Anda di halaman 1dari 162

Health and Safety

Executive

Evaluation of tensioned and non-tensioned


long tendon reinforcement in UK deep
mining conditions
Prepared by Rock Mechanics Technology Limited
for the Health and Safety Executive 2010

RR831
Research Report

Health and Safety


Executive

Evaluation of tensioned and non-tensioned


long tendon reinforcement in UK deep
mining conditions
David Bigby, PhD, BSc (Hons)
Ken Hurt, PhD, BSc (Hons)
Chris Reynolds, BSc (Hons)
Robert Brown, BSc (Hons)
Rock Mechanics Technology Ltd
Bretby Business Park
Ashby Road
Burton-on-Trent
Staffordshire DE15 0QD

A research programme has been carried out by RMT in support of the revision of Part 2 of the British
Standard for strata reinforcement components in coal mines, covering flexible systems for roof
reinforcement. This continued work commenced under a previous HSE Project, Testing and standards for
reinforcement consumables.
A particular focus was to compare tensionable and non-tensionable reinforcement systems, prompted
by the introduction of tensionable systems to British coal mines. A review of previous research indicated
conflicting claims for tensionable systems in terms of theoretical advantages and practical experience. The
research included laboratory testing, underground measurement and analysis of underground monitoring
data. Advice and draft Annexes were provided to the BS Committee and a revision of the DMCIAC
guidance on the use of cable bolts to support roadways in coal mines drafted. The work highlighted
practical problems concerning application of the tensionable systems in use in UK coal mines but did not
exclude their future applicability provided they comply with the revised Standard.
This report and the work it describes were funded by the Health and Safety Executive and co-funded
by the EU Research Fund for Coal and Steel. Aspects were also co-funded by UKCoal Ltd and various
manufacturers through supply of materials for testing. The reports contents, including any opinions and/
or conclusions expressed, are those of the authors alone and do not necessarily reflect HSE policy nor the
opinions of any of the co-funding parties.

HSE Books

Crown copyright 2010


First published 2010
You may reuse this information (not including logos) free
of charge in any format or medium, under the terms of the
Open Government Licence. To view the licence visit
www.nationalarchives.gov.uk/doc/open-government-licence/,
write to the Information Policy Team, The National Archives, Kew,
London TW9 4DU, or email psi@nationalarchives.gsi.gov.uk.
Some images and illustrations may not be owned by the
Crown so cannot be reproduced without permission of the
copyright owner. Enquiries should be sent to
copyright@hse.gsi.gov.uk.

ii

CONTENTS

EXECUTIVE SUMMARY

vii

1.

INTRODUCTION

2.

THEORETICAL ASPECTS OF TENSIONED TENDONS


2.1 Rockbolting and Tensioning Practice
2.2 Analysis of the Pretensioning Effect
2.3 Evidence for the Pretensioning Effect
2.4 Summary

2.5 Bibliography

12

15

17

3.

LABORATORY AND UNDERGROUND TESTING OF LONG TENDONS


3.1 Grout Encapsulation Testing
3.2 Variation of Bond Performance with Grout Strength
3.3 Field Sample Grout Testing

21

21

24

25

4.

UNDERGROUND MONITORING OF PERFORMANCE AND EFFECTS

OF TENSIONED LONG TENDONS


4.1 Historical Data Analysis
4.2 Underground Monitoring of Long Tendon Tensioning at Colliery A

27

27

30

5.

IMPROVED MODELLING OF FLEXIBLE LONG TENDONS


5.1 Representation of Tensioned Tendons and Truss Systems
5.2 Application to Maingate Support on Drivage at Colliery C
5.3 Application to Maingate Support on Retreat at Colliery C
5.4 Conclusions on Modelling Flexible Long Tendons

37

37

39

42

44

6.

ADVICE AND DRAFTS PROVIDED TO B S REVISION COMMITTEE


6.1 Advice and Recommendations
6.2 Draft Test Procedures / Annexes

47

47

48

7.

LABORATORY TESTING OF ALTERNATIVE RIB REINFORCEMENT

SYSTEMS
7.1 Rib Reinforcement Systems Tested
7.2 Test Procedures

7.3 Test Results and Discussion
7.4 Conclusions and Recommendations

51
51

52
53

60

SUGGESTED REVISION OF DMCIAC CABLEBOLTING GUIDANCE

DOCUMENT
8.1 Introduction
8.2 Suggested Revision of DMCIAC Cablebolting Guidance
8.3 Revised Cablebolting Guidance Appendix 1
8.4 Revised Cablebolting Guidance Appendix 2
8.5 Revised Cablebolting Guidance Appendix 3
8.6 Revised Cablebolting Guidance Appendix 4

63
63
63

70

72

74

76

CONCLUSIONS AND RECOMMENDATIONS

79

8.

9.

iii

10.

REFERENCES

83

FIGURES
Figure 2.1
Figure 2.2
Figure 2.3
Figure 2.4
Figure 3.1
Figure 3.2
Figure 3.3
Figure 3.4
Figure 3.5

Figure 4.1
Figure 4.2
Figure 4.3
Figure 4.4
Figure 4.5
Figure 4.6
Figure 4.7
Figure 4.8
Figure 4.9
Figure 4.10
Figure 4.11
Figure 4.12
Figure 4.13
Figure 4.14
Figure 4.15
Figure 4.16
Figure 4.17
Figure 4.18
Figure 4.19
Figure 4.20
Figure 4.21
Figure 4.22
Figure 4.23

iv

Comparison of the load distribution of a normal anchor and a


single bore multiple anchor (after Barley and Windsor, 2000)
The buckling beam concept for roof stability (after Strata

Engineering, 2001)
External load applied to a pretensioned bolted joint
External load applied to a pretensioned lifting bolt
Laboratory short encapsulation pull test results for Megastrands
and CBG grout at 1 and 3 days curing
Laboratory short encapsulation pull test results for Megastrands

and CBG grout at 7 and 42 days curing


Variation of maximum load, bond strength and system stiffness

with grout unconfined compressive strength (cube samples)


Variation of unconfined compressive strength with density

for bottle samples of CBG grout obtained from UK coal mines


Variation of unconfined compressive strength with density

for bottle samples of HPRG grout obtained from UK coal mines


Schematic of 10s maingate, colliery C
Monitoring results for station 4, 10s main gate, colliery C
Monitoring results for station 3, 10s main gate, colliery C
Monitoring results for station 2, 10s main gate, colliery C
Monitoring results from type B telltales, 10s main gate, colliery C
Monitoring results from cablebolt type A telltales,

10s main gate, colliery C


Monitoring results from cablebolt type B telltales,

10s main gate, colliery C


Monitoring results from type A telltales, 22s main gate, colliery C
Combined displacement from type A and B telltales,

570, 590 and 610 MM, 19s tail gate, colliery C


Schematic of T18s, face line, colliery B
Planned support pattern in widened face line
Section of widened face line support and instrumentation pattern
Approximate position of installed instruments on 21 March 2007
Approximate position of installed Megastrands and tensioning on

27 March 2007
Proposed Megastrand monitoring instrumentation, 302s face line
March 2007
Time trend for cablebolt telltale number 13 at 196 m
Colliery C face line station 6 at 192 m
Colliery C 302 face 197 m CL 297 RREXTO1
Colliery C 302 face 197 m CL 297 RREXTO1 cont.
Sonic extensometer 196 m, displacement & strain against

distance into strata


Sonic extensometer 196 m, displacement against time
Sonic extensometer 196 m, displacement against time during

Megastrand tensioning period


Strain gauged rockbolt 1. Mean microstrain and microstrain

difference against distance along bolt

85

86
87

88

89

90

91

92

93

94

95

95

96

97

98

99

100

101

102

103

104

105

106
107
108

109

110

111

112
113

114

115

Figure 4.24
Figure 4.25
Figure 4.26
Figure 4.27
Figure 4.28

Figure 5.1
Figure 5.2a
Figure 5.2b
Figure 5.2c
Figure 5.3
Figure 5.4
Figure 5.5
Figure 5.6
Figure 5.7
Figure 5.8
Figure 5.9
Figure 5.10
Figure 5.11
Figure 5.12
Figure 5.13
Figure 5.14
Figure 5.15
Figure 5.16
Figure 5.17
Figure 5.18
Figure 5.19
Figure 5.20

Strain gauged rockbolt 2. Mean microstrain and microstrain


difference against distance along bolt
Strain gauged rockbolt 3. Mean microstrain and microstrain
difference against distance along bolt
Strain gauged rockbolt 4. Mean microstrain and microstrain
difference against distance along bolt
Strain gauged rockbolt 5. Mean microstrain and microstrain
difference against distance along bolt
Strain gauged rockbolt 6. Mean microstrain and microstrain

difference against distance along bolt


Modelled strata sequence 3.2 m roof mudstone
Coal strength properties
Siltstone strength properties
Mudstone strength properties
Modelled roof displacements with roof bolts failed and no

additional support
Modelled roof displacements with roof bolts failed and pretensioned

flexible bolts as additional support


Modelled roof displacements with roof bolts failed and untensioned

flexible bolts as additional support


Modelled roof displacements with roof bolts failed and tensioned

truss system as additional support


Shear strains and bolt loads with pretensioned flexible bolts

as additional support
Shear strains and bolt loads with pretensioned truss system as

additional support
Proposed bolt pattern at development face
Strata sequences
Roof condition with proposed support and sequence A
Roof condition with proposed support and sequence B
Alternative bolt patterns at development face
Roof movement with alternative support patterns (sequence A)
Bolt strains with alternative support patterns (sequence A)
Stress increase to represent face retreat
Modelled roof condition for retreat
Roof movements for face retreat
Bolt strains for face retreat
Fail bolts and cables

116
117
118
119

120

121

121

121

121

122
122

123

124

125

125

126

126

127

128

129

129

130

130

131

132

132

133

Figure 7.1
Figure 7.2

Mean residual loads at 50 mm displacement


Comparison of achieved mean maximum loads between different bolt
types and increasing hole size

