Anda di halaman 1dari 21

GAZIANTEP UNIVERSITY

CIVIL ENGINEERING DEPARTMENT


Construction Division

Soil Improvement techniques CE-562


Final Exam:
(Two Case studies on Deep dynamic compaction method)
Submitted to:

Do.Dr. Hanifi ANAKI


Submitted by:

Handren Salih M.A.Jaf

Bzhar Muhedin Muhammad


1

CASE HISTORY:
Application of Dynamic Consolidation and Dynamic Replacement for
Rehabilitation of a Landfill for a Housing Development Project

* Project Description and Location


Phase 1 of the project comprised of 108 units of single-storey double-storey terrace houses and
102 units of double-storey terrace houses. The site is located at the junction of old limestone and
Kenny Hill formation. It was previously a tin mine and was later used as a rubbish dumping
ground. The overburden therefore consists of poorly compacted household waste whilst the
subsurface soil is loose, with slime layers, due to the mining process. The site was also scattered
with ex-mining ponds.

* Subsurface Conditions
Two series of soil investigation were conducted which include deep boreholes,
cone penetration tests and pressure meter tests. The boreholes were sunk to 30m
depth terminated upon reaching limestone rock. A sample bore log is given in
figure 12. Borehole BH2, which was, located in the middle of the proposed Phase I
area indicates a waste fill down to 8.5m. Generally, the thickness of this waste fill
(mostly household rubbish) is about 5m to 8m. Underlying the upper waste fill,
layers of loose silty clayey sand and clayey silt were found. The water table level
was about 1.5 - 2m below the existing ground level. Figure 13 shows the SPT tests
results.

* Criteria for Ground Improvement


The acceptance criteria for the ground improvement works was:
i) Safe bearing capacity > 120 kN/m
ii) Differential settlement < 1: 600
These criteria carried with it a performance guarantee valid for 7 years. In addition,
the structural design also includes structural joints at every 2nd house unit along
the terrace row. A shallow foundation design was adopted.

* Design of Treatment, Selection of Plant and Equipment and


Construction Sequence
A combined dynamic consolidation and dynamic replacement techniques were
used (figure 14). Before the commencement of compaction work, a full-scale
calibration test was carried out on site. This calibration test consists of heave and
penetration tests. The purpose of the calibration is to:
1) Determine the optimal number of blows for each phase.
2) Determine the required compaction energies and the number of phases of
compaction.
4

3) Check that the pounder penetration is not a volume displacement but a real
compaction of the soil.
4) Determine the actual spacing of compaction points to avoid any interference of
heaving in between the points.

Dynamic Consolidation to create compacted sand raft


To allow slab-on-grade and for infrastructure

Dynamic Replacement sand columns to support column


Loads; increase bearing capacity and reduce settlement

Based of the results of the calibration tests, dynamic replacement and dynamic
consolidation were used for the structural area while the dynamic consolidation
was used for the infrastructure area (roads and services). The operation parameters
were developed and optimized for the compaction operations as shown in Table 5.
A 165-ton crawler crane (American Hoist 9299) was used for the compaction
works (figure 15). The effective area of compaction includes a periphery strip (or
over width) of 5m beyond the boundary of the houses.

The construction sequence was as follow:


Step 1: Excavation of upper 2.5m recent rubbish deposits (refuse < 5 years old).
Step 2: Backfill with 2.5m of clean sand as working platform and also as drainage
blanket.
Step 3: Performed dynamic replacement on structural areas (especially below
structural columns) and dynamic consolidation over the entire treatment area
(Phase 1).
Step 4: Performed phase 2 and ironing phase of ground improvement work.
Step 5: Carry out quality control, instrumentation and monitoring works
During and after ground improvement works.
Step 6: Complete sand filling to reach finished platform level with compaction to
90% modified proctor standard.
Step 7: Carried out 2m surcharging for 6 weeks. Settlement monitoring.
Step 8: Surcharge removed and proceeds with construction.
6

*Penetration Test (CPT)


Forty-one locations of PMT test were carried out i.e. 8 locations before compaction
works, 12 locations after phase 1, 9 locations after phase 2 and finally 12 locations
after the final ironing phase. From the results, it can be shown that there is an
increase of the pressure limit Pl and pressure meter modulus Em down to about 67m

*Enforced Settlement
The enforced settlements obtained were:
Phase 1: 0.29m
Phase 2: 0.21m
Ironing phase: 0.10m
The total enforced settlement was about 0.6m which represent about 13-14% of the
total of the remaining rubbish deposit after excavation of the upper 2.5-3m.

