PROJECT DESCRIPTION
The Sg Kinta Dam Project is part of the Stage II development of the Ipoh Water Supply on mainland
Malaysia. This stage of the development consists of the construction of a dam with a yield in excess
of 300ML per day, associated raw water pipeline and the water treatment plant to augment the
existing low weir and water treatment plant on the Sg. Kinta.
The Sg Kinta Dam is located approximately 12 km east of the city of Ipoh, which is in turn located
about 200 km north of Kuala Lumpur. The damsite rocks are primarily deeply weathered granites
which vary from closely jointed but healed to massive rocks. Water test results indicate that the
foundations will generally be of low permeability. The RCC aggregate will be produced from crushed
granite to be obtained from a quarry to be developed by the contractor about 1.2 km from the dam.
The Feasibility Study conducted by GHD and Angkasa GHD indicated that either a concrete faced
rockfill or a roller compacted concrete dam would be economic at the site. The subsequent Concept
Design Report completed by GHD and Angkasa GHD concluded that the least cost dam would be a
roller compacted concrete dam.
The Kinta Dam will have a maximum height of 90m and a crest length of 700 m and total concrete
volume of 850,000 m3. It will be the first RCC dam built in Malaysia and its construction is expected
to commence early in 2000.
Design of the dam including evaluation of thermal stresses has been completed. This paper
investigates the simplifications commonly adopted for thermal-structural finite element analyses of
RCC dams. The validity of these, in particular ignoring the effect of strength gain during hydration of
the RCC and the effect of creep is demonstrated with 2 dimensional analyses results. The preliminary
results of 3 dimensional analyses are also presented.
placement. These thermal loads induce structural stresses which can be significant enough to induce
cracking of the RCC structure.
In the design of RCC dams, it is common practice to investigate the development of thermal stresses
during and after the construction of the dam and reservoir filling. The traditional design approach is
based on a simple evaluation of the thermal strain/stress in the concrete material and then estimate the
contraction joint spacing to relieve the stresses (Tatro 1999, Tatro and Schrader 1992, 1995).
Recent developments of sophisticated software based on advanced numerical methods together with
the continually increasing power of computers mean that it is possible to accurately perform complex
analyses such as thermal-structural problems. The ANSYS computer programme based on the finite
element method was used to analyse the thermal behaviour of Kinta Dam including modeling of
elastic modulus change with time, creep behaviour and simulation of the construction process,
reservoir filling and the cooling of the dam over 10 years. The desired outcome of this numerical
modeling is:
to determine spatial distribution of temperature and its evolution with time,
to determine the stress distribution during and following the dam construction and the reservoir
water filling,
to identify the appropriate joint spacing to minimise cracking,
to optimise concrete placing temperature,
to define tensile strength required from the RCC mix and lift joints.
Page 2
Figure 1
Temperature Rise in Dam Core
(90 kg/m3 Slag-Cement + 90 kg/m3 Flyash)
18
16
14
12
10
8
6
Measurement from
Cadiangullong Dam
ANSYS Model
2
0
0
20
40
60
80
Tim e (days)
100
120
140
160
Creep is the timedependent deformation of a material due to a sustained load. This inelastic strain of
the material relieves stresses in mass concrete structures. Creep can play an important role in the long
term stress analysis (Gunn and Bossoney 1996).
Creep is closely related to the modulus of elasticity and compressive strength of the concrete and is
thus a function of the age of the concrete at loading. Concrete with a high modulus of elasticity will
generally have relatively low creep.
The creep coefficient equation given by Ziming Zhang and Garga (1996) for RCC material has been
used as given below.
C(t,) = (1.01+3.23/0.3){1-e-0.036(t-)} 10-5 1/Mpa
Where t is the age of the concrete at the time of loading and is the time of calculation of the strain.
Material properties of RCC strongly depend on the age of the RCC and will significantly affect the
response of the dam at an early age where the mechanical properties are relatively low, which requires
the use of a multi-linear elastic material model. It is important that the early age stress-strain
properties are modelled (Yonezawa 1988, Ishikawa 1991, Ayotte 1997 and Zhu 1999). Some of the
most significant stresses induced into RCC occur as a result of thermal loads from heat released by
hydration of the cement. This process commences soon after placement of the RCC, which means
that, to obtain any degree of accuracy, the early age properties of the RCC should be incorporated into
any numerical model. The stress-strain curves adopted in the multi-linear elastic material model for
the Kinta Dam are shown in Figure 2. The results of the RCC trial mix programme currently under
way will be used to more precisely define these curves.