134

135

Figure 8.1

Water diverting dual height tell-tale for cablebolting (white, blue, yellow
bands)

Water diverting triple height tell-tale for cablebolting (green yellow red
bands)

135

Figure 8.2

135

APPENDICES
APPENDIX 1 DRAFT TEST PROCEDURE GROUT ENCAPSULATION TEST

BOTTOM UP GROUTING
A1.1 Principle
A1.2 Apparatus
A1.3 Procedure
A1.3 Results
APPENDIX 2 DRAFT TEST PROCEDURE GROUT ENCAPSULATION TEST
TOP DOWN GROUTING

A2.1 Principle
A2.2 Apparatus
A2.3 Procedure
A2.3 Results

APPENDIX 3 DRAFT TEST PROCEDURE DETERMINATION OF BOND


STRENGTH AND SYSTEM STIFFNESS CEMENTITIOUS GROUT

ANCHORED SYSTEMS

A3.1 Principle
A3.2 Apparatus
A3.3 Procedure
A3.3 Results
APPENDIX 4 DRAFT TEST PROCEDURE SHEAR TEST ON TENDON / GROUT
SYSTEM

A4.1 Principle
A4.2 Apparatus
A4.3 Procedure
A4.3 Results

vi

137

137

137
137
139
141

141

141
141
142

143

143

143
144
146
151

151
151
151
152

EXECUTIVE SUMMARY
A three year research programme has been carried out by Rock Mechanics Technology Ltd for
the Health and Safety Executive in further support of the revision of Part 2 of the British
Standard for strata reinforcement components in coal mines which is intended to cover flexible
systems for roof reinforcement. This programme continued work commenced under a previous
HSE Project, Testing and standards for reinforcement consumables. Both Projects were co
funded by grants from the EU Research Fund for Coal and Steel and aspects were also funded
by UKCoal Ltd and various manufacturers through supply of materials for testing.
A particular focus of this programme was to investigate the potential of tensionable
reinforcement systems in comparison with non-tensionable systems, prompted by the
application of tensionable systems by the British coal mining industry and the need to include
them within the Standard. To this end a detailed review of previous research into tensionable
systems was first carried out. This indicated conflicting claims for tensionable systems both in
terms of theoretical advantages and practical experience, plus some potential problems.
Much of the Project work involved investigation of practical aspects of tensionable systems
currently available to the UK industry, particularly aspects of grout mixing, pumping,
encapsulation and strength development. This occupied a greater proportion of the available
resources than originally envisaged, as the research encountered unexpected issues in this area.
A laboratory programme of testing the ability of the systems to achieve full encapsulation was
completed. This allowed development of encapsulation tests for both top- down and bottom
up grouting systems to be incorporated into the draft revised Standard. The top-down testing
found problems with achieving encapsulation with the currently used tensionable strand and
thixotropic grout, which could encourage the addition of extra water to the mix, thus producing
a weaker grout and jeopardising full encapsulation and system performance. This prompted a
series of laboratory short encapsulation pull tests to investigate the relationship between
compressive strength of grout and axial bond stress. It was concluded that it would be difficult
to justify any reduction in the grout strength requirements contained in the current version of the
Standard. A database was compiled of the compressive strength test results from samples of
grout collected from underground over the last 14 years. This showed that the actual strengths
achieved, particularly in more recent years, were generally lower than those required from
laboratory tests as defined in the current Standard. However, where the grout achieved the
manufacturers specified density, then the sample strengths were satisfactory. This highlighted
the need for training and good practice underground.
Field experience and monitoring results from recent applications of tensionable tendons in UK
coal mines were analysed, though data was scarce. This indicated that tensionable tendons
appeared to have significant potential but that their use without timely post grouting had
contributed to a severe roof fall. This fall was partly attributed to delaying tendon grouting until
significant roof movement had occurred and the absence of further remedial action levels,
exacerbated by the inherent difficulties in achieving full encapsulation with the particular
tensionable system deployed. It was concluded that, where tensionable systems are used, they
should be post-grouted as quickly as practical and at least within 24 hours of installation, earlier
in rapidly deforming ground. Also, it is essential that secondary action levels and actions are
incorporated into the managers monitoring scheme to ensure that appropriate action is taken if
continued roof deformation occurs following a first level of remedial reinforcement.
An intensely instrumented field exercise, co-funded by UKCoal Ltd, was undertaken to
investigate whether reported re-closure of bed separations during the tensioning of tendons

vii

could be reproduced and measured. In this case no compressive deformation of the rock was
measured during the tensioning period, though some strain gauged rockbolts in the vicinity did
experience compression. It was concluded that significant re-closure of bed separations was
only likely to occur in the immediate roof and where large bed separation had previously
occurred. This exercise demonstrated application of the new generation of geotechnical
instrumentation which has been developed for design and safety monitoring of roadways
reinforced with long tendons, including the remote reading extensometer system with local
underground readout and strain gauged rockbolt readout with data logging facility.
A method of better representing tensionable tendon reinforcement and truss systems in
FLAC3D numerical models of strata and support behaviour was developed. This was applied to
hypothetical cases and real case studies. These studies did not show any advantage from
tensioning fully encapsulated long tendons under the conditions modelled. However, the
limitations of the modelling technique used must be borne in mind, whereby the models are not
able to simulate bed separation and consequent loss of bedding shear strength, nor its re
establishment. This mechanism is often claimed as a significant feature of tensioned systems.
The studies also showed that, where loading and deformation were symmetrical, deployment of
reinforcement tendons towards the centre of a roadway was more efficient than towards the
sides and that it was far more effective than placing tendons over the ribsides where they could
act as truss anchors. However the modelling also showed that truss supports could be
effective in preventing falls of ground albeit after significant rock failure and roof deformation
had occurred. They were unable to prevent this rock failure and in typical UK conditions any
pretension of trusses was rapidly lost due to horizontal stress induced roof shortening.
A significant amount of advice and recommendations were supplied to the relevant British
Standards Committee over the period of the Project, including draft annexes and advice on how
to categorise the various systems and system components. One key recommendation was that
BS7861:Part 2 should only cover systems for roof reinforcement and not those applied to
ribsides. This allowed exclusion of the lower capacity systems often used for ribside
reinforcement, to avoid confusion. A new, Part 3 of the Standard, for ribside long tendon
reinforcement, is recommended for development which can cover these lower capacity systems.
In preparation for such a Part 3 and for revision of the DMCIAC cable bolting guidance
document, which includes rib reinforcement, a comprehensive laboratory short encapsulation
pull testing (LSEPT) programme was undertaken on a range of potential rib reinforcement
consumables, particularly considering their performance in coal under relatively high
deformations. This work was also co-funded by UKCoal Ltd. This work showed that capsule
PUR could be quite effective as a rib reinforcement encapsulant provided that the components
could be properly mixed and that moisture induced foaming could be avoided. The limited
comparisons between laboratory short encapsulation pull tests in coal and sandstone indicated
quite similar results. The tests also revealed the differences in reinforcement performance
depending upon confinement, which is of particular significance in broken coal ribs. In general
this work confirmed that the current practice of employing AT capsule resin embedded rib
reinforcement for application at the face of the heading and pumped cementitious grout
encapsulated reinforcement for outbye remedial reinforcement was generally appropriate.
A draft revision of the DMCIAC document, Guidance on the use of cablebolts to support
roadways in coal mines was prepared based upon the results of the research programme and
developments in the technology since its publication in 1997. It pays particular attention to
underground grouting operations and training. This is intended to be considered for
development with a view to publication alongside the revised BS7861: Part 2. It was also noted
that a minor revision of definitions within the DMCIAC supplementary guidance on the use of
flexible bolts in reinforcement systems for coal mines is required.

viii

1 INTRODUCTION
Long tendon reinforcement of coal mine roof was introduced to UK coal mines around 1990 in
response to increasing use of rockbolts as primary support, and the consequent need to reinforce
above the bolted height, particularly during face retreat. Initially, birdcage cablebolts,
introduced from Australia as part of a technology transfer process, were used with considerable
success. The original British Standard for cablebolting consumables (reference 1) was written to
formalise their use. Since the Standard was published (in 1997) however, a number of different
long tendon designs have been introduced and adopted by the mining industry with varying
degrees of success, and, around five years ago, systems designed to be tensioned before grout
encapsulation, or pretensioned, were introduced. Pretensioned systems were researched
extensively by Australian mining consultants, and used widely in Australian coal mines where
both rockbolts and long tendons were optimised to accept, in some cases, very high pretension
loads. More details on Australian applications and results will be found in later chapters, but
suffice to say here that variants of Australian originated systems have been used in the UK.
Currently there is considerable debate in academic circles concerning the relative merits and
disadvantages of these systems, but little research has been undertaken to improve the level of
understanding in UK mining conditions, which can differ from those experienced abroad,
particularly regarding depth and rock strengths. Some workers argue that tension achieves a
major improvement in ground control. Others suggest that any potential gains are outweighed
by the reduced strain to failure and other potential disadvantages such as problematic
installation. Yet others believe that there is no material benefit to strata control even when
properly installed.
The widespread use of long tendons (other than birdcaged systems) prompted the need for a
revision of the British Standard (reference 1), and a revision committee first convened in 2005.
An earlier research programme (reference 2) carried out by Rock Mechanics Technology Ltd
(RMT) provided the committee with suggested test methods for laboratory evaluation of long
tendon performance, and an extensive test programme provided a performance comparison of
current systems and produced performance bench marks for inclusion in the revised Standard.
However, the project was completed at an early stage relative to revision of the Standard, and
did not include research specific to pretensioned systems now being used. RMT therefore
proposed to carry out a new project providing continuing assistance to the revision committee,
and a comprehensive assessment of pretensioned long tendons. The project would run for three
years from 1st October 2005 to 30th September 2008, with funding provided by the HSE, the
European Research Fund for Coal and Steel (RFCS), and the mining industry.
Via the new project, RMT was to provide technical support to the revision committee, with
particular regard to the provision of further test procedures for assessment of consumable
performance. RMT would also undertake an appraisal of pretensioning and attempt to answer
questions arising from current use, experience and the perceived level of understanding of this
type of support. For example,
a) In what circumstances is their use appropriate?
b) What level of pre-tension is acceptable? (pre-tensions approaching 70% of ultimate
tensile load have been used)
c) What is the effect of pre-tension on the ability of a long tendon reinforcement system to
accept additional load and/or strain?
d) What is the effect of pre-tension on the shear properties of the reinforcement system?
e) Is there a genuine advantage in the use of pre-tension in certain circumstances and if so,
what circumstances?

