Anda di halaman 1dari 8

DEVELOPMENT OF A PLANT HEALTH INDEX FOR ESKOM

DISTRIBUTION SUBSTATIONS
E. Brand; U. Minnaar and W. Fritz
School of Electrical Engineering, Cape Peninsula University of Technology

ABSTRACT Figure 1 illustrates that if we know the condition, we


can extract more out of the equipment, and are
Substation refurbishment planning was traditionally positioned to time the replacement at a point in the
initiated by deteriorated network performance indices life cycle just before intolerable risk.
and the physical observed state of the network.
However, it can also be too late, resulting in
deteriorated customer service and unnecessary Reliability Approach
company risk.
A Plant Health Index is developed, to understand and
assess the condition of equipment and to be used as an 120
input for failure prediction. 100
% R eliability
The rise in demand of electricity supply will now
place an increasing burden on already declining or 80 Replacement
aging utility resources as well as limited service with Age
60
providers. High load factors and wear on aging plant Reliability
has made it necessary to maintain generating plants 40 Prediction
more frequently. This places pressure on remaining 20
capacity. During this time, if unforeseen events and
anticipated utilisation increases, load shedding is 0
required to stabilise the national electricity grid.
5
15
25
35
45
[Eskom Annual Report 2007, pg 47].
Age
Increased failure of aging systems is likely, as
equipment which has traditionally been “idling”, and
is suddenly expected to operate close to 100%
capacity. This is typically understood as the hazard Figure 1. Equipment reliability
function.
Beyond the intended investment period of 25 years, a
1. INTRODUCTION revised maintenance strategy or intervention can be
applied to preserve the equipment performance. In the
A Plant Health Index (PHI) is very much like a case of transformers, more frequent samples of
cholesterol or GP visit. It serves as an indication that insulating oil in order to investigate sources of sudden
impending failure or ill-health condition exists, so that deteriorated health, and moisture extraction are
the desired preventive measure can be taken. Thus, justified in order to establish possible causes of
the question remains what are the indicators of the thermal faults. Typical “life extension” interventions
equipment condition or assets that will indicate how for transformers include filtering or regeneration of
well the equipment is performing. the main tank oil, re-winding or bushing replacement.

The scope of the thesis is focused on the Distribution Often circuit breakers need to be serviced more
substations with primary operating voltage equal to or frequently for deteriorated performance of overhead
less than 132kV and secondary voltage no less than line (frequent faults) or cable (higher fault levels)
11kV, with an installed capacity greater than 1MVA. systems. Reduced dielectric strength occurs during
At this time, only power plant is considered as part of arcing, finger contact wear as a result of the number of
the study. operations due to higher fault current and stress placed
on the mechanism occurs.
Currently, a proposal is being prepared to measure the
reliability of large power transformers [1]. Similarly, all other power plant and even secondary
plant have an expected life span.
2. RELIABILITY

1
3. SELECTION CRITERIA FOR Circuit Ratio Transformer Ratio
EQUIPMENT FORMING PART OF Breaker
Installed 1741 5 365 1
THE SUBSTATION PHI Base
CAPEX R300k 1 R2m 7
A substation contains a number of installed
equipment. The following criteria was used to Restoration Hours 1 Hours 1
determine which equipment would be used in the PHI Times Min
model i.e. capital expenditure (capex) during the Restoration 28 1 96 weeks 11
investment planning stage, supply restoration times Times Max weeks
for each equipment and failure rates.
The above information is averaged values based on
the failure investigations performed in Eskom
3.1. CAPEX FOR EQUIPMENT Distribution’s Western region.

TABLE 1. THE PERCENTAGE CAPEX During equipment failures, a typical contingency


REQUIRED PER EQUIPMENT FOR A NEW HV plan would be to consider either network
SUBSTATION (PROTECTION COSTS configuration switching, using a network spare, a
INCLUDED) strategic spare or even mobile substation equipment
to provide an interim supply.
Equipment Number of Approximate % of
installations Cost overall 3.3 EQUIPMENT FAILURE RATES
Cost
LP 1 R4m 57% The equipment failure rate indicates how many
Transformer instances of equipment are failing. An annual rate is
Circuit 5 R1.25m 18% usually adopted, as can be seen in the literature review
breakers [2]. The network performance indices have been the
Current 15 R0.27m 3.8% major source of reliability measurement for Eskom
Transformer Distribution and its main focus is managing the
Voltage 2 R0.18m 2.6% impact of supply interruption, planned or unplanned,
Transformer to the customer. Utilities, world-wide, also make use
Isolators 1 R0.05m .7% of this measure as an indication of reliability [3].
Busbar 1 R1m 14.3%
Surge 18 R0.24m 3.4% By managing the equipment failure rate one has the
arrestors opportunity to influence future designs, improve
Substation 1 R2m maintenance practices and cater for environmental
facilities influences.
Total R8.99m
Transformers
A study of the capital expenditure over the last 5 years
was undertaken for the figures represented. The table
illustrates that for substation equipment that has Number of Failures per MVA per Year
moving parts typically, transformers represented 57%
and circuit breakers represented 18% of the total 60
investment costs. 50
40 < 10MVA
Number

