ES-1 Introduction
The National Geospatial-Intelligence Agency (NGA) is investigating sites for the construction and operation
of the Next NGA West Campus in the greater St. Louis metropolitan area. This effort is required to replace
mission critical facilities at the current St. Louis facility (South 2nd Street facility), which have exceeded their
service life and can no longer support the technology changes required for the NGA mission.
The Kansas City District of the U.S. Army Corps of Engineers (USACE) has developed the enclosed
environmental impact statement (EIS) in accordance with the National Environmental Policy Act of 1969
(NEPA) to evaluate the social and environmental impacts associated with the construction and operation of
the Next NGA West Campus. NGA is the proponent of this action and the U.S. Air Force (USAF) is a
cooperating agency under NEPA because the USAF may be the ultimate property owner of the Next NGA
West Campus. The Federal Aviation Administration (FAA) is a coordinating agency on this action because it
participated in the purchase of the St. Clair County Site and has associated grant assurance obligations. The
FAA is also acting as the airspace authority for this EIS.
NGA will decide on a site for the construction and operation of the Next NGA West Campus. NGA will
develop the final decision on site selection after gathering information from agencies, the public, and others
through the NEPA process and by performing the environmental impact analysis shown in this EIS. NGA will
consider the information gathered during the EIS, along with other critical factors such as its ability to
perform its mission, maintain a secure environment, and meet the construction schedule. The final selection
criteria and decision will be documented in the Record of Decision (ROD), which will be distributed after
publication of the Final EIS (FEIS).
The scope of this EIS includes the potential environmental impacts caused by the proposed construction and
operation of the Next NGA West Campus in the St. Louis metropolitan area. The intent of the EIS is to
inform the NGA decision makers of the potential project impacts through a complete and objective analysis of
the alternatives. Four site alternatives that would meet the purpose and need of the project, as well as a No
Action Alternative, are considered in the analysis.
If NGA moves from its existing location, the current property owner, the USAF, in conjunction with the NGA
and General Services Administration, will be responsible for addressing the future use of the vacated South
2nd Street facilities. Insufficient information is available to discuss possible future uses of the South 2nd Street
facilities at this time; therefore, use of these facilities after NGA vacates is not part of this EIS. The USAF will
prepare the necessary NEPA documentation and conduct the National Historic Preservation Act Section 106
consultation for the future use of the South 2nd Street facilities when potential alternative uses have been
identified.
ES093014083520ATL
ES-1
EXECUTIVESUMMARY
The purpose of Next NGA West Campus is to enhance current and future missions, improve resiliency, and
resolve security challenges associated with the South 2nd Street facilities. Challenges associated with the
South 2nd Street facilities include the proximity to floodplains and incompatible adjacent industrial activities,
as well as the age and physical setting of the existing buildings, which limit NGAs ability to economically
renovate the facilities to meet current facility standards. In addition, the South 2nd Street facilities cannot be
made to meet post-9/11 requirements for protection of the workforce and mission.
ES-2.2 Need
NGA needs a new campus capable of supporting current and future mission requirements at a location that
complies with established standards for such facilities. Construction and operation of the campus needs to
meet the following site location and facility requirements:
1. Allows for continuity and resiliency for existing and future NGA operations
2. Provides purpose-built facilities that are safe, secure, flexible, and efficient
3. Is conducive to recruiting and retaining top-quality employees
4. Stays within anticipated funding limits for construction, operation, and maintenance
5. Supports future changes to mission requirements
6. Provides necessary utilities, telecommunication, and transportation infrastructure
7. Contains a boundary that is a usable shape for necessary buildings and infrastructure and is outside a
100-year floodplain
8. Provides physical security and force protection with appropriate setbacks from adjacent roads,
railroads, and property boundaries
9. Provides potential to use topography and landscape to enhance security
10. Site is available for acquisition and construction in early 2017
11. Meets or exceeds current building standards and codes, particularly those related to the design,
detailing, and construction of structural and non-structural components, to resist the effects of seismic
and other natural or human-made events
ES-2
ES093014083520ATL
EXECUTIVESUMMARY
ES093014083520ATL
ES-3
Fenton
UNCLASSIFIED
Prospective
Site Locations
2nd Street
Mehlville
D
D
UNC
UNCLASSIFIED
CLA
LAS
L
AS
A
SSI
SIFIED
SIF
ED
D
ES-4
Arnold
UNCLASSIFIED
Figure ES-1
Proposed Site Locations
EXECUTIVESUMMARY
ES-5
EXECUTIVESUMMARY
South 2nd Street facilities for NGA personnel and in community centers near each of the alternative sites for
the public. A detailed summary of the scoping meetings are presented in Appendix 1B NGA EIS Scoping
Report (Vector, 2015), and a full list of comments received along with government responses is provided in
Appendix 1C.
