a r t i c l e
i n f o
Article history:
Received 29 August 2012
Revised 16 October 2012
Accepted 5 November 2012
Keywords:
CHP systems
Thermal energy storage
Building energy
Building emissions
a b s t r a c t
A combined heat and power (CHP) system is investigated with and without a thermal energy storage
option for eight different commercial building types located in Chicago, IL. The buildings electrical and
thermal loads are simulated on an hourly basis over one year and a CHP system operating at a constant
base load is modeled. The CHP system alone is compared with a CHP system which incorporates thermal
storage in varying amounts. In each case, the CHP system reduces operational cost, primary energy consumption (PEC), and carbon dioxide emissions (CDE) with respect to the reference case without a CHP
system. For six of the eight buildings, adding thermal storage provides further reductions in operational
cost, PEC, and CDE. More thermal increases these benets. However, the size of the supplemental boiler
required by the building to satisfy the thermal load is not reduced except in the case of the large hotel. In
addition, the sizing of the CHP systems power generation unit is not signicantly affected by the addition
of thermal storage. Buildings which require higher ratios of power to heat will be less likely to benet
from the addition of thermal storage to a CHP system.
2012 Elsevier Ltd. All rights reserved.
Introduction
Combined heat and power (CHP) systems can potentially reduce
operational cost, emissions, and primary energy consumption associated with power production by capturing the waste heat associated with production and using it to provide space heating or hot
water to a building, thereby making better use of the fuel energy
[1]. One major concern for implementing CHP systems is a mismatch between the amount of electricity and heat provided by
the CHP system and the amount of electrical energy and thermal
energy required by the building it serves [2]. Often this is due to a
low power-to-heat ratio (a ratio of the electric load to the thermal
load) demanded by the building [3], so that the excess heat produced by the CHP system may not be useful to the building it serves.
Often, a CHP system operates most efciently at a constant
load; however, the electrical and thermal energy needs of a commercial building are not constant. If the heat demanded by the
building varies over time, this problem may be alleviated when
thermal energy storage (TS) is available. This will allow the system
to capture thermal energy when it is not being used by the building
and then deliver it when the building needs more thermal energy
than the CHP system provides. This can allow the CHP system to
Corresponding author.
E-mail address: mago@me.msstate.edu (P.J. Mago).
2213-1388/$ - see front matter 2012 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.seta.2012.11.001
operate more protably and for longer periods of time [4]. Thermal
energy storage systems may also be integrated with district heating networks [5,6] and used to store energy on a seasonal basis
[7] in order to reduce cost, primary energy, and emissions.
A properly designed TS system will minimize energy losses and
result in reduced energy consumption [8,9], and may result in signicant carbon dioxide emissions (CDE) reduction [4]. Verda and
Colella [9] found that a TS system could signicantly reduce the
size of the additional boiler needed to meet the thermal energy demand of a district heating system in Turin, Italy, with a sufciently
large TS tank (1000 m3 of storage volume).
The economic benet, or perceived potential for cost reduction,
associated with any commercial CHP project is a key factor which
determines whether CHP will be adopted [10]. Bianchi et al. [11]
found in an economic analysis that for residential buildings located
in Italy, a TS system increased the maximum allowable cost for all
CHP systems studied, along with primary energy savings ranging
from 15% to 45%, depending on the particular CHP technology.
The cost analysis presented in this paper only includes cost reductions caused by reduced fuel input to the buildings boiler. A comprehensive analysis of the potential for TS to save money in a
given situation should include the additional capital cost associated
with installing the device and the operation and maintenance costs
associated with it. For a water tank, a commonly used storage material for hot thermal energy storage, operation and maintenance
costs are usually minimal [12].
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
Nomenclature
CDE
CDECHP
CDEref
CFCDE,e
CFCDE,f
CFPEC,e
CFPEC,f
CHP
CHP-TS
CostCHP
Coste
Costf
Costref
Egrid
Epgu
Ereq
Fboiler
Fboiler,ref
Fpgu
HRS
PEC
PECCHP
Building models
Eight commercial building types with varying characteristics
were selected for the investigation using models developed by
the US DOE Building Technologies Program [20], representing typical US buildings constructed after 1980. The DOE developed a series of model buildings based on Commercial Building Energy
Consumption Surveys in order to represent the US commercial
building stock [20]. The building types selected are present
throughout the US and the models vary in terms of size, purpose,
and occupancy, and therefore in terms of their energy requirements. More information about these hypothetical buildings is
provided in Table 1.
