Anda di halaman 1dari 15

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001

SANGACHAL TERMINAL

REV. NO

4
1/15
CONTRACTORS DOC NO

EXPANSION PROGRAMME

TEKFEN-AZFEN

PAGE / OF

ALLIANCE

269-CN-11-PR-001

PROCEDURE
FOR
ELECTRICAL INSTALLATION WORKS

APPROVAL OF THE COMPANY


STATUS *
NAME
TITLE
DATE
SIGNATURE

* A: Approved
C: Not approved, commented.

4
3
2
1
0
REV.

IO

B: Approved as noted.
IO: Accepted for information only.

Re-issued as a common document for ACG & Shah Deniz Project


Revised as per comments of the Company transmitted by
transmittal No: FFD-24/AIOC/TKAZ/DT-0693 dated 05.02.2003
Revised as per comments of the Company transmitted by
transmittal No: FFD-24/AIOC/TKAZ/DT-0550 dated 27.11.2002
Revised as per comments of the Company transmitted by
transmittal No: FFD-24/AIOC/TKAZ/DT-0436 dated 09.10.2002
Issued for Approval
DESCRIPTION

A.C.C.

I.M.G.

L.K.

N.C.

I.M.G.

L.K.

N.C.

I.M.G.

T.B.

N.C.

I.M.G.

T.B.

N.C.
PREPD

I.M.G.
CHKD

T.B.
APPRD

08/10/2003
06.02.2003
29.11.2002
04.11.2002
28.09.2002
DATE

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

PAGE REV. & ADDITION


PAGE
REVISION NO
NO.
1
0 1 2 3 4
2
0 1 2 3 4
3
0 1 2
4
0 1 2
4
5
0 1 2
6
0 1 2
7
0 1 2
8
0 1 2
9
0 1 2
10 0 1 2
11 0 1 2 3
12 0 1 2 3
13 0 1 2
14 0 1 2
15 0 1 2

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

2/15

CONTRACTORS DOC NO

269-CN-11-PR-001
PAGE REV. & ADDITION
PAGE
REVISION NO
NO.

INDEX

PAGES INSERTION
PAGE
REVISION NO
NO.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

3/15

CONTRACTORS DOC NO

269-CN-11-PR-001

SECTION

TITLE

PAGE

1.0

SCOPE

2.0

DEFINITIONS

3.0

CODES, STANDARDS AND SPECIFICATIONS

4.0

ELECTRICAL INSTALLATION

5.0

EQUIPMENT IN HAZARDOUS AREAS

6.0

CABLE SUPPORT SYSTEMS

7.0

CABLE INSTALLATION

8.0

CABLES INSTALLED UNDER GROUND

12

9.0

CABLE MARKINGS

12

10.0

CABLE TERMINATIONS

13

11.0

EARTHING AND BONDING

12.0

LIGHTNING PROTECTION SYSTEM

15

13.0

INSPECTION AND TESTING

15

5-8

9-11

14-15

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

4/15

CONTRACTORS DOC NO

269-CN-11-PR-001

1.0 SCOPE
This procedure defines requirements for electrical installation works in Construction of
Sangachal Terminal Expansion Programme within the scope of Tekfen Azfen Alliance group.
2.0 DEFINITIONS
2.1 Please refer to Quality Program Doc. No.: 269-QA-00-QD-002 for definitions.

3.0 CODES, STANDARDS AND SPECIFICATIONS


3.1
3.2
3.3
3.4

The applicable codes and standards shall be in accordance with listed in the Company's
Specification,BR-CDZZZZ-CS-SPE-0002
Specifications, drawings and reference data supplied by the Company, as per the contract
shall also be applicable.
Where there is contradiction between documents supplied by Company and the specified
codes & standards or legal requirements, such contradiction shall be immediately
transferred to Company and will be clarified by the Company.
Applicable specifications listed are as follows:
The Company's Specification, BR-1GZZZ-ME-SPE-0001: General Engineering
Specification
The Company's Specification, BR-CDZZZZ-CS-PHI-0004 : Electrical Design
Philosophy
The Company's Specification, BR-CDZZZZ-SA-PHI-0002
: HS&E Philosophy

4.

