EQUIPMENT BOM

CREATION
SAP PM

Equipment BOM Creation


A Bill Of Material (BOM) is a complete , formally structured list
of the components making up a technical object or assembly.The
list contains the object numbers of the individual component
together with their quantity and unit of measure . The component
can be stock or non-stock spares or assemblies , which in turn can
be described using maintenance BOMs.
BOM are primarily used for the following purpose:
Structure description
BOM describes the structure of a technical object or material .
Using maintenance BOMs maintenance tasks can be planned.
Assignment of spare parts
BOM is used in plant maintenance to assign spares for a technical
object or material .
TRIGGER:
A piece of maintenance equipment requires a bill of material for
maintenance purpose. Whenever any equipment created we can
create its BOM for structuring. But before creating Equipment we
need to create Material Master.
Create a BOM for a piece maintenance equipment to describe the
equipment components , maintenance requirements or the
assignment of the spare parts.
Module: PM
Transaction Code:
Create:IB01
Change:IB02
Display:IB03
CREATED BY: GAURAV SOLANKI
|2

Title:Maintaining of Master
date-Equipment
Menu Path: Logistics
Plant
Maintenance Management Of
Technical Objects
Bill of
material
Equipment BOM
DATE: 19.03.2014

Page

Equipment BOM Creation


Create (IB01)

Description:
Use this transaction for creating & maintaining Equipment bill of
material.
Double click on press Enter Key to reach the following screen.
Note:-

CREATED BY: GAURAV SOLANKI


|3

DATE: 19.03.2014

Page

Equipment BOM Creation


If Equipment number is already existing for the BOM and you
want to add another BOM for that equipment then you have to
use IB02 transaction code.
And add the component .

Field name
Equipment
Plant
BOM Usage

Required/Opti User action and allowed


onal
values
R
Select equipment for which
BOM is being created.
R
Enter the plant in which BOM
is being created.
R
Select usage : 4 (Plant
Maintenance)

CREATED BY: GAURAV SOLANKI


|4

DATE: 19.03.2014

Page

Equipment BOM Creation


Press Enter Key to reach the following screen.

Enter the parameters as detailed below : in Material Tab.


Field name
Item Category

Required/Opti User action and allowed


onal
values
R
Select the item category. It can
be stock item or non-stock

CREATED BY: GAURAV SOLANKI


|5

DATE: 19.03.2014

Page

Equipment BOM Creation


Component

Component
Description

Quantity

Units

item.
Enter the item code or
material code which related to
that equipment
System takes default
description of selected
component.
Enter the installed quantity of
component.
System takes defaults UOM of
selected component.

IF component consists sub-items.


Then click on *Subitems*

CREATED BY: GAURAV SOLANKI


|6

click here for


enter
the subitems
Details.

DATE: 19.03.2014

Page

Equipment BOM Creation

Field name
Installation
Point
Sub-item Qty
Sub item text

Required/Opti User action and allowed


onal
values
O
Enter installation point where
it is installed.
O
Quantity of the sub-items
O
Text (40 characters) of subitem

And then click on


to save the Equipment BOM and following
message will be given by the system.

CREATED BY: GAURAV SOLANKI


|7

DATE: 19.03.2014