ES093014083520ATL
EXECUTIVESUMMARY
and natural environments. Direct effects are caused by the action and occur at the same time and place,
whereas indirect effects are caused by the action, reasonably foreseeable, and occur later in time. Cumulative
impacts result from the incremental impact of the action when added to other past, present, and reasonably
foreseeable actions, which may be undertaken by other private or public entities. Fourteen natural and human
resource areas are analyzed in the EIS.
ES093014083520ATL
ES-7
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Socioeconomics
Direct/Indirect
Benefits
Direct/Indirect
Impacts
Cumulative Impacts
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Environmental
Protection Measures
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Direct/Indirect
Impacts
Cumulative Impacts
Environmental
Protection Measures
ES093014083520ATL
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
ES-9
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Direct/Indirect
Impacts
Not applicable
Cumulative
Not applicable
No cumulative impacts
No cumulative impacts
No cumulative impacts
Environmental
Protection Measures
Not applicable
Cumulative Impacts
No cumulative impacts
Environmental
Protection Measures
Not applicable
ES-10
ES093014083520ATL
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Noise
Direct/Indirect
Impacts
Cumulative Impacts
Not applicable
Minor to moderate, negative, and shortterm cumulative impacts for constructionrelated noise
Minor to moderate, negative, and shortterm cumulative impacts for constructionrelated noise
Environmental
Protection Measures
Not applicable
Not applicable
Direct/Indirect
Impacts
Cumulative Impacts
Not applicable
Not applicable
Environmental
Protection Measures
Not applicable
ES093014083520ATL
ES-11
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Utilities
Direct/Indirect
Impacts
Minor to moderate, negative, and shortterm impacts to power supply and service
Minor to moderate, negative, and shortterm impacts to power supply and service
Minor to moderate, negative, and shortterm impacts to potable water supply and
service
Minor to moderate, negative, and shortterm impacts to potable water supply and
service
Minor to moderate, negative, and shortterm impacts to natural gas supply and
service
Minor to moderate, negative, and shortterm impacts to natural gas supply and
service
Cumulative Impacts
Not applicable
Environmental
Protection Measures
Not applicable
Cultural Resources1
Direct/Indirect
Impacts
Cumulative Impacts
Environmental
Protection Measures
No cumulative impacts
Not applicable
No cumulative impacts
No cumulative impacts
1AllfindingsandimpactdeterminationsaresubjecttochangependingconsultationwithStateHistoricPreservationOfficers(SHPOs).
ES-12
ES093014083520ATL
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Visual Resources
Direct/Indirect
Benefits
Cumulative Impacts
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Environmental
Protection Measures
Not applicable
Water Resources
Direct/Indirect
Impacts
Cumulative Impacts
Environmental
Protection Measures
ES093014083520ATL
Not applicable
Not applicable
Not applicable
ES-13
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Biological Resources
Direct/Indirect
Benefits
Direct/Indirect
Impacts
Not applicable
Not applicable
Minor to moderate, negative, and longterm direct and indirect impacts to native
vegetation
Cumulative Impacts
Not applicable
Not applicable
Environmental
Protection Measures
Not applicable
Cumulative Impacts
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Environmental
Protection Measures
Not applicable
ES-14
ES093014083520ATL
EXECUTIVESUMMARY
TABLE ES-1
Summary of Impacts
Resource
No Action
Fenton Site
Mehlville Site
Cumulative Impacts
Environmental
Protection Measures
Not applicable
Not applicable
NGA will implement a Dust Control Plan to control onsite and offsite
fugitive dust emissions, as prescribed in the Missouri CSR
Airspace
Direct/Indirect
Impacts
Cumulative Impacts
Not applicable
Not applicable
Not applicable
Not applicable
Environmental
Protection Measures
Not applicable
NGA will coordinate with the FAA during the design phase to avoid
or minimize glint and glare through selection of building materials
and modifying orientation and angles that could cause glint or glare
ES093014083520ATL
ES-15
EXECUTIVESUMMARY
SocioeconomicsChanging to federal ownership at this location would result in a loss of property tax
paid to the city of Fenton (approximately $5,502) and St. Louis County (approximately $462,308).