f) What monitoring systems are appropriate for tensioned long tendons?


g) What monitoring action levels should be employed to ensure that timely remedial action
is taken prior to system failure?
h) What type of remedial action is appropriate in roadways reinforced by tensioned cables
and what response time is required?
i) Do colliery ground control management systems need reviewing to take account of pretensioned systems and if so, in what way?
j) When should tension be applied and when should a tensioned system be grouted?
k) How can it be ensured that a tensioned system, including any top down grouting system
employing thixotropic grout, is fit for purpose?
l) Should roof support design methodologies such as numerical modelling be revised to
incorporate tensioned systems and if so in what way?
In order to provide satisfactory data in response to these questions, a framework of aims and
deliverables was constructed. The aims of the Project were to achieve a better understanding of
the comparative behaviour of tensioned and non-tensioned long tendon reinforcement in UK
deep mining conditions, and to furnish this understanding to HSE and the industry. The
individual deliverables were as follows:
1. Develop suitable laboratory tests for assessing tensioned long tendon system
performance.
2. Produce a draft addendum/supplement to the DCMIAC document, Guidance on the
use of cablebolts to support roadways in coal mines, covering the use of tensioned long
tendon reinforcement.
3. Provide continued technical input to the Working Party and revision of BS7861:2
1997.
4. Produce a final report (and interim reports) on the outcome of the Project, suitable for
publication on the HSE website.
5. Provide a technical seminar to HSE and other interested parties on the findings of the
Project.
The Project commenced on 1st October 2005, and delivered according to the requirements
described above via regular progress statements. However, some two years in, it was found that
research into and testing of thixotropic grouts required for the pretensioned system used in UK
coal mines was absorbing unexpectedly high levels of effort, and problems encountered in the
research, which reflected obvious difficulties being experienced in the field, needed to be
resolved. After discussion with HSE supervising officials, it was agreed that the work
programme would be altered to allow the completion of the grout studies. Some other aspects
would be terminated or omitted, i.e. a cessation of work on a specific short encapsulation pull
test for tensioned tendons (this being thought unnecessary), and abbreviation of work on
analysis and comparison of tensioned and non-tensioned tendon monitoring data.
This document reports in full the outcomes of the Project in its final form and includes
a review of theoretical treatments of pretensioning
a description of the laboratory and underground testing of long tendon systems
analysis of monitoring data from sites where pretensioned systems were used
(abbreviated)
theoretical modelling of flexible long tendons
recommendations and draft procedures (annexes) prepared for the revision committee
a review of laboratory short encapsulation testing of rib reinforcement systems, and
a proposed revision of the DMCIAC cablebolt guidance document.

2 THEORETICAL ASPECTS OF TENSIONED TENDONS


This review examines the available information worldwide on the tensioning of rockbolts and
tendons, during or shortly after installation, and particularly on the recently adopted practice of
applying higher pretension loads. The purpose of the review is to identify the potential benefits
and drawbacks of high pretension loads.
2.1

ROCKBOLTING AND TENSIONING PRACTICE

2.1.1

What is pretensioning?

The term pretensioning is used in mining, mechanical and civil engineering to describe three
somewhat different processes. It is therefore useful to compare these to avoid confusion and to
see to what extent ideas and practices are generally applicable.
In mining, pretensioning is the practice of applying a predetermined load to rock reinforcement
tendons during or shortly after installation. It was originally applied to mechanical point anchor
bolts in order to lock the bolt head in position but with resin partially anchored types it is also
necessary to tension the end plate to the roof to make the bolt effective as a support. Tensioning
is also used with fully encapsulated rock bolts in conjunction with a two speed resin system.
Tensioning loads as high as 50 tonnes are now used with higher capacity systems such as strand
type bolts (Rataj, 2002). This practice has been claimed to increase tendon effectiveness as
reinforcement.
Pretensioning in civil engineering is the tensioning of steel reinforcing elements passing through
concrete beams before they are cast. Some of this tension is then locked in and generates
compressive stress in the concrete when it sets so that no tension develops in the beam in
service. Because concrete is strong in compression and weak in tension this allows beams to be
lighter and to be used over longer spans. Post tensioning is a similar process except that the
reinforcing tendons are placed in ducts passing through the beams after they have been cast and
cured. The tendons are then tensioned against end plates or anchors to put the beams in
compression.
This situation is fundamentally different from the way in which reinforcement is used around
mine openings. In a mine, the tendon is installed approximately normal to the rock surface,
rather than parallel to it, as a conventional reinforcing action requires. Consequently a
pretensioned mining tendon compresses the rock under the end plate, but a corresponding
tension develops close to the anchor position within the rock. This is in contrast to the concrete
beam situation where the reinforcement induces compression in the concrete along the complete
beam length.
In mechanical engineering, pretension loads are used in tightening bolted joints. A conventional
mechanical bolt used to clamp components together is tensioned by the mechanical advantage
which stretches the bolt. This tension is known as pretension because it exists before any other
forces are applied to the joint. The pretension compresses the mating surfaces, preventing them
from sliding or separating under load. Pretension loads are typically 70% of bolt tensile
strength.
When an external tensile load is applied to the joint the effect is to decrease compression of the
mating surfaces without significantly increasing tension in the bolt - typically 90% of applied
load is absorbed by decompression of mating surfaces. This is because the compression of the

surfaces has a very high stiffness compared with the bolt stretch, so compressive load reduces
much more quickly than the bolt tension increases as joint and bolt strain develop, up to the
decompression point at which joint mating surfaces are no longer in contact.
At first sight this situation might be considered analogous to the mining one. However there are
important differences. The main difference is that the material being bolted together in mining
is rock rather than metal. The elastic modulus of rock is typically some ten to forty times lower
than that of the steel tendon. Consequently we have the opposite situation to the mechanical
engineering one - the joint stiffness could be much lower than the bolt stiffness so that
external loads further increase tension in the bolt or tendon despite the pretension load. The
other major difference relates to the situation geometry - the mechanical bolt clamps together
two components across a single finite joint. In contrast the rock material is semi infinite in
extent and multiple potential failure joint positions may be present both within the tendon
length and beyond it.
In fact the mining pretension situation is analogous to gravity loading from a foundation as
pointed out by Gray and Bates (1998). The elastic solution for a homogeneous medium (the
Boussinesq equation) predicts a rapid dissipation of applied load with distance below the
foundation. Using the solution for a circular footing as analogous to a tensioned tendon end
plate suggests that, directly above the plate and at a distance equal to four times the plate radius,
the maximum induced confining stress is just 10% of the applied stress from the pretension
load. Consequently, if the rock behaves elastically, any strengthening effect from pretensioning
should be limited to a small rock volume in the immediate vicinity of the end plate. Gray and
Bates also point out that maximum confining stresses induced by pretensioning are at least an
order of magnitude less than likely in situ stresses, and that the tensile stress generated just
above the anchor horizon could reduce roof stability.
Fundamental questions therefore arise as follows:
Does pretensioning really strengthen the rock mass?
Are pretensioned tendons more effective than non pretensioned ones as support?
Are there any disadvantages of pretensioning?
The answers to these could lead in turn to further questions:
What is the optimum bolting system for use with pretensioning?
What is the optimum pretension load and how should it be applied?
What effect does tendon length have? Should pretensioned tendons be post grouted? Is
the failure strain of pretensioned tendons the same as non pretensioned ones?
Can pretensioned tendons be used for lifting or suspension of loads?
To try to answer these questions the available evidence from existing publications and
from consideration of engineering principles is considered in the review which follows.
2.1.2

Rockbolt systems

The large majority (about 85% according to Minova, 2006) of rockbolts used in coal mines
worldwide are now full column bonded with the remainder being partially anchored with either
a mechanical, resin or combination anchor. The use of mechanically anchored bolts in the USA
has been in steep decline since 1985 (Tadolini and Mazzoni 2006), although combination
resin/mechanical anchor types are used, particularly in difficult conditions (Mark 2000, Su and
Poland, 2007).

