Commercial Building Consist of 4 basement, Ground floor & mezzanine floor+ 16 Typical floors
Consultant: PAN EMIRATES CONSULT
GENERAL & PARTICULAR SPECIFICATIONS FOR MECHANICAL WORKS
Project:
Demolition of existing building, Construction, Completion
and Maintenance of Commercial Building Consist of
4 basements, Ground floor
& mezzanine floor + 16 Typical floors
Abu Dhabi / Sector: 2 west,
Plot No. C13
File No. 607
Volume 2 / Part 2 B: Mechanical works / General & particular
Specifications
August 2012
Owner:
Obaid Ali Obaid Al Khmairi
&
Meara Ali Obaid Al Khmairi
Consultant:
Tel : 02-6772705
Fax: 02-6778272
Index:
Volume 1 : Part 1: Iinstruction to Tenderers
And forms
Part 2: Standard Construction Contract
Volume 2 : Part 1: Civil works / General & particular
Specifications
Part 2: MEP works / General & Particular
Specifications
Volume 3
: Bill of Quantities
-2-
-3-
INDEX
General Specifications for Electro-mechanical Works
General Specifications for Elevators
Particular Specifications for Mechanical Works
Particular Specifications for Fire Fighting Works
Appendix A List of Approved Manufacturers / AC works
Appendix B List of Approved Manufacturers / Plumbing works
Water Storage Tanks
Plumbing Indicating Instruments
Plumbing and Drainage Service Connections
Submersible Sump Pumps
Domestic Water Booster and Transfer Pumps
Fire Protection General Requirements
Fire Protection Piping and Accessories
Fire Hose Cabinets
Fire Pumps
Appendix_A new version
-4-
TITLE
1.0
Uniformity of Products
2.0
Quality of Products
3.0
Qualification of Manufacturers
4.0
Workmanship
5.0
6.0
Identification
7.0
Inspection
8.0
Concealed Work
9.0
Accessibility
10.0
Exposed Work
11.0
12.0
Installation of Equipment
13.0
14.0
Hangers in General
15.0
16.0
Foundation Fixing
17.0
Fixing to Walls
18.0
Escutcheons
19.0
Warning Tapes
20.0
Inserts
21.0
Notes on Installation
22.0
23.0
24.0
Testing on Site
25.0
26.0
27.0
28.0
-5-
30.0
31.0
Drip Pans
32.0
33.0
34.0
35.0
Flexible Connections
36.0
Gaskets
37.0
38.0
Piping Supports
39.0
Expansion of Piping
40.0
41.0
42.0
43.0
Flashing
44.0
45.0
Motors
46.0
Electrical Characteristics
47.0
48.0
49.0
Pressure Gauges
50.0
Thermometers
-6-
-7-
4.0 WORKMANSHIP
Workmanship shall conform to the appropriate and relevant British Standard Codes of
Practice current at the time of execution of the Works and shall be deemed to be mandatory to
the Contract as though they were included herein.
6.0 IDENTIFICATION
a. After finished painting is completed, identify each piped and ducted service. Locate
identification and flow arrows:
1. Behind each access door.
2. At each change of direction at all jointing pipes and ducts.
3. At not more than 12000mm apart in straight runs of pipes and ducts behind
removable enclosures such as lay-in type ceiling, but on both sides of sleeves.
4. Above each floor or platform for vertical exposed pipes and ducts, preferably 1520
mm above floor and platform.
b. Use stencils and stencil paint on all piping and ductwork. Use minimum 25mm high
letters. Provide the Client with stencils for each service.
Identification shall be at 2M intervals and all branch connections. The color coding
shall be to BSS 1710.
c. Use wording shown on the description portion of the legend on the Drawings or as
instructed by the Consultant.
d. Use the existing color coding system in accordance with British Standards.
e. All pipes, covered and uncovered, except soil waste and vent piping, including electric
feeder conduits shall be marked with stencils to indicate the use of the particular pipe
or conduit. Where water pressure changes occur the stencil shall also indicate the
other pressures. Where pipes are adjacent to each other, stencils shall be properly
-8-
-9-
9.0 ACCESSIBILITY
a. Concealed: Controls, regulators, expansion joints, valves, strainers, unions, cleanouts,
balancing dampers, fire dampers, mixing boxes, and other "products" requiring
accessibility for service, maintenance, or adjustment shall be accessible through
access doors or panels.
b. Services shall be installed, positioned and located to allow proper and sufficient space
for service, maintenance and adjustments.
- 10 -
- 11 -
- 12 -
- 13 -
18.0 ESCUTCHEONS
a. Where exposed pipes or ducts pass through floors, walls or ceilings, they shall be fitted
with a neat heavy spun or stamped brass escutcheon of an approved type firmly secured
to the pipes or duct. Escutcheons shall be of sufficient outside diameter to cover up the
sleeved openings for the pipes or ducts.
b. Escutcheons abutting against tile or terrazzo and at wall and floors shall be chromium
plated; all others shall be painted to match the color of the walls, ceilings or floors as the
case may be. Where escutcheons are not furnished, the Contractor shall provide them.
c. Where necessary to cover beads of fittings, special cast brass deep escutcheons shall be
provided.
d. Hangers for piping 50 mm or smaller shall be the split iron ring type with fastening device.
Hangers for piping larger than 50 mm shall be of the adjustable clevis hanger type.
Hanger rods shall have machine threads. Brackets of approved type may be used along
walls.
e. Any piping which has been insulated having an outside vapor barrier shall have hangers of
adequate size to include the vapor barrier.
- 14 -
20.0 INSERTS
Inserts for securing pipe hangers, etc., to concrete floor construction shall be set before slabs
are poured and shall be of cast iron or steel and must be of a design which will permit use of
the full strength of the bolt. They must permit adjustment of bolt in one direction and must
also permit removal or insertion of bolt or nut after installation of the insert so that different
sizes hanger rods may be used without changing the insert.
- 15 -
- 16 -
- 17 -
- 18 -
- 19 -
- 20 -
26.0 WARRANTY
All the MEP Maintenance will be 24 months from the date of complexion. This include routine
completion add & cleaning filters etc., shall be free from defects in material and workmanship
under normal use and service. If within twenty four (24) months from the date of completion
any of the equipment herein described is defective in operation, workmanship or materials, it
will be replaced, repaired or adjusted at the option of the Contractor free of charge.
- 21 -
- 22 -
- 23 -
- 24 -
36.0 GASKETS
The gaskets used in piping systems shall be best grade for type of service as approved.
- 25 -
MAXIMUM INTERVALS
FOR VERTICAL RUNS
METERS METERS
MAXIMUM INTERVALS
FOR HORIZONT.RUNS
1.2
1.8
2.4
2.4
3.0
3.0
3.0
3.0
3.6
1.0
1.2
1.8
1.8
2.4
2.4
2.7
2.7
3.0
Copper pipework shall be fixed or supported at intervals not exceeding the following:
15mm bore : 1200mm
22mm bore : 1200mm
28mm bore : 1500mm
35mm bore : 1500mm
Exposed copper pipework shall be supported by chrome plated cast brass screw-on brackets
with round base plates, fixed with chrome plated screws.
Concealed copper pipework shall be fixed with copper saddle bands, brackets and brass
screws. Alternatively nylon material can be accepted.
ABS pipework shall be surface fixed with polypropylene saddle clips and stainless steel
- 26 -
- 27 -
- 28 -
12 mm
15 mm
20 mm
25 mm
30 mm
40 mm
50 mm
65 mm
75 mm
100 mm
150 mm
MAXIMUM
SUPPORTS
DISTANCE
HORIZONTAL
MAXIMUM
SUPPORTS
DISTANCE
VERTICAL
0.45 m
0.53 m
0.61 m
0.68 m
0.76 m
0.84 m
0.90 m
1.05 m
1.20 m
1.35 m
1.50 m
0.90 m
1.06 m
1.22 m
1.36 m
1.52 m
1.68 m
1.80 m
2.10 m
2.40 m
2.70 m
3.00 m
MAXIMUM
EXP.JOINT
DIST.VERT.
& HORIZ.
METERS
1.8
1.8
1.8
3.6
3.6
3.6
3.6
- 29 -
45.0 MOTORS
a. Motors:
Motors over 500w shall be in accordance with British Standard 5000 Part 99 'The
Electrical Performance of Rotating Electrical Machinery' or IEC-34-1, in respect of
mechanical details and British Standard 2757 'Classification of Insulatory Materials for
Electrical Machinery and Apparatus on the basis of Thermal Stability in Service' or
IEC-85 in respect of electrical details and the windings shall be as Class F, derated as
necessary in respect of the operating conditions.
All motors shall be in accordance with the requirements of the British Standards. All
motors shall operate satisfactorily under rated load at 10% rated voltage. Motors shall
be suitable for high ambient temperature of 60 degrees Celsius. Class "F", except
where they are in equipment that may be subject to higher temperatures e.g. air
handling units, where they shall be suitable for the operating conditions.
b. Load:
Motors shall be capable of continuous operation at rated full load horsepower or
current without exceeding rated temperature rise at site conditions.
c. Service Factor:
Motors, except totally enclosed, shall have a rated service factor of 1.15 minimum.
Totally enclosed motors may have a service factor of 1.0. Rated motor hp shall
- 30 -
- 31 -
- 32 -
- 33 -
- 34 -
- 35 -
- 36 -
- 37 -
PURPOSE
The document herein is intended to establish design requirements that shall provide a comprehensive reference
text and efficient working document.
1.1
ELEVATOR MODEL
1.
2.
Control system shall be variable voltage variable frequency motor drive and distributed computerized
car controller series G, for low speed elevator [VFGL].
3.
The new MRL shall use a new flat type traction machine, slim type control panel and compact door
operator. Traction machine, Controller and governor shall be located at the top of the elevator well. A
hall inspection panel, which shall be used for inspection operation and emergency operation, shall be
provided at the highest landing serve behind hall button panel.
PART 2 STANDARDS
2.0
GENERAL
Comply with applicable provision of following Codes and/or Authorities, including revisions and changes in
effect on date of these Elevator Specifications:
(i)
Safety Codes for Elevator EN81-1(1998) including all relevant parts and codes of practice.
(ii)
(iii)
PART 3 GENERAL
3.0
PERFORMANCE
B.
C.
D.
E.
F.
G.
Floor-to-Floor Performance Time: Performance figure shall be measured from start of doors closing
until doors are 75% open at the next landing.
900 mm single panel center opening 10.7 sec
- 38 -
Speed
1.6m/sec
Floor height
3300 mm
Landing Open
No
H.
Noise Level: Note more than 55dBA in passenger car (50dBA for 95% period) under rated speed
condition including blower noise. Noise level relating to landing floor shall be limited to max. 50dBA.
I.
3.1
SPECIFICATION
A.
B.
C.
D.
E.
Operation System: Simplex/Duplex selective collective control, for single and duplex elevators.
F.
Traction Machine: Flat type, gearless traction with permanent magnet [PM] motor.
G.
Door System: Single panel center opening (CO) or Two panels side opening (2S)
H.
Environment:
Temperature: -5C to 40C
Humidity: Less than 90 to 95% on a daily average.
I.
Power supply: Power source for elevator shall be 380-400 V/200V AC, 3-phase, 50/60 Hz, and 200240V/100-120V AC, single phase 50/60 Hz for lighting.
J.
Design Life: Equipment and wiring shall be designed for 25 years if adequately maintained.
3.2
Elevator would include all necessary equipment to ensure that the elevator installation complies with Electro
Magnetic Compatibility (EMC) directive, EN12015 (Emission) and EN12016 (Immunity).
PART 4 CONTROLLER
4.0
1.
All control equipment shall be enclosed in sheet steel enclosure, with swing door at the front.
2.
3.
Provided fan and air filter to all ventilation inlet area on controllers.
4.
All drive and control equipment shall be designed to operate reliably with variations in incoming three
phase supply voltages up to 10% to +5% of normal supply voltage.
- 39 -
All cabling etc., shall be routed through entries in the base of cabinet.
6.
Mount control panel on top of elevator well. The grade of protection of the control panel shall be IP21
4.1
1.
2.
The registration of hall call, when the car is parked shall automatically start the elevator and dispatch it
to the corresponding floor.
3.
If a call is registered at the floor where the car is parked, the doors shall automatically open.
4.
Once the direction of travel has been established, the car shall not reverse direction until the car calls
have been answered or until all hall calls, ahead of the car and corresponding to the direction of car
travel, have been answered.
5.
The car shall slow and stop automatically at floors corresponding to registered calls, in the order in
which they are encountered in each direction of travel.
6.
As slowdown is initiated for a hall call, that call shall be automatically cancelled and hall button for that
direction of travel at which the car is remain ineffective, until the car leaves that floor. Car calls shall
be similarly cancelled.
7.
The car shall only answer calls corresponding to the direction in which the car is traveling except that it
may answer a call in the opposite direction if that call is highest (or lowest) call registered.
8.
Registration of a car or hall calls shall cause the appropriate button to illuminate.
9.
When the call is answered the illumination of the button shall extinguished.
10.
Two hall call buttons shall be provided at each hall fixture in order that passengers may register their
intended direction of travel except at terminal floors.
4.2
- 40 -
CONTROLLERS FEATURES
Control features
1.
The car shall be removed from normal operation and is available in inspection operation by using
UP/DOWN button for the maintenance and etc. The UP/DOWN buttons are installed in the car and on
the car top.
2.
The car shall safely and smoothly start in spite of the unbalanced load.
3.
If there is a malfunction of power source failure and the elevator stops between floors, controller shall
perform a diagnostic check prior to moving the car to the nearest floor. In case of a power source
failure, the check is performed either after normal power has been restored or emergency power
supplied.
4.
When a car lands at a hall, doors shall start opening after the car stops completely.
To alleviate temporary traffic congestion, cars shall be automatically assigned (in preferential order) to
floors with the heaviest traffic.
2.
After servicing all car and hall calls, the system shall forecast demand and assigns cars accordingly.
After successive door reverals or obstruction lasing longer than 25 seconds (adjustable) the doors shall
close against any obstruction exerting a controlled force limited by EN81-1
2.
Failure of the landing door interlock to make up if the elevator is committed to a journey shall within 8
seconds initiate a door open cycle.
3.
At all times the `Door Open button shall be in control of door reversal and it shall be wired to and act
directly upon the door open contact via the microprocessor I/O circuits.
4.
Operation of the `Door Close button shall initiate a door close cycle when the threshold is clear.
- 41 -
Timer adjustment
Normal operation
For all elevators on normal operation doors open automatically when the car arrives at a floor to permit
transfer of passengers. Door opening on passenger elevator as required meeting performance time.
