ABSTRACT
The total number of coiled tubing drilling (CTD) jobs
worldwide has grown from 4 in 1991 to 11 in 1992 and will
probably exceed 25 in 1993. While CTD still represents only
a small fraction of the worldwide drilling market, the growth
rate indicates CTD is a technology that is rapidly coming of
age. This paper summarizes the jobs performed to date and
charts the applications in an effort to predict future trends.
In addition, one specific case stUdy is presented for a well
in Alaska. This well was drilled through tubing and underbalanced, thus saving the cost of pulling the completion tubing
and preventing formation invasion damage. Coiled tubing is
routinely used for live well intervention; its use allows an
accepted, safe method for underbalanced drilling.
Underbalanced drilling is appropriate for many mature and
depleted field re-entry projects and offers a method of both
preventing invasion and increasing productivity while enhancing natural flow and ultimate recovery. In addition, differential sticking is eliminated and penetration rate is greatly
increased.
INTRODUCTION
Table 1 shows an updated' summary of CTD jobs completed as of November 1993. As can be seen, the applications for CTD are worldwide and 18 operating companies are
21
IADC/SPE 27433
WELL
re-entry
re-entry
re-entry
re-entry
new
re-entry
re-entry
new
re-entry
re-entry
re-entry
new
re-entry
re-entry
re-entry
re-entry
re-entry
re-entry
re-entry
re-entry
new
new
re-entry
re-entry
re-entry
re-entry
re-entry
re-entry
new
new
new
new
DEVIATION
vertical
horizontal
horizontal
horizontal
vertical
horizontal
horizontal
vertical
horizontal
vertical
vertical
vertical
vertical
vertical
deviated
vertical
horizontal
deviated
horizontal
deviated
vertical
vertical
vertical
deviated
horizontal
vertical
vertical
vertical
vertical
vertical
vertical
vertical
CT SIZE
1.50
2.00
2.00
2.00
2.00
2.38
2.00
2.00
1.75
2.00
1.75
1.75
2.00
2.00
2.00
2.00
2.00
1.75
2.00
2.00
2.00
2.00
2.38
2.00
2.00
2.00
2.00
2.00
2.00
2.00
1.50
1.50
HOLE SIZE
3.88
3.88
3.88
4.75/3.88
4.75
3.88
4.13
4.75
3.75
4.75
3.88
3.88
4.75
6.13
3.75
3.88
4.13
3.75
4.75
3.75/UR
6.25
6.25
4.75
3.75/UR 5.5
2.75
4.75
4.75
4.75
6.25
6.25
3.88
3.88
drill. However, underbalanced re-entry drilling of the reservoir is believed to be one of the primary applications for CTD.
The industry has approached underbalanced CTD cautiously, and until 1993 very few CTD wells had been drilled
underbalanced. Table 2 shows four wells have been c;jrilled
underbalanced by one company in 1993.
Production data from underbalanced drilling are currently
being evaluated to establish the long-term benefits and
provide a basis for economic analysis of potential candidates.
CTD PROBLEMS, CAPABILITIES, AND APPLICATIONS
CTD Problems
The problems encountered with CTD are the traditional
drilling problems:
mud motor failures
differential sticking
22
IAOC/SPE 27433
Table 2: Detailed Coiled Tubing Drilling Experience For One Service Company
WELL
DATE
LOCATION
0-1
0-2
0-3
0-4
6-91
7-92
10-92
10-92
Paris
Texas
Canada
Paris
0-5
0-6
0-7
0-8A,B
0-9
0-10
0-11
0-12
0-13
0-14
0-15
0-16
0-17
0-18
0-19
2-93
4-93
4-93
6-93
8-93
9-93
9-93
10-93
10-93
10-93
10-93
11-93
11-93
11-93
11-93
Holland
California
California
Alaska
Alaska
Texas
Texas
Texas
California
California
Venezuela
Venezuela
Venezuela
Venezuela
Venezuela
CLIENT
TECH
DRILLED
FT
SUCCESS
Elf
Yes
896
Arco
No
382
No
Can. Hunter
3
Elf
Partial
4370
Shell-NAM
Berry
Berry
Arco
Arco
Amoco
Amoco
Amoco
Chevron
Chevron
Lagoven
Lagoven
Lagoven
Lagoven
Lagoven
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
TOTAL
1060
1179
1422
135
199
416
467
424
880
872
1000
1000
1005
1000
1000
COMMENTS
Cored
Whipstock set/drilled, MWO
Gel diesel mud
Software error
Hard stringer below shoe
Motors, differential sticking,
bit balling, disconnects
Liner, 11 times production increase Orienting tool
Washout 1/4 of Rotary
Bit balling
1
Underbalanced, TT
3112 times production increase
Air/mist
Air/mist
Air/mist
PROBLEMS
Off pad
Off pad
Off pad
Off pad
Off pad
drilling
drilling
drilling
drilling
drilling
17,710
weight transfer
bit balling
Mud motor failures occur primarily with the small 271ain.-diameter motors. Problems with shaft coupling breakage
suggest that these motors, which were designed for workover applications, are overstressed when used for routine
openhole drilling. Some component redesign ofthese motors
has taken place, but the average life is still roughly 25 hrwith
some runs lasting over three times this long. The overall flow
rate range of many of these motors needs to be increased to
match the deliverability of coiled tubing.
