The study is made by collecting data from the both primary and secondary
sources.
Review of iron and steel industry and other facts was done by collecting
information from secondary sources like manuals, journals etc.
The company activities and background was studied by interacting with the
executives and information collected from their records and also by the training guide
provided by the company.
The exports activities and information like product mix, pricing, export marketing
procedure, export documents were collected during the discussion with the guide allotted
by the company for the project and the material give by the guide
Other information like marketing plans, various sales and production figures,
were collected from the management information system (MIS) division of marketing
department.
LIMITATIONS:
It is not possible to collect all the data as the managers are not available because
they are busy with their work.
Most of the managers are reluctant to give information because the data is
confidential.
Export marketing is very dynamic .The policies and export procedures are
updated every now and then.
electric reduction of iron ore. It is also manufacturing Ferro alloys and special
steel.
1951-56:
No steel plant came up. First plant was mainly agicultural oriented. But TISCO
was allowed to expand from 1MT/year to 2 MT/year of ingot steel and IISCO from .
5MT/year to 1.0 MT /year. However, the first five plans contemplated a new steel plant
to be erected in public sector. Thus the Hindustan steel ltd was born on 19 th January
1954, with the decision of setting up three steel plant each with one million tonne ingot
steel per year at Rourkela, Bhilai & Durgapur.
1956-61:
It is during this period that additional steel producing capacity was installed and a
bold decision was taken to increase the ingot steel output in India to 6 MT/year. The three
1 MT steel plant one each at Rourkela, Bhilai and Durgapur were completed during this
period. They started production during the end of this plan. In addition we are having the
capacity to produce 300,000 and 350,000 tonnes respectively of pig iron for sale.
1961-66:
During this plan the 3 plants under HSL, TISCO, IISCO, were expanded. The
expansion programs however could be completed only by 1968-69. Also were added
during this plan an alloy steel plant at Durgapur which has capacity of 100,000 tonnes of
ingots or 60,000 tonnes of finished steel, produces more than 100 categories of alloy
steels. The government was also considered to set up a steel plant at bokaro initially with
help of US. This, however, could not be materialized and in 1964 USSR agreed for
completed technical collaboration and assistance for bokaro plant in January 1964 BSL
came into existence.
1966-69:
RECISSION PERIOD:
The ambitious expansion programme taken up during the five-year plan could not
be completed during that period. All the expansion programmes were actively executed
during this period. The work on the first stage on bokaro plant (1.7Mt) started in October
1967.
1969-74:
Balancing facilities have been incorporated in all the steel plants. Work for 2 nd
stage expansion of bokaro was registered on October 25, 1972 to 4.0 Mt. Also started in
this period, Salem steel plant. Work on Sales steel plant project was also taken up during
this period licences were given for the setting up of many mini steel plants and re-rolling
mills. Government has accepted the idea of setting up 2 more steel plants in the south one
each at VISAKHAPATNAM AND and hospat. Both these produce plain, low carbon steel
products initially with a capacity 2 mt. Year of ingot steel. SAIL was also formed during
this period on 24 January, 1973. All the plants tried to increase their production with the
result the total steel output also increased. There was significant increase in the quantity
of steel products exported to other countries. Central research & development
organization was set up in June 1973 to tackle the research and development of the iron
& steel industry countries.
1974-79:
Work on Salem Project programmed well. Bokaro with 1,7 Mt capacity started in
February78, The expansion of Bhilai Steel Plant from 2.5 Mt. To 4.0 Mt. And bokaro
from 1.7 mt to 4.0 mt. Picked up momentum. The idea of setting up the 5 th integrated
steel plant, the first shore-based plant at vizag took a definite shape. More mini steel
plants and re-rollers have been added. Modernization work on RSP also started. By the
end of fifth five-year plan , the total installed capacity from 6 integrated plants was 10.6
mt.
1979-80:
ANNUAL PLANS:
The various plans on hand were reviewed and the progress on different plants
consolidated. Soviet Union has agreed to help in setting up the VIZAG steel plant.
1980-85:
Almost all the units in the expansion work of Bhilai & Bokaro to 4.0 mt
Completed on VIZAG steel plant picked up and the rationalized concept has been
introduced to commission the plant with 3.0 mt liquid steel capacity by 1990.
1992-97:
All units of VIZAG steel plant are commissioned by July 1992. Government of
India has given permission to private parties to set up mini steel plant.
RE-ROLLING MILLS.
8. They serve as centers for the development of ancillary industries around the steel
plants.
9. They are major consumers of refractory materials. About 30-40kg of refectories
are needed to produce one ton of crude steel.
.
CHARACTERISTICS OF THE RE-ROLLING MILLS:
1. They buy the primary rolled product from integrated steel plants or mini steel
plants and process them into finished rolled products.
2. They generally dont have any meeting and refining facilities.
3. Originally re-rolling mills were producing only bars and rods but now they
produce variety of products like light structural, ribbed bars etc. .
4. Though the installed capacity re-rolling mills is 21mt only of the rolling steel. Out
of 1061 re-rolling units, 396 are closed of various problems. Global environment
facility (GFE) a government project has now taken up the revival plan for rerolling industry.
FUTURE PLANS:
Though steel industry is having recessionary trends now, it is bound to stage come
back sooner than anticipate. With the increased volumes, economy of operations becomes
competitive. In recent past steel market has turned into buyer market from seller market.
Steel industry in India has prepared their future plans keeping customer satisfaction in
view.
SAIL has prepared a corporate technology plan for 2005A.D which aims to
achieve target capacities through technology upgradation and moderation, creation of
new facilities and introduction of new technologies. Besides this, SAIL has been also
11
planning to hive off some of its power plants, oxygen plants and fertilizer plants at
Rourkela etc.
RINL has worked out a corporate plan up to 2002ad which envisages to introduce
modern technology in coke ovens and blast furnace to increase their capacities, add
second steel melting shop with a slab caster, by investing an amount of approximately
Rs1520crores .When implemented, plant would produce 3.85Mt of hot metal and 4.05Mt
of steel by the year 2201-2002ad.RINL is now also planning to hive off its power plant.
As a separate company, it would come under infrastructure sector and all the benefits
available to this sector can be availed.
TISCO has also completed its modernization plans. Recently they have set up a
hot strip mill and are now setting up a cold rolling mill which is expected to be
commissioned in the year 2000.Setting up of the new bar mill announced earlier has been
put on hold.
Though majority of steel now in India is producing through LD converters present
trend in the world is to adopt electric arc furnace route. It is predicted that percentage of
steel produced through eaf route in the world in the year 2010 will increase to 50% from
the present level of nearly 35% new steel plants are likely to be commissioned in next
few years adding a capacity of 13mt of steel per annum.
