Hydraulic Design of Upstream Scouring Sluice

1 Basic conditions and dimensions


EL1 =
=
=
=
=
=

Crest elevation of solid overflow weir


Design intake water level
Bed elevation at upstream end of scouring sluice
Bed elevation at scouring sluice gate
Top elevation of guide wall at upstream end of scouring sluice
Top elevation of divider wall

WLi
ELb
EL2
ELg
ELd

m
m
m
m
m
m

Average grain size of river bed material


Roughness coefficient for scouring
Strickler's K
Gravity acceleration

dm
n
K
g

Depth between WLi and ELb


Required height of upstream guide wall

Hs =
H =

3.30 m
1.00 m

S =
L =

4.30 m
1.70 m

Space between upstream end of scouring sluice gate and downstream end of intake
Width of intake
Total width of scouring sluice
Effective width of scouring sluice
Width per channel
Nnumber of channels
Thickness of pier
Nnumber of piers

Bs
Bse
Bse / L
bs
ns
tp
np

=
=
=
=

99.15
99.05
95.75
95.64
96.75
100.65

=
=
=
=
=
=
=

= EL1 0.10 m
= ELb i L1
= ELb + H
= EL1 + 1.00 m

0.05 m
0.018
=1/K
55
9.8 m/s2

2.00
1.00
59
1.00
1
1.00
1

= WLi ELb
= 1.5 hc

m
= ns bs + np tp
m
= ns bs
%
~ 60 %
m
nos.
m
nos.

2 Length of upstream scouring sluice


Space between upstream end of scouring sluice and upstream end of intake
Length of upstream scouring sluice

Ls =
L1 =
say,

5.00 m
11.00 m
11.00 m

= 1.5 Hs
= S + Li + Ls

3 Bed slope of upstream scouring sluice


Maximum grain size of river bed material
Critical velocity required to transport sediment
Critical water depth
Discharge per unit widh
Required height of guide wall at upstream end of scouring sluice

d =
Vc =
hc =
qe =
H =
say,
h =

0.300
2.449
0.612
1.500
0.918
1.000
0.500
OK

Ic =

0.00374

= n2 g / hc1/3

Ie =
Itg =
Check: Ic < Ie < Itg

0.00515
0.00742
OK

= n2 g hc3/{(h+hc)/2}10/3
= 0.0825 dm /{(h+hc)/2}

i
i= 1/
say, 1 /

0.00885
113.1
100

(or more)
(or less)
(or less)

Water depth at scouring sluice gate


Check: h > d

m
m/s
m
m3/s
m
m
m

= (20 d)0.5
= 20 d / g
= {(20 d)3/g2}0.5
= 1.5 hc
> 1.0 m

Bed slope of upstream scouring sluice


i = {h+hc3/(2 h2) -1.5 hc}/L1 + n2 g hc3/{(h+hc)/2}10/3

or,

4 Check velocity at scouring sluice gate in n=0.015 (K=65)


Unit width of scouring sluice
Water depth at scouring sluice gate
Flow area
Wetted perimeter
Hydraulic radius
Hydraulic gradient (= bed slope)

b
h
A
P
R

=
=
=
=
=
R2/3 =
i =
i1/2 =

1.000 m
0.500 m
0.500 m2 = b h
2.000 m = b + 2 h
0.250 m = A / P
0.397
0.01000
0.1000

Roughness coefficient

n =
K =
V =

Velocity
Check: V > Vc

0.015
65
=1/n
2.646 m/s = K R2/3 i1/2
OK

Hydraulic Design of Upstream Scouring Sluice


1 Basic conditions and dimensions
EL1 =
=
=
=
=
=

Crest elevation of solid overflow weir


Design intake water level
Bed elevation at upstream end of scouring sluice
Bed elevation at scouring sluice gate
Top elevation of guide wall at upstream end of scouring sluice
Top elevation of divider wall

WLi
ELb
EL2
ELg
ELd

m
m
m
m
m
m

Average grain size of river bed material


Roughness coefficient for scouring
Strickler's K
Gravity acceleration

dm
n
K
g

Depth between WLi and ELb


Required height of upstream guide wall

Hs =
H =

3.30 m
1.00 m

S =
L =

4.45 m
1.00 m

Space between upstream end of scouring sluice gate and downstream end of intake
Width of intake
Total width of scouring sluice
Effective width of scouring sluice
Width per channel
Nnumber of channels
Thickness of pier
Nnumber of piers

Bs
Bse
Bse / L
bs
ns
tp
np

=
=
=
=

99.15
99.05
95.75
95.65
96.75
100.65

=
=
=
=
=
=
=

= EL1 0.10 m
= ELb i L1
= ELb + H
= EL1 + 1.00 m

0.05 m
0.018
=1/K
55
9.8 m/s2

2.00
1.00
100
1.00
1
1.00
1

= WLi ELb
= 1.5 hc

m
= ns bs + np tp
m
= ns bs
%
~ 60 %
m
nos.
m
nos.