Figure 4 shows an example of the weight-transfer problem
with data from Well 0-4, on which a differential sticking
problem was encountered. During the period from 16:45 to
16:52 hr, surface weight on bit (SWOB) was increased to
over 2,000 Ibf with negligible increase in motor pressure.
After very short trips at 16:42 and 16:54 hr, more motor
differential pressure is evident, including a motor stall at
17:05 hr.
ROP increases most when SWOB is first increased (bottom tagged) and when SWOB or slackoff is increased over
2,500 Ibf. Both these ROP increases may be false-caused
by compression of the coiled tubing in a helical buckling
mode. A downhole ROP calculation that corrects for this
deflection may be helpful in the future.
23
CTO Applications
From this analysis and discussion, several applications
can be identified where CTO should be considered:
small-diameter shallow vertical holes in soft formations
horizontal underbalanced re-entries
re-entry on offshore platform or floating production facility
without a permanent drilling installation
through-tubing re-entry in 3 1/2 -in. or larger tUbing
well deepening
exploration wells that can be plugged or completed as
monitor wells
shallow gas relief wells
drilling in urban or environmentally sensitive areas (low
noise, space limitation, spillage prevention, visual disturbance)
WELL 0-9-HORIZONTAL WELL DEEPENING
THROUGH 3 1/2 -in. TUBING
Planned Action
This well was originally drilled in April 1991 and completed
as a horizontal well with 4 1/2-in. slotted liner completion and
a tapered string of 41/2-in. and 31/2-in. tubing (Fig. 5). The
liner was set in an 8 1/z-in. hole that had been cemented and
redrilled with a 6 1/z-in. bit as a result of drilling problems. The
final setting depth of the liner was at 10,385 ft, 284 ft above
total depth (TO) of the well at 10,669 ft. The well never
24
IAOC/SPE 27433
IADC/SPE 27433
increase in this case study is 3 1/2 times that of the well before
deepening at a cost one-fourth of a rig workover.
Technical success rate has improved drastically from the
early years of CTD. The largest problem area currently is the
reliability of 27/a-in.-diameter and smaller downhole motors.
sidered because of the large size of the previous wellbore8 1/2 in.). In addition, the returning fluid had lost its initial
viscosity and yield point (YP) as a result of unidentified
contamination downhole (fluid loss was not as adversely
affected). This poor fluid quality and large diameter of wellbore from previous drilling operations caused severe
"stick/slip" reactions by the coiled tUbing and weight transfer
to the bit could not be achieved by slowly lowering the tubing
into the well. Instead, it was introduced in small, quick
increments. When the lack of motor pressure reaction indicated BHA sticking, the entire string was picked up and
lowered to bottom to restart the drilling process. This inability
to effectively transfer WOB was anticipated (from the coiled
tubing buckling in the 8 1/2-in. open hole) and proved to be
the single largest problem encountered during the operation.
Despite these constraints, penetration rates started at 6
fUhr and reached as high as 18 ftIhr during some intervals;
the average was 10ft/hr.
After the operations were completed, well production
reached 1,075 BOPD. The operation is credited with successfully cleaning out 285 ft of uncased 8 1/2-in. hole and
creating 199 ft of new 2%-in. wellbore. The overall cost for
the coiled tubing operations was approximately one-fourth
the cost of moving in a rig to perform this work with a
production increase of 3 1/2 times that of the well before the
coiled tubing operations were performed.
A specialized work platform (Fig. 9) to be placed on top of
the arctic wellhouse has been developed for future operations to provide a wind shield and movable work surface.
ACKNOWLEDGMENTS
The authors thank Dowell for permission and encouragement to publish this paper. We also thank the many people
at Area Alaska Inc. who helped make CTD efforts successful;
in particular, we thank Lamar Gantt, Curtis Blount, Steve
Ward, Dave Hearn, Arvell Bass, and Dan Venhaus. Special
thanks are also extended to Denny Doremus of the Dowell
CTD task force. Excellent job execution was the result of
efforts by AI Mahoney, Eloy Muniz, AI Maynard, and Dave
Duerr of Dowell Alaska. We also thank Elf Aquitaine, Berry
Petroleum, and Lagoven for use of specific well data.
