Anda di halaman 1dari 4

TATA PROJECTS LTD

SBU-Utility Services
STANDARD PROCEDURE FOR
SURFACE PREPARATION AND PAINTING
Procedure No.: TPL /US/QMD/ 002
Rev No. & Date: 0 & 20.11.2014

1.0

SCOPE

This Procedure covers the application and testing requirements of


Surface Preparation and Painting on water Purification Plant Structural
Steel Works.
2.0

STANDARD AND SPECIFICATIONS

All works covered by this Procedure shall be carried out in accordance


with the relevant sections of the following documents.
- ISO 8501-1
- ISO 12944-5
- Paint Product Data Sheets
- Approved FQP & Drawings
- Customer Specifications
3.0

ENVIRONMENTAL CONDITIONS
Unless otherwise specified by the Customer / Painting Manufacturer, no
surface preparation or application of top coating shall take place under
the following conditions.
Air temperature is below 10C
Surface temperature is below 5C
Surface temperature is 3C or less than the Dew Point
Relative humidity is 85% or above
Wet or Damp atmosphere
Wet Surfaces
Rain, mist or fog is present
Wind speed above 25 kmph
Atmosphere contaminated by dirt, dust, oil, product or any
pollutant

3.0 PROCEDURE
3.1 SURFACE CLEANING
3.1.1
Mill scale, rust, rust scale and foreign matter shall be removed
fully to ensure that a clean and dry surface is obtained. Unless
otherwise specified, surface preparation shall be done as per Customer
Specification / Approved Drawing.
3.1.2
The minimum acceptable standard for manual or hand tool
cleaning shall be St. 2 or equivalent, in case of mechanical or power
tool cleaning it shall be St. 3 or equivalent.
3.1.3
All other contaminates, oil, grease etc. shall be removed by use
of an aromatic solvent, prior to surface cleaning.
3.1.4
If painting is to be carried out during the rainy days in case of
exigency of projects schedule, it shall be carried out with prior
permission of Customer.
Page 1 of 4

TATA PROJECTS LTD


SBU-Utility Services
STANDARD PROCEDURE FOR
SURFACE PREPARATION AND PAINTING
Procedure No.: TPL /US/QMD/ 002
Rev No. & Date: 0 & 20.11.2014

3.1.5 Surface preparation by Manual / Hand Cleaning. In case of heavy rust


Power tool cleaning shall be done by mechanical striking tools, chipping
hammers, grinding wheels or rotating steel wire brushes. On completion
of cleaning, the detached rust mill scale etc. Shall be removed by clean
rags and thoroughly dried with compressed air jet before application of
paint.
3.2

Coating Procedure and Application

3.2.1 The surfaces shall be cleaned and Primer / first coat of paint shall be
applied within 4 hours of surface preparation.
3.2.2 Application of paint using air gun will not be carried out under the
following conditions.
a)

When the ambient temperature is below 50 C.

b)

When the ambient temperature is above 400 C.

c)
During adverse weather condition of rain, fog, dust, storm and
when humidity
exceeds 85%.
3.2.3 The first coat of primer must be applied by airless spray / as
recommended brand International (Akzonobel), Intergard 251- Grey (KGA905) + Intergard 251 (KGA-905) on (Agitate Base (Part A) + Curing Agent
(Part B)) dry surface. Equipment/spray gun cleaned by Thinner-GTA 220.
3.2.4 The first coat (Primer) Dry Film Thickness (DFT) will be of 50 microns.
3.2.5 The final coat of paint must be applied by airless spray / as
recommended brand International (Akzonobel), Part-A: Interthane 990French Blue (PHA-046) + Part-B : Interthane 990 (PHA-046) on dry
surface. Equipment/spray gun cleaned by Thinner-GTA 773.
Mixing Ratio:
Primer Coat
Final Coat

: 4 (Part A): 1 (Part B) Thinner as required


: 6 (Part A): 1 (Part B) Thinner as required

3.2.6 The final coat Dry Film Thickness (DFT) will be of 50 microns. Primer /
paint will be applied in uniform thickness. Painting works will be done on
daytime only.
3.2.7 The remaining paint in the open container will not be used if signs of
polarization are noticed.
3.2.8 DFT will be checked using calibrated Elcometer after each coat of
primer / paint as per Customer Spec.
Page 2 of 4

TATA PROJECTS LTD


SBU-Utility Services
STANDARD PROCEDURE FOR
SURFACE PREPARATION AND PAINTING
Procedure No.: TPL /US/QMD/ 002
Rev No. & Date: 0 & 20.11.2014

3.2.9 Each Coat must be dried for the time recommended by the Paint
Manufacturer for application succeeding Coat.
3.3 Drying of coated surfaces
1.1.1
No coat shall be applied until the preceding coat has dried. The
material shall be considered dry for re-coating when another coat can
be applied without the development of any film irregularities such as
lifting or loss of adhesion of undercoats. Drying time of the applied
coat should not exceed maximum specified for it as a first coat; if it
exceeds the paint material has possibly deteriorated or mixing is faulty.
1.1.2
No paint shall be force dried under conditions which will cause
checking, wrinkling, blistering formation of pores, or detrimentally
affect the conditions of the paint.
1.1.3
Paint shall be protected from rain, condensation, contamination,
snow and freezing until dry to the fullest extent practicable.
1.2

Repair of damaged paint surface

1.2.1
Where paint has been damaged in handling and in
transportation, the repair of damaged coating of pre-erection /
fabrication and shop primer shall be done as given in Customer
Specification
4.0 Inspection, Testing and Acceptance
4.1 FQE shall check the surface preparation, DFT as per Customer
Specification / approved Drawing.
4.2 All the prepared surfaces shall be inspected and cleared by FQE as per
approved Customer Specification / FQP before applying the Primer.
4.3 Each coat shall be examined for signs of runs, roughness, patches, sags,
pinholes etc and if such short comings occur, the coats shall be repaired
and permitted to dry before the next coat is applied.
4.4 Field Quality Engineer shall inspect each coat for defects and check Dry
Film Thickness (DFT) to ensure compliance to the specified requirements,
before taking up application of subsequent coat.
4.5 The individual DFT measured values between 80 to 100% of the nominal
DFT, are acceptable, provided the overall average (mean) is equal to or
greater than the nominal DFT.
5.0 SAFETY

Page 3 of 4

TATA PROJECTS LTD


SBU-Utility Services
STANDARD PROCEDURE FOR
SURFACE PREPARATION AND PAINTING
Procedure No.: TPL /US/QMD/ 002
Rev No. & Date: 0 & 20.11.2014

5.1

Proper masks will be used during cleaning and painting to prevent


inhaling of dust particles and injurious chemicals. The paint
recommended for spraying by the manufacturer only will be used for
spray painting.
5.2 During painting all hose connections will be checked for adequacy of
the clamps and for proper tightness.
5.3 Use of thinners will be avoided unless it is necessary for proper
application.
6.0

Documentation
Surface Preparation & Painting reports shall be documented either Log
book or any approved format.

Page 4 of 4

Anda mungkin juga menyukai