Ensure lintel is
Ensure a nominal
not damaged.
150mm end bearing
at each end.*
Structural opening
or clear span.
Masonry above lintels should be allowed * For advice on installations where end bearings
to cure before applying floor or roof loads. can be reduced to not less than 100mm, please
contact Catnic Technical Services Department
on 029 2033 7900.
Ensure that masonry overhang
does not exceed 25mm. † Ensure no more than half the safe working load
(SWL) is carried by the outer leaf where the lintel
carries an external cavity wall. The wall should also
be restrained laterally near the top.
Inner Leaf Cavity Outer Leaf
70 71
Installing a Cavity Wall Lintel
Ensure lintel is
Ensure a nominal
not damaged.
150mm end bearing
at each end.*
Structural opening
or clear span.
Masonry above lintels should be allowed * For advice on installations where end bearings
to cure before applying floor or roof loads. can be reduced to not less than 100mm, please
contact Catnic Technical Services Department
on 029 2033 7900.
Ensure that masonry overhang
does not exceed 25mm. † Ensure no more than half the safe working load
(SWL) is carried by the outer leaf where the lintel
carries an external cavity wall. The wall should also
be restrained laterally near the top.
Inner Leaf Cavity Outer Leaf
70 71
Installing a Cavity Wall Lintel Installing a Lintel Supporting Concrete Floors
Open Back - Wide Inner Leaf lintels used with 140mm dense blocks In addition to the Cavity Wall Installation Guide,
please read the following for installing concrete
floors with Catnic steel lintels
To ensure the flanges are equally loaded
the Code of Practice should be strictly
adhered to when building the masonry
i.e. one row of blocks should be raised on the inner leaf, then • Check that the correct lintel is being Typical CX Lintel, supporting a concrete floor
three courses of brick on the outer leaf. Wall ties should then used according to the manufacturer’s
be installed and another row of blocks on the inner leaf lintel schedule/design criteria
followed by three courses of brick on the outer and so on. • Bed the lintel on full blocks and allow
This process ensures that the lintel flanges are equally loaded mortar to cure before applying
and helps prevent rotation. concrete floor loads
The open back lintel should also be suitably propped during • Raise both leaves of cavity wall
construction when being used with wide dense blocks. together and allow masonry to cure
sufficiently before applying heavy
Block inner leaf
loads. Alternatively prop the lintel if
large loads are to be applied to fresh
masonry
• When using the Catnic CH & CX
Open back range with concrete
floors, always ensure that the
blockwork is built tight against the
inner vertical face of the lintel, and
that a mortar joint is added to the top
of the blockwork so that the floor
15 125 units have an even spread over the
inner flange of the lintel
• Avoid shock loading lintels during the
installation of concrete floor units and Concrete floor
Prop centrally for spans up to
also any sideways loading while
2100mm. For larger spans use
being lifted into position
props at 1200mm centres.
Prop if necessary • Precast flooring units should be laid
on a mortar bearing of the full inner
leaf wall width and should
Propping not be dragged over supports
• When propping, a horizontal board • The 140 mm dense blocks should be • If after considering the above • Avoid loading newly laid floors with Continuous
should be placed along the underside installed tight against the inner web information it is not practicable to building materials solid infill block
of the lintel soffit, this will prevent any of the lintel. carry out the mentioned construction • Lintels must be built-in as illustrated,
point loading, which could cause • Therefore, the overhang of blockwork process on site, we are able to offer ensuring that the blockwork infill is
localised deformation of the lintel. on the lintels inner flange could be an alternative box style lintel in place well-jointed during construction and
On small openings a single prop measured at 15mm. of open back. These products are compatible with the strength of the
should be placed centrally within the more robust due to the design of the masonry above
openings and wedged into place. box section and therefore, open to Lintel
The prop can be removed after the greater abuse on site during the
wall ties are effective. The number of construction stage.
props used should be increased for
larger openings.
72 73
Installing a Cavity Wall Lintel Installing a Lintel Supporting Concrete Floors
Open Back - Wide Inner Leaf lintels used with 140mm dense blocks In addition to the Cavity Wall Installation Guide,
please read the following for installing concrete
floors with Catnic steel lintels
To ensure the flanges are equally loaded
the Code of Practice should be strictly
adhered to when building the masonry
i.e. one row of blocks should be raised on the inner leaf, then • Check that the correct lintel is being Typical CX Lintel, supporting a concrete floor
three courses of brick on the outer leaf. Wall ties should then used according to the manufacturer’s
be installed and another row of blocks on the inner leaf lintel schedule/design criteria
followed by three courses of brick on the outer and so on. • Bed the lintel on full blocks and allow
This process ensures that the lintel flanges are equally loaded mortar to cure before applying
and helps prevent rotation. concrete floor loads
The open back lintel should also be suitably propped during • Raise both leaves of cavity wall
construction when being used with wide dense blocks. together and allow masonry to cure
sufficiently before applying heavy
Block inner leaf
loads. Alternatively prop the lintel if
large loads are to be applied to fresh
masonry
• When using the Catnic CH & CX
Open back range with concrete
floors, always ensure that the
blockwork is built tight against the
inner vertical face of the lintel, and
that a mortar joint is added to the top
of the blockwork so that the floor
15 125 units have an even spread over the
inner flange of the lintel
• Avoid shock loading lintels during the
installation of concrete floor units and Concrete floor
Prop centrally for spans up to
also any sideways loading while
2100mm. For larger spans use
being lifted into position
props at 1200mm centres.
Prop if necessary • Precast flooring units should be laid
on a mortar bearing of the full inner
leaf wall width and should
Propping not be dragged over supports
• When propping, a horizontal board • The 140 mm dense blocks should be • If after considering the above • Avoid loading newly laid floors with Continuous
should be placed along the underside installed tight against the inner web information it is not practicable to building materials solid infill block
of the lintel soffit, this will prevent any of the lintel. carry out the mentioned construction • Lintels must be built-in as illustrated,
point loading, which could cause • Therefore, the overhang of blockwork process on site, we are able to offer ensuring that the blockwork infill is
localised deformation of the lintel. on the lintels inner flange could be an alternative box style lintel in place well-jointed during construction and
On small openings a single prop measured at 15mm. of open back. These products are compatible with the strength of the
should be placed centrally within the more robust due to the design of the masonry above
openings and wedged into place. box section and therefore, open to Lintel
The prop can be removed after the greater abuse on site during the
wall ties are effective. The number of construction stage.
props used should be increased for
larger openings.
72 73
Installing a Timber Frame Lintel
In addition to the Cavity Wall Installation Guide,
please read the following for Catnic timber
frame lintel installation
• When propping, a horizontal board • The number of props should be • A timber pinch batten should be fixed
should be placed along the flat increased for larger openings. at the heel of the timber frame lintel in
underside of the lintel soffit; this will Generally props should be installed at order to minimise any rotation.
prevent any point loading, which maximum centres of 1 metre.
• Catnic timber frame lintels
could cause localised deformation of
• The prop can be removed after the (e.g. CTF’s) are intended only to
the lintel flange.
mortar has cured and the wall ties support an outer skin of brickwork
• On small openings a single prop should become effective. where it is tied to an inner skin of
be placed centrally within the opening timber frame and must be suitably
and gently wedged into place. propped during construction.
Centre of lintel
74 75