Related international standards:


ISO 9001/2
Quality Systems
IEC 60364
Electrical Installation of Buildings (Onshore)

TEKFEN Quality Manual for Pipeline and Related Facilities Rev.: 6,


The Contractors approved Quality Program, Doc. No.: 269-QA-OO-QD-002
The Contractors Inspection & Test Plan for Main Works, Doc. No.:269-QA-00-QD-003
to be submitted to Company for approval

ELECTRICAL INSTALLATION

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

4.1

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

5/15

CONTRACTORS DOC NO

269-CN-11-PR-001

General

4.1.1 Due care shall be taken to prevent accidents such as overturn, fall and contact during
transportation and installation of electrical machine and apparatus (hereinafter referred to as
electrical equipment).
4.1.2 On temporary placing, the electrical equipment shall be placed so as to have no obstruction for
traffic, and proper measures shall be taken to prevent the damage due to falling body, etc. and
the decrease in insulation performance due to water penetration, etc.
4.2

Transport.

4.2.1 Transport of electrical equipment to their erection place shall be executed safely after due
consideration of ground condition, access route condition etc.
4.2.2 Slings used for equipment lifting shall be in good condition and of enough strength.
4.2.3 During lifting, sling will be kept on the position of sling mark. If sling mark is not shown on the
case, due care shall be taken to adjust the catching position of wire rope, and prevent damage
for equipment and accessories.
4.3

Unpacking

4.3.1 Unpacking of supplied equipment or materials shall be done under the witness of COMPANY,
to check for equipment name, type, quantity, and no damage during transportation.
4.3.2 Unpacking work shall be done using necessary tools so that the equipment and materials are not
damaged.
4.4

Installation and Mounting

4.4.1 Equipment shall be installed exactly by means of setting them to stipulated foundation elevation,
measuring horizontal level, vertical level, and dimension between base line to the equipment, so
that the equipment can act to the best of its ability.
4.4.2 Liners to be inserted under the chassis of equipment shall be set to both sides of foundation
bolts in the nearest point. In case, distance between anchor bolts is long, liners shall be inserted
to middle point, too. Quantity of liners to be inserted shall be maximum 3 sheets per each point.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

6/15

CONTRACTORS DOC NO

269-CN-11-PR-001

4.4.3 Connection parts where tightening torque is specified, shall be tightened by using torque
wrench. Only a requirement to torque once, this should be done in item 4.4.4
4.4.4 Each bolt shall be tightened again, after completion of installation work, as well as external
inspection of equipment, malfunction and so on.
4.4.5 Panels of boxes to be mounted on wall, shall be basically mounted on bracket or rack
manufactured for this purpose. But, in case of wall of concrete or wood, these panels can be
mounted directly on wall.
4.4.6 Unless otherwise specified in construction documents, installation level of the electrical
equipment shall be as follows, as a rule:
(1) Indoor
Distribution board, power switchboard for repair, etc.:
from floor to upper point of panel

1.8 m

Tumbler switch:
from floor to the center

0.9 m

Plug socket:
from floor to the center

0.45 m

(2) Outdoor
Distribution board, power switch board for repair, etc.:
from ground or floor level to the upper

1.5 m

Tumbler switch:
from ground or floor level to the face of lower side

1.2 m

Plug sockets
from ground or floor level to the upper point

1.5 m

4.4.7 The IP rating of the equipments should be maintained throughout the installation.
4.5

Switchgear and MCC s

4.5.1 Supports, fixing arrangements shall be installed to suit the equipment with which they are
associated.
4.5.2 Switchboards and control panels will be placed on suitable support frames and installed
complete with separate or integral plinths where required and shown at the approved drawings.
They shall be erected and aligned in accordance with the approved drawings.
4.5.3 Transit packing material shall be carefully removed and stored and the complete equipment
thoroughly cleaned from foreign bodies.
4.6

Transformers

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

7/15

CONTRACTORS DOC NO

269-CN-11-PR-001

4.6.1 Transformers will be placed on a flat level, previously prepared base in the position shown on
the layout drawings and shall be positioned using the wheels and lifting points provided.
4.6.2 After positioning, wheeled transformers shall be fastened directly to the base foundation strictly
in accordance with the instructions on the vendor installation drawings approved by the
Company.
4.6.3 On completion of the installation and before the main power cables are connected test and
inspections will be carried out in accordance with inspection and test plan approved by the
Company.
4.7