12
13
INDIA:
India is the 10th largest producer of steel in the world with a production rate of
23.4MT in 1997. With its abundant mineral resources, cheap lab our and strategic
location India has a potential to become force to recon in global arena. After govt. of
India adopted the policy of economic liberalization is looking up 21 projects with
licensed capacity of 12 MT with investment to the tune of RS22000 have been cleared
since 1991 and are in different stages of construction and commissioned 6 more projects
with 5 MT installed capacity are in the pipeline investing about RS 10000. by 2006 it is
expected steel demand will rise to 49MT including provision of 9MT towards exports
however ,presently Indian steel industry is passing through a dark phase due to crashing
of prices on global market and general recess in Indian economy and currency crisis in
south east Asia since august 1996. Dumping of cheap steel by CIS countries and South
Korea, Japan has affected the local steel industry adversely.
14
INTRODUCTION
To set up an integrated steel plant at Visakhapatnam was announced on 17th
August 1970 by Smt. Indira Gandhi in Parliament and the formal inauguration was done
on 20th January 1971.
The plant annual capacity was 3 million tons of liquid steel in October 1977.
USSR helped India in setting up the 3.4 million tons integrated steel plant at
Visakhapatnam in the year 1979. The project is estimated to cost Rs. 6,269.57 tons based
on Mills as on first quota of 1986.
VSP became the first Integrated Steel Plant to achieve the distinction of covering
all the process and products under ISO 9002, ISO 14000 and ISO 18000 for the entire
plant.
Having a total manpower of about 17,000, VSP has envisaged a labour
productivity of not less than 230 Tonnes per man per year of Steel which is the best in the
country and comparable with the International levels.
The main consideration for setting up the steel plant at Visakhapatnam was to have
locational advantage of port on the coast of Bay of Bengal.
However, locational
advantage could not be utilized fully by the Company due to various constraints and nondevelopment of captive harbor adjoining the plant site. The main objectives of RINL on
its incorporation were to take over the VSP from SAIL with all its assets, liabilities, rights
and obligations and to carry on in India and elsewhere manufacturing, trading, importing
and exporting of iron and steel of all qualities.
15
MISSION:
To be a continuously growing company through technological up-gradation,
operational efficiency and expansion, producing steel at international standards of cost
and quality ensuring optimal return on investment to stakeholders and meeting
expectations of the customers.
OBJECTIVES:
16
INFRASTRUCTURE FACILITIES
Location:
The plant is located on the coast of Bay of Bengal. 16 Kms. to the South west of
Visakhapatnam port. It lies between the northern boundary of National highway from
Madras to Calcutta and 7 Kms. the south of the Howrah - Madras Railway line.
Visakhapatnam is well connected by own with unique cities of India.
The area enclosed within boundary wall of steel Plant is about 2,600 hectares.
Additionally 2,600 hectares is occupied by Steel Plant Township and 350 hectares by
Kaniti Balancing Reservoir.
Power:
Total requirement of power in VSP is 280 MW where 3.0 million tons stage is
reached.
Parts of this requirement are met from 4x60 MW generators at VSPs own captive
power plant.
Two steam turbine generators of 7.5MW each generates power using waste heat
of dry quenching unit of coke ovens and 2x12.0 MW temperature pressure recovery
turbines will generate power utilizing high pressure available from temperature gases of
BF.
The balance 1.39MW (about 150MVA) of power is to be supplied by the Andhra
Pradesh state electricity board to meet the maximum demand requirement of power at
VSP.
Water:
The total water requirement of the plant will be 73 million gallons per day, which
is to be met by the Yeleru water supply scheme, which is an Andhra Pradesh government
project.
17
Auxiliary Facilities:
Extensive facilities have been provided for repair & maintenance as well as
manufacture of spares. The repair shop complex houses machine shop, structural shop,
Steel and NF foundry, Forge shop, Loco & wagon repair shops, Electrical repair shop,
Utilities equipment repair shop, Air conditioning & ventilation system repair shop.
In addition to the above basic units to carry out various operations, VSP is having
fully equipped Research & Control Laboratories to monitor and control all the operations
carried out in the Plant.
It is also having well established Training and Development Center to train the
newly recruited personnel and to conduct refresher courses for the employees and make
them able to handle jobs assigned to them during their regular duties.
RAW MATERIALS
SOURCE
Bailadilla, M.P.
BF Lime stone
Jaggayyapeta, A.P.
Jaisalmer, Rajasthan
BF Dolomite
Dubai
SMS Dolomite
Madharam, A.P.
Manganese ore
Chipuripalli, A.P.
Boiler Coal
Talchar, Orissa
Coking Coal
Australia
18
MAJOR UNITS:
DEPARTMENTS
ANNUAL
(000T)
COKE OVENS
2,261
3 Batteries each of 67
ovens
&7mts Height
SINTER PLANT
5,256
BLAST FURNACE
3,400
STEEL
MELTING 3,000
SHOP
3 LD Converters each of
150 cum. volume & six 4
strand bloom casters
LMMM(Light
& 710
850
MMSM(Medium
850
Merchant
Structural
Mill)
Besides these main metallurgical units Captive Power Plant of 247.5 MW
capacities, Oxygen Plant, Acetylene Plant, Compressed Air Plant, Extensive repair and
maintenance facilities form part of the services available at VSP.
Steel Plant can take pride in having a clean & green township with provision of
about 8000 quarters, markets, community welfare centers, clubs, etc. for the employees
and their families besides having a modern hospital with 155 beds
MODERN TECHNOLOGY:
19
Seven-meter tall coke oven worth dry quenching of coke using Nitrogen gas,
steam generated during this process is to be used for power generation. 3200 cum. Blast
furnaces, the longest in the country with conveyor changing the belt less top equipment.
Gas expansion turbines are provided for power generation by utilizing the BF gas top
pressure.
casting of liquid steel into blooms. High speed Rolling mills with computerized controls
and extensive waste heat recovery system were provided
MAJOR PRODUCTION UNITS:
A) Coke ovens:
The coal is proposed before charging into Coke ovens in coal tower.
The
prepared coal in the coal tower is drawn by a changing car on the top of the batteries and
charged into the ovens as per the sequence -0 The charged coal is gradually heated in
absence of air to attain a temperature of 1000-1050 0 C which generally takes about 16
hrs for the coke to be ready. The volatile matter escaping during carbonization is
collected in a gas collection main through stand pipe. The stone is cooled by Ammonia
liquid spray and sent to coal chemical plant. The ready coke is pushed out of the oven by
a pusher car into a coke car and is taken to the dry cooling plant for discharging the hot
coke into cooling chambers.
There are three batteries, each having 7 ovens. Each oven is having a volume of
41.6 m2 and can hold 31.6 T of only coal charge.
The heat for carbonization is being supplied by a mixture of blast furnace gas and
coke oven gas having a calorific value of 1000 Kcal/NM3.
Batteries are of under jet, compound type having twin heating filled and
recalculation of waste gases.