7.
When the car is waiting with door open and the `door close button is pushed, the dwell time or notinterference time shall be ignored and door-closing operation shall be expedited.
8.
While the doors start their closing and car direction is reversed, the doors shall be re-opened.
9.
If the malfunction is detected while doors are opening, the doors shall start their closing immediately.
10. Door load detector (DLD)
If the doors are prevented from opening or closing properly, door direction shall be reversed.
11. Door sensor self-diagnosis (DODA)
If a non-contract door sensor fails, the system shall automatically determines the door closing timing to
maintain the elevator service.
12. Auto door-open time adjustment (DOT)
Door open time is automatically adjusted taking into consideration whether the call is hall call or car
call. The door interference timing shall be modulated as follows:
2 seconds if a stop caused by a registered car call. (Adjustable in the range 2-5 seconds)
4 seconds if a stop is caused by a registered hall call. (Adjustable in the range 2-15 seconds)
4 seconds if a door reopen is caused by registered hall call.
13. Auto door speed control (DSAC)
The system monitors the actual door load conditions at each floor and automatically adjusts door
closing speed and torque-limit accordingly.
14. Door nudging feature without buzzer (KNDG)
If the doors remain open longer than the pre-set period, a temporary override automatically closes the
doors.
15. Repeated door-close (RDC)
In the event that the elevator doors cannot be closed completely within predetermined time due to
presence of dust etc. in the groove of the car or landing sill, the elevator doors shall repeat their doorclosing action in order that the obstruction is taken off.
- 42 -
OPERATION FEATURES
1.
When a car responds to the final car call in up or down direction, the system shall automatically checks
and clears remaining calls from memory.
2.
If the doors are unable to open fully at a destination floor for any reason, the doors shall close and the
car shall go to the next floor.
3.
This feature sounds a buzzer to prevent an overloaded car from leaving the floor.
4.
When the car cannot start to respond to the calls registered for predetermined period, the abnormal lamp
shall be illuminated, and the abnormal bell shall ring on the supervisory board only.
5.
Failure of the hall controller shall immediately render the elevator system malfunction. The car shall
park at the next stop with door opened.
6.
Failure of the car controller shall immediately render the elevator system malfunction. The car shall
park at the next stop with door opened.
7.
A car experience trouble shall automatically withdrawn from the group operation to protect overall
group performance.
8.
If a car cannot carry all waiting passengers because it is full, another car shall automatically be
dispatched for the remainder.
9.
The backup function prevents the loss of group control due to a microprocessor or transmission line
failure.
10. Power on re-leveling (PORL)
- 43 -
SIGNAL FEATURES
1.
For the convenience of visually impaired passengers, soft-click touch and tactile buttons shall be
standard.
SERVICE FEATURES
1.
A car shall be isolated from group service and used without interruption using the button combination
(standard) or the override switch in the car operating panel (Optional).
4.4
1.
An emergency electrical operation shall be provided which under define emergency conditions takes
over the normal control of the elevators from the base controller.
2.
The changeover shall be smooth and bumbles at the onset of operation when the base control system
changes from the car to hall control at the top floor hall panel.
3.
This operation shall not affect the base control system, which shall remain resident at all times.
4.
It shall be possible to manually control the direction of travel up or down from the hall operation panel.
5.
With manual rescue the brake release by pushing the BKD switch in the hall inspection panel.
6.
An indication (marking on governor rope) is given to the maintenance personnel through inspection
window, whilst they are by the hall inspection panel.
7.
Inside the car there are no car call buttons etc. operative.
DRIVE SYSTEM
A.
All drive system shall be close loop AC variable voltage variable frequency (VVVF)
B.
Simultaneous control of voltage and frequency allowing smooth, accurate control of a purpose
manufactured permanent magnet motor shall be provided.
2.
Speed feedback shall be direct driven pulse encoder connected to a digital speed regulator circuit.
- 44 -
C.
3.
Motor speed-signals shall be fed back and compared to the speed reference signal and the drive
shall generate voltage reference signals.
4.
Voltage reference signals shall drive the gate control and thus the output voltage of the IGBT stack
by pulse amplitude modulation.
5.
Current from the inverter shall be controlled by pulse width modulation ensuring high power factor
performance.
6.
The current waveform shall be controlled to provide a sinusoidal waveform in order to minimize
torque ripple in the motors and provide smoother ride quality.
7.
The complete drive unit shall be dead each time the elevator stops.
8.
The drive controls shall ensure that once a elevator is committed to a journey there shall be
immediate movement when the landing locks have made up.
INVERTER DESIGN
1.
Inverter shall be of substantially low noise flux vector control type utilizing IGBT (Insulated Gate
Bipolar Transistor) technology with a matched power filter for reducing high frequency noise.
2.
The forward converter for AC to DC shall utilize diodes with smoothing capacitors.
3.
A true high frequency sine wave PWM (Pulse Width Modulation) regulator shall be used for the
gate control circuit.
4.
5.
A fully digital 32-bit speed regulator shall be utilized to supply the current command for variable
frequency.
6.
(i)
(ii)
(iii)
(iv)
(v)
Over current detection and protection circuit shall be incorporated for inverter.
Over voltage protection device for suppression of surge voltages in the main supply.
Speed monitoring circuits to continuously police and so prevent elevator over speed.
Single phase protection device shall be incorporated in control panel.
Diode converter shall be provided to protect reverse phase.
5.1
1.
Only gearless traction machine shall be used, and located at the top of the elevator well.
2.
Each gearless traction machine shall be capable of having 180 degrees of single roping arrangement
and incorporate an AC permanent magnet motor, brake system, and rope retainers mounted in proper
alignment on a common, isolated support.
3.
All gearless machines shall be equipped with inboard bearings and four, five or six of 8mm diameter
hoist ropes shall be used. The number of hoist ropes shall be chosen to meet the requirements of Owner
specification.
4.
Provided digital pulse encoder for close-loop motor-control mounted on each hoist machine. The drive
arrangement shall be direct type drive.
5.
Isolated the machine and support as a whole assembly from the guide rails with isolation rubber shear
resilient mountings.
- 45 -
Sheave diameter shall be 410mm. The insulation resistance of any conductor to the motor frame or
earth shall not be less than 0.5 Megaohm at 50 degrees centigrade. Class F insulation shall be provided.
7.
8.
The fail safe brake shall be adjusted at the manufacturers works to provide a braking torque per EN811 required to elevator full load plus 25% in the up direction.
5.2
PM MOTOR
Means shall be provided for easily lubricating the inboard bearings in the traction machine.
5.3
1.
2.
The brake shall be able to release in order to bring the car to the floor level in an emergency operation.
5.4
STOPPING ACCURACY
1.
2.
3.
All elevators shall avoid over travel as well as under travel and maintain accuracy regardless of load in
car or direction of travel.
GUIDE RAILS
1.
All guide rails shall be T-profile type for car and counterweight. The ends of guides shall be tongue
and groove joints.
2.
All guide rails supplied shall comply with the ISO 7465/97 standard.
3.
4.
Each section of guide rails shall have a minimum of two fixings. The pitch of fixing shall be 2,500 mm.
5.
Manufacturer shall supply all clips, inserts, guide rail bracket, fishplate etc. as necessary for guide rail
fixings at and between floors to achieve necessary pitch of fixings, requisite ride quality, compliance
with standards and this specification.
6.
All fishplates and bolts supplied shall be proposed manufacturer steel block construction. The fishplate
shall be identical unit modulus to the guide rail section itself.
7.
The manufacturer shall ensure that there is sufficient length of guide to ensure that no part of the car or
counterweight guide shoes could run off the guides.
8.
All guides, sole plates and fixings shall withstand the forces imposed on them when safety gear operates
under full contract load in over speed condition. Adequate sole plates shall be fitted to the foot of each
guide.
9.
Provided automatic rail lubrication devices with purpose made fixing arrangement.
- 46 -
BUFFERS
1.
Provided all elevators with oil buffers complete with blocking to suit pit depth.
2.
3.
Provided electric safety switches on buffers per EN81-1 to ensure elevator cannot operate if buffer is
compressed.
4.
There shall be no permanent deformation of the buffer when it absorbs the impact of stopping the car
(with up to 125% of the car load) or counterweight at contracted speed with contract capacity.
6.2
SHEAVES
1.
2.
Provided all necessary mounting means to support sheaves on guide rails, car and counterweight
structural member.
3.
4.
Provided all underslung sheaves with steel frame incorporating buffer striking plate and mounting it on
the car sling.
5.
6.3
GOVERNORS
1.
The governor shall be centrifugal-type, car and counterweight driven with bi-directional electrical
shutdown switch.
2.
Provided overhung supports required for attachment to guide rails. Governor shall be within bounds of
the top of the elevator well.
3.
Governor rope gripper shall provide adequate pull through force to enable satisfactory operation of
safety gear.
6.4
1.
The tension sheaves shall be mounted to the rail support, and each provided with vertical guide
assembly to enable free vertical movement. The governor tension weight pulley shall be pivoted.
2.
The tension weight pulley shall be restrained by a stopper to prevent the rope being pulled up a
significant distance.
3.
A broken/slack rope switch shall be fitted to the governor tensioning sheave. The switch would operate
in both in the case of the rope breaking or the rope being stretched.
6.5
1.
The 6 x Fi(25) + IWRC ordinary lay, dual tensile construction, 8mm diameter shall be used for all hoist
ropes.
2.
3.
Dead-end hitches shall be provided with rope shackle rods having screw adjustment to equalize tension
in all ropes. Provided shackle rods with compression springs to equalize tension during running.
- 47 -
6.6
1.
Normal and final terminal stopping devices shall be supplied and fitted per EN81-1 para10.5.1.
requirements.
2.
Switches at terminal levels shall be operated by a fixed ramp attached to the car sling.
3.
The ramp shall extend half the height of the car sling.
4.
A limit switch shall be situated at the top of the shaft to work in conjunction with the inspection control
station when the elevator is traveling on inspection.
5.
Operation of this limit switches by a fixed ramp on the car shall ensure that the elevator car stops with
sufficient headroom above it.
6.7
TRAVELLING CABLES
1.
The 300/500 V grade elevator traveling cables shall be used and they shall comply with EN 50214.
Cables shall be located in the hoistway. The traveling cables shall be terminated in car top station.
2.
Manufacturer shall fix the positioning of the traveling cables in ensuring the static balance of the car is
maintained at all time.
3.
Restraining points shall provide adequate secure to traveling cables in all car station compartment so
that their weight is not transferred to any of the electrical connections.
4.
All traveling cables shall have a flame retarding and moisture resistant outer cover.
5.
6.
A traveling cable shall consist of 24 cores and cross section area of each conductor is 0.75 sq. mm.
6.8
COUNTERWEIGHT
1.
Counterweight shall be of steel channel frame construction with steel and cast iron sub-weight.
2.
All counterweight sub-weights shall be checked to ensure they are securely fixed to the counterweight
frame such that no noise emanates from the entire assembly during travel.
3.
All counterweight frames shall be constructed as to withstand the impact of buffer operation.
6.9
1.
Provided a pit stop switch per EN 81-1 accessible from landing of lowest level served (by other).
2.
3.
The lowest hoistway lighting fitting shall be within 500mm of the pit floor.
6.10
LOAD SENSING
1.
Provided at shackle mounted a pulley system device to detect the movement of traction rope at pulley
rope ends to weight passenger load in each elevator.
2.
Manufacturer control system design shall provide a load sensing system that shall be able to detect the
gross weight of passenger during a time period when there is no acceleration or deceleration of the car.
- 48 -
HOISTWAY DOORS
1.
The door emergency release key mechanism shall be of EN 81-1 approved type and standardized
throughout the station.
2.
The emergency release mechanism shall be located such that it is easily operated using the release key.
3.
The release key aperture shall be triangle type. The release key mechanism shall utilize the rear face of
the door as a mounting position.
4.
All landing hanger rollers shall be of metal and rubber construction and two rollers fitter per landing
door.
5.
No metal to metal contact shall exist between rollers and top of track.
6.
All hanger rollers shall be 48 mm diameter fitted with bearings with rubber tyres.
7.
they are universal and individually replaced by on site maintenance personnel and fitted at the extreme
ends of each door panel.
8.
The fixing of any landing door hanger roller bracket to the door panel shall employ tapped holes in a
steel block, which has been welded to the rear of the door panel/
9.
All bottom door guide pieces shall be adjustable and have small clearance between guide piece and sill.
All bottom door guide pieces shall be designed for easy removal and renewal.
10.
The running clearance between car and landing sill shall not exceed 30 mm.
11.
All normally visible surfaces of landing door panels and architraves etc. shall not display any method of
fixing eg. Pop rivets, cover strip, etc.
12.
Each panel of center opening landing door arrangement shall be mechanically linked (belt) to adjacent
panel, the panel that is not mechanically locked being biased closed by suitable and separated closer
such that it shall remain in the closed position if the (belt) breaks.
13.
The center opening arrangement shall be electrically and mechanically interlocked in one landing door
panel.
14.
The landing door coupler mechanisms shall be of all metal construction except for the rollers, which
shall be manufactured from hard rubber. For two panels center opening arrangements couplers shall be
provided on one door as both doors shall be positively driven.
15.
Means shall be provided so that subsequent to final adjustment each landing door coupler unit is pinned
in its position.
16.
The coupler roller assembly shall be manufactured from steel and the emergency release mechanism
shall be so located such that it is easily operated using the release key. The release key aperture shall be
adequately reinforced.
17.
Closer shall be weight type only. Bias weight closer arrangement apply closing force at a low level
upon the door panel.
- 49 -
1.
All shall be manufactured from steel and flat on each vertical edge.
2.
Header support plates to which the top track is formed shall be sufficiently thick.
3.
Pan type screws shall be used for securing the apron to the landing sill.
7.2
ARCHITRAVES
1.
2.
They shall be fixed as in integral part of the landing entrance assembly running from the slab fixing
upwards.
3.
They shall be fixed to the entrance sill by means which ensures that tracks is clear over the whole length
of the sill, thus allowing debris free movement over the whole distance of the sill.
7.3
All sills (car and landing) shall be single piece, and solid aluminium extruded type or optional formed stainless
steel.
They shall extend over the full bottom door guide pieces operating distance (open to close).
All sills shall be capable of taking 400 Kg moving trolley across without deflection.
2.
All door panels shall withstand a thrust of 300 N without deformation complying with EN 81-1 strength
requirement.
3.
Car door panels shall be designed so that they overlap the clear opening by a minimum of 20 mm.
4.
Car door hanger rollers shall be located at the extreme ends of the top of each car door pane.