Page 3
Figure 2
Stress-Strain Curve for Different Concrete Ages
18
16
14
Stress (MPa)
12
10
10 days
30 days
90 days
180 days
360 days
>361 days
0
0
200
400
600
800
1000
1200
Strain (m icrostrain)
1400
1600
1800
2000
MODELING METHODOLOGY
The thermo-mechanical analysis was modelled using an un-coupled approach. The thermal behavior
of the dam was firstly simulated using incremental construction of the finite element mesh. The
results of the thermal model were then applied using direct superpositioning to a structural model,
which also included the step by step construction process. The analysis was time marching to closely
model the construction of 3 m RCC lifts in 10 day intervals over the 270 day construction period.
Reservoir filling was modelled over the subsequent period from 271 days to 330 days. The finite
element mesh adopted is illustrated in Figure 3.
Page 4
Temperature (Deg C)
Figure 4
Predicted Temperature History
46
45
44
43
42
41
40
39
38
37
36
35
34
33
32
31
30
29
28
27
26
25
Node 505
Node 369
365
730
1095
1460
1825
2190
Time (days)
Page 5
2555
2920
3285
3650
Page 6
1.4
Figure 5
Upstream - Downstream Stress (x direction)
(Element Close to Upstream Face, 30 m from base, Node 505)
1.2
1.0
0.8
0.6
0.4
0.2
0.0
-0.2 0
100
200
300
400
500
600
700
-0.4
-0.6
-0.8
-1.0
Case 1 - Linear Elastic
-1.2
-1.4
-1.6
-1.8
-2.0
Time (days)
Figure 6
Upstream - Downstream Stress (x direction)
(Element Close to Upstream Face, 75 m from base, Node 1165)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
-0.2 0
100
200
300
400
500
600
700
-0.4
-0.6
-0.8
-1.0
Case 1 - Linear Elastic
-1.2
-1.4
-1.6
-1.8
-2.0
T ime (days)
Figure 7
Cross Valley Stress (z direction)
(Element Close to Upstream Face, 30 m from base, Node 505)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
-0.2 0
100
200
300
400
500
600
-0.4
-0.6
-0.8
-1.0
-1.2
-1.4
-1.6
-1.8
-2.0
Time (days)
Page 7
700
Figure 8
Cross Valley Stress (z direction)
(Central Element, 21 m above base, Node 369)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
-0.2 0
500
1000
1500
2000
2500
3000
3500
-0.4
-0.6
-0.8
Case 1 - Linear Elastic
-1.0
-1.2
-1.4
-1.6
-1.8
-2.0
Time (days)
Figure 9
Cross Valley Stress (z direction)
(Central Element, 75 m above base, Node 1161)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
-0.2 0.0
500.0
1000.0
1500.0
2000.0
2500.0
3000.0
3500.0
-0.4
-0.6
-0.8
-1.0
-1.2
-1.4
-1.6
-1.8
-2.0
T ime (days)
Figure 10
Cross Valley Stress (z direction)
(Element Close to Upstream Face, 75 m from base, Node 1165)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
-0.2 0
500
1000
1500
2000
2500
3000
-0.4
-0.6
-0.8
-1.0
-1.2
-1.4
-1.6
-1.8
-2.0
Time (days)
Page 8
3500
Figure 7 represents the cross valley stress (z direction) for a point 30 m above the dam base. Again,
the linear elastic model overestimates the compressive stress calculated with 1.55 MPa recorded
against 1.24 MPa estimated by the multi-linear elastic model. The linear elastic model shows a more
rapid return to a lower level stress condition than the creep models which show a residual stress,
clearly evident even at the 720 day mark.
This interpretation of the results is supported by observations of RCC in the field. At early ages the
RCC exhibits low strength and modulus, and high creep rates, which serve to both reduce stress
attraction because of the low modulus and irrecoverable creep strain development.
Of greater significance to the long term behaviour of the dam, is the effect of creep on residual
stresses within the structure. The effect of creep is most clearly shown on figure 8 which shows that,
in conformance with classical elastic theory, the linear elastic model is in compression in the centre of
the dam for the duration that the core is warm, and dissipates to zero stress when the core of the dam
has cooled. Applying a creep model results in dissipation of the compressive stress at relatively early
ages, with a locked in tensile stress appearing when the dam has cooled. This is more in keeping with
observed contraction joint openings of RCC dams following construction. The peak tensile stress
developed at 10 years is 1.04 MPa for the multi-linear elastic model with creep, while the linear
elastic model with creep overestimating the tensile stress slightly with a peak of 1.12 MPa at 10 years.