3.2. FAULT RESTORATION TIMES >80MVA


30
40-60MVA
PER EQUIPMENT 20 11 to 40MVA
10
Supply restoration times for transformers vary from a
0
few hours to a few months depending on the fault, and
2002 2003 2004 2005 2006
similarly for circuit breakers, repair times are in the
region of a few minutes to a few weeks. Year

TABLE 2. THE PERCENTAGE CAPEX Figure 2. Number of Transformer


REQUIRED PER EQUIPMENT FOR A NEW HV Failures per MVA rating per year
SUBSTATION (PROTECTION COSTS
INCLUDED) An average failure rate of 0.55% is calculated based
on the assumption of 1% growth per annum for
transformers [4]. Conducting a sensitivity analysis
2
and assuming a 2% growth per annum, raises the • CAPEX is most significant for these equipment
average failure rate to 0.56%. • Movable parts are prone to wear, and circuit
breaker duty will vary from the network supplied,
Therefore, the transformer reliability for Eskom as well as fault current levels.
Distribution compares favourably with the figures • Restoration times for the two pieces of equipment
produced in the EPRI report 1001707 [2]. are lengthy if no other planned contingency has
been established.
Circuit Breakers • The tap changer has movable parts by definition,
and thus also requires periodic maintenance.
Failure Rate: Furthermore, as the tap changer has been sited as
the second highest component failure next to
Number of failures/Installed Base/Period windings in a report of 2007 [6]. Jagers [5] finds
that tap changer failures represent 22% of the
57/1048/14 = 0.00388 or 0.388% [5] failed components.
• It enhances the Transformer model proposed by
Observations: Geldenhuis [1] by including the tap changer..
• During an investigation of the circuit breaker • Circuit breakers, according to Hamm [7], have a
performance, it was found that the circuit much lower failure rate than transformers.
breakers are not suited for the intended However, the failure is often catastrophic with oil
application i.e. auto-reclose. The mechanism was circuit breakers, given that the oil properties change
originally suited for a cable-fed network as and become flammable during arcing or thermal
opposed to conductor-fed overhead line networks. runaway. Damage to neighbouring equipment occurs
This investigation provides valuable information and even 3rd party damage. By virtue, of its function,
toward scoping a future asset replacement circuit breakers are under constant strain, and thus are
strategy for these circuit breakers. more likely to wear-out if under maintained.
• The next step would be to establish failure rate
benchmarks for Eskom distribution substation
4.1. EQUIPMENT MAINTENANCE
equipment.
STRATEGIES
This failure rate for circuit breakers is higher than the
lower limit published by EPRI report 1001707 [2]. It must be understood how the Plant Health Index is
formulated. Asset management principles have
4. DEVELOPMENT OF THE developed over years with many studies focused on
the different maintenance strategies:
SUBSTATION PLANT HEALTH 1. Replace it when it fails
INDEX MODEL 2. Time based maintenance
3. Condition-based maintenance
Based on the information analysed, the transformers, 4. Reliability Centred maintenance
tap changers and circuit breakers will be selected as
part of the Substation Plant Health Index. For the last 3 strategies, a study of the equipment is
conducted upfront. This study is known as Failure
Circuit Modes and Effects Analysis (FMEA). Such an
Breaker initiative entails identifying each component in the
PHI equipment and describing the function, as well as
Transformer
understanding the impact of its failure with respect to
PHI
+ the overall equipment function. Typical maintenance
Tap Changer tasks include routine inspections or visual inspections;
PHI minor services, routine testing of major servicing or a
+
Substation combination of them. This process involves a
PHI coordinated approach between:
= • Designers
• Manufacturers
• Subject-matter experts
Figure 3. Plant Health Index Model for • Maintenance crews.
Distribution Substations
TABLE 3. THE MAINTENANCE STRATEGIES
FOR THE PIECES OF EQUIPMENT
This plant health indicator will suffice as a short term
measure to the intended audience. The following are
reasons: Large Power Circuit Breakers
Transformers
3
1 Inspection, each Inspection, each month The weightings for the equipment are based on
month. interviews held with the various subject matter
experts including field staff and equipment specialists
Meter readings: cyclo Meter readings: cyclo for the equipment as seen in Table 4. The substation
advances of the tap advances for both load plant health index will be represented by a series of 9
changer; maximum and fault operations, tests as shown in Table 4.
top-oil transformer from the circuit
temperature and oil breaker panel. TABLE 4. THE WEIGHTING PER PLANT
level. HEALTH MEASURES FOR THE EQUIPMENT
2 Oil sampling, annually Trip-testing, annually IS ILLUSTRATED

