Contract
Colin Smyth MRICS MBA
Gary Bogle BSc (Hons) LLM MRICS FCIArb
www.ulster.ac.uk/ceni
Resolving Disputes
Company and Project Performance Measurement
www.ulster.ac.uk/ceni
General Procurement
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Adjudication Agreement
Collateral Warranties
Construction Management
Framework Agreements
Partnering Charter
Generic Contracts
Pre-Construction Services
Agreement
www.ulster.ac.uk/ceni
SBC/Q - 2005
SBC/Q
Appropriate for major works designed and/or detailed by or
on behalf of the Employer. The contract is based on
drawings and bills of quantities to define the quantity and
quality of the works
Where a Contract Administrator and Quantity Surveyor have
roles to play in the administration of the conditions
Variants:
Where the contractor is to design discrete parts of the work
(Contractors Designed Portion)
Where the work is to be carried out in sections
By both private and local authorities
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Section 8: Termination
e.g. Meaning of insolvency, reinstatement and Corruption
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
NEC 3 - Background
Catalyst for NEC:
Sir Michael Lathams industry report
Constructing the Team, 1994
www.ulster.ac.uk/ceni
NEC 3 - Background
Latham
www.ulster.ac.uk/ceni
NEC 3 - Background
Latham
Clients
Well informed know what they want & take decisive
steps to achieve it
Knowledgeable but not necessarily modern in their
approach
Others are feeling their way under new administrative
arrangements
Some know nothing & need extensive help & guidance
for formulate their wishes then match them to the
available budget
www.ulster.ac.uk/ceni
NEC 3 - Background
Latham
Client Objectives
VFM
Pleasing to look at
Free from defects on completion
Delivered on time
Fit for the purpose
Supported by worthwhile guarantees
Reasonable running costs
Satisfactory durability
www.ulster.ac.uk/ceni
NEC 3 - Background
NEC 3 - Background
NEC 3 - Background
Constructing the Team
Taking all reasonable steps to avoid changes to preplanned works information. But, where variations
occur, they should be priced in advance, with
provision for independent adjudication if agreement
cannot be reached.
Express provision for assessing interim payments by
methods other than monthly valuation i.e. milestones,
activity schedules or payment schedules. Such
arrangements must also be reflected in the related
subcontract documentation. The eventual aim should
be to phase out the traditional system of monthly
measurement or remeasurement but meanwhile
provision should still be made for it.
www.ulster.ac.uk/ceni
NEC 3 - Background
Constructing the Team
Clearly setting out the period within which interim
payments must be made to all participants in the
process, failing which they will have an automatic
right to compensation, involving payment of interest at
a sufficiently heavy rate to deter slow payment.
Providing for secure trust fund routes of payment.
While taking all possible steps to avoid conflict on
site, providing for speedy dispute resolution if any
conflict arises by a pre-determined impartial
adjudicator/referee/expert.
Providing for incentives for exceptional performance.
www.ulster.ac.uk/ceni
NEC 3 - Background
Constructing the Team
Making provision where appropriate for advance
mobilisation payments (if necessary, bonded) to
contractors and subcontractors, including in respect
of off-site prefabricated materials provided by part of
the construction team.