CAR HEADER
Car header shall be constructed of metal, shaped to provide stiffening flanges, securely mounted to the car top.
A car door contact shall be fitted to each panel of the car door.
2.
It shall be located in a position above the hanger that is inaccessible to interference by passengers.
3.
The car door contacts shall be wired such that the hoistway interlock circuit is dead once the car door
opens.
- 50 -
All door operators shall have close loop control and accomplish reversal of door movement after door
open button is pressed.
2.
Facilities shall be available to adjust the opening, closing and nudging speed profiles.
3.
Provided three phase A.C. slim type permanent magnetic motors with VVVF speed control and RISC
microprocessor (i.e. reduced instruction set computer) to detect the door load and adjust the door speed
and torque. A compact type motor shall be coupled to the mechanical link directly.
4.
This shall be the means of motor size reduction that afford a compact type door operator.
5.
All car door operating equipment shall be supported by the car sling member.
6.
If the doors remain open longer that the pre-set period, a temporary override automatically closes the
doors.
E.
1.
Door reopening device shall be accomplished on all elevators by a solid state, electronically operated
infra red device mounted on the car door.
2.
It shall utilize one beams of invisible infra red (SR) passing across the car threshold which shall detect,
through the breaking of any beam by an opaque object that may be placed in its path, the presence of
any person or object in the threshold and cause door reversal.
3.
Mechanical door edges (SDE) shall be an option. The sensitive mechanical door edges detect
passengers or objects upon contact during door closing.
4.
An optional independent form of detection system of which must scan well in front of the landing
threshold shall be capable of detecting the presence of persons or trolleys etc.
5.
Destination floor buttons incorporating illuminating alarm button, door open and close buttons, car
direction indicator, intercom (with speaker and microphone) etc. shall be located upon the car operating
panel provided in each elevator car.
2.
The alarm button shall be of plastic (yellow) and letter mark is grey. It shall send a distress signal to the
supervisory room where the intercom facility is located and automatically enable voice communication.
Optional feature except in EN 81-1 type.
3.
Each car operating panel shall be equipped with door open and door close buttons.
4.
These two buttons shall be mechanically actuated push buttons and shall be partially illuminated.
5.
6.
- 51 -
There shall be minimum operating clearance between the mechanical actuated push buttons and the car
operating panel.
8.
The face surface of all button shall however always be set above the surrounding surface of the car
operating panel.
9.
All operating fixtures shall incorporate an earthing stud to which an earth wire shall be attached.
10.
Name plate of all elevators shall be displayed with the capacity and number of person.
11.
Each elevators shall contain a service panel mounted at a low level height within the car operating
panel.
12.
It shall be stainless steel, vandal resistance, hinged, lockable door matching exactly the car operating
panel finish.
13.
The service panel are able to contain the following controls with each control and its operating position
identified by letters:
(i)
A cab light and fan on and off switch (Optional)
(ii)
An independent service (IND) selection switch to permit the selection of independent or
automatic operation (Optional)
(iii)
Inspection service (HAND) operating switch, up and down pass and door control
buttons for passenger elevators (Optional)
(iv)
A start button for closing the doors and starting the elevator when operating on independent
service (Optional)
9.1
1.
Digital position indicator combined with separate car direction indicator and car message indicator shall
be provided.
2.
They shall be installed, flush mounted, at high level, in the car operating panel behind coloured glazed
panel.
3.
4.
These indicators shall indicate car position at all times, direction of travel at all times, and its status
changes if not on normal service.
5.
6.
On all car position indicators, when a car leaves or passes a floor, illuminate floor legend representing
position of car in hoistway.
7.
9.2
1.
Hall buttons shall be micro movement push buttons with LED illumination on button.
2.
Push buttons shall illuminate corresponding direction of travel upon push button.
3.
9.3
1.
Provided at a location specified by the manufacturer (behind the top landing hall panel) a panel with
control fixtures, indicators and window for rescue purpose.
- 52 -
Panel shall contain buttons and switches for maintenance use of list and provided all facilities for
emergency rescue.
3.
CAR FRAMES
1.
Car frames shall be welded, rolled and formed steel channel construction.
2.
The elevator car sling shall be of substantial proportions to withstand operation of the safety gear
without permanent deformation.
3.
Car sling shall substantially extend over the whole of the platform and additional support shall be
provided by four turn buckle bracing rods extending from the stile to the extremities of the sling ensure
the platform is maintained level and uniform.
4.
The car frame shall not extend above the cross members of the car sling to accommodate sliding guide
shoe assemblies at maximum displacement upon the car sling.
5.
The design, construction and engineered factor of safety of all car sling shall be manufacturer type with
damping elements between car sling and car enclosure.
10.1
CAR PLATFORM
1.
2.
Manufacturer shall provide a reinforced base to the platform of all passenger elevators.
10.2
GUIDE SHOES
1.
The car and counterweight of all electric traction elevators shall be fitted with four sets of sliding guide
shoes.
2.
The sliding guide shoes assemblies shall be above and below the cross member of the car sling.
3.
Each guide shoe shall incorporate a replaceable high polymer polyethylene resin.
10.3
One unit, meeting EN 81-1 requirements, shall be fitted to car top of each elevator in a position such that it is
within each reach of the landing sill.
- 53 -
1.
All car top wiring shall be so arranged that no damage to it can result from two persons working
anywhere on the car top.
2.
This shall be achieved by the construction. That is, above the elevator car roof, of car top, working
platform shall be extended over the whole top of car area which shall adequately support the weight of
two average persons standing at any point on it without such weight causing permanent damage to the
elevator car ceiling.
3.
A permanent collapsible car top handrail shall be mounted around the car top.
4.
It shall comprise of left and right balustrades, horizontal member together with one interlocks to detect
fully erected balustrade, and one for fully collapsed and secured position.
5.
The permanent car top rail shall be electrically interlocked such that only when fully collapsed can the
car move on full speed.
6.
The clear standing area on the car roof shall have at least 0.12 m2 in which the lesser dimension is at
least 0.25 m.
10.5
SAFETY GEAR
1.
The safety gear cams shall be positively interlinked and depend for their operation upon an independent
steel wire rope actuated by tension from the tripping of the over speed governor.
2.
A break switch not dependent upon springs shall operate when the safety gear cams are engaged.
3.
4.
The design of all operating rods, pivots, linkages etc. which serve to operate the safety gears shall be
made by manufacturer.
CAR CONSTRUCTION
1.
The side walls and rear of the car shell substructure shall be constructed of metal panel and shall be so
arranged that they may be removed individually for replacement purposes when damaged in service.
2.
3.
Skirting panels shall be integrated with the floor, extending 75 mm above the car platform.
11.1
CAR ROOF
1.
2.
Suitable to withstand weight of two mechanics working anywhere on the car roof without causing
damage to ceiling finishes or any permanent deformation.
3.
11.2
VENTILATION
1.
Fitted a 100V 2-speed or 200C 1-speed ventilator mounted on the cab ceiling.
- 54 -
3.
4.
The blower shall draw the hoistway air into the cab.
5.
Car shall have a natural ventilation located in car side wall at low level in accordance with EN 81.
11.3
FLOORING
1.
Hard wearing vinyl tiles 2 mm thick or rubber tiles (Optional), mounted to the platform with suitable
adhesives.
2.
Kick plates / Skirting shall be used along the sides and rear of the car at low level abutting the flooring.
11.4
CAR LIGHTING
Provided ceiling design complete with all necessary lighting and wiring.
11.5
1.
Provided stainless steel finish, 2 mm thick, shall be reinforced such that it shall not deform or deflect at
any point when subjected to hand pressure.
2.
- 55 -
The work will be carried out concurrently with the work of the Building Contract and the
Main Contractor will be required to carry out certain work in connection with the Specialist
Sub-contract.
BUILDER'S WORK AND ATTENDANCE
The main contractor is to allow for all builders work as per requirements of the Elevator Subcontractor listed elsewhere in connection with the elevator installation.
The Main Contractor shall also provide normal attendance including all usual facilities for the
execution of the Specialist Sub-contract.
AS-FITTED DRAWINGS AND SERVICE MANUALS
On completion of the elevator installation and at least one week prior to the date of inspection,
the contractor shall hand over to the Engineer as-fitted elevator installation drawings. Two
sets of instruction manuals for general running and maintenance and repair are to be provided.
GENERAL
The contractor shall supply, install., test and commission and hand over the complete elevator
installation as specified
The general requirements of the elevators and particular specifications are given in the
Schedules at the end of the specification.
The Contractor shall commence the electrical installation from the circuit breakers provided
in the machine room for this purpose. All the works shall be co-ordinated with the other
Contractors prior to installation, so that there will be no areas of incompatibility.
The elevator system shall be equipped with traction machinery and associated traction
equipment, elevator cars, solid state control systems and all other equipment and accessories
required to provide a complete, modern, durable and efficient vertical transport system.
All the electrical equipment shall be compatible with the available electrical system of the
building, as specified under Electrical Section.
- 56 -
Each Elevator shall have a safe carrying load inclusive of weight of complete car cable and
ropes and in accordance with the attached schedule.
SPEED
The elevator shall be equipped with variable voltage and variable frequency controlled geared
motors, having stepless, smooth speed time characteristics.
The traction machines shall be designed to meet the severe service condition encountered in
the elevator operation.
Traction sheave, hoisting motor, electromagnetic holding brakes etc. shall be mounted on a
heavy steel bed plate. The steel bed frame shall be mounted on a suitable vibration damper to
isolate the machines from the structure of the building.
All rotating parts shall be statically and dynamically balanced to ensure smooth running. All
the rotating electrical machinery shall be fitted with microtherms, to provide overload
protection.
The winding insulation levels of the motors shall be of Insulation Class `b'.
MOTOR DRIVE
The variable voltage, variable frequency motor drive [VVVF] unit will control the motor
speed using a microprocessor.
- 57 -
The VVVF drive unit will be provided with contactors for removing the power from the
motor of the traction machine. The contactors will open each time the car stops. The brake of
the traction machine will be applied while the contacts drop out.
A pulse rotary encoder will detect the actual speed of the car. The difference between the
speed command signal and the actual speed measured by the pulse rotary encoder will control
the motor speed while the car is accelerating, decelerating and landing.
Protective devices will ensure to open the main circuit between the VVVF unit and the motor
of the traction machine to stop the elevator when one of the following conditions occurs:
Phase reversal, phase failure, failure of supply voltage, overcurrent, overheating of
thyristor and transistor, operation of any safety device.
CONTROL SYSTEM
The control system will consist of the VVVF motor drive unit and a computerized controller.
A computer controlled regulator will control the car speed by comparing the actual car speed
detected by a pulse-rotary encoder with an ideal speed pattern generated by a microprocessor.
While the car is accelerating, the ideal accelerating pattern will be generated by the
microprocessor to obtain the smooth and optimum acceleration.
While the car is decelerating, the microprocessor will calculate and provide the ideal speed
pattern to obtain the comfortable and stable riding performance.
At landing, a smooth landing pattern will be generated by a microprocessor, and as soon as
the car has stopped, the mechanical brake will be applied to hold the car.
- 58 -
A)
IF SINGLE CAR:
1.
2.
THE car will be normally parked with doors closed at the main floor.
3.
THE car will answer its car calls of all floors respectively.
4.
Response to hall calls will be on the basis of same direction priority response, long
waiting time prevention etc.,
B)
1.
2.
One car will be normally parked with doors closed at the main floor and the other will
be a "Free" car which parks with doors closed at its last call floor.
3.
Each car will answer its car calls of all floors respectively.
4.
The microprocessor calculates penalty values for such things as by-passing, reversal
and response by distantly positioned elevators and assigns the call to the elevator that
will minimize the total penalty value.
5.
Response to hall calls will be on the basis of same direction priority response, nearest
cage response, long waiting time prevention, car bunching prevention etc.,
HOISTWAY EQUIPMENT
A)
GUIDE RAILS
For smooth running of the counterweight and the elevator car, guide rails with steel
tee sections shall be installed, covering the entire height of the elevator shaft. The rails
shall rest on the hoistway pit to prevent exerting any physical forces on hoistway
ceiling or walls of the building.
- 59 -
HOISTING ROPES
Bright steel wire ropes with fibre cores of adequate cross-section manufactured or
steel wire ropes with adequate cross-section, manufactured.
C)
GOVERNOR ROPES
These shall be manufactured similar to hoisting ropes. The two ends shall be securely
linked to the car and attached to the safety gear operating level. The governor ropes
shall be tensioned by a weight-loaded device located in the pit.
D)
COUNTERWEIGHT
Cast iron blocks enclosed in a steel framework shall be provided to balance the weight
of the car and the specified capacity.
E)
BUFFERS
OIL type buffers shall be fitted in the hoistway pit beneath both car and the
counterweight. These shall be securely mounted on continuous RS channels and
correctly disposed relative to the car and the counterweight.
The plunger shall be of mild steel, accurately machined and designed to provide very
high safety factor. A toughened rubber bumper shall be fitted to the top of the plunger
to withstand the impact of the steel buffer plates mounted on the underside of the car
and the counterweight. An oil gauge shall be provided to check the oil level.
Spring type buffers shall be provided for speeds 60 MPM and below only.
TRAVELLING CABLES
The travelling cables shall be 450V/750V grade multi-core with stranded high conductivity
copper conductors, especially designed for elevator duty. These cables shall be properly
supported by retaining straps and individual cable clamps.
SAFETY EQUIPMENT
The gradual type safety system, comprising of a close loop roping system, over-speed
centrifugal governor, safety gear equipment etc. shall be provided.
The operation of the system shall be such that if the car overspeeds in the downward
direction, the governor jaws shall trip, operating the safety gear. It shall, in sequence, cut off
the motor power supply, apply normal brakes and engage the safety gear gibs when the safety
gear gibs engage with the car guides. It shall apply a constant retarding force to bring the car
to a gradual and smooth stop within defined limits.
- 60 -
Over Travel
Over travel limit switches shall be provided at the top and bottom of the terminal
landings to disconnect the power supply and apply brakes to bring the car to safe stop
position in the event of an over travel in either direction.
b)
Evacuation Devices
Provision shall be made to move the car manually from the machine room to a nearest
landing in either direction to facilitate evacuation of passengers during a power failure.
c)
ELEVATOR CAR
The size of the car, interior design and decorations, ceiling and lighting and other
facilities shall be as called for in the schedule.
the car shall be of rigid steel framework with sound isolation designed and
manufactured all in accordance with relevant Sections.