2 Length of upstream scouring sluice


Space between upstream end of scouring sluice and upstream end of intake
Length of upstream scouring sluice

Ls =
L1 =
say,

5.00 m
10.45 m
10.50 m

= 1.5 Hs
= S + Li + Ls

3 Bed slope of upstream scouring sluice


Maximum grain size of river bed material
Critical velocity required to transport sediment
Critical water depth
Discharge per unit widh
Required height of guide wall at upstream end of scouring sluice

d =
Vc =
hc =
qe =
H =
say,
h =

0.300
2.449
0.612
1.500
0.918
1.000
0.500
OK

Ic =

0.00374

= n2 g / hc1/3

Ie =
Itg =
Check: Ic < Ie < Itg

0.00515
0.00742
OK

= n2 g hc3/{(h+hc)/2}10/3
= 0.0825 dm /{(h+hc)/2}

i
i= 1/
say, 1 /

0.00902
110.9
100

(or more)
(or less)
(or less)

Water depth at scouring sluice gate


Check: h > d

m
m/s
m
m3/s
m
m
m

= (20 d)0.5
= 20 d / g
= {(20 d)3/g2}0.5
= 1.5 hc
> 1.0 m

Bed slope of upstream scouring sluice


i = {h+hc3/(2 h2) -1.5 hc}/L1 + n2 g hc3/{(h+hc)/2}10/3

or,

4 Check velocity at scouring sluice gate in n=0.015 (K=65)


Unit width of scouring sluice
Water depth at scouring sluice gate
Flow area
Wetted perimeter
Hydraulic radius
Hydraulic gradient (= bed slope)

b
h
A
P
R

=
=
=
=
=
R2/3 =
i =
i1/2 =

1.000 m
0.500 m
0.500 m2 = b h
2.000 m = b + 2 h
0.250 m = A / P
0.397
0.01000
0.1000

Roughness coefficient

n =
K =
V =

Velocity
Check: V > Vc

0.015
65
=1/n
2.646 m/s = K R2/3 i1/2
OK

Hydraulic Design of Upstream Scouring Sluice


1 Basic conditions and dimensions
EL1 =
=
=
=
=
=

14.20
14.10
10.70
10.47
11.70
15.70

Average grain size of river bed material


Roughness coefficient for scouring
Strickler's K
Gravity acceleration

dm
n
K
g

0.05 m
0.018
=1/K
55
9.8 m/s2

Depth between WLi and ELb


Required height of upstream guide wall

Hs =
H =

3.40 m
1.00 m

S =
L =

7.00 m
11.00 m

Crest elevation of solid overflow weir


Design intake water level
Bed elevation at upstream end of scouring sluice
Bed elevation at scouring sluice gate
Top elevation of guide wall at upstream end of scouring sluice
Top elevation of divider wall

WLi
ELb
EL2
ELg
ELd

Space between upstream end of scouring sluice gate and downstream end of intake
Width of intake
Total width of scouring sluice
Effective width of scouring sluice
Width per channel
Nnumber of channels
Thickness of pier
Nnumber of piers

Bs
Bse
Bse / L
bs
ns
tp
np

=
=
=
=

=
=
=
=
=
=
=

9.00
6.00
55
2.00
3
1.00
3

m
m
m
m
m
m

= EL1 0.10 m
= ELb i L1
= ELb + H
= EL1 + 1.00 m

= WLi ELb
= 1.5 hc

m
= ns bs + np tp
m
= ns bs
%
~ 60 %
m
nos.
m
nos.

2 Length of upstream scouring sluice


Space between upstream end of scouring sluice and upstream end of intake
Length of upstream scouring sluice

Ls =
L1 =
say,

5.10 m
23.10 m
23.10 m

= 1.5 Hs
= S + Li + Ls

3 Bed slope of upstream scouring sluice


Maximum grain size of river bed material
Critical velocity required to transport sediment
Critical water depth
Discharge per unit widh
Required height of guide wall at upstream end of scouring sluice

d =
Vc =
hc =
qe =
H =
say,
h =

0.300
2.449
0.612
1.500
0.918
1.000
0.470
OK

Ic =

0.00374

= n2 g / hc1/3

Ie =
Itg =
Check: Ic < Ie < Itg

0.00564
0.00762
OK

= n2 g hc3/{(h+hc)/2}10/3
= 0.0825 dm /{(h+hc)/2}

i
i= 1/
say, 1 /

0.00872
114.7
100

(or more)
(or less)
(or less)