Figure 8 also demonstrates the overestimation of peak stresses by the models without creep at early
ages of the RCC. A peak compressive stress of 1.85 MPa is recorded within 20 days of placement by
these models compared to 1.22 MPa with the multi-linear elastic model with creep. The effects of
creep are soon apparent, with a peak compressive stress during a second peak at 300 days after
placement of 1.48 MPa with the multi-linear elastic model with creep comparing to a peak
compressive stress of 1.95 MPa with the linear elastic model without creep. Beyond 100 days after
placement, the effects of the multi-linear elastic model are less apparent, with both creep models
deviating from their no-creep counterparts.
Creep behaviour is strongly dependent on the duration of loading. The creep and no creep
counterparts of both the linear elastic and multi-linear elastic models are shown to exhibit the same
behaviour for the upper levels of the dam, as shown by figure 9 and 10. This is because the heating
and cooling cycle at the upper parts of the dam are more rapid, and creep effects do not have time to
dissipate any compressive loading.
The effect of overestimation of the compressive stress by the linear elastic model is also shown in
figures 9 and 10 for early age RCC. For example, figure 9 shows a peak compressive stress of 1.44
MPa for the linear elastic model compared to 0.96 MPa for the multi-elastic model at the same age.
ACKNOWLEDGMENTS
The authors are grateful to MUC for the permission to prepare and publish this paper. They would
also like to thank Angkasa-GHD Sdn Bhd in Malaysia and GHD Pty Ltd in Australia for the
encouragement and support in the preparation of the paper.
REFERENCES
ACI 207.1R - 87, Mass Concrete for Dams and Other Massive Structures
Ayotte E., Massicotte B., Houde J., Gocevski V. (1997), Modeling the Thermal Stresses at Early Ages
in a Concrete Monolith, ACI Materials Journal, Vol. 94, No. 6, 1997.
Barrett P. R. Foadian H. James R. J. Rashid Y. R. (1992), Thermal-structural Analysis Methods for
RCC Dams, Roller Compacted Concrete III, American Society of Civil Engineers, New York, 1992.
Gunn R. M. and Bossoney C. (1996), Creep Analysis of Mass Concrete Dams, Hydropower & Dams,
Issue Six, 1996.
Fobes B.A., Williams, J. T., (1998) Thermal Stress Modeling, High Sand RCC Mixes and In-situ
Modification of RCC Used for Construction of Cadiangullong Dam NSW, ANCOLD, Sydney, 1998.
Ishikawa M. (1991), Thermal Stress Analysis of Concrete Dam, Computers & Structures, Vol. 40,
1991.
Tatro, Stephen B., and Ernest K. Schrader (1992), Thermal Analysis of RCC - A Practical Approach,
Roller Compacted Concrete III, American Society of Civil Engineers, New York, 1992.
Tatro, Stephen B. (1999), Commentary on the Corps of Engineers Approach to Thermal Analysis,
International Symposium on Roller Compacted Concrete Dam, Chengdu, China, 1999.
U.S. Army Corps of Engineers (1994), Engineering Technical Letter (ETL) 1110-2-365, Nonlinear,
Incremental Structural Analysis of Massive Concrete Structures, Washington, DC, 1994.
Yonezawa T., Takahi K., Yamaguchi Y., Jikan S. (1988), Measurement and Analysis of Cracks
Caused by Thermal Stress in Mass Concrete, ICOLD, San Francisco, 1988.
Zhang Zinming. and Garga V. K. (1996), Temperature and Temperature Induced Stresses for RCC
Dams, Dam Engineering, Vol VII, Issue 2, 1996.
Zhu Bofang (1995), Compound Layer Method for Stress Analysis Simulating Construction Process of
Concrete Dam, Dam Engineering, Vol VI, Issue 2, 1995.
Zhu Bofang., Xu Ping., Wang Shuhe.(1999), Thermal Stresses and Temperature Control of RCC
Gravity Dams, International Symposium on Roller Compacted Concrete Dam, Chengdu, China, 1999.
Page 10