discussions, stats, and author profiles for this publication at: http://www.researchgate.net/publication/222574462
CITATIONS
DOWNLOADS
VIEWS
10
93
256
12 AUTHORS, INCLUDING:
F.-B. Frechen
Sajjad Haider
Universitt Kassel
SEE PROFILE
SEE PROFILE
Martin Wett
SAG Engineering
5 PUBLICATIONS 41 CITATIONS
SEE PROFILE
Abstract
In the future, upgrading of existing wastewater treatment plants (wwtps) will become the more challenging task
than erection of wholly new plants, as most of the plants (e.g. necessary in Germany) do exist already. Since some
time, MBR technology has been taken into consideration and has been realised as an alternative for wwtp upgrading.
This paper gives an overview about some relevant preconditions, basic upgrading concepts and examples of already
upgraded wwtps using MBR technology.
Keywords: Municipal wastewater treatment; Upgrading; MBR technology
*Corresponding author.
Presented at The 4th IWA Conference on Membranes for Water and Wastewater Treatment
May 1517, 2007, Harrogate, UK
0011-9164/08/$ See front matter 2008 Elsevier B.V. All rights reserved
1. Introduction
Many wwtps suffer from an inadequate level
of treatment provided. There are several reasons
for the need of retrofitted and/or upgraded equipment, such as expiry of lifespan, the increase of
wastewater flow or load or higher treatment standards due to a change of legal framework. In general, no standard solutions for the upgrading of
wastewater treatment systems are available and
the transfer of a certain measure from one case to
another is limited. In fact, the optimum answer in
each individual case is largely site-dependent.
Accordingly, there is a broad spectrum of measures that might be employed. In most cases it is
not a singular action to be taken, but the upgrading will incorporate a set of different interlocking
components both at the drainage system and the
wastewater treatment plant.
The MBR process is an emerging advanced
wastewater treatment technology that has been
successfully applied at an ever increasing number of locations around the world. It involves a
suspended growth activated sludge system that
utilizes microporous membranes for solid/liquid
separation as a substitute of the conventional secondary clarifier. MBR technology has not only
attracted increasing interest for the set up of new
wastewater treatment systems but also it has high
potential looking at upgrading tasks of already
existing wwtps.
2. Considerations for the choice of MBR
technology
Since membrane filtration allows raised sludge
concentrations, the activated sludge tank volume
can be significantly reduced. In combination with
the option to convert the secondary clarifier, that
is no longer required as a sedimentation tank, as
an additional activated sludge tank, the treatment
capacity of the existing plant can be largely extended. That way it is possible to upgrade existing wwtps from simple carbon removal to BNR
systems just using the already existing volume.
21
22
initial situation
sed.
tank
biology
biology
FC
biology
biology
FC
biology
biology
23
parallel
sed.
tank
biology
biology
FC
serial
peak flow
biology
sed.
tank
biology
FC
Besides, a fullness of mixing variations is possible. The flow concept of the sludge streams between both biological units at parallel operation
mode or serial operation mode can be operated
separately or combined according to the local circumstances (grey arrows in Fig. 2). In the latter
case possible differences are to be taken into consideration concerning the sludge qualities, in particular, the quality of sedimentation and the MLSS
concentrations.
3.3. Other processes
Beside the combination with the CAS process
also combinations with other wastewater treatment procedures are possible, e.g. with SBR technology [1] or with pond technology. Today SBR
technology integrating membrane technology as
separation process is used at industrial applications or at package plants. Applications combining pond technology and MBR technology are op-
24
to a great extent. Beside the anyway raised effluent quality other advantages of this upgrading
concept can be named:
considerable biological reserve capacities for
future extension;
smaller place consumption compared to a conventional upgrading concept.
Some manufacturers of membrane modules
recommend not falling short of a given MLSS
concentration directly at the membrane or within
a separated filtration chamber. Thus, the suitability of the respective membrane modules for the
low MLSS operation mode is to be clarified.
Nevertheless, by the construction of a separate
filtration chamber optimal MLSS concentrations
at the membrane and within the biological zone
can be adapted accordingly.
3.5. MBR in combination with anaerobic sludge
stabilization
Up to now most municipal MBR plants are
dimensioned with aerobic simultaneous sludge
stabilization. In principle the MBR process also
can be combined with anaerobic sludge stabilization. Some single studies assume dependence between increasing fouling potential and increasing
F/M-ratio or rather decreasing SRT [46]. A final
statement cannot be met yet. If the MBR process
is dimensioned with a short SRT, hence, possible
intensified fouling effects have to be considered.
If the MBR process is dimensioned with a long
SRT, slightly reduced digester gas production can
be expected. A possible process variation features
the digestion of only primary sludge. Thus, in an
upgrading situation the cost intensive new building of digestion volume can be avoided.
4. Experiences from full-scale applications
The full version of DWA WG KA-7.4 report
includes all subsequently mentioned wwtps:
wwtp St. Peter ob Judenburg, Austria
wwtp Schilde, Belgium
25
FC
screen
6 mm
grit chamber,
grease trap
sieve
1 mm
FC
FC
DN / N
FC
concentrate
storage tank,
former secondary
clarifier
The MBR line consists of two sub-lines. Aerobic and anoxic volumes of the MBR process are
dimensioned the way, that in times of maximum
inflow the minimum HRT within the biological
zone prior to the filtration chambers does not fall
below 30 min.
Better effluent quality concerning the conventional process line also is achieved caused by the
less hydraulic load of the secondary clarifiers.
Thus, the requirements that have to be met by the
mixture of both effluent streams can be guaranteed.
5. Conclusions
The presented upgrading concepts raise no
claim to completeness and thus reveal the wide
spectrum of supposable measures. Many of them
are under investigation and appropriate findings
can be expected to be reported soon. However,
the chosen upgrading concept must meet the claim
to be
demand-oriented according the wastewatersided requirements and the load situation,
economical in view of annual costs (operating
expenses and net debt service).
Besides, various other, not only process-related, but also nonmonetary and monetary hardly
assessable aspects are to be followed and to weigh
in each individual case which do not admit a stan-
26
sec.
sed.
BOD
sec.
sed.
prim.
sed.
50%
return sludge
screen
6 mm
grit chamber,
grease trap
MBR process
concentrate
50%
sieve
1 mm
DN / N
(existing)
FC
sieve
1 mm
DN / N
(existing)
FC
prim.
sed.
concentrate
[3]
[4]
[5]
[6]
[7]