Analysis: Assessment Protection


of the dissolved gas maintenance: Either Equipm Plant Test Weighting Sub
analysis; water content annually or 3yearly, ent Health Weight per PHI
and di-electric strength. when the CB is Measure ing Equipmen
isolated and earthed. t
Other: Degree of Circuit Contact 30% 40% 100
polymerisation tests of Breaker Resistanc %
paper insulation. (High e Test
3 Infra-red scanning: Infra-red scanning: voltage per phase
annually annually and
4 Tap Changer service, Minor Service: medium
every 5-6 years voltage)
depending on the OEM Routine tests: Contact Penetrati 30%
where the tap changer resistance tests. For oil on test
is dismantled, and circuit breakers, an oil per phase
visually checked for change is done. Closing 20%
damage. time per
Major service: phase
Tripping 20%
Routine tests: Contact time per
resistance tests; timing phase
tests for opening and Transfor Degree 40% 50%
closing positions and mer of
insulation (meggar) Plymeris
tests ation
5 Commissioning tests: Commissioning tests: Total 30%
Ratio test; tan delta test Same as routine test. Dissolve
of bushings; megger d
test; Combust
6 Other: Other: ible Gas
Sweep frequency Partial discharge Content
response analysis, testing. Detection of (TDCG)
indicating winding unacceptable levels of WC 30%
movement is emerging deteriorating dielectric Tap Electric 60% 10%
technology for strength. Practiced Changer Strength(
Distribution networks. partially for kV)
Distribution networks. Water 40%
Content
The maintenance strategies are courtesy of Eskom (WC)
Distribution [8].These results of these routine tests
during commercial operation will therefore be the A flow diagram for the proposed substation plant
inputs required for the development of the PHI for the health index is shown below in Figure 4.
equipment.

4.2. EQUIPMENT HEALTH


MEASURES

4
Routine Test Results

Circuit Breaker Transformer On-load Tap Changer


PHI PHI PHI

Sub PHI
Score Score Score
In Spec + + = Score

40 50 10 100
No Further Action
Required
Out of Spec
Unacceptable
Investigation 37

Alarm
PHI Improvement Decision 100

In Spec

Maintain Replace/Reinvestment
228

Saturated
Figure 5. Hazard function describes the
Failure Health Gauge probability of failure in time (sawtooth
Prediction
behaviour)
Figure 4. Flow diagram for the substation Finally, a stage will be reached where the equipment
plant health index can no longer be maintained cost-effectively, and
thus a decision for replacement is undertaken. It is
Figure illustrates that the routine test results are the believed that the next step for this model will be the
inputs for the equipment plant health measures. The failure prediction stage. Prediction is influenced by
work instruction is a detailed step-by-step design quality, network operating conditions, climatic
specification for intrusive maintenance, containing the conditions and maintenance quality.
threshold limits required for each routine test during
in-service conditions. 5. PROPOSED ALTERNATIVES
Where tests are within specification, no further action
is required. However, where routine results are out of Three alternatives were considered during the
spec, an investigation is necessary. This investigation development of the substation plant health index.
may be simple, where the field operator has noted that
re-building of the mechanism is required, or moving 5.1 MODEL A (Summated PHI)
contacts may need to be replaced at the next
intervention. A corrective action is required. In Model A, a simple approach was taken by
summating the different values of the equipment
There are rare cases where equipment can be routine test results. However, where multiples of
energised if one of the routine tests has exceeded the equipment exist i.e. >1 transformer or multiple feeder
limits. This decision requires careful consideration circuit breakers, the substation PHI just runs away.
and is often the decision taken by the specialist in This provides difficulty in having a credible range
consultation with relevant staff. The customer supply per in-specification (good), alarm and unacceptable
is restored but, a follow-up action is planned (urgent) rating.
immediately. Often, abnormal spare or replacement
parts may be needed, and the repair time for the Advantages:
defect, may be longer. • Simple mathematical approach where tests results
score are easily summated.
A plant health index will be reviewed each time, a Disadvantages:
failure or intrusive maintenance occurs. This is • A good rating for TDCG PHI Score tends to 0.
because periodic or planned maintenance Thus it counters the summation of the other tests.
restores/preserves the intended function of the The substation PHI is not reflective of the “bad”
equipment as seen in the saw-tooth behaviour TDCG score.
illustrated by the hazard function [3]. • There is no representation of individual
equipment PHI.
• The end score is a challenging number to
manage.