20
An initial mix consisting of ore fines and blue dust, manganese ore,
metallurgical wastes, dolo-fines, sand, 80% of limestone and 80% of coke fines is
prepared. This mix along with sinter returns, Sinter screenings 20% of lime fines and
20% of fine coke is stocked in bunkers. Moisturizing and palletizing is carried out in 4.2
x 24m drum mixer to obtain homogeneous mixture with partial palletizing and optimum
moisture. 10-25 mm size sinter is used as hearth layers of about 40mm thick. This
decreases dust entrapment by exhaust gases, reduce grate bar consumption.
Sinter mix up to 300mm thick is laid on the heath layer. A mixture of coke oven
gas and blast furnace gas having a calorific value of 2,000 Kcal. NM 3 is used for
ignition.
The prepared sinters is crushed to about 15mm size and cooled by forcing
atmospheric air. This sinter is then sends to blast furnace through conveyors.
C) Blast Furnace:
There are two blast furnaces of 3,200 cubic meter useful volumes, each capable of
producing 1.7 Mt of hot metal per year while operating for 350 days are installed. There
are four hot blast stores for each furnace with a total heating surface of 224,000 square
meters. The dome can be heated to a temperature of 1450 0 C maximum while the waste
flue temperature is up to 4000 C. Stores are heated, by a mixture of blast furnace gas and
coke oven gas having a calorific value of 1100 Kcal/N Cum, up to
1300 0C pressure
D) Rolling Mills:
The cast blooms produced in SMS-CCD do not find much applications as such
and are required to be shaped into products such as Billets, rounds, squares, flats, angles
(equal & unequal), T-bars, Channels, I-PE beams, HE beams, wire rods and
reinforcement bars by rolling them in three sophisticated high speed high capacity, fully
automated rolling mills. They are
1. Light & Medium Merchant Mills
2. Wire Rod Mills
3. Medium Merchant & Structural Mills.
All the above-mentioned Rolling mills are Hi-Tech Rolling mills with
full automation and all modern equipments.
Blender reclaims for blending of ores and flux in which the bucket wheel
has a lateral motion across the bed.
Wheel on boom reclaims for reclaiming different materials from some bed
in ore of flux yard and same type coals in CHP.,
22
Preparation of sized iron ore for use in BF to enable close size range of
raw materials.
23
ACHIEVEMENTS:
Commissioned in 1989, it was the shore based, integrated company spread over
an area of 5000 sq.km. Since commissioning, VSP has crossed many mile stones in the
fields of production, productivity and exports. Some of the peak achievements are:
ISO 9002 for SMS and all the downstream units- a unique distinction in
the Indian Steel industry.
24
Rolling Mills.
Light & Medium Merchant Mill (LMMM) Wire Rod mill (WRM)
Auxiliary shops.
Forge shop
Foundry
25
For the financial year 2002-03 ,VSP is expected to achieve a net profit if around
Rs.450 crores inspite of the best efforts by VSP, collective, achieving net profit became
an eluding milestone due to various reasons like long gestation period ,high interest loans
and low demand cycles during the last 10 years. But these odds never deterred VSPs
determination to achieve success. While the tear 2001-02 was the year of achieving
Rated capacities, the year 2002-03 is the year of Turn around for VSP
Five key parameters that led to VSPs turnaround are:
1. Innovation and up gradation of the plant equipment.
2. Efficient operations management coupled with optimum waste
utilization and cost reduction measures.
3. Marketing policies and strategies aided by speedy decision making to
achieve record sales.
4. Healthy HR with emphasis on motivation and morale boosting of
employees.
5. Dynamic financial and cost management.
Marketing performance:
VSP has posted its best turnover of Rs. 5059 crs. This corresponds to 24% in
improvement in total sales over the last year. The total sales include best domestic sales
of Rs. 4443 crs and Rs. 626 crs of export sales. While the domestic sales improved by
19%, exports grew by 69 % over last year. VSP has sold 4.25 lakh tons of special steel, a
growth of 16% over last year.
26
27
28
1. By Inviting Bids:
VSP invites bids from organizations / persons to whom VSP is already exporting
and also to the updated customers. The customer database is regularly updated on the
basis of inquiries received from time to time.
The bids are received by internet/E-mail. After analyzing the bids, VSP allocates
(exports) the products to different bidders on the following basis.
2. By spot Booking:
VSP also believes in the demand forecasting about the products produced by them
for the next quarter and the quantity already committed during the next quarter.
If any surplus is left over and if some of the customers require more quantity VSP
takes spot booking taking into consideration the quantity ordered and the quantity
available.
Spot booking is generally accepted for any price, which is above a minimum price
known as floor level price (FLP) the price is fixed after negotiations between VSP and
the trader booking the order.
29
This step involves opening of letter of credit (L/C) or any other financial
agreement by the customer. Once this is done, it ensures that there is no chance of any
default once the goods are exported by VSP.
It will be confirmed by VSP after the receipt of L/C in VSPs format. In some
exceptional cases, delivery schedule can be extended beyond the quarter by one month at
the decision based on the rolling programmed.
At this stage, the advance license department of the exports gives the advance
license application No. Notice of readiness (NOR) is issued to the customer after rolling
is completed.
This step involves nomination of a vessel to carry the goods to their destination.
VSP mainly follows two ways of nomination vessels, which are
FOB (Free on Board): In these conditions the seller delivers the goods on
board the vessel free of cost to the buyer at a port of shipment named in the
sales contract ( (90% of VSPs export are on FOB basis)
30
CIF (Cost Insurance and Freight): In it the word cost signifies the price for
the goods themselves. In CIF, the seller has to procure insurance against the
risk of loss or damage to the goods during the carriage. The main difference
from FOB is that in CIF the seller (VSP) nominates the vessel and pays for
carriage.
In this step, the acceptance of the nominated vessel takes place. VSP decides the
acceptance of the vessel on the following basis.
Once the product is rolled out as per the customer specification, the next step is
the transportation of the finished goods from the plant to the port. Here, a filled AR4 form
has to be submitted to central excise authorities it keeps in eliminating the needs to pay
central excise duty on the goods to be exported.
31
In this stage, some customs formalities are fulfilled.Filing a shipping bill with the
customs. The shipping bill contains the description & quantity of the goods being
exported & the value of the above mentioned goods.
In this step, when the vessel arrives, loading takes place on the vessel. Generally,
the no of days to be taken for loading is decided before the loading takes of. If VSP loads
the goods in lesser no of days than the agreed no of days (Lay Days) it earns certain
amount of money known as dispatch money from the master of the vessel. In reverse
situation, VSP has to pay to the master of the vessel a penalty, which is known as
demurrage charge.
Description of goods.
Quantity shipped
Loading Port
Destination Port
32
Notify address
lading if registered is issued either by the master of the vessel or his agent on submission
of the masters receipt. Its prepared strictly in accordance with a specified format.
(L) CONTRACT AND AMENDMENTS THERE TO
After finalization of an order, the marketing department informs the details like
material specification, size, quantity, delivery schedule etc. to PPM, works department
concerned, finance, and advance licensing section etc.
