STV Construction, Inc.

DAILY CONSTRUCTION REPORT

Atlantic Yards

Date

5/19/2014

Location

B2

Weekday

Monday

Client

ESD

Report #

Contract #

6717

Weather

Project

Project #
STV Representative:
Work hours

2114659

319
Sunny, Clear

Temp. L/H
49-70
Wind Speed 5 mph gusting to 20 mph+

Phil Amicone

0"

Precip

7:30-4:30

117
930

113
0.126

1.0

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that
6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host
of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be
finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th
floor mods have begun production.
Tower Crane - Inactive for 26th weekday in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 113 work
days = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected
installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.
Other Additional New Observations: Spraying on fireproofing (SOFP) continued behind curtains on west side of ground floor. No particulate
escape observed.

New Information received:

New Information requested:


Information previously requested: 5/1/14 2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 y.

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods.
Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week
of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.

Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

1 of 2

STV Construction, Inc.


Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-20

Navillus

Stearns

J SuporTrucking

MEP trades

5-10

Other

5-10

Equip. Arr./ Departure-Observed

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

Manpower figure is rough approximation by STV.

Materials Delivered other than Mods (Observed)

Philip Amicone

5/19/2014

Prepared by Philip Amicone

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT

Atlantic Yards

Date

5/20/2014

Location

B2

Weekday

Tuesday

Client

ESD

Report #

Contract #

6717

Weather

Project

Project #
STV Representative:
Work hours

2114659

320
Sunny, Clear

Temp. L/H
55-78
Wind Speed 5 mph gusting to 15 mph+

Phil Amicone

0"

Precip

7:30-4:30

117
930

114
0.126

1.0

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that
6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host
of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be
finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th
floor mods have begun production.
Tower Crane - Inactive for 27th weekday in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 114 work
days = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected
installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.
Other Additional New Observations: Spraying on fireproofing (SOFP) continued behind curtains on west side of ground floor. No particulate
escape observed. Removal of water damaged sheetrock in units continues.

New Information received:

New Information requested:


Information previously requested: 5/1/14 .
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods.
Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week
of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.

Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

1 of 2

STV Construction, Inc.


Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-20

Navillus

Stearns

J SuporTrucking

MEP trades

5-10

Other

5-10

Equip. Arr./ Departure-Observed

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

Manpower figure is rough approximation by STV.

Materials Delivered other than Mods (Observed)

Philip Amicone

5/20/2014

Prepared by Philip Amicone

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT
Project

Atlantic Yards

Date

5/21/2014
Wednesday

Location

B2

Weekday

Client

ESD

Report #

321

Contract #

6717

Weather

Cloudy

Project #
STV Representative:
Work hours

2114659

Temp. L/H
64-74
Wind Speed 3 mph gusting to 7 mph+

Phil Amicone

1/4"

Precip

7:30-4:30

117
930

115
0.126

1.0

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that
6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host
of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be
finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th
floor mods have begun production.
Tower Crane - Inactive for 28th weekday in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 115 work
days = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected
installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.
Other Additional New Observations: Spraying on fireproofing (SOFP) continued behind curtains on west side of ground floor. No particulate
escape observed. Removal of water damaged sheetrock in units on 2nd floor continues.

New Information received:

New Information requested:


Information previously requested: 5/1/14 2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods.
Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week
of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.

Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

1 of 2

STV Construction, Inc.


Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-20

Navillus

Stearns

J SuporTrucking

MEP trades

5-10

Other

5-10

Equip. Arr./ Departure-Observed

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

Manpower figure is rough approximation by STV.

Materials Delivered other than Mods (Observed)

Philip Amicone

5/21/2014

Prepared by Philip Amicone

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT
Project

Atlantic Yards

Date

5/22/2014
Thursday

Location

B2

Weekday

Client

ESD

Report #

Contract #

6717

Weather

Project #
STV Representative:
Work hours

2114659

322
Overcast with occasional showers

Temp. L/H
59-66
Wind Speed 5 mph gusting to 7 mph+

Phil Amicone

Trace

Precip

7:30-4:30

117
930

116
0.126

1.0

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that
6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host
of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be
finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th
floor mods have begun production.
Tower Crane - Inactive for 29th weekday in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 116 work
days = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected
installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.
Other - No Con Ed. No Navillus (reportedly ran out of material). No sprinkler subcontractor.
Additional New Observations: Spray-n fireproofing (SOFP) continued behind curtains on west side of ground floor until noon. No
particulate escape observed. Primary machine broke down at approximately noon. Backup machine did not function adequately. Operator
said the backup machine was not breaking the dry SOFP small enough and there was not enough pressure to properly spray the material on
the underside of the decking or the structural steel. Machine repair expected tomorrow. Removal of water damaged sheetrock in units on
2nd floor continues.

New Information received:

New Information requested:


Information previously requested: 5/1/14 .
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods.
Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week
of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.

1 of 2

STV Construction, Inc.


Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

Special instruction(s) given:


Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-20

Navillus

Stearns

J SuporTrucking

MEP trades

5-10

Other

5-10

Equip. Arr./ Departure-Observed

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

Manpower figure is rough approximation by STV.

Materials Delivered other than Mods (Observed)

Philip Amicone

5/22/2014

Prepared by Philip Amicone

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT

Atlantic Yards

Date

5/23/2014

Location

B2

Weekday

Friday

Client

ESD

Report #

Contract #

6717

Weather

Project

Project #
STV Representative:
Work hours

2114659

323
Overcast with occasional showers

Temp. L/H
56-71
Wind Speed 2 mph gusting to 6 mph+

Phil Amicone

1"

Precip

7:30-4:30

117
930

117
0.126

1.0

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that
6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host
of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be
finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th
floor mods have begun production.
Tower Crane - Inactive for 30th weekday in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 117 work
days = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected
installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.
Other -

Additional New Observations: Spray-on fireproofing (SOFP) stopped for the week at approximately noon on Thursday. No spraying
operation today. Resetting the containment tarps for spraying to continue moving east. Spraying expected to start again on Tuesday.
Removal of water damaged sheetrock in units on 2nd floor continues.

New Information received:

New Information requested:


Information previously requested: 5/1/14 .
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods.
Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week
of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.

Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
1 of 2

STV Construction, Inc.


Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-20

Navillus

Stearns

J SuporTrucking

MEP trades

5-10

Other

5-10

Equip. Arr./ Departure-Observed

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

Manpower figure is rough approximation by STV.

Materials Delivered other than Mods (Observed)

Philip Amicone

5/23/2014

Prepared by Philip Amicone

2 of 2