www.ulster.ac.uk/ceni
NEC 3 - Background
Emergence of NEC:
Client Dissatisfaction
Questioned if existing standard forms adequately
served the best interest of all parties
NEC 3 - Background
www.ulster.ac.uk/ceni
NEC 3 - Background
www.ulster.ac.uk/ceni
Improving the
Project Process
Targets for
Improvement
Capital cost
-10%
Construction
time
Predictability
-10%
the
supply chain
-20%
Production of
Defects
Accidents
components
Productivity
+10%
+10%
Committed leadership
Product
development
Partnering
Quality driven
agenda
Commitment to people
Project
implementation
+20%
-20%
Improvement
www.ulster.ac.uk/ceni
Performance
An industry wide group developed a set of
simple headline Key performance Indicators
(KPIs) based on the 7 Rethinking Construction
targets but with the addition of Client
Satisfaction measures:
Product
Service
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Improving the
Project Process
Product
development
Quality driven
agenda
Commitment to people
implementation
Targets for
Improvement
Partnering
the
supply chain
Production of
components
Respect for
Sustainability
People
Construction cost
Construction time
Predictability (cost)
Predictability (time)
Client Satisfaction - P
Client Satisfaction - S
Defects
Profitability
Productivity
Safety
5-6-10 Model
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Demonstration Projects
These provide examples of:
Off-site fabrication
Standardisation
Use of new technology
Sustainability
Respect for people activities
Partnering
Supply chain integration
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
NEC 3 - Background
Difference in NEC3 and other standard forms
of contract:
3 clear objectives:
Flexibility
Clarity and simplicity
Stimulus to good management
Cultural change
Assessment of change
Trust and cooperation
Collaboration
www.ulster.ac.uk/ceni
NEC 3 - Background
3 clear objectives
Flexibility
Clarity and simplicity
Stimulus to good management
www.ulster.ac.uk/ceni
NEC 3 - Background
Objective 1- Flexibility:
Multi-disciplinary can be used by any
discipline in the industry
Design can be used for Employers design
or Contractors design, or partial design
Pricing 6 main options ranging from fixed
price to cost reimbursement
Applicable worldwide on a variety of
projects
www.ulster.ac.uk/ceni
NEC 3 - Background
Objective 2 Clarity and simplicity:
Plain English which avoids excessive use of legal jargon
Simple structure:
short sentences,
same format,
no cross referencing,
no reference to the Law
Procedures are not open ended or conflicting
www.ulster.ac.uk/ceni
NEC 3 - Background
Objective 3 Stimulus to good management:
Encourages collaboration and forward planning
Clear allocation of responsibilities
Early warning procedure
Detailed procedure for dealing with changes
Programming facilities that is used in joint decisionmaking by the contractor and project manager
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
18 Secondary Options
www.ulster.ac.uk/ceni
Core Clauses
Structure of ECC:
9 Mandatory Core Clauses:
1 General
www.ulster.ac.uk/ceni
Main Options
Structure of ECC:
Options:
A Priced Contract with activity Schedule
B Priced Contract with bill of quantities
C Target Contract with activity schedule
D Target Contract with bill of quantities
E Cost reimbursement Contract
F Management Contract
www.ulster.ac.uk/ceni
Secondary Options
Secondary Option Clauses:
X3 multiple currencies
X4 parent company guarantee
X5 sectional completion
X6 bonus for early completion
www.ulster.ac.uk/ceni
Secondary Options
www.ulster.ac.uk/ceni
Secondary Options
Questions ?
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Structure
No main options
No secondary options
Additional conditions can be inserted on page 3
Price list allows for a number of pricing arrangements
(lump sum or rates)
www.ulster.ac.uk/ceni
Contract Data
2.
Clauses
3.
Index
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Co-ordinate Works
Assess CEs
www.ulster.ac.uk/ceni
Early Warning
www.ulster.ac.uk/ceni
Early Warnings
Cl 16.1 Contractor and Employer give early warnings
by notifying the other as soon as either becomes aware
of any matter which could
Increase Prices
Delay Completion
Impair the works
www.ulster.ac.uk/ceni
Compensation Events
www.ulster.ac.uk/ceni
Cl 60 Cl 63
Cl 60 Reduced number of CEs
14 in total
Provisions for dealing with change are largely
same as ECC, but Contractor only notifies
change!
Cl 61 Notifying compensation events
Cl 62 Quotations
Cl 63 Assessing
www.ulster.ac.uk/ceni
He believes its a CE
Employer has not notified him
8 week long stop then NO COMPENSATION
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Accepting; or
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Questions ?
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Type of Programme
Who Plans?