The city of St. Louis would lose approximately $2.19 million in City Total Earnings Tax through the
loss of tax from NGA non-residents of St. Louis.
Traffic and transportationThe surrounding road network would be affected during construction
periods only. There would likely be no transportation infrastructure failures as a result of the
increased traffic.
NoiseNoise from construction activities would be noticeable, but construction activities would
comply with state and local ordinances.
Hazardous material and solid wasteThis site would generate approximately 1,198,730 cubic yards of
solid waste before re-use or recycling. This amount is approximately 0.56 percent of the total
permitted capacity of the three regional landfills that accept construction and demolition material.
UtilitiesSite development would require upgrades to utility infrastructure and new connections,
including supply and service, potable water supply and services, wastewater and stormwater services,
and communications.
Water resourcesNo water resources or regulated waters would be impacted; however, construction
activities could occur within the 500-year floodplain. Any infrastructure located within the 500-year
ES093014083520ATL
ES-17
EXECUTIVESUMMARY
floodplain would be designed and constructed in compliance with all applicable federal guidelines
and regulatory requirements pertaining to floodplains.
Air quality and climate changeAn increase in National Ambient Air Quality Standards (NAAQS)
criteria pollutant and carbon dioxide equivalents (CO2e) emissions would occur. However, emission
levels would be below regulatory thresholds.
Environmental protection measures, including standard best management practices (BMPs) as defined in
Table ES-1 and summarized at the end of each resource section, would need to be implemented to ensure
environmental impacts are maintained below defined thresholds.
SocioeconomicsChanging to federal ownership at this location would result in a loss of property tax
paid to St. Louis County (approximately $545,495). The city of St. Louis would lose approximately
$2.19 million in City Total Earnings Tax through the loss of tax from NGA non-residents of St.
Louis.
Traffic and transportationThere would be an impact to the roadway network at the entrance to the
Next NGA West Campus, along Tesson Ferry Road. NGA would work with MoDOT to install a
traffic signal to alleviate this concern.
NoiseNoise from construction activities would be noticeable, but construction would comply with
state and local ordinances.
Hazardous material and solid wasteThis site would generate approximately 116,920 cubic yards of
solid waste before re-use or recycling. This amount is approximately 0.05 percent of the total
permitted capacity of the three regional landfills that accept construction and demolition material.
UtilitiesSite development would require upgrades to utility infrastructure and new connections,
including supply and service, potable water supply and services, wastewater and stormwater services,
and communications.
ES-18
ES093014083520ATL
EXECUTIVESUMMARY
Water resourcesA single, forested wetland, approximately <0.01 acres in size, is located below an
onsite retention pond. Under the Proposed Action, construction activities could displace surface
waterbodies and the small wetland within the site. The maximum amount of surface water
area/disturbance that would be displaced consists of 2,658 linear feet of intermittent stream,
373 linear feet of ephemeral stream, and a 3.5-acre stormwater retention pond. Impacts to the surface
waterbodies that qualify as waters of the United States would require a CWA Section 404 permit
from USACE, St. Louis District and a Section 401 Water Quality Certification from Missouri
Department of Natural Resources.
Air Quality and Climate ChangeAn increase in NAAQS criteria pollutant and CO2e emissions would
occur. However, emissions levels would be below regulatory thresholds.
Standard BMPs, as defined in Table ES-1 and summarized at the end of each resource section, would need to
be implemented to ensure environmental impacts are maintained below defined thresholds.