Motors

4.7.1 Sufficient length shall be allowed in the power cable cores at the motor terminal box for at least
two cores to be easily interchanged.
4.7.2 Motor specifications will be checked if placed in hazardous area with its requirements.
4.7.3 Cable glands in motor terminal box will be tightened properly.
4.7.4 Motor chassis will be bonded to earth bar to the relevant Switchgear.
4.8

Lighting, small Power and Power Outlets

4.8.1 The exact location of luminaries and socket outlets to within one meter shall be determined by
the Contractor to ensure that they are both accessible for maintenance and avoid obstruction by
other services. In the case of major deviations from the relevant approved drawings the selected
locations shall be subject to acceptance of the Company.
4.8.1 Welding or drilling of primary steelwork, vessels and tanks for supports and brackets are not
permitted.
4.8.2 It shall be ensured that the continuity of the cable armour is maintained where cables loop in and
out of luminaries, socket outlets and junction boxes.
4.8.3 Lighting and small power cables shall be run on main cable routes wherever possible.
4.9 Trace Heating
4.9.1 Trace heating tapes and accessories will be installed strictly in accordance with the suppliers
instructions and approved drawings.
4.9.2 Trace heating tapes will be fixed to pipes in the orientation and pattern shown on the Suppliers
drawings using approved glass cloth tapes supplied.
4.9.3 Adequate trace heating tape loops will be installed at valves and other removable items, in
accordance with the Suppliers installation instructions, to allow equipment removal without
removal of the tapes.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

8/15

CONTRACTORS DOC NO

269-CN-11-PR-001

4.9.4 Overlapping of trace heating tapes, which might cause hot spots shall be avoided.
4.9.5 Trace heating tapes will be protected against direct contact with sharp edges, e.g. at valve
flanges or where tapes leave or enter cladding.
4.9.6 Trace heating tapes will not be cut and left with their ends exposed to the environment for more
time than is necessary to complete the application of end seals, splices or cold end connections.
Tape ends, which are likely to be exposed for any length of time, will be sealed using with
electrical isolation tapes.
4.9.7 End seals, splices and cold end connections shall be made in accordance with the Suppliers
instructions using purpose made tools. Splices and end seals will be made only at positions
shown on the drawings.
4.9.8 Insulaton resistance test will be applied to heating tapes before and after the insulation on the
pipelines. After insulation is completed, warning labels will be attached.
4.9.9 The junction boxes used at the trace heating circuitry to be earthed as shown on the drawings,
the tape cable screen to be connected to the earting busbar inside the junction box and this
busbar to be connected to the nearest earthing grid.
5.0

EQUIPMENT IN HAZARDOUS AREAS

5.1 All equipment and materials intended for use in a hazardous area shall be installed in accordance
with IEC 60079: Electrical Apparatus for Explosive Gas Atmospheres.
5.2 The Contractor shall ensure that all certified electrical equipment has been labeled or marked
by the manufacturer with the correct Ex protection type, gas group and temperature
classification where applicable and that the appropriate certificate has been supplied.
5.3 No certified equipment shall be modified or installed in such a way as to render its certification
invalid.
5.4 Adequately trained and qualified personnel to be assigned by the Contractor on the installation
of the equipment where this is required within areas designated as hazardous shall be fully
competent and conversant with all necessary regulations and standards relating to the
installation of electrical equipment within the hazardous areas.
5.5 Drilling out of entries in flameproof (Eex) enclosures is not permitted. Certified plugs are to be
fitted to all unused entries.
5.6 Only the correct type and size of cable gland shall be used as specified on the approved cable
schedules.
5.7 Painting of flameproof equipment or components, other than applied by the manufacturer, is
prohibited.
5.8 There shall be no obstructions around the flanges of flameproof equipment, other than those
approved by the code.
5.9 A proprietary non-hazardous, corrosion inhibiting grease suitable for use with flameproof
apparatus shall be applied, where required, to the flame path of equipment.
5.10 No alterations or substitutions shall be made to the equipment unless this is allowed in the
equipment certification.
5.11 All flanges of flameproof equipment shall be cleaned and then treated with approved grease on
completion of the installation and on all subsequent occasions that they are being re-assembled
following separation.
6.0