Overall Project
Design
Designer: Architect/
Engineer
Tender
Pre-tender programme
Tendering Contractors
Pre-contract
Master programme
Target programme
Subcontractors
programme Procurement
programme
Contract
Stage programme
Short-term programme
As-built programme
Microsoft Project
Project Management Software
Helps with assigning resources and tasks to a given
project
Assists in monitoring budgets, production progress and
workloads
Can help companies maximise the use of physical and
human resources on numerous production projects
www.ulster.ac.uk/ceni
Microsoft Project
Entering Production Tasks:
The production of buildings can be broken down into a
series of tasks that must be carried out to achieve the
overall result
A task is an activity that requires a period of time or the
input of a physical or human resource, for example:
Concrete and adhesives need a certain amount of
time to cure
Pouring concrete or applying adhesives need human
input before they can cure
www.ulster.ac.uk/ceni
Deleting tasks
Deleting tasks
Inserting tasks
Inserting tasks
Applying milestones
Assigning
a
relationshi
p between
tasks can
be done in
threes
ways.
Firstly, when
tasks have
been selected
use the link and
unlink
commands
under the Edit
menu,
Secondly, when
tasks have
been selected
use the link and
unlink
shortcuts on
the Standard
menu toolbar.
TASK 1
TASK 2
TASK 2
Series tasks
Parallel tasks
Parallel relationships
The task
information box
can be accessed
by double clicking
on the task or
clicking on the
Task Information
shortcut on the
standard toolbar.
The predecessors
tab is used to
change tasks from
running in series
(or one-after-theother) to parallel.
Note that tasks 3
and 4 are now
parallel tasks that
can be carried out
at the same time.
Task 4 through 9
continue in series
with this parallel
pair (task 2 and 3).
Network diagram
Questions ?
www.ulster.ac.uk/ceni
Risk Management
www.ulster.ac.uk/ceni
Application of RM in Construction
RM Application stages
Initial appraisal
Outline or sketch
design
Detailed design
Contract strategy
Construction
www.ulster.ac.uk/ceni
Potential for
Risk Management
Risk Identification
Risk Assessment /
Risk Management Framework
Classification
Risk Analysis / Evaluation Risk Identification
Risk Classification
Risk Response / Control
Risk Analysis
Risk Response
www.ulster.ac.uk/ceni
Activities
Risk
Results
Decisions lead to activities which may differ from
expectations
Uncertainties are the cause of differences
Information allows to foresee results
Helps the decision maker
Example: deep basement construction
www.ulster.ac.uk/ceni
Nature of Risk
Risks occur as a result of poor prediction?
Measured by chance or probability of happening
3 Attributes of risk
Risk factor - Range of outcomes
Optimistic outcome, pessimistic outcome, most likely outcome
Only one will actually happen
Individual consequences
Consequence of each outcome
OO Profit, PO Loss
Probability
Assess the probability of each of the outcomes occurring
www.ulster.ac.uk/ceni
Brainstorming
Team based: identify potential risks
Creative process: generate ideas, no criticism
List of large number of potential risks
Group output better than individual: sense of
involvement
Tree diagrams
Traces: causes, origins and consequences of risks
Multi-level analysis, graphical
Uses probability values for each risk
www.ulster.ac.uk/ceni
Risk Registers
List of pre-identified typical risks
Developed through consultation
example
www.ulster.ac.uk/ceni
113
114
Risk
Sources
Source
Event
Effect
Example:
115
Risk Analysis
Risk Analysis
Process
117
www.ulster.ac.uk/ceni
Example of Analysis
Likelihood of damage to adjoining buildings as a result of pile driving
Risk Measurement
Involves finding what is more risky
Sensitivity analysis