All partially anchored types are tensioned in order to tighten the end plate against the rock.
Without this the bolt would not be effective as support. Since the advent of fully encapsulated
systems in the late 1970s, a distinction has been made between rockbolts which are point
anchored or partially encapsulated and tensioned and provide active support, and dowels
which are fully encapsulated untensioned bolts and provide passive support. However this
distinction is now misleading as most fully encapsulated systems outside the USA are also
tensioned. The use of two resins of different gel times (fast and slow resins) with full
column bolts has been common practice for some years, with the primary object of facilitating
bolt installation. Tightening the nut after the fast resin sets, but before the slow resin gels,
results in tension being imparted into a full column bolt. This is known as the torque tension
system. The loads generated during normal installation (up to about 3 tonnes) are relatively
small.
The majority of bolts used in the USA are forged head rebar bolts (Tadolini and Mazzoni 2006).
Forged head bolts cannot be tensioned in the conventional way and normal practice has been to
use the installation drilling mast to hold these in position until the resin cures. However the
technique of thrust bolting, developed in the USA and patented in 1991, has emerged in
which the drill crowd force is used to push the bolt end and compressible plate tight to the roof
as the resin sets. This results in tension being developed in the bolt following the elastic
expansion of the compressed rock and plate, once the thrust force is removed.
The advent of flexible bolts - strand type steel tendons installed with polyester resin - in the
1990s has significantly increased the maximum length of rockbolt which is available to counter
difficult support conditions. These bolts have an end plate secured using a nut or barrel and
wedge anchor and can be tensioned. Tension loads of around 5 tonnes were originally used in
Australia, but more recently proprietary types such as the Hi-Ten and Megastrand bolts, capable
of being pretensioned to 25 tonnes or more, have been introduced (Rataj and Yearby, 1999). At
the same time, additional tension loads of up to 10 tonnes have been applied to full column
rockbolts. The use of higher pretension loads with bolts and cables in Australia is generally
considered to improve roof control in more difficult conditions (Fuller 1999, Hebblewhite
2006).
2.1.3

Tensioning and tension loss with partially anchored bolts

The use of mechanically anchored bolts has now declined to less than 4% in US coal mines. The
principal reason according to Tadolini and Mazzoni (2006) stems from the problem of tension
loss with these systems during and following installation. This has resulted in additional labour
cost as tension has to be checked regularly, and the bolts re-torqued if necessary. Costs then
compare unfavourably with resin bolts.
The first problem is achieving the desired tension during installation. Generation of the preload
by tightening is problematic. Tadolini (1991) found that torque wrenches over estimate preloads
by more than 45% because of frictional losses as the bolt head is tightened against the plate.
Lubricated thrust washers reduced the problem. Fuller et al (1981) produced design charts for
estimating the tension achieved from the applied torque when tightening a threaded end nut
against the collar plate. The tension developed depends on the torque applied and thread and
collar plate friction. Lubrication again decreased friction. These problems occurred at modest
loads. Consequently the development of very high pretension loads by tightening an end nut is
likely to prove difficult in practice.
Mechanically anchored systems are also vulnerable to loss of tension following installation.
This has been attributed to the high elastic modulus of the steel bolt in comparison with the
surrounding rock (the ratio varies from 10 to 40 or more with a typical value of 15) (Unrug et

al). The explanation given is that only a relatively small anchorage slip, or decrease in bolt
strain through local crushing, shrinkage, weathering or creep of the rock above the end plate, is
therefore needed to allow this tension to dissipate. The use of wooden header boards was
identified as a particular problem because of the tendency of the timber to creep and shrink,
releasing the tension. However this ignores the elastic nature of the compressed rock close to the
end plate which should compensate by expanding to maintain contact with the end plate. More
likely explanations are that anchor slip with mechanically anchored bolts continues under load
to significant levels, especially in weaker rocks, or that permanent deformation of failed
material under the end plate limits the elastic compression taking place.
Whatever the reason, loosening or tension loss with partially encapsulated bolts is a common
experience in mines (Mark 2000, Van de Merwe and Madden 2002). They also concluded that
tensioned bolting in softer rocks such as mudstones was likely to be ineffective due to tension
losses and a fully encapsulated system was needed in this case.
Resin assisted mechanical anchors are partially encapsulated with resin which flows around the
mechanical anchor and provides additional bonding these reportedly alleviate the problem of
tension loss due to anchor slip. They currently comprise about 9% of the US Market although
this appears to be declining (Tadolini and Mazzoni 2006). Su and Poland (2007) describe the
use of resin assisted mechanical shell bolts to reinforce laminated roof by Consol in the USA. A
longer resin column was found to be more effective in reducing the problem of tension loss. The
recent introduction of low insertion force resin has made the installation of this bolt system
easier, allowing four Pittsburgh Seam mines to adopt a full column of resin with 1.8 m long
resin assisted mechanical shell bolts pretensioned to 9 tonnes. Full column bonding is claimed
to lock in the pretension and eliminate the tension loss problem.
2.1.4

Tensioning and fully encapsulated bolts

Resin bonded rebar bolts comprise around 80% of US bolts installed. Although only 12% of
these were reported as being tensioned in 2006, the proportion is growing (Su and Poland 2007,
Tadolini and Mazzoni, 2006).
There is now a general recognition that fully encapsulated rebar bolts provide a high capacity
stiff bolting system which reacts rapidly to rock dilation by transferring load via the bolt to
other parts of the rock mass. Pretensioning is not a necessary part of this process, because of the
high system stiffness, and untensioned rebar systems in the USA are generally considered to be
better suited than partially anchored tensioned types to weak rock, high stress conditions
(Tadolini and Mazzoni, 2006). Su and Poland (2007) however argue for the need for tensioning
as well to counter immediate roof separation, which occurs particularly with place changing
systems in which bolting is carried out up to 12 m from the face. This may provide the motive
for the increasing adoption of tensioning with full column resin bonded systems in the USA.
The torque tension system using two speed resin cartridges dominates European and Australian
rockbolting practice. However the primary motive for adopting the torque tension system in
these countries was originally to facilitate rapid installation with pneumatic leg mounted drills
and the relatively small tension loads (up to around 3 tonnes) were primarily to clamp the end
plate firmly against the rock. The slow resin sets after any tensioning and this may result in the
tension being locked in and not so easily dissipated as it is with partially encapsulated systems
(Unrug and Thompson, 2002).
Thrust bolting is an alternative method of tensioning full column resin bolts. Unrug and
Thompson (2002) describe in-situ tests using a forged head thrust tensioned rebar system using
two speed resin. Strain gauged bolts were used to measure the levels of tension achieved, with

and without the use of a spring washer in addition to the plate. Tensions of 2.7 tonnes were
successfully generated in both cases. Thrust bolting depends on elastic deformation of the rock,
washer and end plate to generate the pretension load and the rock under the end plate must not
fail and deform under the imposed loads. It is unclear from the literature to what extent thrust
bolting is currently used in the USA as a deliberate technique to generate pretension loads.
The concept of increasing rockbolt pretension loads as a means of enhancing bolt performance
originated in Australia in the mid 1990s, (Rataj and Thomas 1997). A thrust bearing was
originally used to reduce thread friction to achieve initial bolt tensions of around 7 tonnes. Later
it was found that the use of high pressure lubricant plus modification to the nut could achieve
the same result. A number of field trials were carried out and the installation of bolts with initial
tensions of 10 tonnes or more using on board hydraulic bolters is now common in Australia
(Hebblewhite, 2006).
2.1.5

Pretensioning of long tendons

Steel wire strand bolts encapsulated with resin (flexible bolts) also originated in Australia in the
early 1990s. As these generally have high load capacity they are obvious candidates for
pretensioning. The maximum length which can be resin encapsulated is around 4 m, although
development work is ongoing to increase the encapsulated length to 6 or even 8 m. Normal
installation tension varied from 2 to 5 tonnes (Rataj, 2002). Tension loads of around 25 tonnes
were used in initial pretension trials (Rataj and Thomas, 1997), but more recently proprietary
types such as the Hi-Ten and Megabolt, capable of being pretensioned to 50 tonnes or more,
have been introduced (Rataj and Yearby, 1999, McKenzie, 2001).
Post grouting of conventional strand bolts is difficult and is not usually undertaken. Most types
can only be post grouted by installing into over-size holes (Fuller 1999, McKenzie 2001).
Megabolts can be post grouted but according to Strata Engineering (2001) this is not necessary
as the tendons are fully effective once installed near the roadway centre and pretensioned. The
more recently introduced Megastrand bolts as used at colliery C in the UK (Adams and
Rennison, 2003) were post grouted.
Techniques and equipment to allow the generation of pretension loads up to 60 tonnes have
been developed. Rataj (2002) describes these developments for strand bolts. With barrel and
wedge type end fittings special rimmed barrels have been developed to reduce tension bleed off
as the tensioning device is removed. However 25% loss of applied tension is said to be typical
for Hi-Ten bolts even with this modification and initial tension loss remains a serious problem
for strand bolts. The application of these high loads in practice is also not without difficulty Springvale Colliery in Australia reduced tendon tension from 20 tonnes to 12 tonnes in order to
replace the 20 kg tensioning equipment with a lighter alternative (Anon, 2000, Bahr 2006).
Barczak et al (2004) describe the application of hydraulic prestressing units as an alternative
means of tensioning tendons. These are inflatable metal bladders placed as a collar between the
tendon end fitting and the rock. Pressurising with water generated 9 tonnes of pretension,
following which the collars are left in place.
In excess of 80% of strand type bolts in Australia are reported to be pretensioned to around 20
tonnes or more (Rataj 2002) and the growth of this practice provides circumstantial evidence of
effectiveness. The use of higher pretension loads with bolts and tendons in Australia is generally
considered to improve roof control in more difficult conditions (Fuller 1999, Hebblewhite
2006). The main documented experience in the UK relates to the application of Megastrand
bolts tensioned to 25 tonnes at colliery C. These were reported as being highly successful when
early post grouting was used (Adams and Rennison 2003). Subsequently a roof failure was

experienced at another site at the same mine where these tendons were being applied without
early post grouting.
2.1.6