The advance licensing informs the advance license application No. or advance
license No. and Duty Exemption entitlement certificate (DEEC) book number to the
concerned officer in exports section. Marketing people then send the detailed contract for
sale and purchase of steel products/pig iron in the approved form in duplicate to the
buyers for his signature. On receipt of the signed contract copies from the buyer, they
sign the contract on behalf of VSP. They also send one copy of the signed contract to the
buyer and a photocopy of the contract to the Finance Dept., independent Inspection
Agency, and shipping section under marketing.
If the buyer insists on some amendments to the approved format the marketing
department obtains the approval of the competent authority and communicates to the
buyer accordingly. In case any amendments is required in the contract including
extension of delivery schedules, the marketing departments takes the approval of the head
quarters Marketing Committee (HQMC) or competent authority as per the delegation of
powers.
33
If the contract copy forwarded to the buyer is not returned to VSP within the
stipulated time.
If the buyer fails to place the vessel for loading within the agreed time or the
vessel placed is not suitable for the loading, negotiate the documents as per the
Red clause. If there is no Red clause cancel the contract.
34
If a buyer fails to open the letter of Credit (L/C) within the stipulated time or fails
to carry out necessary amendments to L/C within the stipulated time. In such
cases the marketing department informs the Finance departments, works Dept.
concerned and Advance License section about the cancellation of the contract.
When a contract is cancelled for any of the above reasons, the marketing
department encashes the performance Bank guarantee submitted by the buyer, if any, as
per the delegation of powers.
(O) APPOINTMENT OF PRE-SHIPMENT INSPECTION AGENCY:
The marketing dept. issues tender Enquiry to at least three parties of International
repute, having operations at Visakhapatnam. (The tender enquiry shall be issued at least
30 days before the expiry of the present contract.
They also allow ten days time to the parties to quote against the enquiry. They
also follow the standard procedure for receipt, opening and evaluation of the tenders
received and finalized the tender.
(P) APPOINT OF TRANSPORTATION HANDLING AND STEVEDORING
AGENTS:
The marketing department issue limited tender Enquiry to all eligible parties with
the approval of the competent authority. They ensure that all parties have got valid license
to work at Visakhapatnam Port.
35
DOCUMENTATION:
A distinguishing feature of international trade is the complex paperwork.
Therefore many small exports are frightened by the extent and complexity of the
documentation.
CLASSIFICATION OF DOCUMENTS
A. DOCUMENTS RELATED TO GOODS:
1. Commercial invoice:
A commercial invoice gives details of the goods, which are the basis of the
the transaction between the exporter and the importer. It is an important document.
This performs many functions
i)
ii)
iii)
2. Performa invoice:
An importer may require a proforma invoice for the following purposes:
i)
ii)
iii)
3. Packing list:
The exporter is required to pack the goods according to the instruction of
36
ii)
iii)
iv)
5. GSP Certificate:
Under the generalized system of the preferences scheme of the united Developing
countries are given the facility to export their manufactured goods to developed
countries, at concession rates of duty. India is one of the recipients of such concession. In
order to avail this benefits a GSP.
Certificate of origin is required to be obtained from a competent authority. The
government has authorized the export inspection council and the director general of
foreign trade (DGFT) to issue the certificate for all the items.
It has also authorizes the central silk board, the courier board, the all India
Handicrafts board, the textiles committee and the jute commissioner to issue such
certificate in respect of items falling under their control.
37
1. Shipping order
2. Mates receipt
3. Bill of lading
Contents of bill of lading:
Name and address of the person to notify when goods reach destination port
Description of goods
Number of packages
38
Sum insured
Period of insurance
39
3. Documentary bills:
Documentary bills are sets of bill of exchange which are attached to the
documents related to the export transaction. Usually documents attached are the Bill of
lading and insurance policy certificate. These documents will enable the Importer to take
physical delivery of the goods either on payment or on acceptance of time bill.
4. Bank certificate of payment:
This certificate is issued by the negotiating bank, that is, the exporter bank
certifying that the bill covering the particular consignment has been negotiated and the
payment has been received in the maker specified under the exchange control regulations.
41
42
there on becomes the buyers problem. The ex-factory arrangement limits the exporter
risk. However, an importer may find an ex-factory deal highly demanding.
The F.A.S contract requires the exporter to be responsible for the goods until
they are placed along side the ship. All charges incurred up to that point must be borne by
the seller. The F.A.S price is slightly higher than the ex-factory price, since the exporter
undertakes to transport the goods to the point of shipment and become liable for the risk
associated with the goods for the longer period.
The F.O.B price includes actual placement of goods aboard the ship. The F.O.B
contract requires the following seller and buyer obligations.
The seller must:
a) Deliver the goods on board the vessel named by the buyer at the port if
shipment on the date specified in the contract.
b) Bear all cost payable on or for the goods until they have effectively
been placed aboard the ship.
c) Suitably packed goods for the mode of transportation specified.
d) Provide documentation indicating proof of delivery of goods aboard the
mode of transportation.
The buyer must:
a) Arrange for transportation specifying the mode of transportation to the
port of departure
b) Bare all cost and risk from the time of goods have been placed on
board the mode of transportation.
In the C.I.F price quotation, the owner ship of the goods passes to the importer as
soon as they are loaded abroad the ship. But the exporter is liable for the payment of
freight and insurance charges up to the port of destination.
The delivered duty paid alternative imposes on the exporter the complete
responsibility for delivering the goods at a particular place in the importer country .Thus
43
the exporter makes arrangements for the receipt of goods at the foreign port ,pays
necessary duties and handling, and provides for further inland transportation in the
importer country. Needless to say, the price of the delivered duty paid goods is much
higher than the goods exported under the C.I.F contract.
Currently VSP follows F.O.B price for exports and C.I.F price for imports as they
are more beneficial.
DISTRIBUTION:
Due to its located near the coastal area base and near to the port, it is having very
much suitability for its distribution of its products. The distribution is mainly from the
exports departments and they will distribute according to the demand. The parties which
what the products of V.S.P. Meet at the export section and marketing department or they
will send message by fax or by telephone they will contact and distribution was done
according to the demand of the party.
MODE OF TRANSPORT:
1. Railways
2. Road
3. Sea Port
PROMOTION:
44
VSP have their website named vizagsteel.com and a few magazines circulated
internally or externally. These are:
1. Steel File (Bimonthly)
2. T.Q.M Journal (quarterly)
3. Gangavaram se (Quarterly)
4. Ukkuvani (Monthly)
45
3. PRICE BASIS:
3.1. Unless otherwise agreed, price of the material shall be free on board
(stowed), Visakhapatnam port, Visakhapatnam, India.
3.2. (Applicable for steel products only): The BUYER shall arrange at his own
cost and expense to provide materials including dunnaging required for stowing,
dunnaging, lashing, shoring and securing of the materials inside the hatches /holds
of the vessel at load port to the master of the vessel nominated by BUYER and
accepted by SELLER for delivery as per clause 5 herin below. Labour charges
involved in the work of dunnaging/stowing /lashing/shoring and securing of the
materials shall be borne by seller.