The operating buttons and keys shall be as given in the relevant Section of the
Specification. The following facilities shall be provided for each car, in addition to
the items already specified.
a)
Ventilation
Electric Ventilator mounted on car roof with proper vents to be provided.
b)
Emergency Lighting
Self contained, non-maintained emergency light, with a trickle charger.
c)
Emergency Exit
An Emergency Exit shall be provided on car roof. This door shall be able to open
either inside or outside. A safety electrical switch shall be provided to prevent the
car travelling when this emergency exit is open.
- 61 -
Intercommunication System
Intercommunication system between the car, main landing and the machine room.
e)
Working Platform
A working platform shall be provided on the roof of the car.
f)
g)
Door Operator
The door operator shall be high speed heavy duty, with a VVVF controlled AC Motor.
The inverter shall include high speed switching device which inturn shall provide a
smooth sine curve of output current to assure smooth, quite and precise door control.
The opening and closing speeds of the doors shall be adjustable. The landing and car
doors shall operate in full synchronism. Advance door opening during car's approach
to a landing could be used to speed up passenger transfer.
h)
Safety Features
Emergency unlocking key from landing side for evacuation and maintenance work.
Manual opening of the doors from inside the car, within landing zones during power
failure.
Full door height safety-edge device in the leading edge of the car doors to reverse the
doors when there is any obstruction for closing.
Electrical interlock to operate in conjunction with the car doors, so that elevator
cannot operate unless doors are closed.
Overload indicator with buzzer. If the car is overloaded it shall prevent from starting.
The blinking overload indicator and the sounding buzzer shall signal the overload
condition to the passengers.
Emergency light with trickle charger.
TESTING
On completion, a thorough test of the elevators under the working conditions shall be
carried out in the presence of and to the approval of the Engineer.
All materials used must be of the highest quality and the best of their respective kinds
and must comply with the relevant . All weights necessary to carry out the full load
and overload tests must be provided by the Contractor and removed after use.
- 62 -
overload.
Overload protection.
Gate sequence relays, if provided and installed.
All interlocks.
Collective control and priority sequences, if installed.
Safety gear mechanism.
Speeds on Up and Down travel with loadings and empty.
Door contacts.
Final terminal stopping device.
Normal terminal stopping device.
Insulation and earth continuity.
OPERATING PANELS AND INDICATORS
a)
- 63 -
c)
1)
Up and Down call buttons with indicator lights to show that the call has been
registered.
2)
3)
Sills manufactured as specified in the schedules shall be fitted at every landing entrance and
on the car platform for the entire width of the door opening.
These sills shall be with integral grooves to act as guide for the bottom of the door panels.
The car sill shall be securely fitted to the car platform and the landing sills securely fitted to
the entrance threshold. These sills shall be flushed with the finished floor level.
The sills shall be designed to provide adequate strength to support the loads excerting on
them, in addition to the safety and decorative entrance plate appearance.
ELECTRICAL INSTALLATION OF ELEVATORS
General wiring throughout the installation shall be carried out as specified in the Electrical
Specifications. GI trunking shall be used wherever possible instead of multiple conduits. GI
conduits and flexible conduits shall be used between trunking and apparatus.
Earthing of all the equipments shall be carried out as specified in Electrical specification and
as per IEE Regulations.
Distribution Equipment shall contain all protection equipment for motors and circuits. These
shall include overload protection, short-circuit protection, single phasing protection, etc. as
appropriate.
- 64 -
1.
Related builder's works, including wire mesh partition, shaft lighting and ladder in pit,
rail guard/mesh/safety chain in the machine room.
2.
3.
4.
Steel separator beams in between hoistway at approx. every 2.0 mtrs interval.
5.
6.
Emergency standby generator of required capacity to run the elevator(s) in the event of
power failure.
7.
Normally, closed type voltage free sensing contact(s) [rating of contact 125V DC 5A]
with wiring from ATS/Generator panel to elevator control panel.
8.
Provision of conduits with draw wire between elevator shaft and security/reception for
elevator interphone/supervisory panel.
9.
10.
Normally open free sensing contact(s) with wiring from fire alarm panel to elevator
shaft, if automatic recalling of elevators during fire is required.
11.
Supply and installation of tubular free standing scaffolding to our requirement inside
the elevator shafts with working platform and removal thereof.
12.
Cranage facility for unloading lift materials from containers and shifting the same to
various floors and machine room.
13.
Temporary power supply for installation and testing purposes upto shaft and machine
room with breakers.
14.
- 65 -
SECTION
TITLE
SECTION A
SECTION B
SECTION C
SECTION D
Elevators
SECTION E
Electrical works
SECTION E
FIRE FIGHTING
- 66 -
INDEX
INDEX
- 67 -
2.
1.1
To check the design and undertake the responsibility of giving the design
Conditions in the occupied areas.
1.2
To supply, install and commission the air conditioning plant to the satisfaction of
The supervising officer.
1.3
To connect air handling units / fan coil units drains to the nearest drain point.
1.4
To provide power supply to the individual air handling units / fan coil units.
Electrical power supply terminating in an isolating switch located within 3 meters
Of the unit shall be provided by the electrical contractor.
1.5
To provide complete control wiring, empty conduits shall be laid on walls by the
Electrical contractor.
Preliminaries
2.1
Interpretation of documents and drawings
The engineer's specification and drawing shall be interpreted in accordance with good
installation practice relevant to the circumstances. The guidelines of codes of practice of the
British standards institution and ASHRAE standard where such codes are relevant shall take
precedence over all others unless stated in these documents.
Where the engineer's drawings are to a small scale and/or are expressed in symbolic terms or
are in the form of an explanatory diagram then indication of the
Exact location or detail of pipes, ducts, cables, valves or other components shall not be
inferred. Any details not shown or specified but necessary for the proper installation and
operation shall be included in the work.
2.2
Coordination of work done by others
Due to the type of the installation, a fixed sequence of operations is required to properly install
the complete system. It shall be the responsibility of the contractor to closely schedule his
work so that this work will be installed at the proper time and without delaying the completion
of the entire project or the work of other trades, and the contractor shall, without extra charge
- 68 -
2.3
Ceiling Heights
Architectural drawings shall be checked for ceiling height requirements.
deviations from these must be approved by the Architect.
Request for
2.4
Cutting and patching
The contractor shall ensure that the necessary pipe and duct opening for this work are built
into the floors and walls in time.
The contractor shall set sleeves for pipes and ducts accurately before the concrete floors are
poured. Details of sleeves are given hereinafter. Should the contractor neglect to perform this
preliminary work, and should cutting be required in order to install his piping, ductwork or
equipment. The expense of this cutting and restoring of surface to their original condition shall
be borne by the contractor.
3.
GENERAL SPECIFICATIONS
3.1
APPROVALS
Wherever hereinafter the works "for approval" or "approved" are used in regard to
manufactured specialties, or wherever it is desired to substitute a different make or type of
apparatus for that specified, any information pertinent to the suitability of the proposed
apparatus shall be submitted to the engineer for approval.
Approvals for equipment specified herein will be given merely upon the submission of the
manufacturer's names. Notwithstanding anything to the contrary in this specification,
approvals for equipment will be given only after the receipt of complete and satisfactory
performance date (covering the complete range of operating conditions) in tabular and
graphical form as required by the engineer. Complete and satisfactory information shall also
be furnished relating to equipment dimensions, weight etc. It is to be understood, however
that approvals for all equipment not specified or shown on the drawings will be granted if each
equipment in the opinion of the engineer conforms to the performance requirements, space
requirements, any additional costs whatsoever (electrical, structural, architectural, plumbing
etc.)To the owner as a result on any approved substitution shall be borne by the contractor.
3.2
3.2.1
Within one month of the acceptance of the tender the contractor shall submit the
Following in triplicate for approval by the engineer: a.
b.
C.
d.
e.
- 69 -
g.
The heaviest lift and hook headroom required (I) for section (ii) for
Normal maintenance.
3.2.2
Within three months of the acceptance of the tender the contractor shall
submit
The following in triplicates for approval by the engineer: a.
b.
c.
d.
Any costs resulting form failure to comply with this requirement shall be
Borne by the contractor.
e.
If the drawings are not approved one copy will be returned to the
Contractor and marked to indicate the alternations required.
f.
Upon final approval one copy will be marked "approved" by the engineer
And returned to the contractor.
g.
The contractor shall, before starting work on the drawings for approval,
Ascertain from the engineer whether any modifications have been made
Since the date of the tender to any of the relevant tender drawings.
h.
After approval of drawings further four copies shall be provided for the
Use of the engineer.
3.2.3
f.
g.
- 70 -
I.
Diagrams for connections between all items of equipment (e.g. main and
Auxiliary switch boards, control boards, motors, starters, batteries, meters,
Instruments, relays, electronic and allied equipment etc. With component
Values and types suitable marked there on).
When d,e,f,g,h & I have been approved by the engineer the contractor shall
provide three black and white prints of each on thick paper for the use of the
employer and one full plate negative of each for the use of the engineer.
The provision of sections 3.2.1, 3.2.2 and 3.2.3 of this clause shall supersede
the provisions of any other contract clauses relating to mechanical and
electrical work where they are in conflict.
DESIGN ELEMENTS
The installation is based on the following design conditions; capacities and
dimensions given in the specifications or drawings will be considered as the minimum
to be accepted and it is the responsibility of the subcontractor to select all unspecified
equipment to attain the required design and guarantee conditions.
a.
b.
Factory area: Summer 87.8 F +/- 2% dry bulb and approximately 50% +/- 5%
Relative Humidity. Other Areas 75 F +/- 2% dry bulb and approximately 50% +/- 5%
Relative Humidity
c.
Power Supply
415/3/50
240/1/50
3.4
3.5
- 71 -
3.7
Equipment Test and Origin certificates:Test certificates for chillers, and pumps to be provided.
The contractor shall submit certificates of origin for chillers, pumps, air side and other
equipments.
3.8
Installation tests:
The contractor shall give the engineer in writing a note at least ten days prior to the
date of commencement of any test.
The contractor shall supply skilled staff and all necessary instruments and apparatus
and carry out any test required by the engineer for determining specified or
guaranteed data, under the supervision of the engineer. Should the contractor fail to
attain satisfactory results or make these tests, the engineer may himself proceed to
make the tests at the risk and expense of the contractor.
Any damage to the building or plant resulting from the tests shall be repaired to the
satisfaction of the engineer, at the contractor's expenses.
All theists, balancing and final adjustment shall be made in accordance with the
chartered Institute of Building Services guide to commissioning.
Piping system will be hydraulically tested before connection of equipment appliances
and before applying insulation. The test pressure should be twice the working pressure
or 150 lbs./sq.in whichever is the larger. Hydraulic test pressure shall be maintained for
a minimum period of 24 hours and witnessed by the engineer.
Duct work shall be tested in accordance with HVAC standard D-144.
Fan Coil Units shall be tested and balanced together with the controls to deliver the
specified air quantities and temperatures.
On completion, all systems will be properly balanced and left in working order and the
trial of the whole plant shall take place during the appropriate season when design
conditions are met or approximated.
The trial of the plant shall last for a period of one calendar month under normal
conditions of operation without any further adjustments or balancing. If any major
defects or deviations occur in the readings or guaranteed figures, they shall be
remedied by the contractor and a further month's tests shall be carried out.
During the said month, the following readings shall be taken:
- 72 -
As soon as all tests prescribed are carried out satisfactorily, the official taking over
certificate will be issued by the engineer.
3.9
Noise level shall be 35 DB for Office areas. Other Areas as per ASHRAE Standards.
This Section gives the general details of Vibration and Noise Controls and Installation. For
specific requirement for the project refer the relevant drawings
All water chillers, pumps, motors and fan coil units shall be mounted on vibration isolators
suitably designed to eliminate any vibrations to be transferred to the building structure.
The contractor shall be fully responsible for preventing noise and vibration throughout each
system and in the environment surrounding the building.
Flexible neoprene connection shall be used in all connections between ducts and all fans or
fan coil units.
Flexible rubber connection appropriate to the working pressure and medium, shall be used to
connect all pipe work to pumps and chillers.
The contractor shall prepare and submit to the architect detailed shop drawings showing the
complete details of all foundations. Including the necessary concrete and steel work, vibration
isolation devices etc.
All floors mounted equipment shall be erected on 100 mm high concrete pads over the
complete floor area of the equipment providing 2" thick cork sheet unless specified to the
contrary herein, wherever hereinafter vibration eliminating devices and concrete inertia blocks
are specified. These items shall in all cases be in turn mounted upon 100 mm high concrete
pads unless specified to the contrary herein.
All mounts systems shall be protected with factory applied corrosion resistance. All metal
parts of mountings (except springs and hardware) shall be hot dip galvanized. Springs shall
be cadmium plated and neoprene coated. Nuts and bolts shall be cadmium plated.
Steel spring isolation systems shall be with spring diameter not less than 0.8 of the loaded
operating height of the spring. Each spring isolator shall be designed and installed so that the
ends of the spring remain parallel. The spring deflection before becoming solid shall be at
least 50% greater than the specified minimum deflection.
- 73 -
All fan coil units shall be mounted on anti-vibration packages and approved made appropriate
to the respective fan coil type.
The installed vibration isolation systems for each floor of ceiling support equipment shall have
a min. Lateral stiffness under equipment start up or shut down conditions of 75% of the
vertical stiffness motions in excess and shall be restrained by approved spring type
mountings.
PRODUCTS
MATERIALS
All vibration isolation devices, factory built silencers and acoustic plenums shall be provided
by an approved manufacture.
Retain the services of an independent Acoustical Consultant to select the noise and vibration
attenuating devices.
- 74 -
General
Provide, to the Vibration and Noise Control Manufacturer, one copy of all shop drawings of equipment
to be isolated.
Supply shop drawings of the Vibration and Noise Control Equipment being supplied.
On system start-up, inspect the complete installation and report in writing.
Support of Piping
Suspend all piping in mechanical rooms on spring hangers. Weld brackets to the piping and support
on floor mountings pipe work.
- 75 -
Pumps up to 5 hp
Pumps 7-1/2 to 25 hp
Pumps 30 hp and above
- 150mm
- 250mm
- thickness to suite requirement
Each base for horizontally split pumps shall include supports for base elbows for the discharge and
suction connections and for vertically split pumps shall include support for base elbow for suction
connection. Bolt and grout base elbows to the steel and concrete pump base.
Mount the steel and concrete base on spring mountings. Where the concrete base is 'T' shaped or
other than rectangular, locate the spring mountings under the projections as well as the main body of
the base.
Spring mountings shall be self-contained concrete inserts with flush openings on the side of the base
for spring adjustment or removal.
Pour bases on roofing felt and elevate 50mm with mounting adjustment bolts after the pumps are
grouted to the base. Alternatively, the bases may be constructed as specified for 'Floor-Mounted
Centrifugal Fans, Mounting Type 2'.
