1. Introduction
This manual is made for workers at a construction site.
So this manual describes the procedure of pipe laying work at the site, points to note, etc.
But description of this manual is general in Lao P.D.R and does not necessarily correspond
to every region.
Therefore please arrange this manual according to local regulation or local manner, and
make use of this manual.
2. Flow chart of pipe laying
The site workers must construct based on design specifications.
This chapter describes a general flow of construction.
The site workers must confirm the flow chart and every part of work in all processes and do
pipe -laying suitably.
This manual does not describe the work of engineer section. If you learn it, refer to textbook for pipe-laying and service installation (after text book) chapter 1,5,6.
Preliminary survey
Design
Preparation for
pipe materials
Site studies.
Land survey.
Engineer
Section
Occupancy
application
Preparation for
materials and equipment
of earthwork
Technician
Section
Earthwork - 1
Water suspension
Measurement (width
and depth of excavation)
Pipeline work
Sand bedding
Pipe cutting, rubber ring
attachment, jointing,
installed valve, etc.
Measurement
(Offset of pipeline, pipe laying
length, earth cover and crossing
position)
Technician
Section
Earthwork - 2
Measurement (Thickness of
pavement, Thickness of upper
and lower of road bed)
Completion of construction
Engineer
Section
Theplaned construction
period
Address of the
construction site
Plan
August
Item
Type of process
Kind of
equipment
1.0
set
Excavation and
back-filling
1.0
set
Pipeline-work
100.0
2.0
place
hydrant
1.0
place
Air valve
1.0
place
2.0
place
20.0
place
5
6
7
Installation of pipe
Gate valve(150)
equipment
Connect to existing
pipe
Service installation
replacement
Road recovery
2025
m
2
150.0
1.0
set
pavement
8
Clean up and
drawing
Completion
October
November December
month
Remark
01020
Preparation work
September
Quantity Unit
K150
Actual
Contents.
! The name of the construction work
! The planned construction period
! Address of the construction site
1. Preparation work
2. Excavation and back-filling
3. Pipeline work
4. Installation of pipe equipment
5. Connect to existing pipe
6. Service installation replacement
7. Road recovery
8. Clean up and drawing
9. Completion
3
01020
01020
01020
01020
01020
Equipments of earthwork
Tamping Machine
Cutter
Backhoe
Truck
Shovel
Dewater pump
Soil
Generator
Asphalt
Earth stopper
Safety equipment
Pipe materials
PVC fitting
PVC pipe
Steel pipe
Steel pipefitting
DIP
Valve
Water! meter
Meter Box
Branch Saddle
Corporation cock
Piping tool
Pipe wrench
Torque & Ratchet Wrench
Thread machine
Saw
Grinder
Engine Cutter
Pipe cutter
(Steel pipe)
Drill
(For branch)
5. Occupancy application
The site worker must submit an occupancy application to road administrator.
In certain cases, it takes a lot of time to get permission takes long time. So you had better to
submit an application as soon as you can.
This chapter describes a general occupancy application in Laos.
Table-2-1.
Table-2-2.
Submit document
1.Application (NPPs application form)
2.Process sheet or schedule.
10
6. Safety control
The construction starts after all necessary equipments, workers, and documents of
construction are prepared.
First of all, securing safety of the site is very important during construction.
This chapter describes a general drawing of safety equipment position on road and presents
some safety equipments with photograph.
If you learn it more in detail, refer to textbook chapter 8.
Fig-1.Safety equipments position
Road
Warning signboard
Construction
Site
Construction Machine
Lighting
Safety fence
Lighting
11
Safety vest
Safety corn
7. Earthwork
The site worker must excavate to lay pipe and backfill after securing safety of the site.
This chapter describes a general procedure for earthwork with photographs.
If you learn it more in detail, refer to textbook chapter 3, 4.
12
Earthwork-1
! Cutting the pavement
! Excavation
13
14
! Measurement of excavation
At the completion of excavation, check the top width, depth and bottom width of its cross
section.