Water depth at scouring sluice gate


Check: h > d

m
m/s
m
m3/s
m
m
m

= (20 d)0.5
= 20 d / g
= {(20 d)3/g2}0.5
= 1.5 hc
> 1.0 m

Bed slope of upstream scouring sluice


i = {h+hc3/(2 h2) -1.5 hc}/L1 + n2 g hc3/{(h+hc)/2}10/3

or,

4 Check velocity at scouring sluice gate in n=0.015 (K=65)


Unit width of scouring sluice
Water depth at scouring sluice gate
Flow area
Wetted perimeter
Hydraulic radius
Hydraulic gradient (= bed slope)

b
h
A
P
R

=
=
=
=
=
R2/3 =
i =
i1/2 =

1.000 m
0.470 m
0.470 m2 = b h
1.940 m = b + 2 h
0.242 m = A / P
0.389
0.01000
0.1000

Roughness coefficient

n =
K =
V =

Velocity
Check: V > Vc

0.015
65
=1/n
2.591 m/s = K R2/3 i1/2
OK

Hydraulic Design of Upstream Scouring Sluice


1 Basic conditions and dimensions
EL1 =
=
=
=
=
=

14.20
14.10
10.70
10.47
11.70
15.70

Average grain size of river bed material


Roughness coefficient for scouring
Strickler's K
Gravity acceleration

dm
n
K
g

0.05 m
0.018
=1/K
55
9.8 m/s2

Depth between WLi and ELb


Required height of upstream guide wall

Hs =
H =

3.40 m
1.00 m

S =
L =

7.00 m
11.00 m

Crest elevation of solid overflow weir


Design intake water level
Bed elevation at upstream end of scouring sluice
Bed elevation at scouring sluice gate
Top elevation of guide wall at upstream end of scouring sluice
Top elevation of divider wall

WLi
ELb
EL2
ELg
ELd

Space between upstream end of scouring sluice gate and downstream end of intake
Width of intake
Total width of scouring sluice
Effective width of scouring sluice
Width per channel
Nnumber of channels
Thickness of pier
Nnumber of piers

Bs
Bse
Bse / L
bs
ns
tp
np

=
=
=
=

=
=
=
=
=
=
=

9.00
6.00
55
2.00
3
1.00
3

m
m
m
m
m
m

= EL1 0.10 m
= ELb i L1
= ELb + H
= EL1 + 1.00 m

= WLi ELb
= 1.5 hc

m
= ns bs + np tp
m
= ns bs
%
~ 60 %
m
nos.
m
nos.

2 Length of upstream scouring sluice


Space between upstream end of scouring sluice and upstream end of intake
Length of upstream scouring sluice

Ls =
L1 =
say,

5.10 m
23.10 m
23.10 m

= 1.5 Hs
= S + Li + Ls

3 Bed slope of upstream scouring sluice


Maximum grain size of river bed material
Critical velocity required to transport sediment
Critical water depth
Discharge per unit widh
Required height of guide wall at upstream end of scouring sluice

d =
Vc =
hc =
qe =
H =
say,
h =

0.300
2.449
0.612
1.500
0.918
1.000
0.470
OK

Ic =

0.00374

= n2 g / hc1/3

Ie =
Itg =
Check: Ic < Ie < Itg

0.00564
0.00762
OK

= n2 g hc3/{(h+hc)/2}10/3
= 0.0825 dm /{(h+hc)/2}

i
i= 1/
say, 1 /

0.00872
114.7
100

(or more)
(or less)
(or less)

Water depth at scouring sluice gate


Check: h > d

m
m/s
m
m3/s
m
m
m

= (20 d)0.5
= 20 d / g
= {(20 d)3/g2}0.5
= 1.5 hc
> 1.0 m

Bed slope of upstream scouring sluice


i = {h+hc3/(2 h2) -1.5 hc}/L1 + n2 g hc3/{(h+hc)/2}10/3

or,

4 Check velocity at scouring sluice gate in n=0.015 (K=65)


Unit width of scouring sluice
Water depth at scouring sluice gate
Flow area
Wetted perimeter
Hydraulic radius
Hydraulic gradient (= bed slope)

b
h
A
P
R

=
=
=
=
=
R2/3 =
i =
i1/2 =

1.000 m
0.470 m
0.470 m2 = b h
1.940 m = b + 2 h
0.242 m = A / P
0.389
0.01000
0.1000

Roughness coefficient

n =
K =
V =

Velocity
Check: V > Vc

0.015
65
=1/n
2.591 m/s = K R2/3 i1/2
OK