No damping or snubbing materials shall be used. Spring deflection shall be at least 25mm and all
mountings shall have 6mm thick neoprene vibration isolation pads at the bottom.
Pump and motor shall be on one-piece base. Base of two or more sections welded or bolted together
is not acceptable.
- 150mm
- 200mm
- thickness to suite
- 76 -
- 77 -
VIBRATION ISOLATORS
All steel spring isolators should include a neoprene pad at least 10mm thick mounted next to and in
series with the spring.
Seismic restraints should be employed on all steel spring isolators to limit movement of the equipment
in the vertical and horizontal directions. These restraints shall not bypass the isolation under normal
operating conditions.
The neoprene used in isolation (unless otherwise stated) should have a durometer between 30 and
70.
All rubber isolators should be double acting with no through-bolted connections.
There shall be at least a 50mm air space between the bottom of the isolated equipment and the floor
slab.
HVAC DUCTING
Flexible duct connections should be provided between all fans and ductwork.
Resilient thrust restraints should be incorporated into the flexible connections to eliminate loading of
the flexible connection. The restraints should be steel spring isolators having a static deflection of at
least 19mm.
Wall or floor duct penetrations should allow for a 13mm clearance around the duct. The gap should
be stuffed with glass fiber insulation and sealed with non-hardening caulking. The duct should be
supported on both sides of the wall.
Variable-air-volume (VAV) units should be mounted as high in the ceiling space as possible, at least
2m away from any return air opening.
- 78 -
- 79 -
3.10
Painting.
All steel work including supports, brackets, exposed ducts, are to be painted two substantial
coats of red oxide primer to BS 1011/32 type 2.
All pipe work services insulated or uninsulated shall be fitted with colored identification PVC
bands according to BS 1810 at 6 meter intervals and at changes of directions, branches,
valves and on both sides of walls or ceilings through which they pass.
All exposed metal surfaces of machinery, motor; air handling units, hangers, valves, etc. must
be painted with priming undercoats and two coats of enamel finish to the approved color.
3.11
Electrical Works
- 80 -
4.
CHILLERS
Air-cooled screw chiller
Equipment:
Factory assembled, single-piece, air-cooled liquid chiller. Contained within the
unit cabinet shall be all factory wiring, piping, controls, refrigerant charge
(HFC-134a), duel refrigeration circuits, screw compressors, electronic
expansion valves.
Quality assurance
Unit shall be rated in accordance with Euro vent standard.
Unit construction shall comply with European directives:
Machinery directive 98/37/EC, modified. Low voltage directive 73/23/EEC,
modified
Electromagnetic compatibility directive 89/336/EEC, modified, and the
applicable recommendations of European standards:
Machine safety: electrical equipment in machines, general regulations, EN
60204-1
Electromagnetic emission EN 50081-2. Electromagnetic immunity EN 500822.
Unit shall be designed, manufactured and tested in a facility with a quality
assurance system certified ISO 9001.
Unit shall be manufactured in a facility with an environment management
system certified ISO 14001. Unit shall be tested at the factory.
Unit controls shall be capable of withstanding 55C storage temperatures in
the control compartment.
- 81 -
- 82 -
Diagnostics
Display module shall be capable of displaying set points, system status
including temperatures, pressures, current for each compressor, run time and
percent loading.
The control shall allow a quick test of all machine elements to verify the correct
operation of every switch, circuit breaker, contactor etc. before the chiller is
started.
The control shall be capable of balancing the compressor operating times and
the number of compressor start-ups.
EXV control, based on throttling optimizes evaporator charging, ensuring
condenser superheat and sub cooling.
- 83 -
The pumps and motors shall be from the same country of origin. Each pump
and motor shall be factory assembled. Proper valid documents shall be
submitted as a proof at the time of delivery. The pump manufacturer shall take
Unit Responsibility for the successful operation of the system supplied by
him.
Identical pumps shall be supplied and installed having duties as shown in the
drawings (One no as stand by). The pump set shall be mounted on an inertia
base with vib spring isolators under each and shall have two pressure gauges
one at suction side and one at discharge side along with all associated
fittings as shown in the drawings.
The pumps shall be of end suction type flexible coupled with TEFC Motors
having class F insulations. The speed of the pumps shall be 1450 RPM.
Winding of the motors shall have thermostats to protect against temperature
- 84 -
6.
Description
Air handling unit shall be of the double skin (50mm thick, 50kg/ m3 density
rock wool or polyurethane insulation. or injected form), horizontal concealed
type. Air handling units shall have fan and coil capacities as specified in the
schedule of equipment at the conditions shown thereon or as shown in the
drawings.
The air handling basic unit shall consist of water coil, one or more centrifugal
fans, electric motor, condensate drain pan, galvanized steel casing panel and
electric junction box.
The fan shall be of eth double inlet double width type having forward curve
impellers, and shall be arranged for horizontal air discharge. The fan and
motor package is to be mounted on a common frame and insulated from the
casing by means of rubber / spring anti vibration mounts and flexible fan
discharge sleeve. Impellers are to be balance both statically and dynamically
and securely fixed to a bright steel shaft supported by ball or roller bearings.
Fan motors are to be of the TEFC type and connected to the fan shaft by
means of a vee belt dive with deep grooved pulleys.
The water coils shall be suitable for chilled water and shall be constructed of
staggered heavy wall seamless copper tubes mechanically rounded to
aluminum. Fins with min. 4Row Coil unless specified on the drawings. Coils
are to be mounted on tracks for side withdrawal and located in a stainless
steel drain pan with condensate connections. Coils to be provided with air
vent.
The condensate drain pan shall be constructed of 18 gauge stainless steel
and shall project under the entire length and width of coil including the
- 85 -
a.
These units shall be of constant volume supplying Fresh air to various zones
and shall be switched on through the starter cubicle.
Components
Fresh Air Handling unit shall comprise and trap louver, fly screen, motorized
damper, pre filters, main bag filters, run around coils and supply fan. All
external FAHUS shall be fitted with weather hood with separate control panel
b.
Construction
Components of the units shall be enclosed in galvanized sheet steel double
skin casing with 50mm thick, 50kg/ m3 density rock wool or polyurethane
insulation.
Casing shall be assembled with frame supporting modular panels with an
integrated base frame made up of heavy gauge painted galvanized steel.
Weather proof painting shall be applied to casing & its frame prior to the
assembly.
In order to avoid any condensation problems on the exterior of the panels,
units shall be selected with inner and outer panels without having any type of
contacts i.e. units with thermal break panels. If any condensation occur after
installation, the contractor shall undertake all measures to rectify.
c.
- 86 -
e.
f.
Intake damper
Damper shall be motorized aerofoil blade profile type. When the fan off, the
damper at Fresh Air Intake shall be closed and the CHW control valve shall
move to by pass position. Upon a signal from the starter panel, the damper
shall open an end switch on the damper operator shall signal FAHU fan to
switch on when damper fully open.
6.3
AHU/FAHU CONTROLS(BMS Compatible):
For all AHUs 3 port modulating control valves, space temperature control
thermostats and ON/OFF switches will be provided. For units cooling fresh air,
additional control elements as detailed on drawings will be provided to give
complete operational system to engineers approval.
6.4
- 87 -
GENERAL
Fan Coil Units shall be horizontal suspended types with insulated air plenum.
Exposed units shall have decorative cabinet. The basic unit shall be
constructed of high gage galvanized steel casing not less than 1mm thickness
lined with fibber glass or polyurethane insulation meeting. NFPA 90 A
requirements. Filter track with cleanable air filter, supply collar, and return air
collar on rear of unit for duct connection. Coil shall be of minimum 4 Rows and
shall have Copper tubes and aluminum fins bonded to the tubes by
mechanical expansion, have a working pressure of 150 Psig. And fitted with a
manual air vent
The fans shall be direct driven double width forward curved centrifugal fan,
statically and dynamically balanced with scrolls and wheel constructed of
galvanized steel. The electric motor shall be capable of running on
240V/Ph/50Hz and shall be 3 speed permanent split capacitor type with all
inter wiring to be in galvanized metal flexible conduit secured to both the motor
and terminal box.
The condensate drain pan shall be high gage galvanized steel, pitched for
positive drainage when unit is level. Interior and exterior surfaces shall be
insulated with fire retardant, closed cell foam. Drain pan should extend the
full length and width of the coil. Drain connection shall be 1 OD male sweat
fitting.
7.2
Fan coil units shall be controlled via a three way modulating valve, On/ Off
cum three- speed selector switch type analog thermostat that controls the
three way modulating valve.
- 88 -
GENERAL
All fresh air inlets shall be fitted with volume control dampers as indicated in
the drawings Dampers shall conform to volume control dampers of this
specification.
All fresh air intake shall be fitted with aluminum mesh bird screens, sand trap
louvers as specified below or other approved device to prevent the ingress of
sand and dust, and 2 cleanable type filter installed in an adequate sealed way
in order to prevent by passing.
8.2
9.
- 89 -
DUCT WORK
GENERAL REFERENCE
This Section gives the general details of Sheet Metal Duct and Accessories and
Installation. For specific requirement for the project refer relevant drawings
PRODUCTS
Duct Size
Nominal sheet
thickness
Upto 300
325 to 600
601 to 800
801 to 1000
1001 to 1500
1501 to 2250
2251 to 3000
0.6
0.7
0.8
0.85
1.0
1.2
1.3
Maximum joint
Spacing plain
Crossed board
Minimum angle
section stiffeners
1500
1200
1200
600
600
600
25 x 25 x 3
25 x 25 x 3
40 x 40 x 4
40 x 40 x 4
40 x 40 x 4
50 x 50 x 5
- 90 -
2000
1500
1200
800
600
Bends, branches, tees, transformations and other fittings shall be constructed from the same material
and to the same thickness as the associated straight ductwork and shall conform to the standard of
fittings prescribed in the appropriate HVCA & DW 142 Specification for the ductwork material
concerned.
In all cases the larger dimension of rectangular ducts shall determine the sheet thickness and
standard of stiffening to be used for the fitting.
Turning vanes shall be incorporated as necessary within the standard bends but where the ductwork
is internally insulated; the recommended spacing of the vanes shall be relative to the internal surface
of the lining.
Non-metallic flexible connections shall comprise a liner and cover or tough, tear resistant, glass fibre,
plastic proofed fabric reinforced with a bonded galvanized spring steel wire helix between the liner and
cover, and an outer helix of glass fibre cord or equal bonded to the cover.
Metallic flexible connections shall comprise a spirally wound rigid metal section, interlocked to give a
bendable duct and manufactured from stainless steel, aluminum, or aluminum coated steel, and lined
internally and/or externally with plastic material, all as specified for the section concerned.
Where flexible connections are indicated or required between rigid ductwork and particular
components or items of equipment the internal diameter of the flexible connection shall be equal to the
external diameter of the ductwork and of the spigot to the item served.
Unless otherwise specified or indicated on the drawings the flexible duct shall be metallic and not
exceed six diameters in length with maximum of 3.500 m. Non-metallic flexible ducts shall be subject
to Engineers approval.
- 91 -
Ducts for conveying grease and moisture-laden vapours shall be of stainless steel of minimum
thickness 1.09mm, to NFPA 96 as defined by ASHRAE E1.10 unless other wise specified.
Carbon steel construction having a minimum thickness of 1.37mm shall be acceptable subject to type
and application to Engineer approval.
Adequately sized cleaning doors should be provided, regardless of whether grease filters are fixed at
the entry points, so that access for interior cleaning is possible at intervals of not more than 3.0m.
Precautions must be taken against possible leakage of condensate and/or grease from the ducts by
avoiding longitudinal seams along the bottom face, and employing suitable gasket material at the
joints between sections.
The ducts shall be fixed with a slight fall, preferably in the direction of air flow, and at low points such
as at the bottom of risers there should be plugged drainage points suitable for the later connection of a
permanent trapped drainage pipe if operating conditions demonstrate the need.
After final regulation and balancing of the system, the position of the damper lever, as set, shall be
indelibly marked on the damper quadrant.
Each primary control damper shall be provided with a 100 mm x 50 mm Trifoliate plastic label fixed to
the outside of the duct stating the actual airflow in m3/s and the duct dimensions.
Each damper blade shall not exceed 1200 mm in width or 175 mm in height, and for ducts in excess of
this width multiple frame dampers shall be used.
Fire Dampers
Fire dampers shall be of the folding stainless steel blade type mounted in a galvanized steel frame
and flame proof to BS: 4683:1971 Parts 1 and 2, with steel blades positioned outside the air stream in
its folded (normal) position.
Fire dampers shall be two hours fire resistance in accordance with BS.476 Part 8. 1972.
- 92 -
- 93 -
Description
Pressure Class
- 94 -
Seal Class
B
C
C
B
- 95 -
Metal duct connections to masonry shafts and other builders work openings shall be made with angle
flanges screwed to a hardwood frame fixed to grounds set in the masonry, and with the duct extended
to form a tailed entry. In the case of fire damper connection to fire barrier walls or floors, the flanged
connection shall be made to a metal companion flange provided with a suitable sealing gasket.
Where a metal duct passes through a wall, roof or other building structure, it shall be isolated from the
structure by a layer of bituminous felt over which shall be superimposed a 25 mm thick layer of
mineral wool flexible slab to which the opening shall be made good. This does not apply to fire
dampers which shall be built in.
All screws, bolts and nuts used for erection of the ductwork shall be sheradized or similarly protected.
All cut edges and other exposed metal shall be painted two coats of red oxide or zinc chromate paint
before erection; and after erection, unless special protection is specified for the service concerned, all
rivets, bolts and nuts and other exposed metal shall receive a further two coats of the same protective
paint.
Separate connections between dissimilar metals by dielectric insulation.
Make joints between dissimilar metal duct sections with companion flanges separated by a
compressed asbestos gasket.
Construct all nuts, bolts, screws and other hardware used in the sheet metal construction of materials
identical or similar to the duct material to prevent galvanic corrosion.
All grease exhaust ducts shall be fabricated to the requirements of SMACNA, ASHRAE, NFPA, and
shall be sloped towards the hood.
All grease ducts shall be constructed of 16 ga mild steel (external liquid tight welds) and covered with
flamebar coating for 2hr. fire rating.
The entire duct system including the hangers shall be certified by Flamebar and also shall bear the
approval of UL and FM.
Provide 50 mm foil faced mineral wool insulation around all grease exhaust ducts and cover 0.7 mm
aluminum jacketing.
Provide cleanouts and access per NFPA 96. Flamebar coating is not required if ductwork does not
penetrate a rated wall.