CABLE SUPPORT SYSTEMS

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
6.14
7.0

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

9/15

CONTRACTORS DOC NO

269-CN-11-PR-001

Cable tray and ladder shall be installed as per approved drawings. The spacing of tray/ladder
supports shall be as stated on the approved drawings.
Cable tray/rack expansion joints shall be installed in accordance with the manufacturers
recommendation.
Site located cable fixings to structural steelwork shall preferably be by means of clamps or
equivalent materials. Welding to vessels, tanks or primary steelwork is not permitted. Welding
to secondary steelwork will be applied where required.
Supports for site routed cable trays or racks shall be provided in accordance with the
manufacturers recommended loading and span distances. If additional support to relevant cable
tray deemed necessary and as directed by the Company additional support can be provided.
Steelwork shall not be drilled without the permission of the Company unless the drilling is
called for on approved drawings.
All cable support metalwork supplied by the Contractor shall be painted after site
manufacturing.
The spacing between adjacent layers of support systems shall permit ready access during the
initial laying of cables and for subsequent inspection or repair
Burrs and sharp edges formed on cable trays or racks when cut, shall be removed to the extent
that the exposed edge will not cause damage to cables nor cause injury to personnel and will
permit protective coatings to adhere to the exposed edge.
Cable tray shall be cut along a line of plain metal and not through a line of perforations. After
cutting, all sharp edges shall be made smooth and the racking finish made good.
Proprietary bends and tees shall be used where shown on the relevant drawings and on site run
cable routes, wherever practical. Site fabrication of accessories shall only be used where
absolutely necessary due to space limitations or equipment arrangements.
Where no more than a single cable is run, it may be supported by clipped or cleated to
steelwork etc., instead of utilizing tray or ladder rack.
At the cable tray system bends, risers, reducers, tees, crosses and other components will be
used to provide continuous cable support system. Unconnected sections shall be avoided
where possible.
Cable trays/racks shall be bolted to supports. Under no circumstances shall the rack or tray be
drilled for fixing purposes. Drilling will only be done for joining tray/racks or earthing
purposes or where detailed on the approved drawings.
All cable tray/rack shall be earth bonded using a suitable sized conductor. All cable tray/rack
requires a minimum of 2 main earth grounding conductors of suitable size.
CABLE INSTALLATION

7.1 All cable to be installed as described and detailed in the approved drawings.
7.2 All cable shall be installed on cable rack and trays where shown at the approved drawings.
However road lighting and main earth ring cables shall be installed underground by taking the
precautions.
7.3 All cable routes shall be accurately measured prior to cutting any cables.
Cable drum shall be handled according to following description.
(1)

Drums will be kept horizontally, but not lay on its side.

(2)

Drums will be turned according to arrow indicated

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

10/15

CONTRACTORS DOC NO

269-CN-11-PR-001

(3)

During cabling work, be sure that the drum does not obstruct the traffic or movement
of persons, and no damage occurs to cable.

(4)

Cable drum lifting jacks and associated equipment shall be of recognized


and certified to use on the required cable drums.

(5)

Transport drum safely and smoothly.

7.4

material

Cable laying work shall be proceeded as following:

(1)

Where cables are liable to damage, suitable protection shall be made before cable laying

(2)

Supervisor shall be posted at the key position such as corner, and pay attention to cable
pulling condition.
Cable laying work shall be done in a way, not to create any damageable tension given on the
cable, by using pulley and so on.

