COURSE OUTLINE

Department&Faculty:
DepartmentofQuantitySurveying
FacultyofBuiltEnvironment

CourseCode:SBEQ2312
CourseName:CostEstimating

TotalContactHours:32
Lecturer

Page:1of5

Semester:1
AcademicSession:2015/2016

RoomNo.

: Dr.FaraDivaMustapa
: B11126

TelephoneNo.

: 075537314

Email

: faradiva@utm.my/faradiva.m@gmail.com

Synopsis

: The aim of this course is to develop students knowledge and understanding

on the principles, techniques and systematic procedures of preparing cost


estimates and building up rates. This course is designed to provide students
with the knowledge and skills in preparing cost estimates for simple
buildings works based on the various methods and techniques and to build up
rates. By identifying the factors that influence the cost, the students will be
able to determine the appropriate cost data and its sources to be applied in
the estimates while enhancing the accuracy and reliability of these methods
and techniques. The course also provides the platform to develop students
communication skills, the ability to work effectively as a team member to
achieve mutual objective, and to seek information from various sources.

LEARNINGOUTCOMES
Bytheendofthecourse,studentsshouldbeableto:
No. CourseLearningOutcome

Programme
Outcome
PO1,P02

Identify appropriate cost data for estimating


construction costs based on different methods
and techniques.

Prepare build-up rates for the various items of


works.

PO3

Prepare accurate and reliable cost estimates


using different methods and techniques.

PO3

Apply appropriate computer skills for cost


estimating.
Seek information from various sources.

PO2

PO7

Taxonomies& Assessment
SoftSkills
Methods
C2,P2,A2
Test,
Assignment,
FinalExam
C3,P3,A2,
Assignment,
CTPS3
FinalExam
C4,P3,A2
Assignment,
CTPS3
FinalExam
C3,P3,A2
Assignment
A3,LL2

Assignment

Preparedby:
Name:Dr.FaraDivaMustapa
Signature:

Certifiedby:
Name:Assoc.Prof.Dr.RazaliAdulHamid
Signature:

Date:3rdSeptember2015

Date:3rdSeptember2015

COURSE OUTLINE
Department&Faculty:
DepartmentofQuantitySurveying
FacultyofBuiltEnvironment
CourseCode:SBEQ2312
CourseName:CostEstimating

TotalContactHours:32

Page:2of5

Semester:1
AcademicSession:2015/2016

STUDENTLEARNINGTIME(SLT)
TeachingandLearningActivities

StudentLearningTime(hours)

1. FacetoFaceLearning
a. LecturerCenteredLearning
i. Lecture
b. StudentCenteredLearning(SCL)

28

i. Tutorials

ii. StudentcenteredlearningactivitiesActive
Learning,ProjectBasedLearning

2. SelfDirectedLearning
a. Nonfacetofacelearningorstudentcenteredlearning
(SCL)suchasmanual,assignment,module,eLearning,etc.

b. Revision

28

c. AssessmentPreparations

10

3. FormalAssessment
a. ContinuousAssessment

b. FinalExam

Total(SLT)

80

TEACHINGMETHODOLOGY
LectureandDiscussion,Tutorial,IndependentStudyandGroupProject

WEEKLYSCHEDULE
Week1

IntroductiontoCostEstimating
Concept,purposeandimportanceofestimatingcostofbuilding/construction
projectsandworks
Componentsofprojectcost;landcost,buildingcost,infrastructurecost,
financecost,legalcostandadministrativecost.
ComponentsofbuildingcostPreliminaries,substructure,superstructure,
finishes,fittings&furnishing,engineeringservices,drainage,externalworks,
primecostsum&provisionalsum

COURSE OUTLINE
Department&Faculty:
DepartmentofQuantitySurveying
FacultyofBuiltEnvironment
CourseCode:SBEQ2312
CourseName:CostEstimating

TotalContactHours:32

Page:3of5

Semester:1
AcademicSession:2015/2016

Week2

EstimatingMethods&Techniques
Generalestimatingprocess
Generalconsiderationsinselectionofappropriaterates.

Week3

Week4

Week5

EstimatingMethods&Techniques
Singlepricerateestimatingmethodsandapplication(unit,superficialarea,
cube,storeyenclosureetc.)
Approximatequantitiesmethodsandapplications.

EstimatingMethods&Techniques
Tutorialsonpreparationofestimatesbasedonseveralestimatingtechniques

EstimatingMethods&Techniques
Tutorialsonpreparationofestimatesbasedonapproximatequantities

Week6

TEST

Week7

Week8

Week9

Week10

BuildupRates&Pricing
Ratesanditsconstituents:labour&materials
Ratesanditsconstituents:plants&equipments,overheads&profit

BuildupRates&Pricing
Buildupratesforpreliminaryworks&WBLFF

BuildupRates&Pricing
Buildupratesforbuildingelements(Structure&Walls)

SEMESTERBREAK(814November2015)

Week11

Week12

Week13

Week14

BuildupRates&Pricing
Buildupratesforbuildingelements(RoofStructure&Finishes)

BuildupRates&Pricing
Buildupratesforbuildingelements(Doors&Windows)

BuildupRates&Pricing
Buildupratesforbuildingelements(FinishesWall&Floor)
BuildupRates&Pricing
Buildupratesforbuildingelements(ElectricalWorks&PlumbingWorks)

COURSE OUTLINE
Department&Faculty:
DepartmentofQuantitySurveying
FacultyofBuiltEnvironment
CourseCode:SBEQ2312
CourseName:CostEstimating

TotalContactHours:32
Week15

Week16

Week1718

Page:4of5

Semester:1
AcademicSession:2015/2016

ITapplicationinConstruction anditsusageinestimatingprocess
AnalysingTenderrates,contractrates,prorata/analogousrates,new/agreed
rates&Dayworkrates

CourseworkPresentation

RevisionWeekandFinalExamination

REFERENCES:
a) Abdullah, A (2005) Anggaran Kos Kerja Bangunan (2nd Edition), Pearson-Prentice Hall, Petaling Jaya
b) Ashworth, A (2004) Cost Studies of Buildings (4th Edition), Pearson Education Limited, Essex
c) Brook, M. (2004) Estimating and Tendering for Construction Work (3rd Edition).
d) Buchan, R. D. , Fleming, F. W. and Grant, F. E. K. (2006) Estimating for Builders (2nd Edition),
Butterworths-Heinemann, London
e) Bathurst, P.E & Butler, D.A (1973), Building Cost Control Techniques and Economics, Heinemann,
London
f)

Chartered Institute of Building (2009) Code of Estimating Practice (6th edition).

g) Geddes, S. (2006) Estimating for Building and Civil engineering Works (9th edition), Butterworths,
London: Wiley-Blackwell
h) Peurifoy, R.L & Oberlender, G.D, (2004) Estimating Consturction Costs (5th Edition), McGraw-Hill,
Singapore
i)

Seeley, I.H (1997) Quantity Surveying Practice (2nd Edition), Macmillan.

j)

Singh, G & Singh J (2010), Estimating Costing and Valuation, Standard Publishers Distributors, New
Delhi

k) Smith, R. C. (2013) Estimating and Tendering for Building Works. Routledge, London

COURSE OUTLINE
Department&Faculty:
DepartmentofQuantitySurveying
FacultyofBuiltEnvironment
CourseCode:SBEQ2312
CourseName:CostEstimating

TotalContactHours:32

Page:5of5

Semester:1
AcademicSession:2015/2016

GRADING:

Method

Number

%Each %Total

Week

Assignment

25

Presentation

15

MidSemesterTest

20

20

FinalExamination

50

50

17

100

Total