All exhaust ducts from shower areas and laundry shall be constructed of aluminum to the US sheet
metal gage per SMACNA.
Dishwasher exhaust ducts shall be stainless steel (316) to SMACNA standards.
All buried ductwork shall be constructed of ABS with gasketted push on joints. Coordinate all duct
locations with the Civil Contractor.
- 97 -
Registers
- 98 -
- 99 -
- 100 -
- 101 -
Duct insulation
Thermal indoor duct insulation shall be glass fibber with embossed aluminum foil factory
applied as manufacture, have thermal conductivity of 0.27 with 1" thick (24 Kg/m3) at mean
temperature of 75 degree Fahrenheit. Insulation shall be fixed on duct as recommended by
the insulation manufacturer.
12.3
Outdoor (ots, roof, top roof and service floor) duct insulation to be 2" thick rigid board
of fiberglass with density of 48 Kg/m3 with vapor barrier of alum. Foil as shown in detail
drawings.
All duct insulation to be protected with 6-oz. canvas and 2 coats of foster 30-36. A third coat of
foster 57.86 shall be applied to outdoor ducting and one layer for antifungal paint in door
Duct insulation and lining to be adhered to sheet metal duct by foster adhesive 81-22 or
equivalent approved adhesive and to be applied on 50% of ducting area on top side and the
full surface of duct on other sides.
14
14.2
Pipe work will be thermally insulated with rigid section of glass fiber insulation with
density of 64 Kg/m3 for the use of between the temperature of 32 degree Fahrenheit
and 150 degree Fahrenheit and having a K factor of 0.23 at mean temperature of 50
degree Fahrenheit with self applied aluminum craft paper.
PRODUCTS
- 102 -
- 103 -
- 104 -
- 105 -
P.CHW
S.CHW
OA
RA
EA
SA
- 107 -
PRODUCTS MATERIALS
- 108 -
- 109 -
16 Ventilation Fans
GENERAL REFERENCE
This Section gives the general details of Ventilation Fans and Installation. For specific requirement for
the particular project refer the Section Project Particular Requirement and relevant drawings
PRODUCTS
GENERAL
For belt-driven fans, fan and motor shall have one-piece base with adjustable motor mount. Each fan
shall be provided with fan sheave, motor sheave, matched V-belts and belt guard. Where motor is 10
hp (7.5 kW) or less, motor sheave shall be variable pitch. Where motor exceeds 10 HP (7.5 kW),
motor sheave shall be fixed pitch, to be replaced with a correctly sized pitch sheave after air
balancing. Drivers shall be designed for 150% of motor nameplate rating. Provide variable frequency
drive with each fan where called for in the fan schedule. Fan motor shall be suitable for VFD
application.
Published performance fan ratings shall be obtained in accordance with the procedures as set forth by
the AMCA test code for air moving and shall be AMCA certified.
Submit the manufacturer's certified sound power ratings with an octave band analysis and the basis
on which they have been established to the Engineer for approval as part of the fan shop drawings.
Make one set of these curves available to the supplier of sound and vibration isolation equipment.
Each fan shall be statically and dynamically balanced at the factory and shall operate quietly and
without pulsation.
On fans 100 l/s and larger, permanently lubricated bearings are not acceptable. Bearings on shafts
15/16 (24mm) and larger shall be split pillow block, self aligning ball or roller bearings with seals less
grease nipple. In addition, bearings on shafts 1-7/16" (37mm) and larger shall have grease nipple
and grease relief valve. Bearings on shafts smaller than 15/16" (24mm) shall be pillow block, selfaligning ball bearings with seals and with grease nipple. Flanged bearings may only be provided for
shafts 15/16" (24mm) and smaller. They shall be heavy duty; four bolt type, self-aligning with seals
and with grease nipple. It is preferred that all bearings be accessible for lubrication and service. Where
it is difficult to provide such access, extended lubrication lines shall be provided. When such lines
- 110 -
Fan motors shall be totally enclosed in aluminum alloy case and shall be protected by a thermal
overload cut-out. Motor bearings shall be self-aligning oil impregnated porous bushes with ample oil
reservoir. Electrical supply shall be single phase.
CENTRIFUGAL FANS
All centrifugal fans handling more than 1000 CFM. (500 l/s), shall have backward inclined blades,
unless shown otherwise.
All fans shall have arrangement as shown in drawings.
Provide access doors on the fan scroll. Doors shall be hinged, in reinforced angle frames and provided
with clamping devices. Minimum size shall be 18" x 14" (450mm x 350mm) or full width of fan scroll, if
scroll is less than 18" (450mm) wide.
Provide drain connections at the low point of fan scroll or where shown. Drains shall be 1" (25mm)
pipe size half coupling welded into the bottom of the scroll with a square headed, threaded, brass
plug.
Utility fans shall conform to the specification for centrifugal fans above with the exception of the drive
arrangement and belt guard. Drive shall be standard utility arrangement and belt guard may be
omitted if a hood is provided over the drive.
Centrifugal fans shall be in accordance with the Fan Schedule.
Acceptable Manufacturers: Refer Approved Manufacturer and Local Supplier Section.
- 111 -
Impellers shall be of the high efficiency aerofoil, adjustable pitch type, precision made and shall be Xray tested after casting.
Casings shall be manufactured from galvanized steel with access facilities for lubrication, maintenance
and pitch adjustment. Alternatively, lubricators may be of the external type using nylon tubes and
grease nipples on the casing. Casings shall be of the long case type and the whole assembly shall be
suitable for horizontal or vertical installation.
Motors shall be suitable for operation in the worst case air stream conditions. As a minimum standard,
motors of the totally enclosed fan cooled, IP 54, Class F type.
All axial fans shall be installed on proprietary mounting plates with matching vibration isolations bolted
to the supporting structure.
Acceptable manufacturers: Refer Approved Manufacturer and Local Supplier Section.
- 112 -
CABINET FANS
Cabinet fans shall be belt drive centrifugal units with forward curved, aluminum fan wheels in
reinforced, galvanized steel housings.
Motor and fan shall be mounted on vibration isolators.
All internal components shall be accessible through removable or hinged access panels.
Provide a disconnect plug mounted on the interior of the fan casing.
Fan casing shall be lined with 1/2" (12mm) thick acoustic insulation.
All cabinet fans shall be licensed to bear the AMCA seal for air flow and sound level performance.
Cabinet fans shall be suspended from rubber-in-shear vibration isolators.
Cabinet fans shall be in accordance with the Fan Schedule.
The units shall be duplicate fan assemblies mounted on heavy gauge plate within a compact casing.
The fans shall be high efficiency double inlet forward curved centrifugal impellers, belt driven by
individual motors and mounted on individual scrolls. Anti-vibration mountings shall support the motors
to the fan motor scrolls and the fan scrolls to the mounting plates reducing mechanical noise and
vibration.
Air operated flow switches shall be fitted in each scroll to sense airflow failure under fault conditions
and shall activate a fault warning signal and automatically changeover to the standby fan.
Automatic shutters shall be fitted at the fan outlets to prevent "blow-back" through the standby fan.
The motors and fan failure switches shall be pre-wired to an isolator fitted to the unit case.
- 113 -
PROPELLER FANS
Propeller Fans shall be belt driven axial type sidewall fans with cast aluminum blades and hubs.
Provide galvanized steel frame and panel assemblies of formed channels, with formed flanges and
deep formed inlet venture.
- 114 -
16
- 115 -
Water Treatment
a) Piping system should be flushed through twice before treatment to remove grease oil;
construction dust, dirt and mill scale to reduce the opportunity for localized corrosion.
b) Inhibitor products chosen for corrosion control must be chemically compatible.
c) Piping system shall have manual dosing to inject the chemicals into the systems.
d) The chemical treatment to be conducted by a competent company.
e) The characteristics of the treated chilled water should comply with
ASHRAE 87.
f) The treatment certificate shall be submitted to the engineer for approval before the initial
handover of the system.
18
- 116 -
- 117 -
- 118 -
APPENDIX A:
- 119 -
ITEM
REMARKS
AIR COND. CHILLED WATER SYSTEM: Approved original certificate of origin to be submitted before erection in site for chillers FCUs A.H.US units chilled water
pumps & Fans
CHILLERS
CARRIER
GEA
TRANE
SCREW COMP.
1)
(USA/WE)
(GERMANY/WE)
(USA/WE)
AIR HANDLING UNITS
CARRIER
GEA
TRANE
AHUS & FRESH AIR
2)
(USA/WE)
(GERMANY/WE)
(USA/WE)
APPLICATIONS, DOUBLE SKIN
TYPE.
FAN COIL UINTS
CARRIER
GEA
TRANE
3)
(USA/WE)
(GERMANY/WE)
(USA/WE)
4)
AUTOMATIC CONTROLS
JOHNSON
CONTROLS (USA /
W.EUROPE)
AURORA (USA)
INVENSYS
(SATCHWELL)
(W.EUROPE)
CRANE (USA)
5)
6)
AURORA
(USA)
CRANE
(USA)
ARMSTRONG
(USA)
TECNALCO (UAE)
BETA (USA)
TECNALCO (UAE
BETA (USA)
FACTORY MADE.
9)
EXPANSION TANK
(PRESSURIZATION
SYSTEM)
GRILLS / DIFUSERS /
LOUVRES
SOUND ATTENUATORS /
DAMPERS (VCD, NRD,
AND, SPLITTER DAMPERS)
FIRE DAMPERS
TECNALCO (UAE
SAFID
(SAUDI ARABIA )
BETA (USA)
10)
GI SHEET
NIPPON (JAPAN)
KOBE (JAPAN)
NKK (JAPAN)
7)
8)
- 120 -
ITEM
REMARKS
11)
KAWASAKI
(JAPAN)
OVEN TROP
(GERMANY)
NIPPON STEEL
(JAPAN)
KITZ
(JAPAN)
ECONOSTO
(HOLLAND)
HATTERSLEY
(UK)
12)
VALVES
13)
STRAINERS
OVEN TROP
(GERMANY)
KITZ
(JAPAN)
HATTERSLEY (UK)
14)
WEISS
(UK/USA)
HUNTER
(GERMANY)
ECONOSTO
(HOLLAND)
15)
AIR YENTS
ECONOSTO
(HOLLAND)
CRANE (UK/USA)
16)
17)
DUCT INSULATION
ACOUSTIC LINER
KIMMCO (KUWAIT)
KIMMCO (KUWAIT)
AFICO (SAUDI)
MANSON (CANADA)
VIBRATION
MANAGEMENT
(USA)
IZOCAM (TURKEY)
KNAUF (USA)
18)
PIPES INSULATIONS
KIMMCO (KUWAIT)
AFICO (SAUDI)
IZOCAM (TURKEY)
19)
CUTLER HAMMER
(UK/USA)
SIEMENS
(GERMANY)
MERLIN GERIN
(GERMANY)
20)
CAPACITOR BANK
ABB (SWEDAN)
21)
CABLE
DUCAB (UAE)
MERLIN GERIN
(FRANEC)
GULF CABLE
(KUWAIT)
ELECTRONECON
(GERMANY)
SAUDI CABLE (KSA)
- 121 -
ITEM
REMARKS
CABLE TRAY
PER FAST
SWIFT
PHILIP GRAHAME
HEAVY DUTY
23)
VIBRATION ISOLATORS
VIBRATION MOUT
(USA)
MASON (USA)
UNIFLEX (USA)
24)
EXHAUST FANS
(DUCTED INLINE)
GEA
(GERMANY/WE)
PENN VENTILATOR
(USA)
25)
PENN VENTILATORS
(USA)
GEA
(GERMANY/WE)
26)
D.D.C CONTROLS
HONEY WELL
SATCHWEL
STEFA
27)
GEA DENCO
(U.K/WE)
LIBIRT (U.S.A)
- 122 -
General
2.0
Scope of Work
3.0
Regulations
4.0
Basis of Design
5.0
Buildings Drainage
6.0
7.0
Materials
8.0
General
9.0
10.0
11.0
Water Heaters
12.0
Sanitary Wares
- 123 -
3.0 REGULATIONS
All water supply and plumbing installation work in connection with the contract shall be
executed in strict accordance with the valid edition and any supplements, agenda or
published revisions thereto up to date of submission of the Contractors tender of the
Regulations for Water Supply and Plumbing installation as issued by ADEWA and Abu Dhabi
Municipality Drainage Department, in the absence of such negotiations, the National
Plumbing code and the relevant BS Codes shall be applicable. The Contractor shall keep a
copy of the latest said regulations supplements etc. on site at all times during the continuance
of the Contract.
- 124 -
7.0 MATERIALS.
Waste and overflow water main pipe work shall be of the push-fit ring seal type to BS 5254
manufactured in polypropylene. Connections of overflow pipe work to tank shall be by
compression nut joints.
All domestic hot water pipe work shall be in half hard condition copper tubes according to BS
2871 Part 1/1971 Table X. Fittings shall be capillary or compression according to BS 864 .
Cold water, hot water, rising main ,I nternal branches shall be in polypropylene .
All Wall drops should be in pex pipes.
a. Ball Valves
Ball valves shall be fitted on the inlet cold water, hot water supply and hot water
return to each sterilizer and these shall be stainless steel double union ball valves.
b. Gate Valves
Gate valves to copper pipework shall be brass to BS 5154 with compression ends.
Exposed valves on chrome plated pipework shall also be chrome plated.
c. Drain Cocks
Drain cocks to copper pipework shall be brass lock shield drain cocks to BS 2879
type A.
d. Strainers
Strainers to cold water rising mains shall be copper.
c. Copper Pipework Joints and Fittings
Copper pipework shall generally have joints and fittings of the capillary type to BS
864; Part 2.
Screwed joints, where approved, shall be made with PTFE tape.
Compression joints at valves etc. shall be made with carefully cleaned tube and
fittings to ensure water tightness. A smear of approved proprietary compound may be
used to assist the joint.
- 125 -
8.0 GENERAL
a. Waste Pipe Gradients
Horizontal waste pipes below basins, sinks, urinals and the like shall fall at a uniform
gradient of 1 in 45.
b. Access to Waste Pipes
Ends of horizontal runs of waste pipes shall be provided with access plugs. Blank
ends shall have plugs to allow horizontal rodding; 921/2
0 bends, where waste drop
vertically, shall have swept tees or crosses with plugs on the top leg to allow vertical
rodding.
c. Cleaning of Sanitary Plumbing Installation on completion
The Contractor shall, on completion of the installation and immediately prior to
handover, thoroughly cleanse and leave the system in sound condition and efficient
working order.
d. Testing of Waste and Vent Pipes
An air test shall be applied to all waste and vent pipes as follows:
A gauge I the form of a glass U tube shall be connected to the drain plug in the
section of pipe under test. Air shall be blown into the section of the pipe until a
pressure equivalent to 100mm of water is indicated on the gauge. Without further
blowing or pumping, the pressure shall not have fallen below 75mm after a period of
5 minutes.