Simulation technique (Monte-Carlo simulation)
Scenario analysis
Correlation analysis
www.ulster.ac.uk/ceni
Probability Analysis
Scenario:
Estimate: need for connection to gas main
Full survey not done, hence, uncertainty as to the
exact condition of the gas main connection costs
Typical cost of new gas main 2,500
Highly competitive: many sub contractors looking
for work
Fixed price job
Option
A
B
C
Price
Probability
Probable
Cost
Some
modification
No modification
5000
0.50
2500
2000
0.30
600
Substantial
modification
Risk free
estimate
15000 0.20
3000
6100
123
Risk Response
Risk Response
Risk Retention
Risk Absorption
www.ulster.ac.uk/ceni
Risk Reduction
Risk Transfer
Risk Avoidance
Retention
Not all can be transferred, not economical to do so
Consider risk reward: insurance - limited excess
provision
Reduction
Spread of risks to other parties
Sub contractors, work packages
Methods:
Education and training (staff training)
Physical Protection (e.g. sprinkler system, protective gear)
Checking & monitoring (QA)
www.ulster.ac.uk/ceni
Transfer
Reduce the burden, not the possibility
Insurance: professional indemnity, all risk
Retention to cover residual risks
1-5% of contract sum
Performance bond
Avoidance
Refusing to accept risks (non contracting)
Rescind the contract for fundamental breach
Questions ?
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Cashflow Forecast
Cash flows for the company are usually
prepared on a contract by contract basis
and accumulated for the company as a whole
so as to give a complete picture of what is
happening
Expenditure Forecasting
www.ulster.ac.uk/ceni
Questions ?
www.ulster.ac.uk/ceni
Dispute Resolution
www.ulster.ac.uk/ceni
Dispute Resolution
Dispute Resolution:
Litigation
Arbitration ?
Alternative Dispute Resolution
Civil Procedure Rules 1998 the courts are to actively
manage the process by encouraging the parties to use an
alternative dispute resolution procedure if the courts
consider that appropriate and facilitating the use of such
procedure r 1.4 (2) (e)
www.ulster.ac.uk/ceni
Dispute Resolution
Alternative Dispute Resolution:
Negotiation
Mediation
Conciliation
Med-Arb
Mini Trial
Expert Determination
Adjudication
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
JCT Provisions
There are 4 methods of dispute resolution:
1. Mediation
2. Arbitration
3. Adjudication
4. Litigation
www.ulster.ac.uk/ceni
JCT Provisions
Article 7: Adjudication
www.ulster.ac.uk/ceni
JCT Provisions
Article 8: Arbitration
Where Article 8 applies, and subject to Article 7 any
dispute or difference between the parties of any kind
whatsoever arising out of or in connection with this
Contract, whether before, during the progress or after the
completion of abandonment of the Works or after the
termination of the contractors employment, shall be
referred to arbitration in accordance with clauses 9.3 to 9.8
and the JCT 2005 Construction Industry Model Arbitration
Rules (CIMAR)
www.ulster.ac.uk/ceni
JCT Provisions
Article 9: Legal Proceedings
www.ulster.ac.uk/ceni
JCT Provisions
Clause 9.1 Mediation:
Parties have the right to resolve dispute via Mediation they are not obligated to do so
www.ulster.ac.uk/ceni
JCT Provisions
Clause 9.2
Adjudication
JCT Provisions
Clause 9.3 Conduct of Arbitration:
www.ulster.ac.uk/ceni
JCT Provisions
Clause 9.5 Powers of an Arbitrator:
www.ulster.ac.uk/ceni
NEC Provisions
Clauses W1 & W2:
www.ulster.ac.uk/ceni
NEC Provisions
Clause W1:
www.ulster.ac.uk/ceni
NEC Provisions
Clause W2:
www.ulster.ac.uk/ceni
NEC Provisions
Review by the tribunal
www.ulster.ac.uk/ceni
NEC Provisions
Review by the tribunal
www.ulster.ac.uk/ceni
Questions ?
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni
Questions ?
www.ulster.ac.uk/ceni
www.ulster.ac.uk/ceni