Fig-2 Excavation
B1
soil/granite soil
Sand covering
( 20 30cm)
1.2.2 or
H
Pipe
B2
Sand bedding
(10 20cm)
House side
Water meter
Ground Line
H1
H2
H3
Drain
Roadside
House side
B1
B3
B1
Service pipe
Distribution
Pipe
B3
B2
Sand bedding
B2
15
Sand bedding
Size of excavation (On H1, H2, H3, B1, B2 and B3, See figures shown above.)
B2
(m)
B3
(m)
0.3
0.5
0.1
0.1
0.5
0.6
0.1
0.1
1.2
1.5
0.6
0.8
0.2
0.2
350 1.5
2.0
400
0.9
1.0
0.3
0.3
Nominal
Service
Installation
Size (mm)
H1
(m)
H2
(m)
H3
(m)
13
B1
(m)
Remark
0.2
20
Min.
Min.
1.0
0.4
25
30
40
0.3
50
Distribution Pipe
75
Min.
1.2
100
150
200
250
300
Earthwork-2
! Backfilling
(a) Backfilling-1
Backfilling of soil with backhoe or shovel.
(b) Compaction
Up to pipe top+ 30cm, the backfill should be tamped manually to avoid
damaging the pipes since mechanical tamping may be harmful.
16
(c) Backfilling-2
Backfilling of soil with backhoe or shovel.
Repetition
(d) Compaction
Over pipe top+30cm, apply mechanical tamping using a tamper, etc.
! Completion of backfill
17
(b) Compaction
Compact with mechanical tamping.
(c) Backfilling of mechanically stabilized crushed stones Thickness and structure depends
on road administrator.
18
(d)Compaction
Compact with mechanical tamping.
8. Pipeline works
After earthwork-1 finished, the site workers carry out pipeline works.
This chapter describes notice of installation of pipe, types of joints, joint connection method
(PVC, Ductile cast iron pipe) and notice of water filling and follow.
If you learn it more in detail, refer to textbook chapter 10,11,12.
! Handling and storage of pipes and valves.
(a) Handle pipes and valves with care and avoid giving impact to them, and be careful
not to damage the coating and lining on pipes.
(b) Always keep a good condition of the work, and place fences to prevent outsider
entering storage site.
(c) If storage site is outdoors, cover pipes and valves with sheet (plastic sheet etc) and
end of pipe with cap to prevent a foreign matter from entering inside of t pipes.
(d) Place sleepers or balance log under the pipes.
(e) Always apply drags at both ends while stacking.
Drag
Example
Tight the wire rope always
through the eye
Less than 60
Cushion material
(h) Rubber parts deteriorate when pipes are exposed to ultraviolet lay, heat, etc. in the
air. Therefore store them indoors with packing.
(i) Make sure rubber rings not to touch any oil or solvent while storing or handling.
(j) Do not place bolts/nuts directly on the ground after opening the package.
! Notice of pipe installation
(a) Confirmation of pipe laying position (earth cover, crossing position) in the design
drawing.
(b) Confirmation if the pipes do not have scars, cracks and other faults.
(c) In case of hanging down the pipe, if earth stoppers such as wooden piles are put out
temporarily, after reinforcing and confirming safety, hang down the pipe carefully.
(d) Since uneven surface on excavation bed gives concentrated load to the laid pipes to
damage them, flatten the bed surface as much as possible.
If necessary, bed the sand or sleeper.
(e) After cleaning the inside of pipe, install the pipe accurately based on design drawing
using spirit level.
(f) While installing the pipe, bed the good quality sand on side and bottom of the pipe
and tamp to prevent the pipe from moving.
(g) When installation of pipe is suspended by sunset, cover the end of pipe with the
wooden cap to prevent soil or spring water from entering inside of the pipes.
(h) Using straight pipes for bend part leads to reduction of room for joints to expand or
contract. Therefore such installation style should be avoided.