REFERENCES
1. Leising, L. and Newman, K.: "Coiled Tubing Drilling," SPE
Drilling Engineering (December 1993).
2. Hightower, C.M., Blount, C.G. and Ward, S.L.: "Coiled
Tubing Sidetrack: Slaughter Field Case History," paper
SPE 26335 presented at the 1993 SPE Annual Technical
Conference and Exhibition, Houston, October 3-6.
3. Faure, A.M., Zijiker, VA and Herman van Elst: "Horizontal Drilling with Coiled Tubing: A Look at Potential Application to North Sea Mature Fields in Light of Experience
Onshore The Netherlands," paper SPE 26715 presented
at the 1993 Offshore European Conference, Aberdeen,
September 7-10.
4. Newman, K.R. and Newburn, D.A.: "Coiled Tubing Life
Modeling," paper SPE 22820 presented at the 1991 SPE
Annual Technical Conference and Exhibition, Dallas, October 6-9.
CONCLUSIONS
The CTD yearly job count has grown at a rate of approximately 2 1/2 times the previous year for the past 2 yr. The
largest growth has been in shallow new wells. Deviated and
horizontal wells account for one-third of CTD jobs.
Underbalanced re-entry drilling of the reservoir is a proven
important application, but its use is progressing more slowly
than shallow wells, because of the higher technical difficulty
and a cautious approach to underbalanced CTD.
Underbalanced drilling is optimum from a formation damage standpoint; however, drilling is also enhanced without
differential sticking and with higher ROP.
A case study is presented of a horizontal deepening
through 3 1/ 2-in. tUbing with a 23/ 4 -in. hole. The production
x 1.589 873
x 3.048 1
x 3.785 412
x 2.54 1
x 4.448 222
x 4.535 924
x 6.894 757
1Conversion
25
factor is exact.
E -01 m3
E -01 = m
E -03 = m3
E + 00 = cm
E + 00 = N
E -01 = kg
E + 00 = kPa
IADC/SPE 27433
Year
Fig.1 Distribution of new and re-entry coiled tubing drilling jobs
100
80
-'i
1 1 1 1 1 I I ~I I .I I .l i.I! I I ~1 I .I~ I ~I
60
Vertical
Deviated
III
Horizontal
~
o 40
""')
20
o
1991
1992
Year
Fig. 2 Deviation of coiled tubing drilling jobs
26
1993YTD
as of 11/93
IADC/SPE 27433
16
14
rn 12
.c
Technical success
.2. 10
o
L-
CD
.c
::::J
8
6
4
2
0+--1991
1992
as of 11/93
1993 YTD
Year
Fig. 3 Coiled tubing drilling technical success rate of one company
Time
hr
16:42
16:43
16:45
16:47
16:48
16:50
16:52
16:53
16:55
16:57
16:58
17:00
17:02
17:03
17:05
17:07
17:08
17:10
17:12
17:13
17:15
17:17
17:18
17:20
17:22
Hole
depth
m
ROP
mlhr
1<0
!Tubing load
Ibf
10, 1<0
964:
10,000 <0
4,000> <3,000
4,200> <-1
27
1> <950
Flow out
liter/min
970> <100
i:
200)
IADC/SPE 27433
-t_f4Yz-in. tubing
U-!13Yz-in. tubing
(90 deg~.
\.
BYrin. hole
/(90deg)
2o/4-in. openhole
10,868 ft MD
(83.4 deg)
-----------------~
/ ..'-,...
...1
./
7-in. @ 9,790 ft
(87 deg)
lIog ~"_h'"
....-.stuffing box
'-7-in. riser
~..;.~~@@)~"~=~~::.-----JA:P~P~ro~x~im~a~t:e~to:p~O:f
wellhouse
"";;........
...
Emergency
kill line
_.re:==~
13f.-in. annulus
Fig. 6
28
IAOC/SPE 27433
Dual choke
manifold wI bypassr.:7"7.':""---,
Wellhouse
Wellhouse
r---tt--:\.....,
Coiled
tubing
unit
well flowline
tr
liquid
returns
nk
1---==m:::::!..!:;J;:=:...J
Separator
skid
Fire
Ext.
2 dual filter
with bypass
1,000
1,500
2,000
2,500
3,000
0
-1,000
-2,000
-3,000
.c
-4,000
'tlI
1j -5,000
:eCD
>
-6,000
7-in. liner
(87 deg)
-7,000
""'"
CD
:::I
"
'"
-8,000
-9,000
",
"
10868ft MD
",--' (83.4deg)
-10,000
41/2-ln.
slotted liner
29
81/2-in.
openhole
23/4-ln.
openhole