The reference building les [21] are provided as input for
Energy Plus [19] and the buildings performance is simulated with
a time step of 15 min. Hawkes and Leach [22] showed that 5 min
time steps for energy demand data were necessary for accurately
analyzing small residential CHP systems, but for the buildings analyzed here, simulations using smaller time steps did not produce
signicantly different results for hourly energy demands. The results of the simulation are used to provide each buildings hourly
demand for electricity and heat over one year. Next, the operational cost, primary energy consumption, and CDE associated with
purchasing electricity from the grid and providing heat with an
auxiliary boiler are computed for the reference case, for the CHP
system, and for the CHP system with a thermal store (CHP-TS).
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
Table 1
Building model basic characteristics by building type [16].
Building type
Area (m2)
Volume (m3)
Occupancya (m2/person)
511
2595
11,345
3804
6871
4014
511
4181
1558
88,863
35,185
11,932
27,484
13,204
2279
25,486
1.4
18.6
[1.5 guests/room, 65% occupancy rate]
4.7
4
[1.5 guests/room, 65% occupancy rate]
18.6
11.6
a
Occupancy is provided for the main area or the most common type of room for a given building type. Exact occupancies used in simulation vary with time/location and
may be found in the Energy Plus input le. See Deru et al. [20, p. 18] for occupancy information.
Rh;CHP 1 otherwise
4b
where Qreq is the thermal energy required by the building. This includes thermal energy for space heating and hot water needs.
The CHP system is assumed to operate at a constant baseload.
This allows the PGU to operate with a high, constant efciency
[23], maximizing its capacity without load-following operation
[10]. Table 2 presents the constant values which are used for the
system parameters in the above equations.
If Epgu does not meet the buildings electricity requirement, Ereq,
then additional electricity is purchased from the grid, Egrid. Some of
the heat produced by the PGU is then captured by the heat recovery system (HRS) and thermal energy, Qrec, is delivered to the
building. If the heat produced exceeds Qreq, then excess heat is produced, Qexcess. If Qrec is less than Qreq, additional heat is provided by
a supplemental boiler, Qboiler.
Q boiler 0 otherwise
F pgu
Epgu
where gpgu is the electric efciency of the PGU. This is normally estimated based on the manufacturers performance data as the ratio of
power generation and rate of fuel consumption.
The heat recovered by the CHP system in an hour is given by [1]:
where n accounts for energy losses before the heat recovery system,
and grec is the thermal efciency of the heat recovery system.
The fraction of the thermal demand that is satised by the CHP
system [1] is given by:
Rh;CHP
Q rec
Q req
if Q rec 6 Q req
4a
Table 2
CHP system parameters.
Parameter
Value
gpgu
0.3
0.95
0.8
grec
5b
Next, the CHP system is investigated with a thermal storage option as shown in Fig. 2. In this situation, when the CHP system produces excess heat, it may be stored in the TS device until the device
reaches its capacity. The capacity of the device is varied in the analysis with respect to the average thermal load of the building under
consideration in order to investigate the effect of different TS device sizes on the potential benets resulting from adding TS to
the CHP system.
gpgu
5a
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
F boiler;ref
Q req
gboiler;ref
where Egrid represents any additional electricity that must be purchased from the grid (Ereq Epgu), Fpgu is the fuel energy consumed
by the PGU, and Fboiler is the fuel energy consumed by the boiler of
the CHP system and it can be calculated as
F boiler
Q boiler
gboiler
if Q storage-old Q rec
Q req
10a
otherwise
10b
11b
Q storage-new Q storage-old
12
Equations (10) through (12) do not take into account any heat
losses associated with the TS device and there are no limitations
placed on the amount of heat which can be transferred in a given
time period. In an actual system, the limitations of the heat
exchangers must be considered, and while a hot thermal storage
tank must be well-insulated [12], thermal dissipation must be taken into account if a TS device is considered for a specic device
serving a given building. Different types of TS will have differing
amounts of thermal losses, and these expressions should be obtained or approximated in order to optimize a specic device in a
specic situation [24].