Ground anchor installation and progressive debonding

There are obvious parallels between the installation of ground anchors in Civil Engineering and
rock and cable bolting in mining - the only essential difference is one of scale as noted by
Barley and Windsor (2000). Ground anchors are normally stressed to a design load equivalent to
a maximum of 80% of the tendon strength after installation. Very large loads per anchor are
often used compared with mining practice although bond stresses over extended anchor lengths
are likely to be lower - typically around 1-3 MPa for stranded tendons (Barley and Windsor,
2000).
Prestressing of ground anchors has been cited as justification for introducing similar high levels
of pretensioning for mining tendons. The purpose is to restrain the anchored structure in place
against imposed loads, and prevent any strain and incipient failure from developing. The length
of ground anchors, which usually includes a significant unbonded section, means that
considerable displacement would have to take place to generate the design load if prestressing
was not practised. Mining tendons are much shorter, frequently fully encapsulated and generate
load very quickly in response to rock movement. Consequently there is not the same obvious
requirement for prestressing mining tendons as there is for ground anchors.
Ground anchorages consist of a fixed anchor, a free tendon length and a substantial anchor head
which transmits the tensile load in the tendon to the rock surface or structure. The free tendon
length is deliberately decoupled using plastic sheathing and/or grease to limit the anchor length
over which stress is transmitted to the ground (Littlejohn 1991). The limited length is used to
ensure that stress is applied to the planned anchor zone in stable ground and also to prevent a
phenomenon known as progressive debonding which is a perceived problem arising with long
anchorage lengths.
Progressive debonding arises as a result of the non linear distribution of bond stress along
extended anchorage lengths. Bond stress is concentrated at the proximal end and the distal end
is not initially stressed. As the load increases, bond yield occurs at the proximal end and the
load concentration zone progresses along the anchor length. Consequently the bond can fail
despite the apparent average anchor bond stress being well below the bond failure stress. This
has the consequence of limiting both the maximum load which can be applied to a single anchor
and the maximum effective bond length. Typically a 6-7 m bond length is optimal according to
Barley and Windsor (2000) - beyond that load capacity does not increase with bond length. The
concept of single bore multiple anchors was devised by Barley to get round this problem. A
number of tendons in one borehole are anchored in progression to distribute the load along the
anchor length (Figure 2.1).
Progressive debonding has not been considered as a problem for mining tendons to date. It is a
function of the anchor stiffness (controlled by the tendon) compared with the ground stiffness
according to Barley and Windsor. The worst case applies with low stiffness tendons such as
GRP installed in relatively stiff ground such as harder rock. Barley and Windsor give data
relating to tendons installed in London Clay which indicate the maximum effective bond length
could be as little as 2 m for GRP and 4 m for steel. This suggests that progressive debonding
potentially could lead to bond failure developing at lower than expected loads for mining
tendons installed into stiffer rock and then pretensioned to high loads. The potential for this
problem to occur needs to be considered for tensioned tendons. This would be indicated by a
non linear distribution of load along the tendon anchor length following tensioning, with load

not initially developing towards the distal end, and this could be checked with strain gauged
tendons.
Progressive debonding can be suppressed by making the grouted length greater than the fixed
anchor length, because the additional grout column along the decoupled length provides
additional support to the proximal end of the fixed anchor length grout where the bond stress is
applied (Barley and Windsor, 2000). In mining terms for pretensioned tendons this implies that
decoupling the tendon over part of the encapsulated length could prevent progressive debonding
from developing.
2.2

ANALYSIS OF THE PRETENSIONING EFFECT

2.2.1

Pretensioning and reinforcement mechanisms

The main mechanisms by which pretension improves roof support have been claimed to be as
follows:
i. Compression of the roof above the end plate adds confinement and so strengthens the
roof material (Zhang and Peng 2002)
ii. Clamping together of thinly laminated roof beds using pretension forms them into a
thicker beam which better resists shear deformations (Stankus and Peng 1996)
iii. Pretension increases the support stiffness so that it provides immediate resistance to
roof movement and so enhances support performance (Tadolini and Mazzoni 2006)
(Seedsman 1998)
iv. The application of pretension reduces or eliminates bed separations, which develop
before bolts are installed, to restore the structural integrity of the roof (Seedsman 1998,
Zhang and Peng 2002, Hebblewhite, 2006)
Most advocates would consider that a combination of some or all of these mechanisms operates
in practice. Perhaps the most prominent explanation of the pretensioning effect to date has been
developed by Strata Engineering in Australia (Rataj M and Thomas R 1997, Strata Engineering
2001). Pretensioned tendons installed near the roadway centre prevent or limit buckling of
immediate roof beds under end loading from horizontal stress. The mechanical advantage
accruing from the tendon position means that a relatively small restraining tension load provides
a large additional resistance to roof bed buckling. Pretensioning is effective because it prevents
buckling from developing more effectively than passive tendons (Figure 2.2).
It is unclear if Strata Engineering consider that application of pretension to tendons can close up
existing bed separations. This is put forward as a mechanism by Seedsman 1998 and others and
has been reported in practice - for example by Adams and Rennison (2003).
Gray and Finlow Bates (1998) considered pretensioning loads as applied through the tendon end
plate to an elastic rock mass and drew the analogy with application of foundation load to the
ground. This is dissipated rapidly in three dimensions so any strengthening effect should only be
local to the plate. In any case the additional confining pressures generated by pretension across
potential shear planes are small in comparison with likely in situ stresses.
There are also disadvantages to pretensioning according to Gray and Finlow Bates. A tensile
stress zone is generated above the anchor zone and, because rock is weak in tension, this could
make failure just above the tendon more likely. The bolt stiffness is unchanged by pretensioning
since it depends on the elastic modulus of steel which is constant. However, the remaining
elastic stiffness range before yield is reduced - effectively a loss of capacity. Overall they
consider that pretensioning tendons brings no significant advantage, and that longer bolts and
tendons should be fully grouted for maximum effectiveness.

The presumption that the rock behaves elastically is however questionable - at higher in situ
stresses shear deformation and possibly bed separation and buckling may be developing before
reinforcement takes place. It is in this latter situation that pretension is usually claimed to be
effective in preventing tensile bedding plane separation in the first metre or so, resisting bedding
plane shear and increasing the residual strength of failed rock within the compression zone.
In contrast to Strata Engineering, Seedsman (1997) advocates, in laminated roof conditions, the
use of pretension at the edges of intersections to resist shear movements, with unpretensioned
types to maximise capacity in the centre. He also considers that the outward inclination of bolts
away from the roof centre line could be as effective as pretensioning as a means of increasing
shear resistance.
2.2.2

Numerical modelling of bolt pretension

Very few modelling studies to examine rockbolt pretension mechanisms have been reported to
date. Some work has been done in the USA and Canada looking at partially anchored and
tensioned bolts within larger roadway models. Stankus and Guo (1997) described the
development of a two dimensional elastic finite element model with gap elements to represent
bedding plane partings and one dimensional bar elements as bolts. This approach is too
simplistic to give reliable predictions as noted by Mark (2000).
Bouteldja (2000) used modelling to predict load distributions in pretensioned and non
pretensioned cable bolts, again using two dimensional finite elements. A spring connection
between the cable and ground was used to represent the grout column and the end plate was
fixed to the rock. The load distribution along tensioned post grouted cable bolts and rock bolts
was found to depend on the type of grout and the type of anchor used. Pretension directly added
to loads imposed by ground movement.
Zhang and Peng (2002) describe a more sophisticated three dimensional modelling approach
using the ABAQUS finite element program. In this case element failure was detected using the
Mohr Coulomb failure criterion. Strata layers and two bedding planes were simulated and the
bolts were modelled as three dimensional beams with the anchor length tied to the rock and the
end plate in contact with the rock surface. A 10 tonne pretension load was applied to the bolts.
Bolt installation 8 m from the face was simulated by which time significant displacement could
develop depending on loading conditions.
The model suggested that bed separation develops as the immediate roof bed deforms under
horizontal stress loading. Pretensioned bolting was effective within the lower zone of
compression up to 0.9 m into the roof in closing the separation and increasing the residual
strength of yielded roof material. The compressive stress magnitude in the upper compressive
zone was very small compared with the vertical stress at this point and therefore had no effect
on model behaviour. They conclude that pretension closes cracks and separations and gives a
high resistance to subsequent movement.
In subsequent papers, Zhang and Peng modelled three way and four way intersections supported
by tensioned bolts and verified the model by comparing predictions with an instrumented case
study from 1991. Agreement was reported as good. They simulated bedding planes 0.6 m and
1.5 m into the roof. These opened when mining was simulated. With a three way intersection
10 tonnes pretension closed both bedding planes. For a four way intersection, 12 tonnes
pretension closed the lower bedding plane but not the upper. They conclude that the benefits of
pretensioning in terms of increased shear resistance and closing of bed separations was normally
limited to the first 0.9 m of roof.

10

Although recent modelling work demonstrates improved sophistication, more development is


needed to give a fully convincing simulation of rockbolt pretension mechanisms. In particular
the simulation of the bolt system needs to be improved to include the resin annulus and
associated interfaces, together with their engineering properties. Morsey et al (2004) describe a
more realistic 3D simulation of a fully grouted bolt using beam elements for the rebar embedded
in brick elements for the grout. Friction properties for the interfaces can be input. A pull test
was simulated in this case, but potentially similar models would be of value in examining
pretension in a more realistic way.
2.2.3

Pretension and the lifting or suspension of loads

The use of rockbolts to suspend pipe ranges or other services, or as anchor points for lifting
equipment is normal practice in mines. UK guidance limits the load which can be imposed on
standard support bolts to less than 1 tonne. For greater loads dedicated lifting bolts should be
installed. These are normally partially anchored and unplated to prevent load build up on the
bolt end resulting from rock deformation. Adams and Rennison however report the use of
pretensioned Megastrands as lifting bolts at colliery C. In this case a 25 tonne pretension load
was first imposed. This raises the question of the remaining bolt capacity for lifting-does the
pretension load reduce the available lifting capacity by the same amount, and does the load
being lifted then add its full weight to the load in the pretensioned bolt?
The weight of evidence from the above review suggests that the answer in both cases is yes,
principally because the steel bolt is stiffer than the host rock.
There is general agreement that the imposed pretension loads the bolt between the anchor and
the end plate, and therefore directly reduces the remaining bolt capacity. Any subsequent strata
loading is likely to directly add to this load.
Figure 2.3 illustrates the mechanical engineering situation described in section 2.1.1 in which a
bolt fastening together two metal components is pretensioned. A subsequent service load
applied to the joint or bolt end, decreases compression of the mating surfaces without
significantly increasing tension in the bolt because the compression of the surfaces has a very
high stiffness compared with the bolt stretch, so compressive load reduces much more quickly
than the bolt tension increases as joint and bolt strain develop. So in the mechanical engineering
situation an extra tensile load imposed on the bolt end does not significantly increase the load
along the bolt, providing it is not so large that the joint mating surfaces are no longer in contact.
The mining lifting bolt situation is different because of the relatively low stiffness of the
surrounding rock compared with metal components (Figure 2.4). A tensile load imposed on the
end of a lifting bolt will stretch the bolt, but because the compressed zone of rock has a lower
stiffness, the corresponding elastic expansion of the rock will not be large enough to
significantly reduce the pretension load. Consequently most of the imposed end load will be
seen along the bolt length as additional loading. In this case we would expect to break the bolt
before the plate loses contact with the rock surface.
The technique of thrust bolting (section 2.1.4) relies on this stiffness contrast between the bolt
and rock to generate bolt pretension. Unrug and Thompson (2002) showed that even without a
spring washer in the system, tension loads could be generated by elastic expansion of the rock
when the bolt was released.

