DISTRIBUTION SUBSTATIONS
E. Brand; U. Minnaar and W. Fritz
School of Electrical Engineering, Cape Peninsula University of Technology
The scope of the thesis is focused on the Distribution Often circuit breakers need to be serviced more
substations with primary operating voltage equal to or frequently for deteriorated performance of overhead
less than 132kV and secondary voltage no less than line (frequent faults) or cable (higher fault levels)
11kV, with an installed capacity greater than 1MVA. systems. Reduced dielectric strength occurs during
At this time, only power plant is considered as part of arcing, finger contact wear as a result of the number of
the study. operations due to higher fault current and stress placed
on the mechanism occurs.
Currently, a proposal is being prepared to measure the
reliability of large power transformers [1]. Similarly, all other power plant and even secondary
plant have an expected life span.
2. RELIABILITY
1
3. SELECTION CRITERIA FOR Circuit Ratio Transformer Ratio
EQUIPMENT FORMING PART OF Breaker
Installed 1741 5 365 1
THE SUBSTATION PHI Base
CAPEX R300k 1 R2m 7
A substation contains a number of installed
equipment. The following criteria was used to Restoration Hours 1 Hours 1
determine which equipment would be used in the PHI Times Min
model i.e. capital expenditure (capex) during the Restoration 28 1 96 weeks 11
investment planning stage, supply restoration times Times Max weeks
for each equipment and failure rates.
The above information is averaged values based on
the failure investigations performed in Eskom
3.1. CAPEX FOR EQUIPMENT Distribution’s Western region.
4
Routine Test Results
Sub PHI
Score Score Score
In Spec + + = Score
40 50 10 100
No Further Action
Required
Out of Spec
Unacceptable
Investigation 37
Alarm
PHI Improvement Decision 100
In Spec
Maintain Replace/Reinvestment
228
Saturated
Figure 5. Hazard function describes the
Failure Health Gauge probability of failure in time (sawtooth
Prediction
behaviour)
Figure 4. Flow diagram for the substation Finally, a stage will be reached where the equipment
plant health index can no longer be maintained cost-effectively, and
thus a decision for replacement is undertaken. It is
Figure illustrates that the routine test results are the believed that the next step for this model will be the
inputs for the equipment plant health measures. The failure prediction stage. Prediction is influenced by
work instruction is a detailed step-by-step design quality, network operating conditions, climatic
specification for intrusive maintenance, containing the conditions and maintenance quality.
threshold limits required for each routine test during
in-service conditions. 5. PROPOSED ALTERNATIVES
Where tests are within specification, no further action
is required. However, where routine results are out of Three alternatives were considered during the
spec, an investigation is necessary. This investigation development of the substation plant health index.
may be simple, where the field operator has noted that
re-building of the mechanism is required, or moving 5.1 MODEL A (Summated PHI)
contacts may need to be replaced at the next
intervention. A corrective action is required. In Model A, a simple approach was taken by
summating the different values of the equipment
There are rare cases where equipment can be routine test results. However, where multiples of
energised if one of the routine tests has exceeded the equipment exist i.e. >1 transformer or multiple feeder
limits. This decision requires careful consideration circuit breakers, the substation PHI just runs away.
and is often the decision taken by the specialist in This provides difficulty in having a credible range
consultation with relevant staff. The customer supply per in-specification (good), alarm and unacceptable
is restored but, a follow-up action is planned (urgent) rating.
immediately. Often, abnormal spare or replacement
parts may be needed, and the repair time for the Advantages:
defect, may be longer. • Simple mathematical approach where tests results
score are easily summated.
A plant health index will be reviewed each time, a Disadvantages:
failure or intrusive maintenance occurs. This is • A good rating for TDCG PHI Score tends to 0.
because periodic or planned maintenance Thus it counters the summation of the other tests.
restores/preserves the intended function of the The substation PHI is not reflective of the “bad”
equipment as seen in the saw-tooth behaviour TDCG score.
illustrated by the hazard function [3]. • There is no representation of individual
equipment PHI.
• The end score is a challenging number to
manage.
5
5.2. MODEL B (9-point PHI) Action would be: Action maintenance issues and
consider revised maintenance strategy to maintain
In order to overcome the challenge working with a current service levels. Unforeseen opex expenditure is
summated score system, a converted score model encountered here. Re-prioritise the completion date of
was developed. refurbishment project. A comprehensive Risk Model
is to be conducted. Contingency plan should be ready
to be activated.
The routine test results are converted to a score
between 1 and 3 where 1 = a good score, 2 = an alarm
score and 3 = an urgent score. The blue phase of the 5.3. MODEL C (17-point PHI)
F1 circuit breaker has a contact resistance value of
842. The test limits for contact resistance are [9]: We now have a total of 17 individual tests that are
being monitored.
Range Score Status Based on the same principles as in Model B above
<100 1 Good except, that each test (per phase for the circuit breaker)
Between 101 and 280u- 2 Alarm is counted as part of the final substation PHI score.
ohm
>281 3 Urgent Advantages:
Therefore, a rating out of 3 for each of the 9 tests is • Simple scoring model to manage although
developed. In this model, an average score is used for Alternative B is easier
the instances where multiples of equipment exists. In
the model itself, the user will still see the result for Disadvantages:
each piece of equipment, such that a specific problem • The circuit breaker is overrepresented in the
is still dealt with. substation PHI rating. It counts 40% to the
substation PHI, but consists of 12 tests.
Advantages:
• Each piece of equipment will have an individual 5.4. REPORTING REQUIREMENTS
PHI rating.
