Anda di halaman 1dari 2

Federal Register / Vol. 72, No.

121 / Monday, June 25, 2007 / Notices 34677

any resource agency, Indian Tribe, or of: (1) Intake works consisting of a 50- www.ferc.gov using the ‘‘eLibrary’’ link.
person believes that an additional foot-long, 15-foot-high headgate and Enter the docket number excluding the
scientific study should be conducted in intake structure; (2) primary and last three digits in the docket number
order to form an adequate factual basis secondary steel trash racks; (3) a 200- field to access the document. For
for a complete analysis of the foot-long, 40-foot-wide, concrete-lined, assistance, contact FERC Online
application on its merit, the resource open flume head race; (4) a 435-foot- Support at
agency, Indian Tribe, or person must file long, 30-foot-wide brick and masonry FERCOnlineSupport@ferc.gov or toll-
a request for a study with the powerhouse; (5) two vertical shaft free at (866) 208–3676, or for TTY, (202)
Commission not later than 60 days from turbine/generator units with an installed 502–8659. A copy is also available for
the date of filing of the application, and capacity of 2.25 megawatts; (6) a 435- inspection and reproduction at the
serve a copy of the request on the foot-long, 30-foot-wide, concrete-lined, address in item (h) above.
applicant. open tailrace section which returns
m. Deadline for filing additional study p. You may also register online at
flows to the Augusta Canal, and (7) http://www.ferc.gov/esubscribenow.htm
requests and requests for cooperating appurtenant facilities. There is no dam
agency status: July 30, 2007. to be notified via email of new filings
or impoundment, as approximately 881
All documents (original and eight and issuances related to this or other
cfs of water is withdrawn from the
copies) should be filed with: Kimberly pending projects. For assistance, contact
Augusta Canal when operating at full
D. Bose, Secretary, Federal Energy FERC Online Support.
capacity. Developed head is
Regulatory Commission, 888 First approximately 32 feet. The estimated q. With this notice, we are initiating
Street, NE., Washington, DC 20426. generation is 14,366 MWh annually. consultation with the Georgia State
Additional study requests and Historic Preservation Officer (SHPO), as
Nearly all generated power is utilized by
requests for cooperating agency status required by § 106, National Historic
the Standard Textile Plant, located
may be filed electronically via the Preservation Act, and the regulations of
within the King Mill building, for textile
Internet in lieu of paper. The
production. No new facilities or changes the Advisory Council on Historic
Commission strongly encourages
in project operation are proposed. Preservation, 36, CFR, at § 800.4.
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions o. Locations of the Application: A r. Procedural Schedule: The
on the Commission’s Web site (http:// copy of the application is available for application will be processed according
www.ferc.gov) under the ‘‘e-Filing’’ link. review at the Commission in the Public to the following Hydro Licensing
n. Project Description: The existing Reference Room or may be viewed on Schedule. Revisions to the schedule
King Mill Hydroelectric Project consists the Commission’s Web site at http:// may be made as appropriate.

Milestone Target date

Issue Scoping Document 1 for comments .............................................................................................................................. September 2007.


Request Additional Information (if necessary) ........................................................................................................................ November 2007.
Notice of Acceptance/Notice of Ready for Environmental Analysis ....................................................................................... February 2008.
Filing of interventions, recommendations, preliminary terms and conditions, and fishway prescriptions .............................. April 2008.
Reply comments due ............................................................................................................................................................... May 2008.
FERC issues single EA (without a draft) ................................................................................................................................. September 2008.
Comments on EA due ............................................................................................................................................................. November 2008.