(i) The sequence of pipe installation is from the lower to the higher point and direction
of faucet is height.
(j) Confirmation of safety. (Especially, if the inside of excavation is safety or not.)
20
Demerits
Comparatively heavy
Anti-escapement measures are necessary at
fittings
Demerits
Demerits
lower cost
as
ser
Merits
Demerits
Highly corrosion-resistant
Easily connected
Corrosion resistant,
alkalinity-resistant
acid-resistant,
Merits
Demerits
Inside smooth
contamination
with
no
scale,
Inexpensive
Easy to construct
! Types of joints
This section describes a general joints used in Laos. If you learn it more in detail, refer to
attachment material.
(a) PVC pipe (Polyvinyl chloride pipe)
(i) Flexible Type (RR type)
RR
Rubber ring
Fig-3 Cross section of Flexible Type (RR type)
Rubber ring
Spigot
Socket
Spigot
Socket
22
Bolt/Nut
Sleeve
Rubber Ring
Spigot
Spigot
Rubber Ring
Rubber Ring
Spigot
Push Ring
Rubber Ring
Bolt/Nut
Faucet
Push Ring
Rubber Ring
Spigot
23
Rubber Ring
(iii) T-type
Fig-8 Cross section of T-type
Rubber Ring
Faucet
Rubber Ring
Spigot
Bolt/Nut
Flange surface
GF type gasket
RF type gasket
RF type RF type
RF type GF type
24
25
(iv) Chamfering
Chamfer with a file or grinder certainly.
Chamfering drawing
2
15
/2
26
Table-3
t- size (Reference)
55
65
80
100
150
200
250
300
t(PVC 5)(mm)
1.8 0.2
2.2 0.2
2.5 0.2
3.2 0.25
4.6 0.3
5.4 0.35
6.6 0.4
7.8 0.45
(v) Cleaning
Clean the outer parts of the pipe on the area which is going to be inserted and the
rubber ring groove.
27
Rubber ring
55
65
80
100
150
200
250
300
L (mm)
75
95
110
135
155
170
195
220
55
65
80
100
150
200
250
300
10
20
25
30
35
29
(ix) Jointing
Place the pipe to be jointed into one straight.
Insert it to marking of spigot with the lever, the puller or hand.
Wooden panel
Check gauge
(x) Inspection
Check with a check gauge to
ensure that the rubber ring is
located properly.
30
marker
31
(iv) Cleaning
Remove any moisture or oil sticking to the pipe surface where the cement is to be
applied with clean cloth.
(vi) Jointing
Immediately insert the pipe into the socket until it bottoms at alignment mark.
Turn the pipe or filling 1/4 turn during connection (but not after the pipe is bottom )
to distribute the cement evenly.
Leave the connected pipe to stand alone for approximately 15 seconds.
33
(vii) Completion
Wipe the remaining cement off with a cloth, then let the solvent harden for 5 minutes
before put into use.
Set straightly
Marking
34
Sleeve
80
100
150
200
250
300
70
80
90
100
100
100
(iv) Jointing
Insert the one spigot into the sleeve.
10mm
Marking
(iv) Fitting the rubber ring and the flange
Fit the rubber ring until
marking line.
Rubber ring
Sleeve
Flange
Sleeve
35
Sleeve
Wipe inside the faucet, especially the contact surface of rubber ring with cloth.
Clean inside and outside surface of the push ring.
(Sand, oil and other foreign matter should be removed)
37
(iv) Clean the rubber ring and place the rubber ring on the spigot.
Wipe the rubber ring with cloth.
38
K-type
20cm
39
Faucet
A-type
K-type
(viii)
Setting the push ring
Adjust the bolt holes of the pipe to the holes of push ring.
Place a wedge between the push ring and spigot to ensure correct centering.