Thus the equipment PHI score is an average of the


number of installed units.

5
5.2. MODEL B (9-point PHI) Action would be: Action maintenance issues and
consider revised maintenance strategy to maintain
In order to overcome the challenge working with a current service levels. Unforeseen opex expenditure is
summated score system, a converted score model encountered here. Re-prioritise the completion date of
was developed. refurbishment project. A comprehensive Risk Model
is to be conducted. Contingency plan should be ready
to be activated.
The routine test results are converted to a score
between 1 and 3 where 1 = a good score, 2 = an alarm
score and 3 = an urgent score. The blue phase of the 5.3. MODEL C (17-point PHI)
F1 circuit breaker has a contact resistance value of
842. The test limits for contact resistance are [9]: We now have a total of 17 individual tests that are
being monitored.
Range Score Status Based on the same principles as in Model B above
<100 1 Good except, that each test (per phase for the circuit breaker)
Between 101 and 280u- 2 Alarm is counted as part of the final substation PHI score.
ohm
>281 3 Urgent Advantages:
Therefore, a rating out of 3 for each of the 9 tests is • Simple scoring model to manage although
developed. In this model, an average score is used for Alternative B is easier
the instances where multiples of equipment exists. In
the model itself, the user will still see the result for Disadvantages:
each piece of equipment, such that a specific problem • The circuit breaker is overrepresented in the
is still dealt with. substation PHI rating. It counts 40% to the
substation PHI, but consists of 12 tests.
Advantages:
• Each piece of equipment will have an individual 5.4. REPORTING REQUIREMENTS
PHI rating.
• Simple scoring model to manage The substation model is easily implemented using
Disadvantages: Microsoft Excel. The conditional formatting function
• None allows you to program visual indications of the
severity of the equipment routine test result. In this
Severity Ratings for the 9-point Substation PHI: instance, the following applies for the model:
• RED = 3
A Sub Score of 0-2 points mean that there are a • YELLOW = 2
maximum of 2 test results that are of concern. We will • GREEN = 1
call this score a Good Rating. This is because we can Furthermore, Figure 9 below illustrates the substation
always expect WC and kV for an OLTC to deteriorate PHI scores for a number of substations. Here, the
with time. We have at least 2 routine tests defined per substation PHI is scored as follows:
Equipment. • RED = >5
Action would be: Investigate track record and the • YELLOW 3-5
work order feedback reported, and action accordingly. • GREEN <=2
Continue monitoring all other Equipment, as per
normal. Substation PHI Score PHI Score
(Current (Following Year)
A Sub Score of 3-5 points mean that there are 5 test Year)
results that are Problematic. We will call this an A 6 4.5
Alarm Rating. This is because we can always expect B 6 4.5
WC and kV for an OLTC to deteriorate with time, as C 4 4
in 1.1 above. The Sub PHI Score of 5, indicates D 2 3
problems with at least 2 pieces of equipment out of Scenario
the 3. In the following year, the rating of 6 comes done to
Action would be: Immediately action the 4.5. This indicates that an intervention improved
reliability levels.
abnormalities, conduct probability of failure analysis
I believe that having status such as:
and evaluate the contingency plan. • Investigation completed Yes or No
• Maintained Yes or No
A Sub Score of >6 points mean that there are • Replacement required
abnormalities encountered with all 3 pieces of for all RED zone scores will improve the monitoring of
equipment in the Substation. the equipment or substation PHI.
This score would be an Urgent Rating.
6
Figure 10. Dashboard management the substation equipment is formulated once spares
principles used for Substation PHI model become a problem or call-outs become too frequent.