s. Final amendments to the a. Filing Type: Whitewater Access (2835–026) on any comments or
application must be filed with the Plan. motions filed.
Commission no later than 30 days from b. Project No: 2835–026. k. Description of Proposal: NYSEG
the issuance date of the notice of ready c. Date Filed: May 23, 2007. filed a Whitewater Access Plan (plan)
for environmental analysis. d. Applicant: New York State Electric pursuant to article 414 of the project
and Gas Corporation (NYSEG). license. The plan addresses impacts of
Kimberly D. Bose, e. Name of Project: Rainbow Falls
Secretary. whitewater access and public usage on
Hydroelectric Project.
the upper Chasm boating on other
[FR Doc. E7–12188 Filed 6–22–07; 8:45 am] f. Location: On the Ausable River, in
recreational users of Ausable Chasm and
BILLING CODE 6717–01–P Clinton County, New York.
g. Filed Pursuant to: Federal Power Ausable River downstream. It includes
Act, 16 U.S.C. 791(a)–825(r). an estimate of potential demand for
DEPARTMENT OF ENERGY h. Applicant Contact: Mr. Hugh Ives, whitewater boating, costs estimates for
89 East Avenue, Rochester, NY 14649. providing and maintaining access to the
Federal Energy Regulatory Phone: (585) 724–8209. upper Chasm, and a proposal to
Commission i. FERC Contact: Any questions on possibly limit, continue, or discontinue
this notice should be addressed to Gina whitewater access at the project. The
[Project No. 2835–026] plan recommends that whitewater
Krump at (202) 502–6704 or
gina.krump@ferc.gov. access be discontinued at the site due to
New York State Electric and Gas
j. Deadline for filing comments and low usage, and safety and security
Corporation; Notice of Compliance
/or motions: July 6, 2007. concerns.
Filing and Soliciting Comments,
All documents (original and eight l. Locations of the Application: This
sroberts on PROD1PC70 with NOTICES

Motions To Intervene, and Protests


copies) should be filed with: Kimberly filing is available for review and
June 15, 2007. D. Bose, Secretary, Federal Energy reproduction at the Commission’s
Take notice that the following report Regulatory Commission, 888 First Public Reference Room, located at 888
has been filed with the Commission and Street, NE., Washington, DC 20426. First Street, NE., Room 2A, Washington,
is available for public inspection: Please include the project number DC 20426, or by calling (202) 502–8371.

VerDate Aug<31>2005 23:08 Jun 22, 2007 Jkt 211001 PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 E:\FR\FM\25JNN1.SGM 25JNN1
34678 Federal Register / Vol. 72, No. 121 / Monday, June 25, 2007 / Notices

