SECTION - 8001
GENERAL SPECIFICATIONS FOR ELECTRICAL SYSTEMS
1.0
SCOPE OF WORK
The scope of this contract covers all operation and activities required for
proper and complete construction of internal/building electrification, external
electrification & sub-station works and communication systems.
The works related to the Electrical & Communication systems that are
included in the scope of this Contract are shown on the Tender Drawings,
stated in the Bill of Quantities and explained in these specifications. All the
equipment & allied accessories and their installation shall also comply with
General Specifications described here-under, with other relevant provisions of
Tender Document and WAPDA/other utilities latest Specifications/Standards.
Electrical & Communication systems shall broadly include but not limited to
the following:
-
8001-2
Design, Supply, installation, testing and commissioning of PreAmplifiers, Mixing Amplifiers Power Amplifiers, Micro-Phones & Ceiling
& column Speakers for Public Address system and sound systems.
The scope shall include the continuing of the contractor to remain responsible
for removal of defects detected in the works and for achieving satisfactory
operation/functioning/service of the works during defect liability period.
The contract shall include furnishing of all construction equipment, tools,
labour,
supervisory
staff,
plants,
transport,
power,
testing
apparatus/arrangements and all construction materials as shall be required for
satisfactory completion of works strictly in accordance with the technical
specifications and bill of quantities forming part of these tender documents
and as per levels and dimensions as shown on the drawings supplied with
these tender documents and in drawings which may be supplied by the
Employer from time to time under approved variation orders.
The Contractor shall also be responsible to supply any other equipment not
specifically mentioned in these Documents but which is necessary for proper
operation of the works/ system included in the scope of this Contract. The
Contractor shall solely be responsible for ensuring proper functional
requirements of various equipments. He shall also be responsible for
furnishing any additional piece of equipment and for making modification in
the equipment as desired and/or approved by the Engineer to achieve proper
co-ordination with various other equipments offered in the bid and also with
those installed by others.
2.0
8001-3
All works shall be carried out in accordance with the latest edition of the
Regulations of the Electrical Equipment of Buildings issued by the Institute of
Electrical Engineers-London, 16thed. NEC 1999, the Contract Documents, the
Electricity Rules 1937 and bye-laws that are in force from time to time.
Any discrepancy between these specifications and the standards/ regulations
shall be brought to the notice of Engineer for his instructions and decision of
the Engineer shall be final and conclusive.
The Contractor shall be responsible for completing all formalities and
submitting the test certificates as per prevailing rules and regulations, and
shall have the installation passed by the Government Electric Inspector of that
region. All requirements of the Electric Inspector and the utility company
WAPDA shall be complied with.
3.0
AMBIENT CONDITIONS
All material and equipment supplied and installed shall be designed,
manufactured and tested to meet the following ambient conditions unless
specifically stated otherwise for any material/equipment.
Minimum indoor ambient temperature:
+ 40 Degree Celsius
+ 50 Degree Celsius
90 Percent
10 Percent
MARKINGS
The Contractor shall provide "Danger Boards" and "Shock Charts, wherever
required, to comply with the requirements of local Electricity Rules and
according to normal practice.
5.0
SYSTEM DATA
Unless otherwise specified elsewhere, all equipment and material shall be
designed to operate satisfactorily with the following minimum requirements
with the specified tolerance without any derating.
a.
MV
1500V
8001-4
b.
6.0
500V
250V
c.
DC voltages
24V DC
12V DC
Others
+ 10%
d.
Frequency
50 HZ
+ 2 HZ
STANDARDS
The latest standards and codes of reputable organizations shall be applicable
for the material and equipment specified herein and for installation work. Such
organizations to be British Standard Institution (BSS), International Electro
technical Commission (IEC), IEEE and NEC. In case the Specifications laid
down herein differ from those given in the standards, then the better
specifications shall govern. Wherever applicable, the equipment shall also
conform to the requirements of Pakistan Standard Institution (PSI).,Pakistan
Telecom Authority.
7.0
8.0
DEVIATIONS
The entire design of the Electrical systems of the project has been carried out
to fulfill the Users requirements. The design is based on International
standards/norms and practices. Special considerations have been made for
ease in operation and maintenance of electrical systems of the project.
Deviation may be allowed for the works covered under present scope of work,
with the approval of Engineer/Client
9.0
8001-5
8001-6
The time required for review and approval shall be considered included in the
total time of completion of job.
Three sets of drawings and data for each equipment shall be furnished by the
Contractor for the Engineers approval before commencement of fabrication
and manufacturing. The drawings to be supplied by the Contractor shall be as
follows:
-
Arrangements
Dimensional Plans, elevations and front view
Foundation Plan, anchors and configuration
Incoming and outgoing cable termination positions
Earthing arrangement
Electrical Drawings showing:
-
Single-Line diagram
Detailed wiring diagram
All interconnections
Other electrical devices including meters instruments and their
wiring diagram.
Signal and alarm circuit
Shop Drawings
The locations, routing and installation heights of the equipment etc. Which are
given on the tender drawings, are approximate. These drawings depict only
the position of various fixtures and outlets. All the detailed planning for
electrical and communication systems including conduit routes etc. shall be
carried out, well in advance of the actual execution of work, by the Contractor
to the satisfaction of the Engineer. For this purpose the Contractor shall
prepare shop drawings and obtain prior approval of the Engineer. Three prints
of each shop drawings shall be submitted for obtaining approval. No piece of
work shall be allowed to be executed at site without the availability of these
approved shop drawings. These shop drawings shall clearly depict the load
balancing chart of each distribution board. Time required for the preparation
and approval of shop drawings shall be considered to have been included in
the total time allowed for the completion of the work.
