtr x inch 11KV rubber mat - 2
Nos
b. One set of 4 Nos. 9 litre fire buckets with
metal stand frame - 1 set
c. First aid box with medicines 1 No.
d. 11KV rubber hand gloves 2 Nos.
e. 2 kg capacity dry powder type fire
extinguisher - 2 Nos
h. Battery water acidity tester 1 No.

Page 7

Sl.N
o.
3

Qty

Description of work

4 Nos Earthing as per the ISI specification with an


earth electrode of 2.1mt class 'B' GI pipe of
dia not less than 40mm, with copper earth
plate of size 125mm x 50mm x 6mm, with
necessary funneling arrangements with
necessary masonry work and with 38mm RCC
cover slab for the brick masonry.
(SD-233)
50 Mts Providing earth connection and inter
connection of earth pit by No:8SWG copper
conductor.
(DATA-B))
1 Set Supply of tools required for the maintenance
and operation of the Generator set as follows
1 No 15 Cutting plier
1 No 6 Screw driver
2 Nos 9 Screw driver
6 Nos Double end spanner
1 No Adjust table spanner
1 No spanner for removing engine oil plug
1 No line tester
1 No lb hammer (MR)
L.S
Towards seggregation of Light and power
loads including LTUG Cabling&change over
arrangements.

Rate

Per

Amount

1693.30

Each

6773.20

66.40

Mtr

3320.00

2000.00

1 set

2000.00

40000.00
409651.20

LS

PS & Contingencies Charges 2.5%


Total
(Rupees Four Lakhs and Twenty Thousand only)

Total Amount for the year 2014-15

10348.80
420000.00

420000.00

(Rupees Four Lakhs and Twenty Thousand only)


Total Amount for the year 2015-16@ 10% Escalation

(Rupees Four Lakhs and Sixty Two Thousand only)

462000.00

DATA SHEET
(DATA-A)
ADD/
LESS

Qty.
1 No

1 LS
1 LS
ADD

15 Mtr

Description

Cost of 25 KVA Diesel Generator set with


standard accessories and acoustic
enclosure (As per Quotation).
Concrete foundation with cc 1:2:4 and
sand cushion
Erection charge of generator, Fuel tank,
etc.
31/2x25 sqmm PVC LTUG cable ( 3 mt)
with laying under ground (SD - 204)

4 Nos 31/2x25 sqmm cable gland and

termination - (SD-235)
First charging of 75 litre fuel. (MR)
LS

First charging of Lubricating oil - 10 Ltr


(MR)

Rate

Amount

314669.00

314669.00

20000.00

20000.00

10000.00

10000.00

385.20 Mtr

5778.00

146.10 Ea

584.40
0.00

526.00 LS

526.00
351557.40

Say Rs.

351558.00

(DATA-- )
ADD/
LESS

Qty.

Description

Rate

As per SD-74 (without Sundries & labour


charges)
LESS
ADD

9.5 Kg

No.8 SWG GI Wire

Amount
848.125

88.00 Kg

-836.00
12.13

10.378 Kg

No.8 SWG Copper conductor

519.00 Kg

5386.18
5398.31

1 % sundries
ADD

LS

Labour charges

53.98
526.00 LS

526.00
5978.29

Rate/mtr.= Rs. 5878.29/90= Rs. 65.26

66.43
Say Rs.