This filing may also be viewed on the DEPARTMENT OF ENERGY recovery of penalties for Reliability
Commission’s Web site at http:// Standard violations assessed against
www.ferc.gov using the ‘‘FERRIS’’ link. Federal Energy Regulatory Independent System Operators and
Enter the docket number excluding the Commission Regional Transmission Organizations, as
last three digits in the docket number [Docket No. RP07–310–000] set forth in Midwest Independent
field to access the document. For Transmission System Operator, Inc., 119
assistance, please contact FERC Online Mojave Pipeline Company; Notice of FERC ¶ 61,222 (May 31, 2007) in Docket
Support at Informal Settlement Conference Nos. ER07–701–000 and AD07–12–000.
FERCOnlineSupport@ferc.gov or call This notice is to alert you to the date
June 18, 2007. of the conference. Further notices will
toll-free 1–866–208–3676, or for TTY,
contact (202) 502–8659. A copy is also Take notice that an informal define the issues to be explored in
available for inspection and settlement conference will be convened greater detail. The conference will be
reproduction at the address in item (h) in this proceeding commencing at 10 transcribed and Web cast. All interested
above. a.m. on June 27, 2007, at the offices of parties are invited, and there is no
the Federal Energy Regulatory registration fee to attend.
m. Comments, Protests, or Motions to Commission, 888 First Street, NE., Questions about the conference
Intervene: Anyone may submit Washington, DC 20426, for the purpose should be directed to Don Lekang by e-
comments, a protest, or a motion to of exploring the possible settlement of mail at donald.lekang@ferc.gov or by
intervene in accordance with the the above-referenced dockets. phone at 202–502–8127.
requirements of Rules of Practice and Any party, as defined by 18 CFR
Procedure, 18 CFR 385.210, .211, .214. 385.102(c), or any participant as defined Kimberly D. Bose,
In determining the appropriate action to by 18 CFR 385.102(b), is invited to Secretary.
take, the Commission will consider all attend. Persons wishing to become a [FR Doc. E7–12183 Filed 6–22–07; 8:45 am]
protests or other comments filed, but party must move to intervene and BILLING CODE 6717–01–P
only those who file a motion to receive intervenor status pursuant to the
intervene in accordance with the Commission’s regulations (18 CFR
Commission’s Rules may become a 385.214). DEPARTMENT OF ENERGY
party to the proceeding. Any comments, FERC conferences are accessible
protests, or motions to intervene must under section 508 of the Rehabilitation Federal Energy Regulatory
be received on or before the specified Act of 1973. For accessibility Commission
comment date for the particular accommodations please send an e-mail [Docket No. RM93–11–000]
application. to accessibility@ferc.gov or call toll free
1–866–208–3372 (voice) or 202–208– Revisions to Oil Pipeline Regulations
n. Filing and Service of Responsive
1659 (TTY), or send a FAX to 202–208– Pursuant to the Energy Policy Act of
Documents: Any filings must bear in all
2106 with the required 1992; Notice of Annual Change in the
capital letters the title ‘‘COMMENTS’’, Producer Price Index for Finished
‘‘RECOMMENDATIONS FOR TERMS accommodations.
For additional information, please Goods
AND CONDITIONS’’, ‘‘PROTEST’’, OR
contact Hollis Alpert at
‘‘MOTION TO INTERVENE’’, as May 16, 2007.
hollis.alpert@ferc.gov (202) 502–8783.
applicable, and the Project Number of The Commission’s regulations include
the particular application to which the Kimberly D. Bose, a methodology for oil pipelines to
filing refers. A copy of any motion to Secretary. change their rates through use of an
intervene must also be served upon each [FR Doc. E7–12179 Filed 6–22–07; 8:45 am] index system that establishes ceiling
representative of the Applicant BILLING CODE 6717–01–P levels for such rates. The Commission
specified in the particular application. bases the index system, found at 18 CFR
o. Agency Comments: Federal, State, 342.3, on the annual change in the
and local agencies are invited to file DEPARTMENT OF ENERGY Producer Price Index for Finished
comments on the described application. Goods (PPI–FG), plus one point three
A copy of the application may be Federal Energy Regulatory percent (PPI+1.3). The Commission
Commission determined in an ‘‘Order Establishing
obtained by agencies directly from the
Applicant. If an agency does not file [Docket No. AD07–12–000] Index For Oil Price Change Ceiling
comments within the time specified for Levels’’ issued March 21, 2006, that
filing comments, it will be presumed to Reliability Standard Compliance and PPI+1.3 is the appropriate oil pricing
have no comments. One copy of an Enforcement in Regions With index factor for pipelines to use.1
agency’s comments must also be sent to Independent System Operators and The regulations provide that the
the Applicant’s representatives. Regional Transmission Organizations; Commission will publish annually, an
Notice of Technical Conference index figure reflecting the final change
p. Comments, protests, and in the PPI–FG, after the Bureau of Labor
interventions may be filed electronically June 15, 2007. Statistics publishes the final PPI–FG in
via the internet in lieu of paper. See, 18 The staff of the Federal Energy May of each calendar year. The annual
CFR 385.2001(a)(1)(iii) and the Regulatory Commission will hold a average PPI–FG index figures were
instructions on the Commission’s Web technical conference in the above- 155.7 for 2005 and 160.4 for 2006.2
site at http://www.ferc.gov under the ‘‘e- referenced proceeding on September 18,
Filing’’ link. 2007, at the Federal Energy Regulatory
sroberts on PROD1PC70 with NOTICES

1 114 FERC ¶ 61,293 at P 2 (2006).


Commission, 888 First Street, NE., 2 Bureau of Labor Statistics (BLS) publishes the
Kimberly D. Bose, final figure in mid-May of each year. This figure is
Washington DC. It will be held in the
Secretary. publicly available from the Division of Industrial
Commission Meeting Room (Room 2C) Prices and Price Indexes of the BLS, at (202) 691–
[FR Doc. E7–12189 Filed 6–22–07; 8:45 am] starting at 9:30 a.m. ET. The conference 7705, and in print in August in Table 1 of the
BILLING CODE 6717–01–P will explore issues associated with cost annual data supplement to the BLS publication

VerDate Aug<31>2005 23:08 Jun 22, 2007 Jkt 211001 PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 E:\FR\FM\25JNN1.SGM 25JNN1

Anda mungkin juga menyukai