3.3.
SELLER
shall
under
no
circumstances
be
liable
for
any
46
4.1. Subject to these terms and conditions (and expressly agreed deviations
/deletions/additions of any) , the SELLER is obliged to sell material of technical
specifications as agreed and the BUYER is obliged to buy the same.
4.2. (Applicable for steel products only).
Size wise and specifications wise break up shall be as agreed. Unless otherwise
agreed , SELLER has a right to sell/dispatch ./ship the material as per agreement
with quantity variance of +of 5% on total quantity with + of 10%for each size
and specification at SELLER s option with packing and marking as usually done
by seller .Unless otherwise agreed, SELLER shall invoice on the basis of actual
net weight. Quantity and quality shall be certifier in Inspection Certificate by an
independent inspection agency at BUYERS cost to co-jointly carryout survey
with the independent
Inspection agency appointed by the SELLER, in accordance with international
standards, regarding the physical condition and packaging of the cargo at the
transit storage yard port on a lot wise basis.
4.3. (Applicable for pig iron material):
Unless otherwise agreed, the tolerance on quantity to be delivered shall be +/-10%
at buyers option .The option shall be exercised by the BUYER at the time of
nomination of the vessel. Weight (quantity) shall be established by draft survey at
loading port by an independent inspection agency, and the quantity and quality
established at load port shall be final. Weight of deleterious impurities such as
nonferrous dirt, dust, moisture over 0.5 %( half percent) shall be deductible from
the final weight. Buyer has freedom to nominate their own agency at Buyers cost
to co-jointly carryout out quality and quantity survey with the independent
inspection agency appointed by the SELLER, and the inspection is to be carried
out in accordance with international standards applicable for pig iron of quality
inspection and draft survey.
47
4.4 The cost of inspection by the independent inspection agency appointed by the
SELLER. The inspection certificate issued by them certify, inter-alia
that the materials were inspected at the loading port prior to loading and that the
marking were as per requirements of the Agreement between the SELLER and the
BUYER;
the size wise break-up of quantity loaded on board the vessel indicating the
number of bundles /coils (APPLICABLE FOR STEEL PRODUCTS ONLY): and,
that materials were loaded on board the vessel without apparent damage were
found to be in good order and that the materials were properly lashed and secured
inside the hatches /holds of the vessel.
5. DELIVERY/ SHIPMENT:
5.1. The SELLER shall deliver the materials free in the holds of the vessel
nominated by BUYER and accepted by the SELLER as per these terms and
conditions in one or more safe berths reachable on arrival always afloat at loading
port which shall be Visakhapatnam, India .Unless financial arrangement is made
by the BUYER se per clause 6 .below of otherwise as agreed by SELLER, the
SELLER is not obliged to confirm delivery.
5.2. The BUYER shall nominate a vessel not more than 25 years old with lay
date/cancellation date within 30 days of Sellers notice of readiness of materials
for shipment of within the laydays in case given by the SELLER of acceptable to
the SELLER whichever is earlier .The BUYER shall take into account limitations
of the port such as maximum LOA of 12 mts , maximum beam length of 30.48
mts and maximum laden draught of vessels as .448 mts in some berths and 10.06
mts in others.
5.2.1 In case there is a delay by the SELLER to confirm notice of readiness of
materials and the BUYER had made financial arrangements
as agreed the
BUYER has the option to cancel the contract or take the delivery of the material
48
at the contract price & terms within a period of 90 days beyond the original
agreed delivery period.
5.3 While nominating a vessel the BUYER shall communicate following
particulars for the nomination.
a) Name of the vessel
b) Year of built & Flag
c) Classification
d) LOA/Beam/Draft at max .DWT.
e) Loadable tonnage /nominal tonnage for delivery
f) No of Decks /single decker/TWEEN decker if TWEEN, the third deck if
any)
g) No of holds/hatches
h) Hatch Openings: Weather deck/Tween deck
i) Type of hatch covers: Weather deck /Tween deck
j) Cargo gear capacity: Cranes-single swinging Derricks-Configurations
hatchwise-Derricks working in union purchase-not acceptable.
k) ETA /laydate/ cancellation date at load port.
5.3.1 The SELLER is entitled to following additional information if required :
a) Original name of vessel if changed at present
b) Whether disponently owned
c) Owners P & I Club
d) Disponent Owners P & I Club
e) Last special survey
f) Last dry docking
g) Position of engines
5.4 The vessel nominated by the BUYER shall be geared and equipped with
cranes/derricks capable of lifting minimum specified tonnage at a time as below
from the wharf and placing the materials in the places of the hatches including
49
wing spaces and having minimum four available hatches. The SELLER shall
guarantee a loading rate 2000MT per weather working day of 24 consecutive
hours Sundays , holidays and non-weather working days excepted even if used
(2000 MT PWWD SASHEXEIU) for steel products and a rate of 4000 MT
PWWD SASHEXEIU for pig iron subject to these terms and conditions of the
basis of five or more available workable hatches of hooks ,whichever is less . The
SELLER is not obliged to accept vessels with gear capacities ,less than three
hooks .If due to any reason , a vessel is accepted with lower gear capacity or
lesser number of hatches /hooks ,the load rate shall be reduced prorata .The rate of
demurrage/despatch shall be as mentioned in the below table:
In the case any /all vessel gears are not suitable for loading the cargo , due to any
reason and in case buyer provides shore crane berths & shore cranes at his cost
the same will be considered as gear for the purpose of laytime calculations. In
such an event waiting time for getting shore crane berth shall be excluded from
time used.
In case and hatches is doubled up, it shall be considered as double hatch only
when two cranes that are capable of being worked by two gangs simultaneously
are made available for not less than 75% of loading time of that hatch.
Product
Norm.Qty
Gear
Demurrage/
for delivery
Capacity
Despatch
(MT)
(MT)
USD
(MIN)
per day
Pig iron
9999 or below
15
NIL/NIL
Pig iron
10000-19999
15
4000/2000
Pig iron
15
6000/3000
Steel
9000 or below
NIL/NIL
Steel
9001 9999
4000/2500
Steel
10000 -19999
5000/2500
Steel
10
6000/300
50
NOTE: Union Purchase Type Gear is not acceptable .The loading shall be on
CQD basis for cashews of NIL demurrage/despatch .It is preferable to have tween
decker for wire rods and single decker for pig iron .Stacking below the coils will
be rolled on plates below wing space will be three high for wire rods ,above
which the coils will be rolled on plates below the wing space and drop stowed in
the hatch openings . Tank tops should be able to support forklift along with
materials for loading steel cargo. Tank top strength should be 10T/M2 in respect
of 3T forklift for 3 high stacking and 16T/M2 for 10T forklift for 4 high stacking.
All cargo except WRC will be drop stowed in the hatch opening with in the reach
of vessel cranes only.