* Bearing Capacity
The pressure meter test is a type of load test which in particular yields the limit
pressure Pl that corresponds to the failure of the soil. Experience and theory have
shown that the ultimate bearing capacity of a foundation is proportional to Pl
value. The factor of proportionality so-called the bearing factor K is a function of
the relative depth and the foundation shape. The bearing capacity is calculated
according to the D60AN manual for Interpretation and Application of Pressure
meter Test Results to Foundation Design (Sol Soils No: 26 - 1975) - Rule 4 based
on equivalent limit pressures. The equivalent limit pressure Ple defined as the
9

geometric mean of the Pl values obtained near to the level of the foundation is
given by:
Ple = 3 _ {Pl1 * Pl2 * Pl3} . (5)
Where
Pl1 is the mean of the limit pressures measured from 0 to 2m depth
Pl2 is the limit pressures measured from at 3m depth
Pl3 is the limit pressures measured at 4m depth The bearing capacity (q) is then
calculated using equation (6) below with a bearing factor of K = 0.8 and a factor of
safety of 2.5.
q = {Ple * 0.8}/2.5 . (6)
The calculated safe bearing capacity before compaction works varies from 90
kN/m to 160 kN/m. After compaction works the calculated safe bearing capacity
varies from 320 kN/m to 500 kN/m with mean value of 410 kN/m. The bearing
capacity is increased by a factor of 3.3.

* Settlement
Estimation of settlement is carried out using the Schmertmanns method based on
the cone penetration tests results. The calculated settlement due to a load of 120
kN/m on a square footing of 1.65 x 1.65m ranges from 8mm to 19mm with a
mean value of 12mm after compaction works. A similar calculation is carried out
using the pressure meter results. The estimated total settlement after compaction
works ranges from 5mm to 11mm with a mean value of 8mm. To obtain the
maximum differential settlement between two footings, the worse possible
conditions of loading combined with the results of the pressure meter tests is used.
The calculation is based on the following details:
Shape of footing: square
Size of footing: 1.65m x 1.65m
Maximum distance between footings: 2.5m
The computed maximum differential settlement is 1:544.

* Surcharge
Surcharge was carried out after the compaction works to: (i) Consolidate the presence of any cohesive layer below the rubbish deposit.
(ii) Reduce the potential differential settlement.
(iii) Reduce future secondary compression. It was however, primarily used as a
simple load test. A surcharge of 2m fill was placed for 6-7 weeks until the timesettlement behavior reached at least 70% degree of consolidation according to
10

Field measurements of the settlement plate. The settlement readings taken from 12
sets of settlement plates vary from 4mm to 30mm. Out of the 12 readings, 8
readings have settlement less than 15mm, 3 readings have settlement less than
25mm and only 1 reading has exceeded 25mm. The average value is 13mm.
The 1st phase of the project was completed in 1990. Occupation of the houses was
almost immediate and until today (1999) there is no structural defect reported.
Figure 18 shows the completed structure after 7 years upon completion

11

* CONCLUSION
From the various case histories cited in this paper, the dynamic consolidation
technique is applicable for densifying landfill to allow for additional storage space.
Furthermore, it is also possible when it combines with dynamic replacement
technique to permit developments such as housing projects to be carried out over
landfill sites as in any ground improvement projects; instrumentation and
monitoring still play a very important role in the success of the works.