The amount of heat transferred from TS to the building in a time
step, QTS, is:
Q TS Q storage-old Q storage-new
if Q storage-old Q storage-new
>0
13a
Q TS 0 otherwise
13b
Rh;CHPTS
Q rec Q TS
Q req
if Q rec Q TS 6 Q req
Rh;CHPTS 1 otherwise
14a
14b
Q boiler 0 otherwise
15a
15b
6 TScap
Q storage-new TScap
Q storage-new 0 otherwise
if Q storage-old
11a
16
17
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
where Fboiler is determined according to Eqs. (5) and (9) for CHP and
Eqs. (9) and (15) for CHP-TS.
Finally, the PEC of the CHP system and the PEC of the CHP-TS
system are compared with the PEC of the reference case.
Emissions analysis
The carbon dioxide emissions (CDE) of the reference case are
calculated.
18
where CDEe is the CDE factor for purchased electricity and CDEf is
the CDE factor for natural gas.
Next, the CDE of the CHP system is calculated.
19
where Fboiler is again determined according to Eqs. (5) and (9) for
CHP and Eqs. (9) and (15) for CHP-TS.
Finally, the CDE of the CHP system and the CDE of the CHP-TS
system are compared with the CDE of the reference case.
Results
The thermal and electric requirements, Qreq and Ereq, respectively, need to be known to apply the methodology presented in
Methodology section. These two parameters are determined from
the results of the Energy Plus simulation. They will vary from timestep to timestep and will vary among the different building types.
The total yearly electrical and thermal energy requirements as well
as the power-to-heat ratio for each of the evaluated buildings are
presented in Table 3. In addition, the cost of electricity and natural
gas as well as primary energy and emission conversion factors for
electricity and natural gas have to be known. The following values
were used in this investigation: The cost of electricity and the cost
of natural gas for Chicago are, respectively, $0.0867/kW h [26] and
$8.21/MMBtu ($0.028/kW h) [27] as of November 2011. The conversion factors CFPEC,e and CFPEC,f are 3.546 and 1.092, respectively
[19]. The conversion factors CDEe and CDEf are 0.0007689 ton/
kW h [28] and 0.0001996 ton/kW h [29], respectively.
reduce cost, PEC, and CDE with respect to the reference case.
Therefore, the PGU size was held at 50% of Eave in all cases to provide consistency in the comparison among building types. Table 4
presents the average hourly electrical demand, the PGU size which
provides 50% of this amount of energy over an hour, and the thermal energy which can be recovered from this PGU in one hour given the assumed efciencies in Table 2.
TS and boiler sizing analysis
The CHP and CHP-TS systems were simulated using the PGU
sizes given in Table 4 which were determined to be potentially
benecial by the previous calculations. The size of the TS device
was varied according to the maximum thermal energy required
by the building in one hour, Qmax. TS sizes ranging from 0.25Qmax
to Qmax were simulated, and the cost, PEC, and CDE were calculated. This provides a range of TS sizes over which, for most of
the buildings studied, the cost, PEC, and CDE reductions changed
based on the size of the TS system. The No TS case represents a
CHP system without TS available and is presented for all results
along with the varying TS sizes for reference. Table 5 presents
the storage capacities that were evaluated. If the storage device
was found to provide additional benets in terms of cost, PEC, or
CDE reduction, each value for TScap was examined in order to
determine whether it could reduce the size of the boiler needed
to satisfy the thermal load of the building. In other words, because
the TS device can provide some of the heating load, if the maximum thermal energy required from the boiler is reduced due to
the addition of TS, then the boiler size necessary to meet the buildings thermal needs may become smaller.
Building analysis
Table 3
Yearly energy requirements [15] and power-to-heat ratios by building type.
Table 4
PGU sizing based on average electrical demand of the building.
Building type
Ereq (GJ)
Qreq (GJ)
PHRb
Building type
Eave (MJ)
Qrec (MJ)
1205
42,674
16,049
5708
3771
2748
312
7295
1512
17,681
13,724
4682
2873
1160
138
4877
0.80
2.41
1.17
1.22
1.31
2.37
2.27
1.50
138
4871
1832
652
431
314
36
833
19
675
255
90
60
44
5
115
1213
4309
1628
575
383
132
32
557
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
Table 5
Sizing of thermal store based on maximum thermal demand of the building.