As-Built Drawings
Clearly annotated As-Built electrical drawings and diagrams shall be
maintained upto date on site on completion of the Job. One reproducible and
three prints of each drawing shall be submitted to the Engineer alongwith a
recommended maintenance schedule chart and manuals/operating
instructions for equipment supplied. The Contractor shall also provide
complete detailed identifications of MV incoming and LV outgoing circuits, in
the form of line drawings, for each pad mounted transformer. The line
drawings shall be made on 20 SWG sheet metal work. The line drawings shall
be clearly identified with permanent colors. The MV and LV. circuits shall
being different colors. The sheet metal work shall be of suitable dimensions so
8001-7
12.0
MANUFACTURER'S INSTRUCTIONS
The Contractor shall supply to the Engineer Three (3) copies of
manufacturer's instruction manuals in properly bound form for installation,
testing commissioning, operation and maintenance of the specified equipment
including manuals of spare parts and tools of the equipment. One copy of the
documents shall be submitted in original. The installation instructions shall be
submitted four (4) weeks prior to commencement of installation of each
equipment, and operation & maintenance instruction at least two (2) weeks
before the time of commissioning. If the contractor fails to provide the
documents the Engineer shall withhold issuance of requisite certificates and
deduct suitable amount from the payments to the Contractor.
13.0
GUARANTEE
In addition to the Contractor guarantee and liabilities for satisfactory operation
of the works, wherever advised by Engineer, the Contractor shall also furnish
written guarantee of the manufacturer or supplier with respect to satisfactory
performance, of each equipment. Guarantee shall be given for replacement
and repair of part or whole of the equipment that may be found defective in
material or workmanship. The guarantee shall as a minimum cover the
8001-8
INSTALLATION INSTRUCTIONS
The Contractor shall furnish all labor, materials, tools and equipment required
to install, connect, test and commission all electrical equipment specified
herein, whether or not such equipment is furnished by him or by others.
For all equipment to be installed by the Contractor, the Contractor shall supply
and install all erection materials such as foundation bolts, washers, nuts, etc.
as required and without any additional costs.
The Contractor shall set out the works himself as per Specifications and
Drawings and shall properly position the equipment on specified
foundation/location. In general, the manufacturer's instructions for installation
shall be followed.
Any defect or faulty operation of equipment due to the Contractor not following
the manufacturer's instructions shall be corrected and repaired by the
Contractor at his own cost as per these specification and to the satisfaction of
Engineer.
For any deviation from the working drawings that are deemed necessary by
the Contractor due to site conditions, he shall submit the details and obtain
the Engineer's approval before starting such works.
15.0
General
All equipments and materials covered in scope of this contract are
subject to pre-shipment inspection & testing at the manufacturers
factory/works. The Contractor, in coordination with the manufacturers
of relevant materials shall arrange for the pre-shipment inspection &
testing by the Engineer at the manufacturers factory/works. The
Contractor shall make all necessary arrangements and cater for all
expenses in this regard for the traveling, boarding and lodging of the
Engineer plus daily allowance @ Rs. 500 per day per person within
Pakistan and US $ 100 per day per person outside Pakistan, for the
pre-shipment inspection and to witness the tests at the manufacturers
factory/works.
15.2
8001-9
15.2.1
15.2.2
8001-10
250 volts and meggar of 1000 volt for circuits between 250
and 500 volts. The Engineer shall advise the exact testing
voltages. The insulation resistance values of cables,
switchgear, etc., shall be as per BSS, IEC, ICEA and
Pakistan Electricity Rules.
15.3
Field Tests
15.3.1
General
Upon completion of the installation, the Contractor shall
perform field tests on all equipment, materials and systems.
All tests shall be conducted in the presence of the Engineer
for the purpose of demonstrating equipment and systems
compliance with Specifications. The Contractor shall submit
for Engineer's approval complete details of tests to be
performed describing the procedure test observations and
expected results.
The Contractor shall furnish all tools, instruments, test
equipment, materials, etc., and all qualified personnel
required for the testing, setting and adjustment of all
electrical equipment and material including putting the same
into operation.
All tests shall be made with proper regard for the protection
of the personnel and equipment and the Contractor shall be
responsible for adequate protection of all personnel and
equipment during such tests. The cost of any damages or
rectification work due to any accident during the tests shall
be the sole responsibility of Contractor.
The Contractor shall record all test values of the tests made
by him on all equipment. Four (4) copies of all test data and
results certified by the Engineer shall be given to the
Engineer for record purposes. These shall also include
details of testing method, testing equipment, diagrams, etc.
The witnessing of any tests by the Engineer does not relieve
the Contractor of his guarantees for materials, equipment
and workmanship, or as any other obligations of contract.
15.3.2
8001-11
8001-12
15.4
Completed Tests
After any equipment has been tested, checked for operation,
etc., and is accepted by the Engineer, the Contractor shall be
responsible for the proper protection of that equipment so that
subsequent testing of other equipment do not cause any
damage to the already tested equipment.
16.0
17.0
18.0
Lighting fixtures
Earthing system
Telephone system
8001-13
19.0
PAYMENT
No separate payment shall be made for work involved within the scope of this
section, unless specifically mentioned in the respective items of Bill of
Quantities.