11

It follows that it is inadvisable to use pretensioned bolts for lifting loads as the load capacity is
reduced both by the pretension load and by any subsequent strata loading. The latter load is
unknown unless instrumented bolts are used.
2.3

EVIDENCE FOR THE PRETENSIONING EFFECT

2.3.1

Field trials

Mark et al (2000) summarise instrumented field measurements of roofbolt performance in the


USA which investigated the effect of a range of parameters. Three studies compared tensioned
and non tensioned bolts. The results were inconclusive because of changes in conditions and
mining procedures which so often compromise field trials. At one site bolt loads in non
tensioned fully bonded bolts equalled or exceeded those of tensioned partially anchored bolts
after a few days, suggesting that in actively deforming roof, high pretension loads may not be as
important as the use of a stiff bolting system.
The wider introduction of pretensioning in Australia was preceded by field trials with rockbolts
and with pretensioned flexible bolts (Rataj and Thomas, 1997), (Strata Engineering, 2001).
Pretensioned roofbolts were reported to reduce roof displacement at Teralba Colliery, and
combinations of roofbolts and flexible bolts gave similar results at West Wallsend and Newstan
Collieries.
As part of ACARP project C8019, completed in 2001, tensioning equipment was developed to
allow 50-60 tonnes of preload with strand tendons. Project trials took place in a maingate travel
road at Crinum mine, longwall installation roads at Oaky North, and a maingate belt road at
Wyee Colliery.
The Megabolts at Wyee were installed after development. Increase of bolt pretension from
20 tonnes to 40 tonnes in the trial area reportedly slowed roof movement and improved visible
conditions in front of the retreating face.
At Oaky North, Megabolts were being installed as secondary support in longwall installation
roads. Road widening tended to cause instability at this site. In this case the Megabolts were
post grouted after tensioning to loads between 20 and 50 tonnes. However conditions during the
trial were better than expected and the results are not particularly conclusive. Five bolt-end load
cells all registered slow loss of pretension load by around 20% during the course of the trial.
This presumably reflects slight bedding in or creep at the bolt ends and suggests the absence of
dynamic strata loading in the lower part of the grouted length.
At Crinum Mine, Megabolts were again being used as secondary support on development in
weak roof conditions. Where the tension load was increased from 20 to 48 tonnes the roof
movement after tensioning was significantly reduced. The 48 tonne tensioned Megabolts were
not post grouted although the others were. Load cells showed static end load for the ungrouted
higher pretension load bolts and slowly increasing loads for the others. The effects of face
retreat are not reported in this study.
Although not a field trial as such, the introduction of Megabolts at colliery C in the UK (Adams
C and Rennison G, 2003) is described in some detail, including reports of the roof being pulled
back up into position as 25 tonnes pretension was applied, together with success in limiting
movement and improving conditions when early post grouting was being used. Greater
pretension is said to have had more effect. However a roof failure subsequently occurred at a
nearby site at the mine where early post grouting was not applied.

12

Mining field trials are extremely difficult to conduct because of the number of uncontrolled
variables - such as rock conditions and installation practices - which can influence the results.
Although the field trial data described here suggests that pretensioning may bring benefits, it is
not sufficiently comprehensive to be fully conclusive. The wider adoption of high pretension
loads in Australia as reported by Hebblewhite (2006) however provides further corroborative
evidence of this.
2.3.2

Laboratory studies

It is difficult to replicate the geometry associated with pretensioned bolt systems in the
laboratory. A single bolt or tendon can be installed across a joint plane in rock or concrete, and
tensioned for example, but, unless the sample blocks are very large, this does not realistically
reproduce the in-situ geometry - especially the dissipation of compression from the end plate. It
is difficult to obtain intact samples of weaker rocks and, in order to simulate an in-situ stress
field, the rock sample would also need to be installed into some sort of confinement system
which is only practical for small samples. Consequently there are few laboratory studies
reported, and these involve compromises in terms of test geometry, loading conditions and the
test medium.
A number of studies have looked at the distribution of load along a bonded tendon. These were
reviewed by Hagan (2003) who noted that applying load to a grouted bolt end generates a
tension which usually dissipates exponentially along the bolt, whilst loads generated by bed
separations within the bolted length are associated with linear load reduction on either side.
Laboratory testing of a strain gauged bolt with a bonded length of 175 mm, installed into a
simulated rock sample in a biaxial cell was undertaken to investigate this effect. Based on
limited results, the method of loading appeared to be the cause. The explanation put forward is
as follows: in the pull test a jack is used to stress the tendon and this bears against and
compresses the rock surface around it. The end plate maintains this compression after
tensioning and constrains the rock free surface around the bolt. In contrast when bed separation
occurs at some point along the bolt there is no corresponding surface restraint or compressed
zone and therefore rock confinement conditions differ between the two cases. The rate of force
reduction (a measure of efficiency) is greater in the former case suggesting that the bond
strength and load transfer rate in the initial bonded length are increased. This suggests that
pretension loads may not be distributed linearly through the resin bonded length although it
should be noted that post grouting would further change the situation.
The use of a 150 mm internal diameter biaxial cell to confine the rock specimen during tendon
testing was introduced by Fabjanczyk et al (1998). Previously steel tubes were commonly used.
Apart from the absence of initial stresses, these also impose an unrealistic boundary condition
because of their high stiffness compared with the rock test medium. Fabjanczyk et al showed
that in the biaxial cell bond strength results were lower than in steel tubes. A 500mm long strain
gauged rockbolt installed into sandstone in the cell with 10 MPa confinement was pretensioned
to 15 tonnes. The resulting load distribution was highest towards the proximal end as expected,
and initially non linear. After four days the distribution had changed towards linear, with a drop
at the proximal end and an increase towards the distal end. This suggests that either creep or
progressive debonding (see section 2.1.6) may have taken place, and the difference between the
two loading cases discussed by Hagan may be more complex than assumed. The results suggest
that in a static situation, high pretension loads could dissipate through resin creep, or could
damage the resin bond, and further investigation of these effects is needed.
Clifford et al (2001) report a laboratory pull test with a 2.4 m long Megabolt installed into
sandstone core contained in steel tubes. The bolt was anchored using resin, tensioned to 20
tonnes and post grouted. The tension load increased beyond the pretension value as additional

13

strain was applied to the bolt end. This would be expected if the compressed rock is more elastic
than the bonded tendon and so tends to confirm the conclusion from the discussion in section
2.2.3.
Mahoney et al (2005) describe the development of a laboratory test facility for shear loading of
reinforcement tendons. Shear loading along a single shear plane can be applied to fully installed
tendons. In this mode the tendon clamps the surfaces together and applies a normal force across
the shear plane to maximise the frictional resistance to movement. Concrete blocks of 1 m total
length were used as the test medium, with a single smooth joint surface formed at 250 mm as
the parting. Only a few test results with rockbolts were reported. Although initial pretension
increased early shear stiffness, it had no effect once stiffness reduced with further shear strain.
Axial collar loads of 16 tonnes developed in both pretensioned and non pretensioned bolts prior
to bolt shear failure.
The same conclusion - that pretension did not change the maximum shear resistance, only the
shear stiffness - was reached by Japanese experimenters in 1981 according to Jalalifar et al
(2006). Ferrero (1995) conducted laboratory shear tests with encapsulated steel bars installed
across a sawn joint in rock or concrete, and again concluded that pretension had no effect on the
final shear resistance, only on the initial stiffness.
McHugh and Signer (1999) studied the shearing behaviour of strain gauged resin grouted bolts
installed in high strength concrete blocks. The 600 mm long fully threaded bolts were tensioned
using end plates and nuts prior to the resin setting. Pretension loads up to 10 tonnes were used.
They found that pretension load had little effect on shear resistance.
Jalalifar et al (2006) reported a laboratory study of bolt double shear in concrete containing two
preformed joint planes. Total test length was 600 mm with joints at 150 mm from each end. The
fully grouted test bolt was tensioned axially with nuts and load cells to apply confinement
across the joint planes. Increased bolt tension again increased the early shear stiffness and
tended to increase the shear resistance at bolt yield. The tests were not continued to bolt failure
but the trends again suggest that pretension does not have a strong influence on maximum shear
resistance.
In summary these studies suggest that, for encapsulated bolts installed across a shear plane, the
only measurable effect of pretension is to increase the initial shear stiffness up to bolt yield. At
first sight this finding is surprising, but it presumably reflects the high stiffness of the bonded
bolts, such that high axial loads are generated by dilation during shearing, irrespective of the
initial tension load.
It should also be noted that these laboratory tests do not fully simulate real conditions in terms
of the stress field, the artificial nature of the joints and the bolt/rock installation and geometry.
The latter effect could be especially important as the laboratory set up maximises pretension
induced confinement across the joint plane and the pretensioned bolt axial stiffness. In the real
situation both parameters could be significantly reduced compared with the test set-up and this
would be likely to further reduce any benefit from pretensioning.
In summary it appears that, even under favourable test conditions, the laboratory studies
undertaken show little or no benefit in terms of shear resistance. For encapsulated bolts installed
across a shear plane, the only measurable effect of pretension is to increase the initial shear
stiffness up to bolt yield. As a significant increase in roof shear strength is the main anticipated
benefit usually claimed by advocates, this is surprising.