12

2- A case study on soil improvement with heavy dynamic compaction


ABSTRACT: In this paper, soil improvement works by means of heavy dynamic
compaction method performed for the foundation subsoil of Carrefours
Hypermarket and Trade Center in Bursa, Turkey is given as a case study. In order
to increase the bearing capacity of the foundations subsoils as well as to regulate
the total and differential settlements underneath the foundations Heavy Dynamic
Compaction (HDC) together with High Energy Pillars (HEP) is implemented.
1 INTRODUCTION
In this paper, soil improvement works by means of heavy dynamic compaction
method performed for the foundation subsoil of Carrefours Hypermarket and
Trade Center in Bursa, Turkey is given as a case study. The project site covers
approximately 100,000 m2 area, on which a Hypermarket, Trade Center and a
Parking structure together with future extension zones and slab-on-grades are
Constructed. A soil improvement with dynamic compaction method is
implemented underneath the foundations and slab-on-grades for the structures
named as Block A, B and C with a total improvement area of approximately
78,500 m2. The planned structures are named as Hypermarket Block A, Trade
center and parking structure Block B and future extensions as Block C.
General layout of the site is given in Figure 1. Block A consists of a single storey
hypermarket structure covering and area of 20,400 m2. Block B consists of trade
Centre and closed parking structure located on a base area of 48,500m2. Block B
has a basement level of height 4.0 m. The rest of the structures in the site are
designed without basements. The finished grade elevations for structures, slab-ongrades and open parking areas are designed at elevation +112 m. The finished
grade elevation of basement within closed parking structure is +108 m and
designed as a partial basement underneath Block B. A quality control program is
implemented during the soil improvement works. This case study presents the
design, construction and performance of the implemented soil improvement by
means of heavy dynamic compaction/dynamic replacement. The geotechnical
modeling based on soil Investigation data is presented and the performance of the
implemented soil improvement is evaluated based on the quality control/quality
assurance testing.

13

Figure 1. General layout of the site

14

2 LOCAL GEOLOGY AND SUBSOIL CONDITIONS


The subject site is located at about 5 km west of Bursa on the main highway from
Bursa to Izmir. The site is located in an area basically covered with the alluvial fan
deposits of the river Nilfer flowing north, where the river reaches the flat alluvial
plain of Bursa. The site was previously utilized as a borrow area and after being
abandoned was further utilized as damp area for excavated material of various
origin. As a result, the site contained depressions as deep as 14 m from the present
ground elevations, whereas some part of the site was covered with uncontrolled
fills formed by damped material of debris, blocks, bricks, concrete, clay and
excavated material of various origin. The thickness of uncontrolled old fills
reaches to maximum 14 m. Occasional parts of the site are covered with alluvial
deposits formed by mixtures of clay, sand and gravel down to maximum 15 m
depth. Below these depths native soil is the Neogene aged deposits of clayey sandsandy clays. The subject site is located in the first degree earthquake zone in
Turkey with the highest seismic ity. Three main zones are identified within the site
based on soil investigations. These are, natural ground, uncontrolled old fill, and
excavated empty zones. Natural ground areas are undisturbed natural ground
located approximately at elevations +110 m and +112 m. The subsoil is composed
of sandy gravely alluvial soil underneath a topsoil cover. The thickness of the
sandy gravel layer is in the order of 12 m to 15 m and hard sandy clays are
encountered below this layer. Uncontrolled old fill areas consists of uncontrolled
fills damped at the site in time from excavated material of various origin ,
including topsoil, debris and blocks. Alluvial sandy gravel layer is not encountered
in these areas during soil investigations. Excavated areas are the zones of
excavated parts of the former borrow area with elevations ranging between +100 m
and +104m. The subsoil in these zones consists of sandy gravel layer to a limited
depth which was utilized as borrow material and clay-sandy clay layer underneath.

15

3 FOUNDATION ENGINEERING DESIGN


3.1 Foundation system
Block A and partially Block B was designed to be located on uncontrolled old fills,
and part of Block B was designed to be located on the previously excavated zone.
For the foundations of the structures the depressions within the site are filled
partially with the excavated uncontrolled fill material and partially with the
imported material in order to achieve a graded level for foundations. The view of
site to backfilling together with the utilized dynamic compaction equipment is
given in Figure 2.

