o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
f>
tb
A. Road Works
1.
of Items
The description of items is given briefly and linked with the relevant clause of the MoRT&H
Specifications for Road and Bridge Works, which may be referred for detailed description, provisions.
and interpretation ..
2.
Mechanical
Means
Due to mechanization of construction work, rate analysis for various items have been prepared
using mechanical means. However, manual means have also been provldedforcertain
cases,
where areas maybe inaccessible for machines or quantum of work may not be large enough to
justify use of machines.
3.
Overhead
Charges
selling up plant, access road, water supply, electricity and general site
c)
w. Mobilisation/de-mobilisation
of resources
viii. Minor T&P and survey instruments and setting out works, including verification
dimensions, trial pits and bore holes, where reqUired
of line,
4.
For the purpose of calCulation of overhead charges, the projects are categorized into 2 types
as under and overhead charges, provided as indicated against each.
Category 1: Cost up to Rs. 50 crores
10 percent
8 percent
Contractor Profit:
5.
Basic Inputs
Basic inputs are only given in the standard data book. The rates for material and labour are to be
obtained from local authorities for thlil area where the project is located.
6.
6.1.
A dozer is proposed for excavation where cutting and filling for the roadway is within 100 m. For
longer leads, a combination of hydraulic excavator and tipper is proposed.
6.2.
Keeping in view the job and managerial factors and thlil aglil factor of machines, the output of plant
and lilquipment is taken approximately 70 per cent of thlil rated capacity given by manufacture
under ideal conditions.
----_.
t'-
6.3.
would make
one trip
charges have flOt'beert inQIUdedfor items Where the Rlquirement is very nominal. It is assumed
that the same would be covered under sundries.
6.4.
Output of plant/equipment
6.5.
The usage charges for machines include ownership charges, cost of repair and maintenance
e
o
including replacement of lyres and running and operating charges which includes crew, fuel and
lubricants.
'
7.
Materials
7.1.
Quantities of materialsgivenin
and include normal wastages. ActUal consumption would have to be based on mix design.
7.2.
7.3.
'. The rates fo material shoukBnclude basic costat locations of stone crushers, loading, unloading,
cost fo carriage and stacking at plant sites as the case may be.
The alternative proposal for curshingown aggregate by installing Crusher should be compared
with procurement of crushed aggregates from the market and proposal found economical may be
adopted.
7.4.
The specifications of materials shall be govemed by section 1000 of MoRT&H Specifications for
Road and Bridge Works.
8.
Labour
8.1.
8.2.
8.3.
Skilled labour include mason, carpenter, blacksmith, mechanics and other trades.
9.
Carriage
9.1.
The unit for vehicle for carriage has been taken as under.
o
~
o
o
of Materials
a)
b)
tor loading
Is variable. The loading and unloading for such cases have been
o
o
o
o
and unloading.
5
I