- 126 -
Table of Contents
1.0
2.0
3.0
2.2.
Specification for Motor Driven Self Lubricated Vertical Turbine Pumps: ................ - 135 -
2.3.
2.4.
- 127 -
GENERAL
REFERENCE
PRODUCTS
Packaged domestic water booster pumps
SUPPLY
DOMESTIC
THE
- 128 -
THE
- 129 -
PROVIDE
End of curve
Motor overload
Pump flow surges
NPRSHR and NPSHA
Hunting
System efficiency program
Efficiency optimization program.
c. EFFICIENCY
d. SYSTEM
EFFICIENCY
PROGRAM:
THE PUMP LOGIC
CONTROLLER SHALL BE CAPABLE OF CALCULATING AND
DISPLAYING SYSTEM EFFICIENCY.
e. FAILURE: IN
AN ASME
BOOSTER
- 131 -
1.2
TYPE
Each pump shall be of the vertical turbine centrifugal type comprising stages which accommodate rotating
impellers and stationary bowls possessing guide vanes. The pump shall be vertical line shaft driven,
above/below ground delivery as shown in the diagram.
1.2
UNIT RESPONSIBILITY
The contractor shall cause all equipment specified under this contract to be furnished by
the pump manufacturer who shall be responsible for the adequacy and compatibility of
all pumping unit components. Any component of each pumping unit not provided by the
pump manufacturer shall be designed, fabricated, tested and installed by factory
authorized representatives experienced in design and manufacture of such components.
This requirement, however, shall not be construed as relieving the contractor of the
overall responsibility for this portion of work.
1.3
DESIGN REQUIREMENTS
The arrangements shown on the drawings are based upon the best information available to the Engineer at the time of design and
is not intended to show exact dimensions peculiar to any specific equipment unless otherwise shown or specified. Therefore, it
may be anticipated that the structural supports, foundations, connecting piping and valves shown in part or whole, may have to be
changed in order to accommodate the pumping equipment furnished. No additional payment will be made for such changes. Any
such changes shall be submitted to the Engineer for his approval.
Pumping units shall be designed to operate without over loading cavitations or damaging vibration at the specified speed, flow
and head conditions. The shut off head of the proposed pumps shall be at least 10% more than the specified head at the specified
capacity.
The motor shall be supported independently on the motor room floor above and shall be connected to the pump with intermediate shafts
a shown in the drawing nos. ..
Motor rating shall be at least 10 % more than the power required by the pump at the specified duty point in case of pump running solo.
The motor base shall be designed for anchor bolting to a concrete foundation, assuming that the pump, without restraint at the
suction and discharge connections, is subjected to a displacing force equal to that developed by an internal pressure equal to three
times shut-off head at the operating speed.
The motor shall be coupled to the pump through vertical drive shafts as specified under 2.1.7.
The complete pumping unit shall be designed to operate without overload on any component at any point along the pump curve at
the specified speed.
1.4
CRITICAL SPEEDS
Each complete system, including pump, motor and all appurtenances, shall have no
dangerous critical or resonance frequencies or multiples of resonance frequencies within
20% above and 35% below the operating speed of the pump.
For the purposes of design, a dangerous vibratory critical speed shall be defined as one,
which produces a torsion stress exceeding 2.4 x 107 Nm-2.The contractor shall be
responsible for the analysis of critical speeds, which shall be analyzed and certified by a
professional engineer regularly engaged in this type of work.
1.5
FACTORY TESTING
1.5.1
Materials
Melt and strength tests of the cast iron used in the manufacture of the pumps major
components shall be performed in accordance with the applicable BS standards as
- 132 -
MATERIALS
1.5.2
Material
Pump shaft
Impellers
Bowls
Column pipes
Impeller Neck
Rings/Casing wear
rings
Gland
Line shaft
Performance Tests
Pump shall be factory tested for performance in accordance with ISO 9906 by a testing
agent approved by the Engineer and shall be to accuracy class C. The supplier shall
submit these test curves prior to shipment of the equipment. These test curves shall
include Head, Efficiency, Power absorbed and NPSH required against Capacity. The
Engineer shall witness these tests.
Pump to be supplied under this contract with more than 30 kW shall be tested with its
distinctive contract motor.
1.5.3
Hydrostatic Tests
Each pump shall be hydrostatically tested. Test pressure shall not be less than twice the
shut-off head as shown on the approved head-capacity curve.
The test procedure shall be as follows:
Condition
Time (Minutes)
Test Pressure
180
Atmospheric
05
- 133 -
Test Pressure
15
Atmospheric
05
Test Pressure
30
At no time during this test shall the casing show undue deflection or signs of weakness at
any point, nor shall the external surfaces of the casing show sweating through porous
metal or leaking through gasket or cracks or other defects.
The contractor shall furnish the Engineer with certified results of the tests.
1.5.4
Vibration Tests
Vibration tests shall be carried out in accordance with ISO 2372 1974.
1.5.5
Motor Tests
Motor shall be tested in accordance with NEMA and IEEE Procedures. The tests shall
include,
a. Routine Tests
i. No load current
ii. Locked Rotor Current
iii. Winding Resistance
iv. High Potential Test.
b. Complete Tests
i. Rated Load Temperature Rise.
ii. Slip.
iii. Locked Rotor Torque.
iv. Breakdown Torque.
v. Efficiencies at 100, 75 and 50 percent of Full Load.
vi. Power factor at 100, 75 and 50 percent of Full Load.
The contractor shall furnish the all certified test results before shipment.
- 134 -
PUMP
SEALS
WITHOUT
DISTURBING
PIPING
PUMP
BEARING HOUSING ASSEMBLY SHALL HAVE HEAVY-DUTY REGREASE ABLE BALL BEARINGS, REPLACEABLE WITHOUT
DISTURBING PIPING CONNECTIONS AND HAVE FOOT
SUPPORT AT COUPLING END.
- 135 -
THE
EACH
PUMPS
PUMPS
- 136 -
NEMA-JP.
Control Panels
REFER
CONTROL PANELS
THE SET OF WATER SUPPLY PUMP CONSIST OF TWO PUMPS ONE DUTY
AND ONE STANDBY, WHEN A SIGNAL FROM PRESSURE
SWITCH TO OPERATE THE PUMP, PRIMARY PUMP WILL
WORKING FIRSTLY AND FOLLOWED BY SECONDARY PUMPS.
EXECUTION
INSTALLATION
-End of Section-
- 137 -
For sanitary Fixtures specification refer to Civil works specifications / Particular Specifications,
MECHANICAL
SECTION C
SEWAGE & DRAINAGE
INDEX
1.0
General
- 138 -
Scope of Work
3.0
Regulations
4.0
Trench Excavation
5.0
Road Crossings
6.0
7.0
Sub-Drains
8.0
9.0
Standard of Compaction
- 139 -
1.0 GENERAL
All work under this heading shall be subject to THE TERMS AND CONDITIONS OF THE
CONTRACT, THE GENERAL REQUIREMENTS, THE GENERAL PROVISIONS, THE BASIC
PRODUCTS & METHODS ETC herein before written for the entire work.
Titles and divisions and paragraphs in these Contract Documents are introduced merely for
convenience and shall not be taken as part of the Specifications, and furthermore, shall not be
taken as a correct or complete segregation of the several units of materials and labour. No
responsibility, either direct or implied is assumed by the Engineer for omissions or duplications
- 140 -
3.0 REGULATIONS
All sewage and drainage installation work in connection with the Contract shall be executed in
strict accordance with the valid edition and any supplements, agenda or published revisions
thereto up the date of submission of the Contractor's Tender of the regulations for
sewage/drainage installation as issued by Abu Dhabi Municipality Drainage Department. The
Contractor shall keep a copy of the latest said regulations supplements etc. on site at all times
during the continuance of the Contract.
- 141 -
7.0 SUB-DRAINS
If necessary for the construction of the works, the Contractor shall lay sub-drains where
directed, to convey the water to pumping sumps or soak ways. Sub-drains shall be laid and
jointed with the invert not less than 300mm below the formation level of the permanent works,
and shall be covered with gravel to formation level. The Contractor shall ensure that these
drains are kept free from silt. These pipes need not be of highest quality but shall be approved
by the Engineer before use.
- 142 -
- 143 -
- 144 -
- 145 -
- 146 -
- 147 -
Where pipes are built into manholes, pits, chambers, thrust blocks and other firmly-founded
structures, at changes in class of pipe bedding and at other locations where differential
settlement can be expected, the first two pipes on each side shall not exceed the following
lengths:
Diameter
First pipe
Second Pipe
Mm
(length projecting)
mm
mm
Less than
300
150
600
- 148 -
300
2 x diameter
450
1200
28.0 JUNCTIONS
The Contractor shall install junctions where directed. Before the trench is refilled, he shall
make accurate measurements of the distance from each junction to the centres of the nearest
manholes upstream and downstream, and record the invert level of the branch and shall
furnish this information to the Engineer, with details of the size and direction of the branch.
- 149 -
- 150 -
33.0 GULLIES
Road gullies shall be polypropylene or GRP in accordance with BS 556: Part 2, 450mm
internal diameter by 900 or 1,050 mm deep with 150 mm outlet and without trap for
soakaways but with trap for a positive drainage system. They shall be complete with GRP
perforated basket and incorporate a 100 mm dia, opening in the base, unless otherwise
directed by the Engineer.
35.0 LADDERS
Ladders shall be aluminium alloy of approved design and obtained from an approved
manufacturer. The dimensions of ladder widths, rung spacing etc. shall comply with BS 4211.
Aluminium alloy shall be A25 anodized in accordance with BS 1615.
- 151 -
39.0 TESTING
The Contractor shall ensure that all pipes, fittings, specials etc. are watertight to the
satisfaction of the Engineer.
The Contractor shall supply all the necessary labour, blank flanges, anchors, air-valves, test
pumps, gauges, clips, stoppers, etc. for testing. Prior to use, the pressure gauge shall be
tested at an approved independent testing laboratory.
Water required for testing shall be obtained from an approved source. The pipeline shall be
filled in such a way that the pipework is not damaged in any way. The Contractor shall supply
and dispose of the water for testing.
The Contractor shall give the Engineer adequate notice in writing of his intention to test any
pipeline (at least 24 hours for pressure pipelines). Testing shall not proceed until permission to
do so has been received from the Engineer. Permission to test shall not imply approval of the
method nor relieve the Contractor in any way of his responsibilities in connection with the
Works.
All pipes shall be cleaned and tested as the work proceeds. If 3 months or more shall elapse
between the final test and the pipeline being taken over, the Engineer may require the pipeline
to be retested as specified for the final test.
Pipes, fixtures and fittings which fail under test, or are broken by or found to be broken under
test, or considered by the Engineer as a result of the test to be unserviceable shall be rejected
and removed from the site forthwith and shall be replaced. Replacement shall be at the
Contractor's expense if, in the opinion of the Engineer, failure is due to the Contractor's
treatment, faulty installation of the component or inadequate inspection. After replacement the
testing shall be repeated.
In the event of failure of a section of pipeline causing damage to any adjacent road, pavement,
structure or existing service, the Contractor shall be liable for all remedial work necessary to
restore the damaged item to its original condition.
On completion and prior to disinfection, if so desired, pipes and specials shall be cleaned out
and flushed with water, all silt, mortar, concrete debris and other obstructions being removed.
Such testing or inspection of any other works shall not be held to relieve the Contractor from
his responsibility to deliver the whole of the Contract Works in a sound and clean state, free
from leakage and other defects under the maximum test or operating pressure whichever is
the greatest.
Upon satisfactory testing of a pipeline or section of a pipeline the Contractor shall submit a
test acceptance form in a format to be mutually agreed, for signature by the Engineer. This
form shall be the true record of all acceptable tests. The Contractor shall retain one copy on
site at all times.
- 152 -
- 153 -
Quantity
Equipment type
Overhead traction
- 154 -
Speed
Control system
Operation
Travel
As per drawing
Pit depth
Overhead height
Location of machine
Car doors
Cabin flooring
Entrance frames
On ground floor
- 155 -
On ground floor
Finished / cladded with hairline finished stainless steel
with etching in pattern selected to consultants choice
from Manufacturers standard range of designs.
On other floors
Finished / cladded with hairline finished stainless steel.
On ground floor
Vertical combined unit comprising of digital hall position
indicator, directional arrows and micro stroke click
buttons which self illuminate on registration of a call,
(face plate in stainless steel hairline with dark gray
plastic case).
Cabin indicators
- 156 -
to
inform
waiting
Interphone:
Interphone for three way communication between the
elevator cabin, machine room and security personnel at
ground floor lobby near the lift entrance.
Overload holding stop:
When a car load exceeds pre-determined capacity,
the elevator will stop its operation with the doors
open at the floor and a buzzer will sound. The buzzer
will stop when enough passengers have exited the
car to reduce the load to below the excess capacity.
Door load detector:
When an object is caught in opening / closing doors, the
doors will reverse its direction when a excess load is
detected. For example, when a pebble becomes lodged
in the door track, rather than force itself open/closed,
the reverse cycle is to be repeated until the problem is
eliminated.
Automatic door open time adjustment:
The system judges the situation whether each car stops
responding to a car call or a hall call and controls the
time of the doors stay open accordingly. The time spent
waiting for the elevator is thereby shortened and
operating efficiency is increased.
Car light and fan off automatic:
To save energy, car lighting and ventilation fan are
turned off automatically if there is no call registered
within a predetermined period of time.
False call cancellation: (P1~P3)
All car calls will be automatically cancelled to avoid
unnecessary stops by registration of nuisance car
calls if the number of calls registered does not
correlate with the car load.
Safety door edge:
- 157 -
Safety ray
An infra-red light beam covers the full width of the door
as it opens or closes to detect passengers or objects.
Emergency car lighting:
Turns on immediately when power fails, and provides a
minimum level of illumination within the car.
Door nudging feature:
In the event of any door safety device malfunction, a
temporary override function is to be automatically
engaged to close the doors, thereby preventing a fault
in elevator operation. Once the doors close completely,
the override has to be cleared and normal operation
resumes.
Next landing facility with main power supply
uninterrupted:
If an elevator door becomes jammed for some reason
[ex. A pebble] and passengers are unable to get off at
the desired floor, the elevator automatically proceed to
the next floor with functioning doors closed in order that
the passengers do not get stranded at the affected floor.