Considering the presence of distributed loads of various intensity and slab-ongrades within the planned structures, the soil improvement with dynamic
compaction is then implemented for the whole site from the graded level with
subsoil being composed of uncontrolled old fill, uncontrolled new fill and natural
ground. In order to increase the bearing capacity of the foundations subsoils as
well as to regulate the total and differential settlements underneath the foundations
Heavy Dynamic Compaction (HDC) together with High Energy Pillars (HEP) are
implemented. The areas between the foundations for slab-on-grades are also
improved by means of Heavy Dynamic Compaction (HDC) and Dynamic
Compaction (DC). The selected improvement scheme was the most economical in
comparison to other alternatives based on the summarized conditions. The
foundations of structures were designed as spread footings tied with tie -beams in
two directions located on the improved soil.

16

3.2 Dynamic compaction as a soil improvement


The dynamic compaction for soil improvement of the subject site was implemented
by MENARD Soltraitement and quality control/quality assurance testing during
construction was carried out by ZETAS Zemin Teknolojisi A.S. Initial soil
investigations for the site was performed by ZETAS Zemin Teknolojisi A.S.
(1998) composed of rotary boreholes with systematic SPT and pressuremeter
testing. The SPT-N values varied between N=10 to refusal, revealing the presence
of large cobbles and blocks within the uncontrolled fill. Based on grains size
analysis of the retrieved representative samples percent passing No.200 sieve
varied between %8 and %98, indicating the variable nature of the encountered soils
within the site. In order to be able to follow the soil improvement, prior to soil
improvement works six boreholes of 15 m depth with systematic pressuremeter
testing at every 1.0 m were performed in different subsoil conditions that will
represent the site. Pressuremeter test results revealed that the limit pressure values
as low as Pl=2.5 bar, with %70 of the Pl values below 5 bars. Consequently,
pressuremeter tests results are in agreement with the soil investigations results
indicating a heterogeneous nature of the subsoil. Consequently, heavy dynamic
compaction (HDC) together with high energy pillars (HEP) was selected as soil
improvement. Dynamic compaction is a soil improvement method employed to
increase the mechanical properties of subsoils at greater depths. The technique was
first developed and pioneered by Menard 1976). In this method, a heavy ponder is
dropped on soil surface from various heights with free drop within a grid-wise
manner and hence subsoil is compacted by means of the energy delivered to the
soil surface. The basic equipment consists of a heavy mobile crane and ponders
with various weight. The special cranes are utilized which can drop a 40 tonnes
weight from 40 m height, which can deliver a 1600 ton.m energy with a single
drop. The effective depth of soil improvement, D during dynamic compaction is
directly proportional with the energy delivered (weight, W and drop height, H) for
each drop and can be estimated with the following expression.
0.5 (WH)1/2 < D < 0.8 (WH)1/2 (1)
Accordingly, the effective depth of soil improvement D, for a weight of 40 tonnes
dropped from 40m height would be in the range of 20.0m < D < 32.0m, which was
in excess of the total thickness of the uncontrolled fills present within the subject
site. Therefore, a weight of W=20 tonnes from a drop height H=20m was
implemented for the subject site achieving an improvement depth in the range of
10.0m < D < 16.0m for an energy level of 400 ton.m.
17

With this kind of soil improvement average settlement of the ground surface of a
soil treated by dynamic consolidation shows that the density is increasing (usually
around 5%). This increase in density corresponds to a much greater increase in
relative density Dr (20% or more). Method of High Energy Pillars HEP is a
dynamic replacement method similar to dynamic compaction. In this method, the
ponders are dropped repeatedly on a replaced granular soil layer, which force a
large diameter densified granular soil column into the soil and combines the
advantages of dynamic compaction with the stone columns and permits the transfer
of impact energy to deeper soil layers.

