AbstractA traditional secondary selective residual bus automatic transfer scheme is reviewed, and the basic logic necessary for
automatic transfer operation is discussed. Although many transfer
scheme documents are available, the authors believe the scheme
complexity should challenge application engineers to better understand the Whys rather than the How Tos of the application.
A modern programmable logic controller approach is proposed as
a contemporary solution to a complex control application.
Index TermsGroup motor reacceleration, programmable
logic controller (PLC), residual bus, secondary selective system,
10-Switch.
I. INTRODUCTION
A. Overview
A secondary selective system is a closed main breakeropen
tie breakerclosed main breaker configuration supplied by two
transformers. Fig. 1 represents a typical secondary selective
system with residual bus automatic transfer. The purpose of the
residual bus automatic transfer scheme is to reestablish power
on one of two main buses following transient conditions and
to block transfer during through fault conditions. Transfer is
allowed during stable system conditions with normal system
voltage available to maintain or reaccelerate operating loads.
Some transient conditions are as follows:
1) loss of one utility source at the upstream main substation;
2) transformer upstream cable fault;
3) local substation transformer failure;
4) substation incoming cable or bus duct failure;
Paper PID-0308, presented at the 2002 IEEE Petroleum and Chemical
Industry Technical Conference, New Orleans, LA, September 2325, and approved for publication in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS
by the Petroleum and Chemical Industry Committee of the IEEE Industry
Applications Society. Manuscript submitted for review September 15, 2002
and released for publication September 29, 2004.
R. E. Coss, Jr., and J. E. Bowen are with Powell Electrical Manufacturing Company, Houston, TX 77075 USA (e-mail: rcosse@powl.com;
jbowen@powl.com).
S. H. Kerr is with ExxonMobil Development Company, Houston, TX 77060
USA (e-mail: steve.h.kerr@exxonmobil.com).
Digital Object Identifier 10.1109/TIA.2004.841014
113
Fig. 1. Abbreviated one-line diagram for traditional discrete device residual bus automatic transfer system. Note that devices 51G-1, 51G-2, 63A, 63B, 86TA,
86TB, 87TA, 87TB, 94A, 94B, metering devices, and others may not be shown for better readability.
of 52A closure, tie breaker 52T immediately trips. (Momentary closure of 52A, 52T and 52B may significantly increase the
114
Fig. 2. High-resistance ground closed transfer permissive. Note: When high-resistance ground exists on both A side and B side, closed transition transfer is
inhibited. Transfer is blocked until 86HRGA or 86HRGB is reset.
115
116
117
Fig. 3. Abbreviated one-line diagram for modern PLC residual bus automatic transfer system. Note that devices 63A, 63B, 86TA, 86TB, 87TA, 87TB, 94A, 94B,
metering devices and others may not be shown for better readability. For device numbers and abbreviations, refer to Fig. 1.
4) Using meter/protection/transfer control black box devices may result in accidental operation trips during periods of manually reviewing metering data.
5) Although the PLC approach recommends separate metering, protection and control devices, multifunction
meter/protection/transfer control devices provide increased reliability because fewer devices are required.
B. Flexibility
1) PLC logic enables users to perform software modifications rather than hardware additions or changes. One
example is adding a transfer pushbutton (or control
switch) to perform manual transfers in conjunction with
the 10-Switch. By prudent design, the transfer pushbutton
could be located across the room from the switchgear,
118
VI. SUMMARY
Secondary selective systems are a proven, effective method of
enhancing system availability, however, the purpose and device
setting philosophy are rather complex and are often overlooked.
Design of a secondary selective residual bus automatic transfer
system is typically implemented by using the Company Standard. Through right sizing, company standards have not been
revised to incorporate modern technology developments and
trends.
Transfer system implementation may be in the form of discrete relays, multifunction relays, or a PLC-based system.
1) The discrete system is the original method, but it is space
intensive, requires significant intercompartment wiring,
cannot perform diagnostics, and cannot be confirmed before switchgear is assembled and ready for checkout.
2) Multifunction black box relays can provide additional
diagnostics and sensing, while requiring less space
than discrete devices, but may not be flexible to system
modifications and changes. Multifunction relays may
119
Stephen H. Kerr (A92M97) received the B.S. degree in electrical engineering from Texas A&M University, College Station, in 1976.
After working for an engineering contractor for
three years, he joined Exxon at the Baton Rouge
Chemical Plant as Project Engineer for facility
design projects. In 1983, he transferred to the
Exxon Production department as LaBarge project
Lead Electrical Engineer. After project completion,
he transferred to the LaBarge Operations on-site
engineering group, where he was responsible for
surveillance, project development, and design. In 1991, he transferred to the
Production Technology Department, where he was involved in large project
development and execution, including a 15-month stint to the Santa Ynez
project to assist in construction completion and startup. In 1997, he transferred
to Houston, TX, as Lead Electrical Engineer for the Diana project, and he is
presently Lead Electrical Engineer for the ExxonMobil Kizomba Project.