The above scenario confirms the sawtooth behaviour Transformer Condition Results:
of reliability that was described earlier. Substation A: Good, 28 years old
Substation B: Good, 18 years old
Substation C: Good, 30 years old
6. RESULTS WITH MODEL B Substation D: Good, 23 years old

The routine test results of four distribution substation Average Transformer age = 24.75 years old.
were sourced, and used for the simulation. The
substation PHI results are shown below in Figure 10. Plant Health Index Results:
Substation A:
Substation CB PHI Trfr PHI OLTC Sub PHI The medium voltage (MV) circuit breakers are
PHI showing early signs of wear. Closing and tripping
A 5.313 1.6 1.8 3.1052 times are of particular concern for 100% of the
B 4.725 1.6 1.8 2.87 installed base.
C 4 2 1.8 2.78 Substation B:
D 3.857 2 1.8 2.72 The MV circuit breakers are of a concern. Closing and
tripping times are of particular concern as well as the
Figure 10. Simulated results for the contact resistance of 75% of the installed base.
Substation C:
information of 4 substations, using the
Feeder 1&2 of the MV circuit breakers are showing
alternative B model. early signs of normal wear and tear. Investigate the
abnormal contact resistance values. Feeders 2 and 3
Transformer reliability ranges between fair and good have unacceptable readings for tripping times and
for the substations evaluated. In all 4 cases, we find needs to be investigated.
circuit breaker health to be of concern. A detailed Substation D:
investigation is required as the next step in order to Circuit breakers are showing early signs of wear.
determine normal ageing, or areas of risk for the Closing and tripping times are of particular concern.
circuit breakers.
In sample B, one of the CB routine test results was not A PHI for circuit breakers and tap changers is now
available. If one assumed the same performance for available in the proposed model.
this breaker as the others, the substation PHI score
increases by 30%, but the substation PHI still remains This is useful, when considering that in each case, the
in the Alarm zone. circuit breakers are failing whilst, the condition of the
For sample C, the Transformer PHI is skewed. The large power transformers varies from good to very
water content value must be evaluated in conjunction good.
with the temperature at the time of sampling i.e. we
expect the water content to be “higher” for lower
operating temperatures, typically observed with the
8. CONCLUSION
lighter loaded transformers. For sample C, a capex
The following conclusions are made:
project has already been approved for replacement of
a. Eskom Distribution now has a dashboard
the circuit breaker. The target completion date can
indication of the plant health for its circuit
now be influenced based on the PHI evaluation.
breakers and tap changers installed at its Dx
In the last sample, D, the same findings were made for
substations.
the WC as in the previous case for the transformers.
b. A policy to replace transformers at 30 years is not
One of the installed seven circuit breakers, needs
justified. However, circuit breakers are failing
attention however, whilst the rest are in the alarm
just at the 25 year investment period.
stage, indicating on-set of the wear-out stage. The
c. Reliability trending is limited, with only 1 set of
circuit breakers are 25 years old.
test results available.
d. Network contingency planning and equipment
7. EVALUATION OF MODEL A spares policies are enhanced due to early
indications of deteriorated equipment behaviour.
Till now, the substation health was represented by the e. The substation PHI requires review, as equipment
condition of the transformer routine test results. The condition will be affected by failures or operating
oil sampling of transformers and tap changers has been conditions.
outsourced for approximately 7 years and is well f. Unexpected opex expenditures are reduced and
managed [1]. However, an action plan for the rest of planning of CAPEX is improved.

7
9. ACKNOWLEDGEMENTS
The author would like to acknowledge the
contributions from Ulrich Minnaar, Lester Geldenhuis
and Siraj Williams.

10. REFERENCES

[1] Geldenhuis, L.M.: “Transformer Risk Model”


Eskom Distribution, 2006.

[2]Hamm, G.L.: “A Review of the Reliability of


Electric Distribution System Components”, EPRI,
2001.

[3] Ross, D.P.: “Sensitivity of System Reliability to


Component Aging in Metropolitan, Urban and
Rural Areas”, IEEE, 2001.

[4] Brand, E.: “Preliminary Investigation Into The


Feasibility Of Establishing a Distribution Plant
Health Index”, Eskom Distribution, 2007.

[5] Koen P.: “Investigation Into LMS Circuit Breaker


Performance”, Eskom Distribution, 2004.

[6] Jagers, J.: “Large Power Transformer Reliability


Improvement in Eskom Distribution”, CIRED,
2007.

[7] Hamm, G.L et al.: “Estimating Reliability of


Critical Distribution System Components. EPRI
Report 1001704”, EPRI, 2003.

[8] Tyusha, M.: “Preventive Maintenance Strategies”,


Eskom Distribution, 2000.

[9] Ntombela, D.: “Circuit Breaker: Reyrolle Type:


LMT MKII Work Instruction”, Eskom
Distribution, 2004.

11. AUTHORS ADDRESS


E. Brand
Eskom
P.O. Box 222
Brackenfell 7561

W. Fritz
School of Electrical Engineering
Cape Peninsula University of Technology
P.O. Box 1906

U. Minnaar
Eskom
P.O. Box 222
Brackenfell 7561

Anda mungkin juga menyukai