Building type
52.5
172
340
57
232
19
12.5
301
105
344
680
114
464
38
25
602
157.5
516
1020
171
696
57
37.5
903
210
688
1360
228
928
76
50
1204
Fig. 3. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a full service restaurant.
Large hotel
Fig. 7 presents the reductions in cost, PEC, and CDE with respect
to the reference case obtained with a CHP system and CHP-TS systems with varying thermal storage capacities for the large hotel
building. As can be seen in Fig. 5, the CHP-TS system does reduce
cost, PEC, and CDE more than CHP alone. As the size of the TS device increases, these reductions become more favorable. Similar to
the full service restaurant, once TScap is about 75% of Qmax, the
gains resulting from additional thermal storage capacity are very
small. The PHRb of the large hotel is 1.17, larger than that of the
restaurant but much smaller than that of the hospital.
The Rh,CHP and Rh,CHP-TS values are 0.871 and 0.912 (Fig. 5) representing a 4.7% possible increase in the fraction of thermal load
supplied by the CHP system. The required boiler size decreases
when TS is added to the CHP system, from 1361 to 1329 kW h.
The reduction is the same whether TScap is 0.25Qmax or equal to
Qmax. This is only a 2.4% reduction in the overall size of the boiler
required to meet the buildings thermal energy requirement. However, it illustrates that the CHP-TS system is functioning as desired,
by reducing the peak thermal load required from the boiler.
Outpatient
Fig. 8 presents the reductions in cost, PEC, and CDE with respect
to the reference case obtained with a CHP system and CHP-TS
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
Fig. 5. Average Rh values for the fraction of required heat provided over one year by CHP and CHP-TS systems for eight building types.
Fig. 6. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a hospital.
Fig. 7. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a large hotel.
Fig. 8. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for an outpatient building.
10
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
Fig. 9. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a primary school.
Fig. 10. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a small hotel.
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
11
Fig. 11. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a small ofce.
Fig. 12. Variation of Cost, PEC, and CDE from reference case for CHP without TS and CHP-TS with varying TScap for a supermarket.
CDE, and it was shown that a larger increase from Rh,CHP to Rh,CHP-TS indicated greater potential for TS to further reduce cost,
PEC, and CDE. Also, it is important to highlight that for all buildings
the carbon dioxide emissions is the parameter that benets most
from the use of the CHP-TS system, followed by the PEC and operational cost.
Conclusions
This paper presented a methodology to investigate the benets
of a thermal energy storage option combined with a CHP system.
The methodology was applied to eight different commercial building types located in Chicago, IL.
The results of this study indicate which types of commercial
buildings may show benets from CHP-TS systems and which
types are unlikely to benet from the addition of TS. Because any
TS device will require additional capital which is not accounted
for in this analysis, it is desirable that the addition of TS should
provide substantial economic benets in terms of reduced fuel
costs, and reduce or eliminate the requirement for supplemental
heating. Cold climates such as that of Chicago are generally better
for CHP due to the increased heating requirements compared with
warmer climates, but adding TS will not always reduce the need for
a supplemental boiler or signicantly reduce the operating costs,
even if the TS device is large compared with the buildings maximum heating demand. The TS device modeled does not suffer from
thermal losses or limitations on its ability to receive and deliver
heat. When this idealized device does not show the potential for
a cost, emission, or energy-saving benet, a TS device in practice
certainly will not produce this benet; when the idealized device
does show the potential for benet, a real device may not achieve
the benets shown here due to limitations which need further
analysis depending on that particular devices technology.
12
A.D. Smith et al. / Sustainable Energy Technologies and Assessments 1 (2013) 312
References
[1] Mago PJ, Smith A. Evaluation of the potential emissions reductions from the
use of CHP systems in different commercial buildings. Build Environ
2012;53:7482.
[2] Barbieri ES, Melino F, Morini M. Inuence of the thermal energy storage on the
protability of micro-CHP systems for residential building applications. Appl
Energy 2012;97:71422.
[3] Cardona E, Piacentino A, Cardona F. Matching economical, energetic and
environmental benets: an analysis for hybrid CHCP-heat pump systems.
Energy Conv Manage 2006;47:353042.