7.5 Where it is noted in the relevant drawings that routing to be left as Site Routed or Field Routed to
the discretion of the site personnel representatives of the Company and the Contractor shall
cooperatively determine by inspection the cabling requirements for equipment to be installed.
Where practicable, common cable routes by taking into consideration of the cable types and
specification requirements shall be established to minimise duplication of installation work.
7.6 Cables of different voltages and services e.g. telecommunications fire and gas shall be segregated
to prevent interference between electrical power, control and instrumentation circuits. The
Company in the approved drawings will supply specific requirements for cable routing and
segregation. Where intersection between groups of cable is unavoidable, the routing shall be
arranged such that power and control/electronics/signal cables cross at right angles. Barriers to
be used where possible when cables cross.
7.7
The cables installed on cable rack or tray require the cable tie material to be approved prior to
using them.
7.8
All cables shall be left clear of process and service pipes. It should be noted that many process
lines are eventually lagged therefore clearances between cable runs and pipe runs shall take this
into account.
7.9 Cables must not be supported from or attached to pipes either directly or on top of lagging unless
shown on the relevant drawings or approved by the Company.
7.10 Each cable shall be run as a continuous length from origin to destination without joints, except
as follows or where designated specifically on the relevant drawings and for long distances
where the cable manufacturing length is not sufficient to run one pieces.
7.11 Where cables pass vertically through floors, platforms, walkways, etc., protection against
mechanical damage shall be provided as detailed on the approved drawings.
7.12 Cables crossing a fire or gas barrier for example firewall or gastight wall shall pass through a
certified multi cable transit to maintain the characteristics of the barrier. These transits shall be
installed as detailed in the approved drawings.
7.13 The minimum-bending radius of any cable shall be as per manufacturers recommendation.
7.14 Cables shall be handled and installed in a manner, which does not cause damage by abrasion or
by excessive tension. Cables shall be laid in smooth parallel formation. Twisting, crossing or
intertwining of cables will be prevented.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

7.15
7.16
7.17
7.18
7.19
7.20

7.21
7.22

7.23
7.24
4.25
7.25
7.27

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

11/15

CONTRACTORS DOC NO

269-CN-11-PR-001

Cables will not be attached to pipes or structural steel members unless specially designated in
the approved drawings.
Access holes, for cables passing through solid floors or walls must be sealed by the use of an
approved system, or where the number of cables is small by the use of individual cable glands.
Where cables leave the support system they shall do so in a manner which does not cause any
damage to the cable
Records of cable quantities used and available during the installation and for final
reconciliation shall be maintained.
When the ambient temperature is at or below -10 oC, installation of thermoplastic cables shall
not be carried out, because of the danger of damaging their insulation sheath.
Cables installed on horizontal runs shall be strapped in convenient bundles at intervals of 600
mm, at each bend or change in direction and not more than 300 mm from a transit or gland
position. For vertical and horizontal runs, temporary ties will be used prior to the installation
of permanent clamps, plastic coated stainless straps to be used for vertical cable running at
regular distance of 1 to 3 meters in order to prevent the release of cables during a fire.
Tie wraps shall be of non-corrosive, plastic covered and be of such dimensions that when
tensioned for the final installation they do not damage the cable sheath.
All cables shall be so supported that no strain is placed upon the cable, cable gland or
equipment. After pulling, each cable is to be cut back to within two meters of its final length
and left for at least 24 hours before final glanding and terminating to allow redistribution of the
tensile forces, to prevent armour/insulation shrink back.
Motor control cables shall be laid alongside their respective motor power cable.
There individual power and control/instrument cable should be run in a same route, they will
be installed in same tray using a separation between them.
All outgoing cables from cable racks and trays to equipments shall be bottom or side of trays
and racks. Protection against sharp edges to be installed.
A suitable conduit to be used for the cables to be run inside the concrete. Cables never be cast
directly into concrete.
All cables and earth cables coming from underground to surface to be protected with conduit
or channel.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

8.0

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

12/15

CONTRACTORS DOC NO

269-CN-11-PR-001

CABLES INSTALLED UNDER GROUND

8.1 Cables run underground shall be laid into cable trench in accordance with approved drawings.
8.2 The routing and arrangement of underground cables, particularly in areas adjacent to substations
and control houses, shall be planned concurrently with main pipe routes and vehicle access
ways, to give as far as possible, unimpeded direct routes.
8.3 Cables shall be laid on 100 mm of sand and covered with 100 mm of sand. The sand shall be
screened to remove sharp objects and compacted to eliminate voids. Marker tape and
protection red brick shall be installed over the cables as indicated on the relevant drawings.
8.4 The minimum depth of cover from the cable to the finished grade shall be as follows:

For street lighting and telephone cables: 700 mm

For power cables up to and including 1000 V and control cables: 700 mm

Power cables above 1000 V: 800 m.


