Buried pipeline construction

services
Technical specification C.1.9

14.09.09

Pipeline Construction Services


C.1.9
Specifications for final documentation
for construction of buried pipelines

Petrom E&P reserves all rights to this document


and will take legal action against anyone who uses or passes it on without authorisation.

Page 1 of 5

Buried pipeline construction

services
Technical specification C.1.9

14.09.09

1. Introduction
For all buried pipeline construction projects performed, the final documentation contains
the originals of all documents listed below.
Details about required format of documents including the number of required copies, as
well as the timing for handover of this final documentation will be specified within the
contract for the specific scope of work.
As specified in the framework agreement, Petrom reserves the right to retain parts of the
remuneration and of the performance guarantee for the construction services of a
specific project until all final documentation has been delivered and approved completely
as requested in contents and requested quality.
2. Specification of required documents for final documentation
Document key
code

Deutsch

English

Romn

Enddokumentation

Documentation

Documentaie

Prf- ,
Schlubescheinigung

Final certificate
(obtained by
independent 3rd
body or authorities)

Certificat final (obinut


de la o companie ter
sau de la autoriti)

HQA 31

Technische Beschreibung

Technical
description - project

Descrierea tehnic
(proiectul)

HEA 03

Konformittserklrung

Declaration of
conformity( with
Romanian laws
given by
construction
company)

Declaraia de
conformitate (conform
legilor din Romnia
dat de compania
constructoare)

HQA 10

R&I Schemata

PID Drawings
(process &

Schiele DPI (diagrama HFB 03


procesului &

Petrom E&P reserves all rights to this document


and will take legal action against anyone who uses or passes it on without authorisation.

Page 2 of 5

Buried pipeline construction

services
Technical specification C.1.9

14.09.09

Document key
code

Deutsch

English

Romn

Enddokumentation

Documentation

Documentaie

instrumentation
diagram)

instrumentaia de
msura i control)

Isometrien mit
zugehrigen Materialstck
und Schweinahtlisten

Isometric drawing
and the belonging
bill of materials and
welding seam list

Schema izometrica i
lista cu materialele ce
trebuie folosite i
lista sudurilor de
efectuat

HFB 02

Verrohrungsplne

Piping drawings (for


piping in facilities
like manifolds)

Schema de aezare a
conductelor (pentru
facilitile conductelor,
cum ar fi claviaturiile)

HFB 04

Maps of the
(1) general survey
(2) pipeline routing,
(3) details (for eg.
Under-/ overcross,
tie-in),
(4) process
automation/ -control,
(5) typicals

Hri cu
supravegherea
general, traseul
conductei, detalii ( de
ex. Subtraversri,
supratraversri,
cuplri) automatizarea/
- controlul procesului,
specificaii

Rohrwanddickenberechnu
ngen

Calculation of the
pipe wall thickness

Calculul grosimii
peretelui conductei

HQA 26

Isolationsbescheinigung

Insulation certificate

Certificatul izolatiei

HQA 39

Umstempelbescheinigung

Material
identification
certificates

Certificatele de
indentificare a
materialelor

HQA 37

Druckprfungbescheinigun Pressure test


g
certificate

Certificatele probei de
presiune

HQA 20

Rohrbuch

Manualul conductei

HQA 33

(1) bersichts-,
(2) Trassen-,
(3) Detail-,
(4) Regel- und
(5) Typenplne

Pipebook

(1) HLA 02
(2) HLD 02
(3) HLD 03
(4) HLD 04
(5) HPD 05

Petrom E&P reserves all rights to this document


and will take legal action against anyone who uses or passes it on without authorisation.

Page 3 of 5

Buried pipeline construction

services
Technical specification C.1.9

14.09.09

Document key
code

Deutsch

English

Romn

Enddokumentation

Documentation

Documentaie

Schweiereinsatzlisten

List of Welders
(approved and
working on this site)

Lista cu sudorii (care


sunt aprobai tipul de
antier respectiv)

HQA 45

Schweianweisungen

WPS welding
procedure
specification
(approved)

WPS specificaia
procedurii de sudur
(aprobat)

HQA 22

Schweierzeurgnisse

Welder certificates

Certificatele sudorilor

HQA 23

Protokolle ber
zerstrungsfreie
Werkstoffprfungen

Report of nondestructive material


tests (performed like
eg. Radiographic
tests)

Buletinele controalelor
nedestructive al
materialului (ex.
controlul radiografic)

HQA 16

Prfbericht ber
zerstrende Prfungen an
Testnhten

Report of
destructive tests for
welding joints

Buletinele controalelor
distructive pentru
legturile de sudur

HQA 24

Abnahmeprfzeugnisse

Acceptance
certificates

Certificate de recepie

HQA 02

The document key code specified shall be used for communication, table of contents
and filing of the above documents required for final documentation. They are
standardized within Petrom and OMV group and can be used to denominate the
documents only by their standard number.
3. Contact person for documentation questions
In case of questions about the contents or details of creating the final documentation,
the QA/QC-department of Petrom E&P will be able to give further information.
Please contact your Petrom site supervisor for further details and contact information.

Petrom E&P reserves all rights to this document


and will take legal action against anyone who uses or passes it on without authorisation.

Page 4 of 5

Buried pipeline construction

services
Technical specification C.1.9

14.09.09

4. Change list
Rev

Date

Type of change

Revised by

Checked by

Released by

Petrom E&P reserves all rights to this document


and will take legal action against anyone who uses or passes it on without authorisation.

Page 5 of 5