14

2.4

SUMMARY

This review has attempted to answer the questions posed in section 2.1.1. The most basic of
these is simply does pretensioning work? In other words does the application of high pretension
loads to untensioned fully encapsulated tendons, or lightly tensioned fully or partially
encapsulated types, really strengthen the rock mass, and are highly pretensioned tendons more
effective as support?
There does not currently appear to be any definitive proof or demonstration that high pretension
loads enhance support performance or significantly strengthen the rock mass. There is some
evidence from field trials of improved support performance and the wider adoption of increased
pretension loads provides further circumstantial and anecdotal evidence. Laboratory tests to date
have not however demonstrated any significant advantage.
A mechanism by which higher pretension loads improve support effectiveness has not been
confirmed in practice. The most widely asserted explanation - that higher pretension increases
shear resistance across joints and bedding planes - would seem to be ruled out by laboratory
studies. For encapsulated bolts crossing a shear plane these have consistently shown that an
increased initial shear stiffness up to bolt yield is the only measurable effect of pretension. Even
this effect would be limited to the zone of compression in the vicinity of the end plate.
An alternative explanation is that applying high pretension loads closes bed separations which
develop prior to bolting, and therefore re-establishes frictional contact between beds in the
immediate roof. This would provide a significant enhancement to the roof shear strength. Some
modelling work suggests that bed separations do develop at weak interfaces and that the
installation of tensioned bolts can close separations within the compressed zone-the higher the
pretension, the higher into the roof that separations can be closed.
The Strata Engineering concept of buckling immediate roof beds, which can be stabilised by
centrally placed pretensioned tendons, also involves the bed separation idea. In this case roof
stability is achieved from the mechanical advantage obtained by centrally supporting a buckling
beam, so it does not rely on closing the bed separation. The higher the pretension, the higher the
resistance to compressional forces acting on the ends of the beam due to horizontal stress.
Consequently horizontal stress is retained in the immediate roof and stability enhanced.
Acknowledging the practical difficulties associated with underground investigations, it should
still be possible to use field measurements to check the validity of these ideas by monitoring
roof deformations at multiple points as tendons are installed and tensioned, but this does not
appear to have been carried out to date. The identification of an underlying mechanism would
be the key to confirming that high pretension loads improve roof support.
The question of disadvantages associated with pretensioning was also raised in the introduction.
The main one cited is reduction of available tendon capacity. Additional strain resulting from
rock deformation will add directly to that imposed by the pretension load, so the tendon yield
strain will be reached with less additional strain. Tendon failure could in theory also be expected
at a slightly lower level of roof movement. However by far the major proportion of total tendon
strain to failure occurs post yield, and this is unaffected by pretensioning. So in deforming roof
conditions in which tendons are strained beyond yield this disadvantage is unlikely to be
important.
It follows from this that it is inadvisable to use pretensioned bolts for lifting loads as the load
capacity is reduced both by the pretension load and by any subsequent strata loading. The latter
load is unknown unless instrumented bolts are used.

15

There are other possible drawbacks. Progressive debonding (section 2.1.6) is one. There is at
least a theoretical possibility of failing the bond through this phenomenon, by application of
higher pretension loads, or subsequent additional loading, and this needs to be considered.
A reduction in rock confining stress above the anchor position is another potential drawback.
The pretension load generates a tensile reaction at the top of the tendon anchor length (Gray and
Bates 1998). In practice this should only slightly reduce the compressive stresses acting at this
position due to the in-situ stress field, but it could initiate instability in a marginal case.
It seems evident that tensioned tendons should be post grouted. One publication does question
the need for it (Strata Engineering, 2001), but the consensus is strongly in favour, with the
following reasons put forward:
i.
ii.
iii.
iv.
v.

It locks in the pretension load, preventing subsequent loss.


It ensures the tendon acts as an effective stiff support even without any benefit from the
pretension itself-the belt and braces principle.
It reduces moisture access to the rock through the annular space-this can cause long
term deterioration in weaker mudstones (Unrug et al 2004).
It reduces potential corrosion of the tendon from moisture and salts emanating from the
rock.
It reduces the risk of injury to personnel through violent failure of the tendon or end
fittings.

Post grouting could also provide a precaution against progressive debonding, should this prove
necessary.
It seems to be generally assumed that post grouting locks in the pretension load, preventing
subsequent tension loss, although this does not appear to have been verified by test work, either
in the laboratory or in-situ. Some laboratory work suggests that the initial load distribution may
change with time. However, pretensioned bolts are typically used in actively deforming roof
where additional loading rapidly develops, so longer term load change or loss is usually not an
issue.
It follows that the optimum bolting system for this application combines the facility to
pretension and post grout, with a high bond strength and stiffness in both the anchor and post
grouted lengths. There is however insufficient information to reach definitive conclusions on the
optimum pretension load and tendon length.
In order to fully resolve the considerable uncertainties which still surround the practice of
pretensioning, the following investigation programme is recommended:
i.

The question of the mechanism(s) by which higher pretension loads may improve
support effectiveness needs to be resolved. Field measurement, supplemented by
numerical modelling, appears to be the appropriate method in this case. Field studies
should seek to identify in detail the pattern of deformation of roadway roof and, in
particular, confirm the development of bed separations (as opposed to bed dilation)
prior to support, and establish if these are reduced or closed by the installation of
pretensioned support. Numerical modelling should be used to simulate the field
situation and add parametric studies. It is likely that a number of field sites will be
needed to obtain a representative range of conditions.

16

ii.

The detailed mechanics of tendon load transfer do not seem to be fully known, and this
adds to the difficulty in resolving the pretension question. Laboratory studies of rock
deformation and tendon behaviour under more realistic loading conditions should be
carried out to investigate load distributions in bonded tendons. These should make use
of findings regarding in-situ rock deformation processes obtained in the field studies. In
particular the difference between load distributions associated with tensioning the bolt
and those induced by rock deformation within the bonded length needs to be explained,
and if necessary allowed for in the experimental procedures. Factors to be investigated
should include pre and post yield interface shear strengths and stiffnesses, the
progressive debonding process, tension losses and the effect of post grouting.

iii.

The use of 3D modelling adequately simulating the tendon, encapsulant and rock, is
considered essential to complete the study of both the load transfer and pretensioning
processes. The shear behaviour of the resin/rock and tendon/resin interfaces, especially
at large strains, is an important factor and laboratory measurements should be used to
obtain the necessary data to allow simulation of this behaviour.

2.5

BIBLIOGRAPHY

Tadolini SC 1991 The Effects of torque tension relationships on roofbolt systems CIM Bulletin
July vol 84 no 951
PG Fuller GW Cadby 1981 Pre-tensioning rockbolts Division of Applied Geomechanics,
CSIRO technical report 112, March
Tadolini and Mazzoni 2006 Twenty four conferences, 170 papers and understanding roofbolt
selection and design still remains priceless 25th International Conference on Ground Control in
Mining, Morgantown
Unrug K et al 2004 Tensioned vs non tensioned systems 23rd International Conference on
Ground Control in Mining, Morgantown pp258-261
P Gray PF Bates 1998 The pretensioning placebo: Australias longwalls March pp78-81
Minova 2006 The Minova guide to resin-grouted rockbolts, Minova International Ltd, Chipping
Norton, Oxfordshire, UK.
Su D and Poland R 2007 Fully grouted high strength mechanical shell tensioned bolt improves
Pittsburgh Seam primary Roof Support 26th International Conference on Ground Control in
Mining, Morgantown pp235-241
M Rataj and M Yearby 1999 The Development of roofbolting in Australian coal mining, in
Rock Support and Reinforcement practice in Mining, Villaecusa, Windsor and Thomson,
editors Balkema Rotterdam pp425-435
P G Fuller 1999. Roof strata reinforcement - achievements and challenges Keynote Lecture in
Rock Support and Reinforcement practice in Mining, Villaecusa, Windsor and Thomson,
editors Balkema Rotterdam pp405-415
Tadolini SC 1991 The effects of torque tension relationships on roofbolt systems CIM Bulletin
July vol 84 no 951

17

PG Fuller GW Cadby 1981Pre-tensioning rockbolts Division of Applied Geomechanics, CSIRO


technical report 112, March
Van der Merwe JN and Madden B 2002 Rock Engineering for Underground Mining SAIMM
Special Series Publication no 7.
Mark C, Dolinar D, Mucho T 2000 Summary of field measurements of roofbolt performance.
Proceedings of New Technology for Coal Mine Roof Support NIOSH IC9453 pp81-86
Mark C. 2000 Design of roof bolt systems. Proceedings of New Technology for Coal Mine
Roof Support NIOSH IC9453 pp111-131
Hebblewhite B 2006 25 Years of ground control developments, practices, and issues in
Australia 25th International Conference on Ground Control in Mining, Morgantown pp111-117
Su D and Poland R 2007 Fully grouted high strength mechanical shell tensioned bolt improves
Pittsburgh Seam primary Roof Support 26th International Conference on Ground Control in
Mining, Morgantown pp235-241
Rataj M and Thomas R 1997 New methods and technologies of roof bolting in Australia coal
mines 16th Conf on Ground Control in Mining, Morgantown pp149-157
Strata Engineering (Australia) Pty Ltd. 2001. Application of 50 to 60 tonne cable pre-loads to
roof control in difficult ground conditions. End of Grant Report, ACARP Project C8019. report
no 97-079-ACR March
McKenzie R 2001 Cablebolts - a market review. International Longwall News, March 1st,
Aspermont Limited.
Anon 2000. Domestic market focus alters Springvale plan. International Longwall News, March
31st, Aspermont Limited.
Bahr A 2006. Springvale: solution to tough conditions. International Longwall News, October
19th, Aspermont Limited.
Adams C and Rennison G 2003 The application of pretensioned grouted tendons at colliery C
UK 22nd Int. Conf on Ground Control in Mining, Morgantown pp249-255
Rataj M 2002 Improvement in pretensioning strand bolts in Australian coal mines. 21st Int.
Conf on Ground Control in Mining, Morgantown pp145-149
Littlejohn S 1993 Overview of rock anchorages Comprehensive Rock Engineering vol 4
pp413-449 Pergamon Press
Barley AD and Windsor CR 2000 Recent advances in ground anchors and ground reinforcement
technology with reference to the development of the art GEO 2000 Int. Conf on Geotechnical
Engineering, Melbourne 19-24 Nov
Unrug K and Thomson E 2002 Field testing of fully grouted thrust tensioned bolts 21st
International Conference on Ground Control in Mining, Morgantown pp141-144