8.5 The infilling is to be compacted and free from large stones or other injurious objects local to
the protective covers.
8.6 Proprietary cable marker posts shall identify all cable routes in unpaved areas not more than 25
m intervals on straight runs and each change of direction.
8.7 The installation of direct buried cables shall not commence until the entire route has been
excavated, inspected and cleared of all stones and debris.
8.8 Where cables are installed in trenches the backfilling is to be clean debris and care shall be
taken when fitting the bricks to ensure that they are properly positioned and seated.
8.9 No cables shall be run directly beneath pipes, which follow the same direction as the cables,
whether the pipes are laid in or directly on the ground.
8.10 Underground (direct buried) cable shall have a warning tape 150mm below grade.
8.11 Under ground works shall not be covered until after visual inspection by the Company.
9.0
9.1
9.2
9.3
9.4
9.5
9.6
9.7

9.8

CABLE MARKINGS
All cables will be uniquely numbered as per relevant cable schedule plan.
Cable markers shall be located at each end of the cable and at either sides of cable transits
where required.
Cable markers shall be clearly visible from the direction in which the cables would be normally
inspected
To indicate a cable is being used for intrinsically safe (I.S.) circuits a blue colored heat shrink
sleeves will be added at each end of the cable.
Core identification, where specified at the approved drawing, shall be provided in accordance
with the approved drawings and be readable in the terminated position.
Core identification, shall be provided for cables by means of numbered or lettered plastics.
Core markers will be fixed to the cores of instrument and control cables, which will consist of
the designated terminal number which the core will be terminated to. Power cable cores will
not be marked since the color marking of the phases which exist on the cables will be unique
and predetermined for the whole project.
Cable markers shall be Critchley type K or approved equivalent one.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

13/15

CONTRACTORS DOC NO

269-CN-11-PR-001

10.0 CABLE TERMINATIONS


10.1 Unless otherwise specified all cable shall be terminated using cable glands in accordance to
approved drawings.
10.2 Cable glands for armoured cables shall have inner and outer seals and armour clamps. Cable
gland type and size shall be as specified in the approved documents.
10.3 Compression type lugs to be used for the following cables;
(a) Power cables having a solid conductor core and a conductor size over 10 mm
(b) Cables having a stranded type conductor and a conductor size over 0.75 mm
10.4 Compression type lugs not to be not used on the cables connected to equipment with clamp type
terminals.
10.5 The correct size of lug and crimping tool shall be used to ensure good conducting properties
and mechanical strength as per approved drawings.
10.6 All glands installed externally on all hazardous area electrical equipment shall have suitable
hazardous area classification. The installation requirements of the respective protection class and
certificates shall be satisfied.
10.7 Where cables are terminated in a certified enclosure, suitable cable gland sealing components
shall be provided as necessary to maintain the integrity of the terminal enclosure.
10.8 Cable glands for armoured cable shall have seals and armour clamps.
10.9 When preparing cables prior to fitting glands, the gland manufacturers instruction for cable
preparation shall be observed. In all cases where armoured cables are used, care shall be taken
to ensure that the lay of the armour is maintained after the gland is completely fitted.
10.10 HV cable terminations shall be made using stress relieving type terminations or elbow
connectors as indicated in the approved drawings and in accordance with manufacturer
specifications.
10.11 Power cables terminations at stud type terminals will be done using suitable cable lugs. The
correct size of lug and crimping tool shall be used to ensure good conducting properties and
mechanical strength.
10.12 Not more than one conductor shall be connected to one side of a block type terminal. Terminal
jumper links and additional terminals shall be employed for common connections with more than
one conductor.
10.13 One cable lug to be used for one cable core.
10.14 All unused cable entries in apparatus shall be sealed by the use of the appropriate type of
screwed plug where applicable. For hazardous area apparatus compatible certified plugs shall be
used.
10.15 All spare cores shall be terminated in spare terminals. Where spare terminals are not available,
spare cores shall be terminated at the earth bar as detailed in the approved drawings.
10.16 Cable entry to panels and equipments shall be bottom wherever possible. Where bottom entry is
not possible, side entry may be used. Side entry cables shall be provided with a drip loop to
prevent water settling at the gland seal.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