If one or more parties nominate a vessel for lifting part quantity of pig iron in
different sale contracts .the dem/dis amount shall be calculated as per the rates
applicable for the total quantity loaded in the vessel by all parties concerned and
the dem/dis amount so arrived shall be payable on prorata bases as per the
quantities lifted by the respective individual p0qrties /in different sale contracts.
In case party nominates part vessels for steel consignment ,the despatch
/demurrage calculations will be made based on per working per hatch per day of
per workable hatch per day basis as given below: PER WORKING HATCH
PER DAY or PER WORKABLE HATCH PER DAY means that laytime is
to be calculated by dividing the quantity of cargo in the hold with the largest
quantity by the result of multiplying the agreed daily rate per working workable
hatch by the number of hatches serving that hold. Thus:
Laytime = Largest Quantity in one hold
--------------------------------------- = Days
Daily Rate per Hatch x number of
Hatches serving that hold
51
5.5 The SELLER shall communicate acceptance /non acceptance within next
working day and with reasons in case of non-acceptance. However, the SELLER
is not obliged to consider any nomination of the vessel unless financial
arrangement is made by the BUYER as agreed.
5.6. Upon arrival of the vessel within the limits of the loading port and after.
a) Ensuring that the hatches /holds of the vessel have been thoroughly
cleaned
b) obtaining free pretique and
c) ensuring that the vessel is load ready in all respects,
the Master of the vessel shall serve the Notice of readiness of the vessel to load
the Materials (i.e. Masters N/R) on the port office of the SELLER at the loading
port, during normal office hours which are 9.30 AM to 4.30 PM from Monday to
Saturday .The masters N/R shall not be server on Sundays /Port holidays /Charter
Party holidays. /Non weather working days.
5.7.Upon arrival of the vessel within the limits of the loading port or at any time
later till completion of loading ,if the SELLER or the load port authorities
consider that the cranes / gears of the vessel are not capable of lofting the
materials of the weights and dimensions as agreed, from the wharf and placing the
material inside the hatches as required for loading ,the SELLER has right to
reject the vessel outright without any liability including freight and all other
consequences/losses arising thereof. Incase it is considered that the loading rate
52
53
5.8.6. The master of the vessel shall allow on board the vessel the representative
of the independent inspection agency appointed by the SELLER and provide such
information/ assistance as may be required by such agency in connection with the
performance of their assignment duties.
5.8.7. The master of the vessel shall provide free use of light on board the vessel
as may be required for working the vessel at the loading port at all times and in
each case free of expense to the SELLER The master of the vessel shall make
available all the hatches for loading of the materials throughout the period the
vessel is worked for loading of the materials except in such hatches where the
materials have been completely loaded.
5.8.8.1. Laytime shall commence at 1300 hrs if Masters N/R is serve in the
afternoon.
5.8.8.2. Time between noon on Saturday and 0800 hrs on Monday and /of
between noon on the last working day preceding a legal holiday and/of port
holidays /Charterparty holidays and 0800 hrs in the next working day shall not
count as laytime even if used .unless the vessel is on demurrage.
5.8.8.3. After berthing if the port authorities of representative of the SELLER find
that the vessel is not ready in all respects to load ,the laytime will not commence
until the vessel in proceeding from the anchorage to the berth shall not count as
laytime unless the vessel is on demurrage.
5.8.8.4. In the event of breakdown of vessel gear or other equipment of the vessel
by reason such as insufficient power etc, not attributable to shipper the period of
such break down shall not count as laytime.
5.8.8.5. Time lost due of the following reasons shall not count as laytime unless
the vessel is on demurrage:
54
Non weather working days declared by the port authorities even if the
vessel is worked.
Accidents at Wharf
Stoppage, whether partial or total, due to other causes beyond the control
of the SELLER.
5.8.8.6. The opening and the closing of the hatches of the vessel shall always be
done by the vessels crew and the cost involved therein shall be to the account of
the vessel.
5.8.8.7. The time lost due to shifting of the vessel within the port limits shall not
count as laytime . However, if the shifting is required by the SELLER, the shifting
charges shall be to the account of the SELLER and time lost in shifting shall
count as laytime.
5.8.8.8. The overtime of the crew and officers shall be to the account of the
vessel.
5.8.9. If any damage is caused to the vessel at the loading port at the time of
loading of the materials by the Stevedores engaged by the SELLER,. The claim, if
55
any, for such damage shall owners and the stevedores. The Master of the vessel
shall lodge such claim, if any, on the stevedores, promptly after the damage
Reports ,prior to the departure of the vessel from the loading port ,failing which
the claim shall stand barred and the stevedores shall stand absolved and relieved
of all responsibility .Subject to compliance with the conditions enumerated in the
clause ,in case the stevedores fail to settle the same ,the SELLER shall be
responsible for settlement of such claims.
5.8.10 Statement of Facts: Immediately after completion of loading of the
materials into vessel and before the sailing of the vessel from the loading port (s)
a statement of facts shall be made out at the loading port(s) duly signed by and
distributed amongst; (a) Master of the vessel /Agent of the vessel at the loading
port (b) Agents/Representative, if any of the BUYER at the loading port and (c)
representative of the SELLER at the loading port.
5.8.11. The Master of the vessel shall deliver a stowage plan in triplicate duly
signed by him before loading and immediately after completion of loading and
sailing of the vessel, if sought by the SELLER..
5.8.12. The ship owners shall instruct their Agents at the loading port to issue the
Bill(s) of Lading with marking as per LC (see 6.2.1(a) to the representative of the
SELLER ,immediately but within one day from the date of completion of loading
of the materials in the materials into the vessel.
5.9 Freight enquiries shall be notified in advance to:
Ministry of surface Transport,
Chartering wing (transchart)
Transport Bhavan , Sansad Marg.
NEW DELHI 1100001(INDIA)
TELEX:031-61147,61158,61159 VAHAN ND.
While nominating a vessel and preference is to be given Indian flag vessels.
56
Bank of Baroda
Vadlapudi Branch
SWIFT:
SBININBBA145
as per the negotiating documents negotiable at the counters of any branch or any
bank of India.
6.2. PAYMENT AGAINST LC
6.2.1. The LC shall be available for payment of 100% of value of invoice (less if
any advance is already paid by the BUYER, covering the material shipped against
presentation of the SELLER drafts drawn at sight accompanied by following
Bank documents (and also against clause no.6.8 herein below)
57
Note: One copy each of the aforesaid documents shall be despatched by courier
by the date of BL.
6.2.2. In case the LC shall be available for payment against 100% of invoice value
as per clause 6.8 herein below.
6.2.3. The LC shall specifically provide that Bills of Lading and pre-shipping
Inspection Certificate with remarks such as:
Some ties broken/missing, atmospheric/surface /superficial rust/edge rust
unprotected cargo, stored in open area prior to loading, rust stained/partly rust
stained shall be acceptable for negotiation.