(If necessary)
Wedge
41
42
80
100
600
700
800
900
2,600
M16
M20
M24
M30
Torque(kg-m)
10
14
20
43
Allowable
bending angle
()
Difference (X)
between
measure of A1
500
500
500
500
400
320
450
410
350
320
250
230
210
200
150
140
130
120
110
130
130
130
130
130
130
130
130
and A2
4m
5m
6m
8
10
15
19
19
19
31
31
31
31
31
32
32
32
33
33
33
33
32
43
45
48
53
55
58
63
70
35
35
10
10
10
10
10
10
10
10
44
44
35
13
13
13
13
13
13
35
50
43
40
35
29
26
22
21
19
17
15
14
12
A1
Allowable
bending
Xmm
44
A2
X=A1A2
angle()
kg/m
All joints must satisfy following conditions or disassemble and joint again.
i. The torque is within -20Nm and +30Nm of the specified torque.
ii. Condition of rubber gasket is good.
iii. The difference between max. and min. of the gland-socket clearance a at each joint is within
3 mm.
46
Clean
the rubber ring
47
Rubber ring
Faucet
(iv) Fitting the rubber ring
Insert the rubber ring into the faucet.
Form a heart-shape with the rubber ring.
Rubber ring
Faucet
48
49
(vi) Connection
Lubricant
Lubricant
White line
50
51
Wooden panel
(vii) Inspection
Confirm the proper position of the rubber ring all around the socket by inserting a
check gauge into the gap between the spigot and faucet.
Record the clearance between the faucet face and the rubber ring, the clearance between
the faucet face and white line to the check sheet. .(Refer to T type joint check sheet)
Check gauge
52
Allowable
bending angle
()
500
500
500
500
500
400
400
330
300
300
300
230
230
230
200
200
200
200
200
200
200
200
200
Difference (X)
between
measure of A1
and A2
4m
5m
6m
8
10
15
19
22
21
24
24
24
26
31
31
35
39
35
38
42
47
52
56
58
63
70
35
35
14
14
14
14
44
44
44
18
18
18
18
42
42
37
31
31
31
26
26
26
21
21
21
21
21
Xmm
A1
Allowable
bending angle()
A2
53
X=A1A2
Check sheet
Nominal diameter,
Type of the pipe
Chief
of
pipin
g
work
Instructo
r
Person
in
charge
Measuring
positions
Thickness gauge
Socket groove
Rubber gasket
Arrow view
White lines
(Note)
If the nominal diameter is less
than 300mm, four positions
1,3,5,7 should be measured.
1
2
3
4
5
The clearance between
6
Socket face and rubber
7
gasket
8
1
2
3
4
5
The clearance between
6
Socket face and white line
7
8
Judgment
*! On each joint, if one of the measuring points is 9mm or larger than other 7 points, the rubber
gasket may be twisted. Disassemble immediately for re-assembling.
54
Gasket
(iii) Contact the flanges surface
Install several bolts at equally distances around the periphery.
Contact the flanges surface.
55
Table 8
(vi)
M16
Tighten
torque(kg-m)
60
M20
90
250 300
M22
120
350 400
M24
180
450 600
M30
330
700 1200
Bolt size
75 200
56
Set the gasket in the groove so that the outer diameter of the gasket is in contact with
outer diameter of the groove.
Straight forward.
57
58
59
9. Service installation
Service equipment refers to service pipes installed by branching from the distribution pipe
installed by water supplier and auxiliary devices are directly connected to such service pipes.
For general household use, small caliber service pipes ranging from 13mm to 25mm in
diameter are used. For factories and larger building, there are service pipes from 30mm to
75mm diameter.
Service devices directly connected to service pipes means such devices are connected to
service pipes in such a manner that they are not easily removed.
They are such devices as saddle corporation cocks, curb cocks, water meters, service cock, etc.
This chapter describes general flow chart of service pipe installation, general branching
method and notice of service pipe installation.
If you learn it more in detail, refer to textbook chapter 13.