Safe landing with main power supply uninterrupted:
This feature is so designed to prevent passengers from
being stranded in the car when an elevator malfunctions
and stops between the floors. The source of this
malfunction has to be automatically searched out and
when elevator operation is determined to be safe, the
car shall proceed to the nearest safe landing at reduced
speed and the doors then open.
Automatic bypass (ABP) ( P1~P3)
A full loaded car will bypass hall calls in order to
maintain maximum operating efficiency.
- 158 -
- 159 -
Oil type
Safety
Gradual type
Guide rails
Counterweights
Power supply
Lighting supply
- 160 -
MAIN:
Number of Elevators
Lift type (passenger, goods, firefighting, scenic, vehicle,
bed)
LOAD Q (kg)
LOAD (PERSONS)
Speed (m/s)
LIFT CODE
LIFT MACHINERY / CONTROLLER
Machine Location
Machine Type
Drive System
Control system
Operation ( Simplex , Duplex , Triplex , Four Car
Group etc)
Number of stops and openings
Floors Served Front
Floors Served Rear
Travel (m)
Hoistway size [ Width (W) x Depth (D) ]
(mm)
2
Passenger
630
8
1.75
EN81-1
Machine Roomless
Gearless Permanent Magnet
Synchronous motor
VVVF
Microprocessor
Triplex with L3
22 / 22
B4 to B1, G, M, 1 to 16
none
74.3 m
5800 x 1700 - common shaft
for three lifts
1600
4000
N/A
By Lift contractor
By Lift contractor
Bolted
Yes , to be provided
By Lift contractor
By Lift contractor
By Lift contractor
By MEP contractor
PVC
LIFT CAR
Car: Width (W) x Depth (D) x Height (H)
(mm)
- 162 -
DOOR PROTECTION
SILL MATERIAL
LANDING DOORS FIRE RATING
LANDING SIGNALISATION:
LANDING CALL STATIONS
MAIN FLOOR MODEL
FACEPLATE MATERIAL
FACEPLATE SHAPE
BUTTON TYPE (Square or Round, Flush or
Surface)
CALL REGISTERED BUZZER
COLOUR
HANDICAPPED REQUIREMENTS
HALL LANTERNS / INDICATORS
- 163 -
FACEPLATE MATERIAL
POSITION
FACEPLATE SHAPE
COLOUR
CAR SIGNALISATION:
CAR OPERATING PANEL
- 164 -
MAIN:
Number of Elevators
Lift type (passenger, goods, firefighting, scenic, vehicle,
bed)
LOAD Q (kg)
LOAD (PERSONS)
Speed (m/s)
LIFT CODE
LIFT MACHINERY / CONTROLLER
Machine Location
Machine Type
Drive System
Control system
Operation ( Simplex , Duplex , Triplex , Four Car
Group etc)
Number of stops and openings
Floors Served Front
Floors Served Rear
Travel (m)
Hoistway size [ Width (W) x Depth (D) ]
(mm)
1
PASSENGER / SERVICE
900
12
1.75
EN81-1
Machine Roomless
Gearless Permanent Magnet
Synchronous motor
VVVF
Microprocessor
Triplex with L1 & L2
22 / 22
B4 to B1, G, M, 1 to 16
none
74.3 m
5800 x 1700 - common shaft
for three lifts
1600
4000
N/A
By Lift contractor
By Lift contractor
Bolted
NON
By Lift contractor
By Lift contractor
By Lift contractor
By MEP contractor
PVC
LIFT CAR
Car: Width (W) x Depth (D) x Height (H)
(mm)
- 165 -
- 166 -
DOOR PROTECTION
SILL MATERIAL
LANDING DOORS FIRE RATING
LANDING SIGNALISATION:
LANDING CALL STATIONS
MAIN FLOOR MODEL
FACEPLATE MATERIAL
FACEPLATE SHAPE
BUTTON TYPE (Square or Round, Flush or
Surface)
CALL REGISTERED BUZZER
COLOUR
HANDICAPPED REQUIREMENTS
HALL LANTERNS / INDICATORS
MAIN FLOOR MODEL
- 167 -
FACEPLATE MATERIAL
POSITION
FACEPLATE SHAPE
COLOUR
CAR SIGNALISATION:
CAR OPERATING PANEL
- 168 -
Earthquake option
Lift announcer, English Language
Information screens inside the Car (LCD Display)
Elevator Monitoring and Command System (EMCS) BMS roomEmergency battery drive , automatic
Firemans drive Key Switch, to operate the lifts during
Fire
Fire detection, whole building, alternative return floor,
doors open
Emergency intercom car-machine room -control room
Door close button
Accurate relevelling, automatic
Two touch car call cancel
Operation of car light, automatic, switch to turn off
Operation of car ventilation, automatic, switch to turn
off
Provision for loudspeaker in car
Out of service switch in car, doors open, lights on,
indication
Parking at pre-defined floor, doors closed
Car call registered buzzer
CCTV Camera in the Car, Provision Only
Bypass load function
Advance door opening
Nudging service, by measuring load
Emergency stop switch on car roof
Emergency stop switch in well, one switch
Car calls from machine room
Buttons to operate car doors for service purposes on
car roof
Alarm bell at main floor
Alarm bell under/top of car
Car emergency lighting, separate light
Emergency exit contact in car
Buffer switch
Correction drive feature
Car roof blocking device switch
- 169 -
Lift Type
PASSENGER
LIFTS L1 &
L2
PASSENGER /
SERVICE Lift
L3
ZONE 1A
YES
NO
ZONE 1A
YES
NO
NO
NO
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
Yes
Yes
Yes (G)
YES
YES
YES
YES
YES
YES
YES
YES
Yes (G)
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
- 170 -
Appendix B
List of Approved Manufacturers / Plumbing works
- 171 -
ITEM
MANUFACTURER
ORIGIN OF
MANUFACTURER
UAE
UK
UK
2. COPPER TUBES/FITTINGS
YORKSHIRE
WEDNESBURY
OUTOKUMPO
MUELLER
UK
UK
MARLEY
KEY TERRAIN
HEPWORTH GEORGE FISHER
USA
UK
UAE
WIRSBO
ACOME
FRIPEX
GIACOMINI GERMANY
COMPAQ
GERMANY
GERMANY
GERMANY
UPNOR
GIACOMMI
UKAND
ITALY
ARZETE
6. SUMP PUMPS
ABS
KSB
FLYGT
GERMANY
GERMANY
SWEDEN
CRANE
HATTERSLEY
TOUR & ANDERSON
UK
UK
SWEDEN
FLAMMCO
ISOFIX
DIAMOND
WICCO
EUROPE
ARMSTRONG
ITT BELL GOSSPAT
PACO
- 172 -
UK
USA
USA
PATTERSON
ITT BELGOSSPAT
PEERLESS
ARMSTRONG
ABS
ITT LOWARRA
KSB
DALLMAR
SPIRAX SARCO
SOCLA
HONEYWELL
USA
USA
USA
GERMANY
ITALY
GERMANY
GERMANY
UK
USA
ARMAFLEX
AEROFLEX
KAIMOFLEX
ZENITH
TATA
GUJARAT STEEL
WALKER
UNISAFE
ANGUS
SHEIL
UK
UK
UK
UK
VIKING
RELIABLE
GRINNELL
CENTRAL
USA
USA
USA
USA
VIKING
NAFCO
CROCKER
ANDUL
USA
UK
USA
USA
RSI
RBA
DUCAST
INDIA
INDIA
UAE
ARISTON
A.O. SMITH
THERMAX
21. GRILLES/DIFFUSERS/SAND
TRAP LOUVRES
TECHNALCO
BETA
AIRMASTER
BEST CHOICE
NISSIHIN
UNISCO
SUMITAMO
ISCOR
- 173 -
INDIA
INDIA
ITALY
HOLLAND
UAE
UAE
UAE
UAE
JAPAN
SOUTH AFRICA
JAPAN
SOUTH AFRICA
ADVANCED
IDEAL
IDENDEN
C.M.S.
CRANE
BENKEN
NEFIT
ZURN
WADE
DALLMAR
TERRAIN
HEPWORTH
MARLEY
UK
USA
UK
JAPAN
HOLLAND
U.K
U.K
HONEYWELL
BAILY
WATTS
ZURNWILKINS
ZEST
SAFID
RUSKIN
MASON
KINETICS
USA
USA
KINETIC
HODGSON
USA
UK
PIONEER
MITSUBISHI
POLYCON
- 174 -
AUSTRALIA
JAPAN
UAE
- 175 -
- 176 -
- 177 -
- 178 -
- 179 -
- 180 -
- 181 -
- 182 -
- 183 -
- 184 -
- 185 -
- 186 -
- 187 -
- 188 -
- 189 -
Table of Contents
1.0
GENERAL ...............................................................................................................................
2.0
PRODUCTS .............................................................................................................................
3.0
2.1.
2.2.
ELECTRIC MOTOR
2.3
FITTINGS ............................................................................................................................
2.4.
GEAR DRIVE
2.5
2.6
2.7
2.8
JOCKEY PUMP
PUMPING SYSTEM COTROLLER
DIESEL TANK AND ASSOCIATED PIPE WORK
EXECUTION
- 190 -
1.0 GENERAL
1.1. VERTICAL TURBINE FIRE PUMPS
Electric Motor and Diesel Engine Driven
The pumps furnished for fire protection service shall be supplied with the
specified drivers, controls and pump accessory items by the pump
manufacturer. The pump, driver and control shall be
--Underwriters Laboratories (UL) Listed
-- Factory Mutual Research Corporation (FM)Approved
The pumping equipment shall be installed as recommended in the National
Fire Protection Association (NFPA) 20,Standard for the Installation of
Centrifugal Fire Pumps.
The fire pump shall be designed to deliver U.S. gallons per minute (gpm)
at a total differential pressure of psi. or (m of H2O ) The fire pump shall also
be capable of delivering not less than 150% of rated flow at not less than
65% rated head. Furnished with driver, controllers and accessories as
detailed in this specification. Pump manufacturer shall have unit
responsibility for the proper operation of the complete unit assembly as
indicated by field acceptance tests.
1.2
1.3
- 191 -
2.0
PRODUCT
- 192 -
- 193 -
--mounted on a common base with the fire pump and wired to the
motor by the pump manufacturer.
2.3 FITTINGS:
The pump manufacturer shall furnish piping accessory items for the pump
installation which will adapt the pump connections to the fire
protection system and test connection as follows.
Fittings subjected to pump discharge pressure shall be
ANSI (125)(250) pound rating. Fittings subjected to
suction pressure shall be ANSI 125 pound rating.
- 194 -
- 195 -
- 196 -
2.6
JOCKEY PUMPS
CIRCUIT BREAKER - TIME DELAY TYPE WITH TRIPS IN ALL PHASES SET
FOR 300 OF THE MOTOR FULL-LOAD CURRENT.
- 197 -
2.7.5 PILOT
LAMP
AVAILABLE.
LAMP
AVAILABLE.
- 198 -
PILOT
LAMP
AVAILABLE.
2.7.18
2.7.20 MANUAL
2.7.21 MEANS
ALARM
2.7.22
ELECTRONIC
WATER
LEVEL
INDICATOR:
- 199 -
2.8
2.8.3
2.8.3.1
FUEL
2.8.3.2
2.8.3.3
LEVEL SWITCH
ENGINE.
2.8.3.4
2.8.3.5
2.8.3.6
FILL
CONNECTION
CONTAINMENT.
WITH
WITH
HIGH/ LOW
OPW
1-2100
SPILL
BE OF STEEL CONSTRUCTION.
14
2.8.4
Diesel piping:
2.8.4.1
PIPING
2.8.4.2
2.8.4.3
53 STEEL
PIPING WITH A
- 200 -
3.0
EXECUTION
3.0.1
3.0.2
3.0.3
3.0.4
3.0.5
3.0.6
- 201 -
3.0.7
3.0.8
3.0.9
3.0.10
3.0.11
3.0.12
3.0.13
3.0.13.1
3.0.13.2
SET
3.0.13.3
FOR PRESSURE SIGNAL TO OPERATE THE JOCKEY PUMP, FP3P WILL OPERATE BEFORE FP-3S.
3.1.13.4
For any signal to operate the electrical or diesel pump
FP-1P & FP-2P will operate FP-2S & FP-3S.
3.0.14
- 203 -
3.0.14.1
THE
3.0.14.2
OVERHEATING: THE
3.0.14.3
3.0.14.4
3.0.15
THE
CONTROLLER:
THE AUTOMATIC CONTROLLER SHALL BE PUT THROUGH NOT
LESS THAN
TEN AUTOMATIC AND TEN MANUAL OPERATIONS.
A
AUTOMATIC
THE
3.0.17
3.0.18
3.0.19
- 205 -
3.06
A.
B.
Check suction line connections for tightness to avoid drawing air into pumps.
C.
Perform field-acceptance tests for each fire pump unit (fire pump, driver, and
controller) and system piping when fire pump unit installation is complete.
Comply with operating instructions and procedures of NFPA 20 to demonstrate
compliance with requirements. Where possible, field-correct malfunctioning
equipment, then retest to demonstrate compliance. Replace equipment that
cannot be satisfactorily corrected or that does not perform as specified and as
indicated, then retest to demonstrate compliance. Verify that each fire pump
unit performs as specified and as indicated.
COMMISSIONING
A.
B.
2.
3.
4.
5.
Provide fire hoses in number, size, and of length required to reach a storm
drain or other acceptable location to dispose of fire pump test water.
These fire hoses are for field acceptance tests only and are not intended to
become property of the Owner.
2.
3.
Disconnect coupling and check electric motor for proper rotation direction
marked on pump casing.
- 206 -
Prime pump by opening suction valve and closing drains, and prepare
pump for operation.
2.
3.
Start motor.
4.
5.
Observe leakage from stuffing boxes and adjust sealing liquid valve for
proper flow to ensure lubrication of packing. Do not tighten gland
immediately, but let packing run in before reducing leakage through
stuffing boxes.
6.
- 207 -
- 208 -
Steel Pipes
a) Black or mill galvanized , ASTM A 53 , ERW, Schedule 40 , with epoxy coat
and anticorrosive surface protection . Proposed materials shall be submitted for
approval.
b) The fittings shall be butt welded or socket welded. Joints shall be flanged .
Non Metallic Pipes
Use of Non metallic pipes CPVC and others shall be used for sprinkler system in
accordance with provisions of NFPA 13 D & 13 R.
Valves
General
All isolating on off valves shall be OS & Y type and Listed unless otherwise
specified. The Valve downstream of Flow Meter shall be Globe Type to for ease of
- 209 -
- 210 -
- 211 -
- 212 -