6.4 The LC should provide for shipment of materials with quantity tolerance as
specified in clause 4 herein above or as otherwise agreed .It should be valid from
date of shipment as per the agreement and upto date of completion of shipment in
the vessel nominated by BUYER and 21 days beyond that for negotiations of
documents.
6.5 All Bank and other charges incurred outside the territory of India shall be
borne and paid for by the BUYER .LC confirmation charges ,if required shall be
and paid for by the SELLER.
6.6. The financial arrangement required to be made by the BUYER shall
deemed to be made only on receipt of L/C at the bank as specified in clause 6.1
58
above unless agreed otherwise .In case the financial arrangement is not made by
the BUYER within the agreed time the SELLER may forfeit the EDM if any
within the agreed time .the SELLER may forfeit the EDM, if any with the
SELLER.
6.7. If any advance is made by the BUYER against any contract ,in part of full, if
the BUYER IS not able to indicate size wise breakup of the material at least 4
weeks prior to the expiry of contractual; delivery period.
(1) In case of fall in prices , the SELLER is entitled to recover difference in
contract price and the weighted average price realized by SELLER for
the deliveries made in the last month within the contract delivery period
and return the balance and EMD to the BUYER without interest.
(2) The SELLER will return the advance without interest in case the
weighted average price realized for the last month of delivery as per
contract is more than the contract price.
6.8. In the event of
(a).The failure of the BUYER to nominate suitable vessel within lay days
given in Sellers notice of readiness of cargo or otherwise acceptable to Seller, of
within 15 days from the N/R of cargo whichever, or
(b).The vessel nominated by the BUYER and accepted by the SELLER
failing to arrive at the designated load port within the agreed lay-days for reasons
other than Force Majure as defined under clause no.10 herein below ,or
. The vessel (nominated by the BUYER and accepted by the SELLER )
being found unsuitable after its arrival at designated load port as certified by
independent marine surveyors.
59
The seller shall be entitled to negotiate his commercial Invoice against the LC
opened by the BUYER and realise 100% of the value of the Materials ready for
shipment on the basis of certificate issued by the SELLER, certifying the quantity
of the materials ready for shipment and alse certifying that the materials are ina
good condition. The materials will therefore be held in custody by the SELLER at
the risk and responsibility of the BUYER at the storage yard of the SELLER at
the load port . While the SELLER shall hold the materials free of ground rent for
period of 15 days from the date of payment ,for a storage extending beyond 15
days from the date of payment BUYER shall pay to the SELLER groune rent
calculated at the rate of USD 1.00 per metric ton per week of part therof .The
BUYER shall however nominate another suitable vessel within reasonable time
for taking delivery of the cargo for which payment has been realised by the
SELLER as aforesaid and subject to such vessel arriving at load port within the
agreed lay-days the SELLER shall at his cost deliver FOB (stowed ) the materials
for which payment has been realised by the SELLER as aforesaid .The LC
established by the BUYER in fovour of the SELLER shall make specific and
unconditional provision to the above ,.
Saved shall
be
arranged to be remitted by the BUYER to the SELLER within sixty days from
the date of receipt of the claim of the SELLER with laytime statements .EMD
shall be released after receiving remittance in full towards pending despatch
mondy pending from the BUYER if any .If not , the amount of deurrage within
sixty says from the date of receipt of claim from buyer with
supporting
documents.
60
resulting
from this
transferee of all or substantially all of its assests , and in the case of any such
assignment of transfer, the contract shall binding upon and shall isure to the
benefit of such successor of transferee.
10. FORCE MAJEURE:
If the SELLER and /of the BUYER be prevented from discharging its or their
obligation under this agreement by reasons of arrests or restraints of privacy of
rules
,government
of
people
,war
.Blockade,Revolution,Insurrection
prevented by any such causes as herein above mentioned, provided that in the
event of sluch delay exceeding ninty days ,the party other than the party which
61
invokes the force majeure may at their option ,cancel this agreement by Notice in
writing to the other party in respect of the undelivered quantity of the materials
without ,however ,any right against or being responsible to the other party for
sluch cancellation .The party invoking force majeure causes ,put the other party
on notice supported by certificate from the Chamber of Commerce of concerned
government authotity and shall likewise intimate the cessatioin of such causes. If
the force-months the SELLET or the BUYER may at his option cancel thie
agreement by notice in writing to the materials without ,however ,any right
against or being
.The party invoking force majeure causes, put the other party on notice
supported by certificate from the Chamber of Commerce of concerned
government authority and shall likewise intimate the cessation of such causes. If
the force-months the SELLET or the BUYER may at his option cancel the
agreement by notice in writing to the materials without ,however ,any right
against or being
62
15.MODIFICATIONS / WAIVERS:
No change in respect so these term and conditions are valid unless the same is
agreed to in writing by both the parties .All previous negotiation / understandings
between parties are cancelled while entering into an agreement as per these terms
and conditions .Failure to enforce any condition hereunder contained shall neither
be deemed as waiver of the conditions itself nor authorize any subsequent breach
thereof.
63
Wire rods
Angles
Channels
Beams
Billets
Pig Iron
The below table shows the various specifications and grade levels
1. WIRE RODS:
64
Specification Grade
Remarks
ASTMA510.96
SAE
1008
0.30%Max)
(Si-
ASTMA510.96
SAE
1010
0.40%Max)
(Si-
ASTMA510.96
SAE
1012
0.40%Max)
(Si-
ASTMA510.96
SAE
1015
0.40%Max)
(Si-
Note 1: In straight lengths 12m +/-0.1m but 2% short length in a bundle to be allowed. In
coils of dimensions as for Wire Rod Coils
Note 2: Rib design and Sectional Weight as per VSP's design. Size 32 & 28 also likely to
be available. Availability of 32, 28 & 18 size subject to economic quantity of orders.
2. HOT ROLLED REBARS:
Specification
Grade
Size (mm)
JISG3112
SD35
BS 4449
250
65
BS 4449
460
JISG3112
SD35
8, 10
3. ANGLES:
Size (mm)
100 X 100 X 8 /
12.10 / 14.90, +5% -3%
10
90 X 90 X
6/8
75 X 75 X
6/8
6.80 / 8.90,
+5% -3%
65 X 65 X
6/8
5.80 / 7.70,
+5% -3%
4. CHANNELS:
Size (mm)
Sec.Wt Kg/mtr
50 X 75 X 5.71
16.8 +/-2.5%
125 X 65 X 5.3
13.1 +/-2.5%
100 X 50 X 5
9.56 +/-2.5%
66
75 X 40 X 4.8
7.14 +/-2.5%
5. BEAMS:
Size
(mm)
Web
Thickness
Remarks
Sec. Wt
180 X 91
5.3
+/-0.7%
Flance Thickness : 8.0 +/- 1.0%
18.80 +/-4%
120
114
X 5.0
+/-0.7%
Flance Thickness : 8.0 +/- 1.0%
19.90 +/-4%
6. BILLETS:
Size (mm)
125
x
125
10,000 +/-400
Chemistry
x
65 X 65 X 6,000
Is : 2830(C:0.12-0.23%; SI:0.40% Max
+/-100
75 X 75 X 6,000
Mn : 0.3-1.5 Mn:0.3-1.5
+/-100
Note 1: Chemistry (other than Billets) JIS G3101 SS400 or IS; 2830; Bundle Wt: 5MT
(Max), Length 12+/- 0.1m (for 6+/-0.1m ends would be gas cut); Allowable short length
upto 2%.