! Flow chart of service pipe installation
Calculation of design
water consumption
Design
Preparation
Water use
The number of people using water
The number of outlet
Engineer
Section
Equipments of earthwork
Materials of earthwork
Safety equipment
Pipe materials
Piping tool
Earthwork - 1
Technician
Section
60
Earthwork - 2
Technician
Section
Completion of installation
! Safety control
Refer to chapter 6.
! Earth works
Refer to chapter 7.
! General service pipe installation
Show an example of standard service equipment used for normal households.
Fig-10 General service pipe installation
Stop Valve (Bronze)
Meter
40cm
Pipe
(GSP)
Pipe
(GSP)
Corporation cock
Branch saddle
Distribution
i
Pipe (GSP)
26cm
Elbow 90
Nipple
Union
Valve Fitting
Meter Box
Service Tap
Pipe (GSP)
Pipe (GSP)
16.5cm
42cm
50cm
Interval of more than 30cm
61
62
Number of thread
(mm)
(N)
15
20
25
32
40
50
65
11.0
12.0
10.0
11.0
11.0
13.0
15.0
63
flat
Polygon thread
Inflection thread
File
(iv) Jointing
tape a pipe with seal tape.
Seal tape
64
15
20
25
32
40
50
65
Insert number(L)
screw a pipe
screw a pipe
with manual
with wrench
4.5
5.5
4.5
5.5
5.5
7.0
7.5
1.5
1.5
1.5
1.5
1.5
2.0
2.5
Remain
Total
number(M)
number(N)
5.0
5.0
4.0
4.0
4.0
4.0
5.0
11.0
12.0
10.0
11.0
11.0
13.0
15.0
65
L M
Branch saddle
Corporation cocks
Tools
66
(b) Cleaning
67
68
(f) Drilling
! Meter installation
Handle meter with care and avoid giving impact to it
Prevent a foreign matter from entering inside of meter.
Check the meter position.
Check the meter flow direction.
Check the horizontal installation of meter.
69
This section describes only about water meter installation. But there are various kinds of meter.
If you learn it more in detail, refer to attachment material.
! Notice of service pipe installation.
This section describes general notice of service pipe installation.
If you learn it more in detail, refer to attachment material.
(a) At the place where external forces cause strain in the ground surrounding service pipes or
where the ground is not firm, the pipes should be flexible enough to absorb the stress and
prevent damage that leads to water leakage.
(b)To maintain water quality, the service pipe can not be connected to a pipe or
equipment that may cause a reverse flow of contaminated water.
Cooling tower
Cooler
Tap water
Well water or
industrial water
Ball tap
Heat radiating
water
Liaison
Valve
Liaison
valve
Tap water
Service pipe
Service pipe
Do not connect.
Do not connect.
(b) Distributing pipe end connector shall be located more than 30 cm away from the end
connector of other service installation.
(c) The end connector diameter of water supplying pipe to distributing pipe shall not be
70
excessively large as compared to the water consumption rate of the relevant service
installation.
! Determining for the service pipe size
(a) Designed water usage
For the direct connection water service system, the water usage should be determined from
the instantaneous flow rate expected with the possibility of simultaneous usage of taps. In
general, it is determined from the relationship between the total number of taps and those
used simultaneously, (see Table 11 ) or between the number of taps and the usage ratio (see
Table 12 ). The water delivery by tap-type and size, should be considered and reflected in
the total water usage (see Table 13 ).
Table 11
Number of
simultaneously used taps
Total
Number of
number of simultaneously used
taps
taps
1
24
5 10
11 15
16 20
21 - 30
2
3
4
5
6
Table 13
Table 12
Usage ratios
Total number of
1
2
taps
Usage ratio
1
1.4
Total number of
8
9
taps
Usage ratio
2.8
2.9
1.7
2.0
2.2
2.4
2.6
10
15
20
30
3.0
3.5
4.0
5.4
Applicable
usage
tap size
12-40
13-20
12-40
13-20
Wash basin
8-15
13
Bathtub (Japanese)
20-40
13-20
Bathtub (Western)
30-60
20-25
Shower
8-15
13
12-20
13
15-30
13
12-20
13
70-130
25
5-10
13
130-260
40-50
Usage at one
time (8 to 12
seconds):
13.5 to 16.5
Sprinkler
15-40
13-20
liters
35-65
20-25
Application
Note
Usage at one
time (4 to 6
seconds):
2 to 3 liters
For industrial
use
pressure for the distribution pipe. A larger size should be selected with respect to both the
possible increase in future demand, and the minimum operating pressure for water heaters
and other devices.
