400 KV MSDS-1 , JSPL Angul

TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL &INSTRUMENTATION

MONTHLY MAINTENANCE OF TRANSFORMER


Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.

ACTIVITY

Check Colour of Silica Gel in Breather ,If crystals are Pink,Replace


with Reactivated Crystals.Check Oil Level in Oil cup,Top-up if
required

Checking of Oil Leakage ,rectify wherever found.

Oil pumps and cooling fans to be cleaned and lubricated and


trailrun of each fans and pumps .

Checking of insulation & bushing and inspection for any crack/


chipping &oil level
BDV &DGA test to be made

YES/NO

Signature of
Maintenance Engg.

400 KV MSDS-1 , JSPL Angul


Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000

MONTHLY MAINTENANCE OF TRANSFORMER

REMARKS

Signature of
Substation Incharge

400 KV MSDS-1 , JSPL Angul


TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL (O&M)

QUARTERLY MAINTENANCE OF TRANSFORMER


Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.

ACTIVITY

YES/NO

Whether permit on the transformar taken.

Whether the bay and the transformer in which maintenance is to done is


identified correctly and the primary part discharged with the help of
portable earth rod.

Whether isolation of deluge (Fire fighting) system is done.

Whether oil BDV, DGA,Oil PPM taken and recorded.

Whether Ground level earth connection on transformer & Transformer LA.


Clean Corrosion as Required

Electrical Checking of Bucholz relay, Oil Surge Relay & Pressure Relieve
Devices

Whether permit cancelled after completing the job.

Permit No.:

Observation

Date:

Signature of
Maintenance Engg.

400 KV MSDS-1 , JSPL Angul


Doc. No.:- ELE (O&M)/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000

LY MAINTENANCE OF TRANSFORMER

REMARKS
PTW No.

Signature of
Substation Incharge

400 KV MSDS-1 , JSPL Angul


TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL &INSTRUMENTATION

MAINTENANCE OF TRANSFORM
Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
1
2
3
6
12

ACTIVITY
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of portable
earth rod.
Whether isolation of deluge (Fire fighting) system is done.
Inspection of main and OLTC MB's /contactors/ switches etc. to be carried
out.for mark of overheating in the TB/power & control cable.
Take Main Tank & OLTC Tank oil samples. Carry out DGA ,BDV &Oil PPM Tests &
Record Results

14

Calbration of OTI and WTI to be carried out and Oil level in thermometre oil
pockets checking and charging.
Cooling system , buchholz relay ,oil surge relay &PRV, interlock etc. to be
checked .

15

Whether permit cancelled after completing the job.

16

Manual/ Auto starting of oil pumps & fans checked.

17

Permit No.:

13

18

Observation

Signature of
Maintenance Engg.

Date:

SDS-1 , JSPL Angul


Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000

CE OF TRANSFORMER

YES/NO

REMARKS
PTW No.

Signature of
Substation Incharge

400 KV MSDS-1 , JSPL Angul


TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL &INSTRUMENTATION

YEARLY MAINTENANCE OF TRANSFO


Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
1
2
3
4

ACTIVITY
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of portable
earth rod.
Whether isolation of deluge (Fire fighting) system is done.
The radiators clened externally.

The insulation & bushing are cleaned and inspection for any crack/ chipping
carried out.

Inspection of main and OLTC MB's /contactors/ switches etc. carried out.for
mark of overheating in the TB/power & control cable.
Inspection of OLTC operation .

Neutral Earth Pit Resistance

Cleaning of oil pumps and cooling fans and lubrication and trailrun of each
fans and pumps .

9
10

Oil level of conservator tank, HV bushing checking and topping.


Insepection of Oil leakage and gasket damages and rectified wherever found.

11

Insepection of LV bushing chamber for any oil seepages.

12

Carry out IR Measurment & PI of wdgs


Tan delta,oil BDV, DGA,Oil PPM,winding resistance,IR value test to be taken
and recorded.

13
14
15

Calbration of OTI and WTI to be carried out and Oil level in thermometre oil
pockets checking and charging.
Checking of cooling system , buchholz relay , interlock etc.

16
17
18
19

Whether permit cancelled after completing the job.


Manual/ Auto starting of oil pumps & fans checked.
Permit No.:
Observation

Signature of
Maintenance Engg.

Date:

SDS-1 , JSPL Angul


Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000

NANCE OF TRANSFORMER

YES/NO

REMARKS
PTW No.

Signature of
Substation Incharge

400 KV MSDS-1 , JSPL Angul


TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL 7INSTRUMENTATION

MAINTENANCE OF TRANSFORMERSwitchyard Name :


Equipment Name :
DATE :
MAKE :
RATING :
S. No.
1
2
3
4
5
6

ACTIVITY
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of portable
earth rod.
Whether isolation of deluge (Fire fighting) system is done.
Inspect Selector & Diverter Switch and Maintain in accordance with
Manafacturer's specification
Measurment of Winding resistance at all tap position
Measurment of winding Turns Ratio

Whether permit cancelled after completing the job.

Permit No.:

Observation

Signature of
Maintenance Engg.

Date:

SDS-1 , JSPL Angul


Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000

OF TRANSFORMER-5 YEAR

YES/NO

REMARKS
PTW No.

Signature of
Substation Incharge