67
Note 2: Chemistry for Billets: C: 0.14-0.20%; Mn: 0.5-0.9%; S/P: 0.05% Max; Si:
0.35% Max; OR SAE 1015; OR Forging Quality chemistry as per JIS G4051 GR S20C /
S45C.
7. PIG IRON:
BASIC GRADE STEEL MAKING PIG IRON :
CHEMISTRY: C: 3.5 - 4.5%; Mn : 1% MAX; Si : 1.25% MAX; P : 0.15% MAX; S :
0.05% MAX.
SIZE: Pigs with upto two notches upto 45kgs in weight. Chips/broken pieces below
25mm not exceeding 5%, dust, dirt and moisture exceeding 0.5% deductible from draft
survey wt.
68
D) Registration formalities
E) Export Order
69
H) Post- Shipment
70
The Duty Exemption Scheme enables duty free import of inputs required for
export production.
An Advance Licence is issued under Duty Exemption Scheme.
The Duty Remission Scheme enables post export replenishment/ Remission of duty on
inputs used in the export product.
Duty Remission Scheme consist of
a.
b.
allows drawback of import charges on the inputs used in the export product.
An application for grant of an advance licence/ DFRC/DEPB may be maid by the
Registered office or head office or a branch office or manufacturing unit of the eligible
exporter, to the licensing authority concerned.
1. ADVANCE LICENCE:
An advance licence is issued to allow duty free import of inputs, which are
physically incorporated in the export product. Advance licence can be issued for
1. Physical exports
2. Intermediate supplies
3. Deemed exports
Advance licence for physical exports and intermediate supplies are exempted from
payment of basic customs duty, additional customs duty, anti dumping duty and safeguard
duty, if any. However, Advance licence for Deemed products shall be exempted from
payment of basic customs duty, additional customs duty only.
An Advance licence shall specify:
1. the names and description of items to be imported and exported.
2. the quantity and value of individual inputs which are to be imported, as per SION
norms.
3. the aggregate CIF value of imports.
71
Revalidation of Licence:
72
The regional licensing authority may consider a request of the original licence
holder and grant revalidation for a period of 6 months from the date of expiry of the
original licence.
terms of quantity, the licence holder shall, for the regularisation, pay:
73
terms of value, no penalty shall be imposed if the licence holder has achieved the positive
value addition. However, if the value addition falls below positive, the licence holder shall
be required to deposit an equivalent amount through TR in the authorized branch of Central
Bank of India, so that the 100 times the deposited amount rupees together account for
positive value addition over the CIF value.
iii)
If the export obligation is not fulfilled both in terms of quantity and value, the
licence holder shall, for the regularization, pay as per (i) and (ii) above.
Port of Registration:
74
The export/import made from the specified ports given shall be entitled for DEPB.
Seaports: Mumbai, Kolkata, Cochin, Dahej, Kakinada, kandla, Mangalore, Marmagoa,
Mundra, Chennai, Nhavasheva, Paradeep, Pipavav, Sikka, Tuticorin, Visakhapatnam,
Surat, Nagapattinam and Okha.
The DEPB shall be issued with single port of registration, which will be the port from
where the exports have been made effected.
Credit under DEPB and Present Market Value:
In respect of products where the rate of credit entitlement under DEPB scheme
comes to 10% or more, the amount of credit against each such product shall not exceed
50% of the Present Market Value (PMV) of the export product.
Application for DEPB:
An application for grant of credit under DEPB may be made to the licensing
authority concerned in the form given, along with the documents prescribed therein. The
FOB value in free foreign exchange shall be converted into Indian rupees as per the
exchange rate for exports, notified by Ministry of Finance, as applicable on the date of
order of Let Export by the Customs.
Restriction on use of DEPB credit:
The CIF value of imports affected under DEPB shall not exceed the FOB value
against which the DEPB has been issued.
Time period:
75
The application for obtaining credit shall be filed within a period of 6 months from
the date of exports or within 3 months from the date of realisation, whichever is later.
Verification by Customs:
The licensing authority shall ensure that while issuing the DEPB, the shipping bill
no., and date, FOB value in Indian rupees as per shipping bill and description of export
product. Before allowing the imports against DEPB, the Customs shall verify that the
details of the exports are as per their records.
Revalidation:
No revalidation shall be granted beyond the original period of validity of DEPB.
Filling of Application:
76
77
is 6399284.65(13079.25*10.41*47)
CONCLUSION:
So we conclude that by comparing the two schemes DEPB is more beneficial to VSP.
78
FINDINGS:
The findings of the study are:
VSP is making alliances with some trading companies abroad .This may
strengthen the market of VSP in the foreign market.
VSP has no branch offices abroad. Generally exports orders are booked at VSPs
main office at Visakhapatnam only.
Presently VSP is spending nearly Rs. 90 crores per year as transportation charges.
79
SUGGESTIONS:
After analyzing the data and information collected from various sources during
the source of project work and the limitations and problems found, some suggestions are
given which may be help full to the organization in shot run and long run.
As VSP is producing iron and steel products of high standards and company has
given a major thrust to exports, it has to take promotional activities in large scale.
As in the present marketing situation where customers hold the key it is important
to influence the customers. It has been found to have taken up promotional activities at
the national level in a big way; similarly the company has to go for global promotional
campaign.
VSP can conduct seminars and customer counseling at international level so as to
make foreign customers aware of the quality product available in India at a competitive
price.
VSP has only one office in the exports division .This makes it difficult for
procuring orders directly from the customers. So it will be better for the company
to open international branch in regions where VSP exports large share of its total exports.
80
CONCLUSION:
In the past the customer had no choice .The government policy and the main
producers options was prevailing in the market .Today with the liberalization the steel
industry decontrolled with abolition of freight reduced drastically, so the compulsory
licensing of the steel industry has been repelled. As a result a lot of secondary producers
with variable product mix are coming up in the steel industry. All these have threatened
the status quo of all the major producers.
In such a situation customer holds the key unlike yesterday, he is not dependent
on a few main producer. Thus customer oriented marketingshould be adopted.
All the suggestions given are directed towards the twin objective of strengthening
the market and improving the customer relationship between the company and its
customers. Both should care for each other without suffering a lot. Then VSP can face all
the competitions and challenges in the market. VSP have their valuable customers with
them for all times. VSP has yet to do a lot towards customer oriented marketing to
attract more and more customers because todays steel market belongs to customer only.
81