4 DETAILS OF SOIL IMPROVEMENT


4.1 Heavy Dynamic Compaction (HDC)
HDC is applicable either on unsaturated soil or granular soil under groundwater table. The basic
Principle consists of transmission of the high energy impacts to the surface of ground which is

initially compressible and with low bearing capacity. In unsaturated soil


conditions, the HDC results a quick decrease in void ratio of the soil and an
instantaneous settlement of ground under impact. Ponders weighing from 18 tons
to 25 tons were dropped in free fall from heights ranging between 15 m to 25 m
based on heave and penetration tests performed at various parts of the site prior to
Commencement of work. The craters formed by the drop of pounder at the
predefined grid of ponder prints were back filled with soil of the platform, hence
resulting the an average settlement of site as well as densification. The
performance of two different trail areas based on the improvement characteristics
according to pressure meter tests enabled to determine the grid of tamping and the
number of blows per print.
4.2 High Energy Pillars (HEP)
HEP method is derived from HDC and same type of equipment is utilized. The tamping energy is
used to create large diameter stone inclusions in a soft soil. These columns are realized by successive
filling and tamping of the pounder print penetrating into soft ground. By means of creating a high
modulus large diameter stone column, the tamping energy can also be penetrated to deeper layers of
the ground through the compacted high modulus pillar resulting a compaction in the deeper layers of
the subsoil beneath HEP.
HEPs were implemented underneath the footings of the structure composed of selected material
Backfill. The material used in the HEP were calibrated in order to obtained a homogeneous strength
of
Stone column or pillar. The material for the execution of pillar was the present granular material
Selected from the site. The total quantity of HEP material was in the order of 38,000 m3. The quality
Of the material was decided by soil improvement subcontractor, where the site material did not meet
The requirements, granular material of equivalent properties were imported to site.
18

4.3 Ironing
The last phase of tamping consists of a dense grid of lighter dynamic compaction
in order to homogenise the surface layer.
4.4 Quantities
The soil improvement work included the execution of total of 2048 HEP
underneath the columns of the superstructure based on the column loads. The total
average settlement of the site based on the topographical surveys prior and after
soil improvement could be summarized as:

5 QA/QC TESTING
Quality control/quality assurance of the soil improvement as well as the
performance monitoring of the implemented method is performed by means of a
series of testing. The QA/QC testing includes the following:
Systematic pressure meter testing was performed before and after the soil
improvement randomly below the slab-on-grade areas at every 2500 m2 down to
14 m depth with one test per meter. In addition to slab-on-grade areas, pressure
meter test points below the footings at every 1250 m2 down to 6 m depth with one
test per meter, were performed in order to verify the desired compaction \for HEP
implemented below footings. A typical test result with before and after tests for
HEP location is given in Figure 3.
Two test zones were selected that would represent the soil conditions within the
site. In these test zones heave and penetration tests before the initiation of job in
order to optimize and determine the number of blows per print in different subsoil
types as well as determination of optimum energy delivery. Once the optimum
compaction energy level and number of blows were determined, the HDC and HEP
production and quality control is followed by systematic pressure meter testing.
19

Figure 3 Sample pressuremeter test results before and after soil improvement
Magnetic settlement columns after the compaction in order to monitor, any further
settlement due to foundation and superstructure loads are installed. Magnetic
settlement columns consisting of five different levels of measurement within 20 m
depth. The construction continued upon verification of no additional settlements
based on monitoring data. Seismic tests were conducted by means of measuring
Rayleigh waves before and after dynamic compaction in order to observe the
increase in modulus of the subsoil. By means of measuring wave velocities before
and after compaction and hence determining consequent shear and Young modulus
of subsoil, the increase in modulus values as well as percentage of increase were
observed. Consequently, HEP and HDC are appeared to be very effective method
in terms of performance of structures and the cost for the improvement of
unsaturated granular soils.

20

REFERENCES
Menard Soltraitement (2000), Method Statement and Schedule, HEP, HDC, DC
and PMT, Bursa Carrefoursa
Project, Paris
Menard Soltraitement (2001), Soil Improvement of a Filled Area by Dynamic
Consolidation and Dynamic
Replacement Final Report Carrefoursa Bursa, Paris
Menard, L ve Broise, Y. (1976), Theoretical and Practical Aspects of Dynamic
Consolidation, Institute of
Civil Engineers, Ground Treatment by Deep Compaction, London
ZETAS Zemin Teknolojisi A.S. (1998). Carrefoursa Bursa Hypermarket and
Trade Centre Soil Investigation
and Foundation Engineering Evaluation Report, Istanbul

21

Anda mungkin juga menyukai