• Simple scoring model to manage The substation model is easily implemented using
Disadvantages: Microsoft Excel. The conditional formatting function
• None allows you to program visual indications of the
severity of the equipment routine test result. In this
Severity Ratings for the 9-point Substation PHI: instance, the following applies for the model:
• RED = 3
A Sub Score of 0-2 points mean that there are a • YELLOW = 2
maximum of 2 test results that are of concern. We will • GREEN = 1
call this score a Good Rating. This is because we can Furthermore, Figure 9 below illustrates the substation
always expect WC and kV for an OLTC to deteriorate PHI scores for a number of substations. Here, the
with time. We have at least 2 routine tests defined per substation PHI is scored as follows:
Equipment. • RED = >5
Action would be: Investigate track record and the • YELLOW 3-5
work order feedback reported, and action accordingly. • GREEN <=2
Continue monitoring all other Equipment, as per
normal. Substation PHI Score PHI Score
(Current (Following Year)
A Sub Score of 3-5 points mean that there are 5 test Year)
results that are Problematic. We will call this an A 6 4.5
Alarm Rating. This is because we can always expect B 6 4.5
WC and kV for an OLTC to deteriorate with time, as C 4 4
in 1.1 above. The Sub PHI Score of 5, indicates D 2 3
problems with at least 2 pieces of equipment out of Scenario
the 3. In the following year, the rating of 6 comes done to
Action would be: Immediately action the 4.5. This indicates that an intervention improved
reliability levels.
abnormalities, conduct probability of failure analysis
I believe that having status such as:
and evaluate the contingency plan. • Investigation completed Yes or No
• Maintained Yes or No
A Sub Score of >6 points mean that there are • Replacement required
abnormalities encountered with all 3 pieces of for all RED zone scores will improve the monitoring of
equipment in the Substation. the equipment or substation PHI.
This score would be an Urgent Rating.
6
Figure 10. Dashboard management the substation equipment is formulated once spares
principles used for Substation PHI model become a problem or call-outs become too frequent.
The above scenario confirms the sawtooth behaviour Transformer Condition Results:
of reliability that was described earlier. Substation A: Good, 28 years old
Substation B: Good, 18 years old
Substation C: Good, 30 years old
6. RESULTS WITH MODEL B Substation D: Good, 23 years old
The routine test results of four distribution substation Average Transformer age = 24.75 years old.
were sourced, and used for the simulation. The
substation PHI results are shown below in Figure 10. Plant Health Index Results:
Substation A:
Substation CB PHI Trfr PHI OLTC Sub PHI The medium voltage (MV) circuit breakers are
PHI showing early signs of wear. Closing and tripping
A 5.313 1.6 1.8 3.1052 times are of particular concern for 100% of the
B 4.725 1.6 1.8 2.87 installed base.
C 4 2 1.8 2.78 Substation B:
D 3.857 2 1.8 2.72 The MV circuit breakers are of a concern. Closing and
tripping times are of particular concern as well as the
Figure 10. Simulated results for the contact resistance of 75% of the installed base.
Substation C:
information of 4 substations, using the
Feeder 1&2 of the MV circuit breakers are showing
alternative B model. early signs of normal wear and tear. Investigate the
abnormal contact resistance values. Feeders 2 and 3
Transformer reliability ranges between fair and good have unacceptable readings for tripping times and
for the substations evaluated. In all 4 cases, we find needs to be investigated.
circuit breaker health to be of concern. A detailed Substation D:
investigation is required as the next step in order to Circuit breakers are showing early signs of wear.
determine normal ageing, or areas of risk for the Closing and tripping times are of particular concern.
circuit breakers.
In sample B, one of the CB routine test results was not A PHI for circuit breakers and tap changers is now
available. If one assumed the same performance for available in the proposed model.
this breaker as the others, the substation PHI score
increases by 30%, but the substation PHI still remains This is useful, when considering that in each case, the
in the Alarm zone. circuit breakers are failing whilst, the condition of the
For sample C, the Transformer PHI is skewed. The large power transformers varies from good to very
water content value must be evaluated in conjunction good.
with the temperature at the time of sampling i.e. we
expect the water content to be “higher” for lower
operating temperatures, typically observed with the
8. CONCLUSION
lighter loaded transformers. For sample C, a capex
The following conclusions are made:
project has already been approved for replacement of
a. Eskom Distribution now has a dashboard
the circuit breaker. The target completion date can
indication of the plant health for its circuit
now be influenced based on the PHI evaluation.
breakers and tap changers installed at its Dx
In the last sample, D, the same findings were made for
substations.
the WC as in the previous case for the transformers.
b. A policy to replace transformers at 30 years is not
One of the installed seven circuit breakers, needs
justified. However, circuit breakers are failing
attention however, whilst the rest are in the alarm
just at the 25 year investment period.
stage, indicating on-set of the wear-out stage. The
c. Reliability trending is limited, with only 1 set of
circuit breakers are 25 years old.
test results available.
d. Network contingency planning and equipment
7. EVALUATION OF MODEL A spares policies are enhanced due to early
indications of deteriorated equipment behaviour.
Till now, the substation health was represented by the e. The substation PHI requires review, as equipment
condition of the transformer routine test results. The condition will be affected by failures or operating
oil sampling of transformers and tap changers has been conditions.
outsourced for approximately 7 years and is well f. Unexpected opex expenditures are reduced and
managed [1]. However, an action plan for the rest of planning of CAPEX is improved.
7
9. ACKNOWLEDGEMENTS
The author would like to acknowledge the
contributions from Ulrich Minnaar, Lester Geldenhuis
and Siraj Williams.
10. REFERENCES
W. Fritz
School of Electrical Engineering
Cape Peninsula University of Technology
P.O. Box 1906
U. Minnaar
Eskom
P.O. Box 222
Brackenfell 7561