Care should be taken to prevent an excessive water velocity in service pipes
Head of design
minimum
hydrodynamic
water pressure (H)
Surplus head
Lift head (h)
(h + h) < H
(c) Calculation of the total head loss
(i) Weston's formula
This formula is applied when pipe size is less than 50mm.
And material of pipe is PVC, GSP, Stainless steel pipe, and Polyethylene pipe.
h
{0.0126 (0.01739 0.1087d )/v }
l/d
v 2/2g
Q=(d2/4) v
v=Q/A=Q/(d2/4)
I (h/l)
1000(0/00)
h: Total head loss( m )
l : Length of service pipe(m)
g: Acceleration of free fall( 9.8m/s2 )
v: velocity in pipe( m/s )
d: Diameter of pipe ( m )
I : Hydraulic gradient(0/00)
Refer to drawing of Weston's formula flow curve(P-48)
(ii) Hazen-Williams' formula
This formula is applied when pipe size is more than 75mm.
v
0.35464CD 0.63I 0.54
Q
0.27853CD 2.63I 0.54
d
1.6258C 0.38Q 0.38I 0.205
(h/l)
1000 = I {10.666C 1.85D 4.87Q 1.85 }
1000
h: Total head loss( m )
l: Length of service pipe(m)
v: Velocity in pipe( m/s )
Q: Flow(m3/s)
d: Diameter of pipe ( m )
I : Hydraulic gradient(0/00)
C: Coefficient of Velocity(110)
Refer to drawing of Hazen-Williams' formula flow curve.(P-49)
(iii) Conversion of head loss of service device
Head loss of Service devices, such as saddle corporation cock, water meter, stop valve,
and service cock are converted into head loss of straight-line pipe.
72
Saddle
corporation
water meter
cock stop valve
service cock
Nominal Size
13mm
1.5m
4.0m
3.0m
20mm
2.0m
11.0m
8.0m
25mm
3.0m
15.0m
8.0m
40mm
6.0m
26.0m
50mm
8.0m
35.0m
{(l
l ) I}
H
H : Head of design minimum hydrodynamic
water pressure (m)
h : Lift head ( m )
l : Length of service pipe(m)
l : Head loss of service device(Conversion )(m)
I : Hydraulic gradient(0/00)
h = 10.0 3.0
7.0
pressure:1.0kg/cm2
I
h/l = 7.0 / 35.0 = 200 / 1000
Get flow at drawing of Weston's formula flow curve
35.0m
Q = 0.18
/sec
73
3.0m
Flow(
/sec)
20
0.18
13
200
240
I : Hydraulic gradient(0/00)
I: Hydraulic gradient(0/00)
Distribution pipe
service pipe 13
100
service pipe 20
Main service pipe 25
service pipe 20
10. Postscript
Description of this manual is for general use in Lao P.D.R.
Proper construction work is very important to lead to reduce future water leakage accidents.
On pipe-laying, you should carry out the construction work according to this manual.
Description of pipe materials is also for ordinary use in Lao also. But in the future, when water
supply technology progresses in Lao, high quality and high performance materials will be
required.
And as living standard and life-style change in Lao, water use and form will change also.
This manual is not satisfactory for receiving these changes.
Therefore please revise this manual timely by yourselves.
And if you have some questions in this manual or you would like to know other water
supply equipments that are not included in this manual, please ask WASA (Water Supply
Authority) or NPNL (Nampapa Nakkhone Luang) .
74
75
76
77
78