ES093014083520ATL
ES-19
EXECUTIVESUMMARY
Following the analysis performed for the St. Louis City site, it is anticipated that other minor to moderate
negative environmental impacts could occur to the following resources:
SocioeconomicsChanging to federal ownership at this location would result in a loss of property tax
paid to the city of St. Louis (approximately $64,180), but the City would retain the City Total
Earnings Tax from NGA personnel.
Land UseThe city of St. Louis is working on agreements with local community members for
property purchases and relocations. All relocations and displacements would occur in compliance
with the Missouri relocation statutes, which require fair compensation for relocated individuals.
Health and safetyRoad realignments could result in a minor impact to emergency response times in
the area.
Traffic and transportationThere would be an impact to the roadway network at the two entrances to
the NGA campus without signals, which are located along Jefferson Avenue and Cass Avenue. NGA
would coordinate with MoDOT to install actuated traffic signals to alleviate this issue.
Hazardous material and solid wasteThis site would generate approximately 85,650 cubic yards of
solid waste before re-use or recycling. This amount is approximately 0.03 percent of the total
permitted capacity of the three regional landfills that accept construction and demolition material.
UtilitiesSite development would require upgrades to utility infrastructure and new connections,
including power supply and service, potable water supply and services, wastewater and stormwater
services, and communications.
Air quality and climate changeAn increase in NAAQS criteria pollutant and CO2e emissions would
occur. However, emission levels would be below regulatory thresholds.
Standard BMPs, as defined in Table ES-1 and summarized at the end of each resource section, would need to
be implemented to ensure environmental impacts are maintained below defined thresholds.
ES-20
ES093014083520ATL
EXECUTIVESUMMARY
are currently reaching out to the Illinois State Historic Preservation Office and local interest groups to
determine the appropriate mitigation for impacts to this resource.
Minor to moderate benefits may result from the reduction of potential noxious weeds on the site, health and
safety improvements, land use improvements.
Following the analysis performed for the St. Clair County site, it is anticipated that minor to moderate,
negative environmental impacts could occur to the following resources:
SocioeconomicsThe city of St. Louis would lose approximately $2.19 million in City Total Earnings
Tax through the loss of tax from NGA non-residents of St. Louis. There would be no change to the
Countys property tax revenue; the site is already exempt from property taxes because it is
County-owned. However, St. Clair County would no longer receive the income associated with
current agricultural leases.
Traffic and transportationThere would be an impact to the St. Clair County Site roadway network at
the signalized intersection of Route 158 at Wherry Road. NGA would coordinate with IDOT to add
an exclusive right turn lane to westbound Wherry Road to alleviate this issue.
UtilitiesSite development would require upgrades to utility infrastructure and new connections,
including power supply and service, potable water supply and services, wastewater and stormwater
services, and communications.
Water resourcesA single, forested wetland, approximately 2.1 acres in size, is located in the
southwestern part of the site. Under the Proposed Action, construction activities would most likely
displace the wetland on the site. Other surface waters include a 2,092-linear-foot perennial stream, an
intermittent stream, and a 0.9-acre pond. Impacts to the surface waterbodies that qualify as waters of
the United States from the proposed infrastructure construction would require a CWA Section 404
permit from USACE, St. Louis District and Section 401 Water Quality Certification from IEPA.
Air quality and climate changeIt is anticipated that an average roundtrip commute would increase
from 26.4 miles to 58.2 miles based on current workforce zip codes. Despite the increase in commute
distance, the annual operational emissions would be less than the federal de minimis thresholds for
criteria pollutants and the 25,000-metric ton reporting threshold for CO2e.
AirspaceBecause of the proximity to Scott AFB, NGA would coordinate with the FAA to perform an
aeronautical study under 14 CFR 77 to determine the potential impacts to flight patterns and operations
within the existing airspace. There should be minimal change to flight patterns if this site is selected.
Standard BMPs, as defined in Table ES-1 and summarized at the end of each resource section, would need to
be implemented to ensure environmental impacts are maintained below defined thresholds.
ES093014083520ATL
ES-21