14/15

CONTRACTORS DOC NO

269-CN-11-PR-001

11.0 EARTHING AND BONDING


11.1
11.2

11.3

11.4
11.5
11.6
11.7
11.8
11.9
11.10
11.11

11.12
11.13
11.14
11.15
11.16
11.17
11.18
11.19
11.20

The earthing and bonding installation shall be carried out in accordance with the relevant
approved drawings
Earth bars shall be provided within switch rooms for bonding equipment. External equipment
shall be bonded directly to the relevant switch room earth bar or to the topsides structure via
dedicated earth conductor. Additionally external equipment will be connected to the module
steel work.
A buried earthing grid shall be installed which shall take the form of stranded copper cable,
forming a ring network around the plant with all splices, tees and cross connections made by
cadweld type joints. The above earth ring shall be connected to the main pile steelwork as
indicated on the approved drawings using compression type joints.
Power and instrument earth bars shall be installed in the Switch rooms. All earth connections
for equipment within the MCC module shall be made to the appropriate earth bar.
The power transformer secondary star point shall be connected to the MCC neutral bar.
Connections from earthing grid to local metalwork, process and electrical equipment shall be
carried out using yellow/green stranded copper cable.
Precautions shall be taken to prevent corrosion between any dissimilar metal joints due to
electrolytic action in the presence of moisture.
All non-current carrying metal parts of electrical equipment shall be effectively bonded to the
earth network.
Cable racking and cable trays shall have earth continuity throughout their lengths by using
bonding straps and shall be bonded to the structural steelwork at the intervals of 25 meter.
Pipeworks, vessels and tanks shall be bonded utilising the earthing bosses.
All pipework, HVAC ductwork and metallic insulation cladding shall be bonded to local
steelwork when entering a hazardous area or when entering or leaving a module enclosure,
unless connected to earth elsewhere. In addition, earth continuity shall be maintained
electrically and mechanically throughout.
If insulating flanges used at pipework, earthing plates will be provided for bonding across the
flange.
All cables glanded into clearance holes shall have their metal sheaths or armouring effectively
bonded to earth at both ends via earth tags in contact with the cable glands.
The cable screen on HV multi core cables shall be earthed at both ends..
The ends of all runs of rack and perforated tray shall be bonded to the steelwork. Adjoining
lengths of rack or tray shall be jointed together using bonding straps as described at item 6.14.
Ventilation ducts, when entering or leaving a module, shall be bonded across joints and to
earth, using tinned copper ground straps in accordance with approved earthing detail
drawings.
Every earthing connection after completion shall be liberally smeared with anticorrosive paste.
The paste approval will be taken before use it.
Spare cores of glanded multicore cables shall be terminated and collectively earthed within the
termination enclosure to prevent harmful induced voltages.
Socket outlets shall be earthed by a third core of the power cable as indicated in the approved
drawings.
Cable terminations at equipment shall be bonded to the equipment using a copper crimped type
earthing lug and suitable section of copper wire or strip. When plastic enclosures are used care
will be taken to ensure that internal equipment is properly earthed to a suitable earth terminal
in the enclosure and that earth continuity is maintained between incoming and outgoing cables.

SANGACHAL TERMINAL EXPANSION PROGRAMME

TEKFEN-AZFEN
ALLIANCE

PROCEDURE
FOR
ELECTRICAL INSTALLATION

COMPANY DOC NO

TB-CDOAZZ-CS-PRO-0001
REV. NO

PAGE / OF

15/15

CONTRACTORS DOC NO

269-CN-11-PR-001

11.21 Where non-metallic equipment or fittings are supplied, all armour clamp type glands shall have
the cable braid terminated in the gland. Non-metallic junction boxes, luminaries and control
stations shall have earth continuity plates or tags fitted inside the units so as to achieve earth
continuity. The cable gland must be bonded to the earth plates.
11.22 Earth continuity between cable glands and metallic equipment with tapered threaded entries
shall be achieved via the threaded entry to the enclosure.
11.23 Any special earthing requirements for equipment installed within a hazardous area shall be
provided in accordance with the specific equipment certification documents.
11.24 Earth cables shall have green/yellow colored sheaths.
11.25 All below grade work shall not be covered, until after a visual inspection by Company.
12.0 LIGHTNING PROTECTION
12.1 Complete lightning protection system shall be installed in accordance with the approved layout,
installation drawings and project specifications.
13.0 INSPECTION AND TESTING
13.1 Inspection and testing of the electrical equipment and installation shall be in accordance with the
Inspection and Test Plans, Doc. No.: 269-QA-00-QD-003 will be submitted to Company for
approval.

Anda mungkin juga menyukai