18

T M Barczak S C Tadolini P McKelvey 2004 Hydraulic prestressing units: an innovation in


roof support technology 23rd International Conference on Ground Control in Mining,
Morgantown pp286-294
Strata Engineering (Australia) Pty Ltd. 2001 Application of 50 to 60 tonne cable pre-loads to
roof control in difficult ground conditions. End of Grant Report, ACARP Project C8019. report
no 97-079-ACR March
Seedsman R 1998Less steel in the roof, more brass in your pocket Australian Longwalls March
p83
Seedsman R 1997 Geotechnical design of roof support and reinforcement ACARP SUMMARY
OF PROJECT c3027
Guo S, Stankus JC 1997 Control Mechanism of a tensioned bolt system in the laminated roof
with large horizontal stress 16th Conf on Ground Control in Mining, Morgantown WV
Zhang Y and Peng S 2002 Design considerations for tensioned bolts 21st International
Conference on Ground Control in Mining, Morgantown pp131-144
Peng SS Zhang Y 2003 Numerical model for tensioned bolting design: a case study Trans Soc
Min Metall. Explor. vol 314 sect 3 pp59-65
Zhang Y and Peng S 2003 Intersection stability and tensioned bolting 22nd International
Conference on Ground Control in Mining, Morgantown pp208-217
Morsey K, Yassien A, Han J, Khair Aw and Peng S 2004 3D FEM simulation for Fully
Grouted Bolts 23rd International Conference on Ground Control in Mining, Morgantown
pp273-277
Bouteldja M 2000 Design Of Cable Bolts Using Numerical Modelling PhD thesis, Department
of Mining and Metallurgical Engineering, McGill University, Montral, Canada, April
Fabjanczyk M, Hurt K and Hindmarsh D 1998 Optimisation of Roof Bolt Performance
Proceedings International Conf on Ground Control in Mining, Wollongong
Clifford B, Kent L, Altounyan P, Bigby D 2001 Systems used in Coal Mining: Long Tendon
Developments. 20th International Conference on Ground Control in Mining, Morgantown
Mahoney L Hagan P Hebblewhite B Hartman W 2005 Development of a laboratory facility for
testing shear performance of installed rock reinforcement tendons 24th International Conference
on Ground Control in Mining, Morgantown pp357-365
Jalalifar H, Aziz N, Hadi M 2006 The effect of surface profile, rock strength and pretension
load on bending behaviour of fully grouted bolts. Geotechnical and geological engineering 24
pp1203-1227
Ferrero A M 1995 The shear strength of reinforced Rock Joints Int. Jnl. of Rock Mechanics and
Mining Sciences 32(6) pp595-605
Hagan P 2003 Observations on the differences in load transfer of a fully encapsulated bolt.
Proceedings of 1st Australasian Ground Control in Mining Conference UNSW Sydney,
November.

19

Frith R 2000 The use of cribless tailgates in longwall extraction. 19th International Conference
on Ground Control in Mining, Morgantown pp84-92

20

3 LABORATORY AND UNDERGROUND TESTING OF LONG


TENDON SYSTEMS

Long tendon system testing was carried out to determine how effectively long tendons could be
encapsulated using candidate grouts and available mixing and pumping systems, and, in the
process, establish testing procedures for inclusion in the revised cablebolting Standard. Work
was also done to determine the effect on system bond performance of varying grout strength,
and the long term trends in grout strength were established via monitoring of comprehensive
field sample data. This work is described below.
3.1

GROUT ENCAPSULATION TESTING

This work was concentrated on development of laboratory tests for grouting and encapsulation
of flexible reinforcement systems. These should be suitable for:
checking that a particular grout is suited for use with a range of flexible reinforcement
systems,
checking that any particular flexible reinforcement system is suitable for use with grouts
which comply with other aspects of the Standard.
The key criterion is that full encapsulation of the strand can be achieved.
3.1.1

Bottom up testing

Grouting from the bottom-up is where a feed tube is located at the mouth of the installation
hole, and encapsulation progresses from the bottom to the top of the cablebolt. It is the most
common form of grouting. A test based upon that for double birdcaged cablebolts in the current
British Standard (reference 1) was devised, and tests on double mini-cage, double nut cage and
tensionable Reflex cablebolts carried out with Pozament CBG grout, the only grout currently
used for this type of installation in UK mines.
A 6 m length of strand was selected as the test datum - most cable bolts are 6 m long. The strand
was housed in a clear pvc (or similar) tube so that the encapsulation could be observed. For a
realistic test, the internal diameter of the tube selected was as near as possible to that of the
underground installation hole. The double mini and nut cable samples were prepared by first
attaching a breather tube to the strand the purpose of which was to bleed air from the
installation during grouting. Next, the grout tube was secured to the lower section of the strand,
the top of the tube being located approximately 0.5 m above the cable end. The tube was placed
on the opposite side of the assembly to the breather. Overall length of the grout tube was
approximately 2.5 m. The assembly was then located in the 45 mm diameter tube and slid into
the tube until the top of the cable was around 100 mm below the tube cap. To complete the
assembly, a seal around the mouth of the tube was required and this was achieved initially using
an expansive foam sealant. However, this proved only partially reliable and a fabric sock filled
with pre-mixed grout was also used.
Unlike the mini and nut cage cables, one version of the Reflex strand, is designed such that it
can be pre-tensioned prior to grouting by installing into polyester resin capsules located at the
top of the borehole, and then tensioning against a washer plate fitted at the borehole mouth. The
provision of a seal at the mouth of the hole prior to grouting is at least partially to be achieved
by the tensioning-induced tight fit of the plate against the roof strata. The strand supplied was
factory fitted with a steel breather tube located in the lay of the strand. The Reflex strand is

21

designed to be grouted using a feed tube and a special arrangement simulating a counter bored
hole at the mouth of the installation was used to accommodate this.
The tube assembly was placed alongside an aluminium scaffolding pole which was to act as a
support providing straightness and rigidity when erected to the vertical. The tube was taped to
the pole at 1 m intervals (to assist as a marker for grout flow) and jubilee clips were also used
to secure the assembly. The assembly was lifted and placed into a purpose made swivel bracket
mounted approximately 2.5 m above ground level. The bracket acted as a support and swivelled
to assist in placing the assembly in a vertical position. Once vertical, the assembly was clamped
in position. The breather tube (pvc in the case of mini and nut cage, steel for the Reflex bolt)
was immersed in a clear container of water. The flow (and cessation) of air down the breather
tube would be detected as bubbles in the container of water.
Mixing and pumping were carried out using a high-shear-mix system comprising tank, mixing
paddle with air motor, and Whyte-Hall Model GB7 pump unit. Separate air lines were
connected from the compressor to the mixer motor and pump to minimise pressure losses. The
pump was connected to the test piece via an 11 m long hose with pneumatic usage rating. Prior
to grouting, the grouting hose was flushed clear with compressed air to remove any standing
water and avoid dilution of the mix. The hose was then connected between the pump and the
grout tube in the test assembly. Grout pumping was then started and progress monitored first by
the show of air bubbles at the water container and then flow in the test piece, rotation of the
mixing paddle being continued throughout the process. Progress of grout encapsulation was
videoed. Following encapsulation, the equipment was flushed and cleaned.
The tests on double mini cage and nut cage cables, using 13 mm bore grouting tube and 10 mm
breather, were successful, and showed the method used produced consistent results. Average
encapsulation time was slightly shorter for the nut cage cables but this was almost certainly due
to variation in operator control. The tests showed that successful encapsulation can be indicated
reliably by a show of grout at the mouth of the breather tube, and this could be incorporated
both into codes and rules for underground installation and the acceptance procedure for the
revision of the British Standard (reference 1) - at least for systems which incorporate a
substantial breather tube. For the Reflex bolt tests, a show of grout at the breather exit was not
in evidence - due to the necessarily small bore of the tube. In this case full encapsulation was
coincidental with a cessation of bubbles at the breather exit. Provided this feature is shown to be
consistent, it could also be incorporated into procedures for this type of design.
Sealing at the mouth of the hole is probably the most unreliable part of the operation. The most
effective seal was formed by using a tubi-grip sock filled with grout and surrounding the cable
assembly. The Reflex bolt tests showed that sealing around the end plate was problematic but,
once accomplished, full encapsulation could be achieved. However, due to the sealing problems,
only one fully successful test was carried out; another test achieved full encapsulation but
leaked.
Procedure for mixing and grouting for the mini and nut cage tests involved connecting the grout
hose to the assembly grout tube before any pumping took place. This was subsequently changed
for the Reflex bolt tests following experience with Megastrand trials. Here, the grout hose was
first flushed clear with compressed air, and then the outlet returned to tank to allow a flow to be
established prior to grouting. This was shown to have advantages in allowing the flow to be
observed and regarded as satisfactory (or otherwise) prior to the grouting operation. This part of
the procedure should be incorporated into any future tests and the recommended acceptance
procedure for revision of the Standard.

22

The testing programme showed that the mounting arrangement with support pole and swivel
bracket was a practical proposition. However, the steel support pole used initially was relatively
heavy, and use of an aluminium pole made the procedure much easier and probably safer.
The testing procedure evolved from this test series was formally written up as a suggested
Annex to the revised Standard and this is included in a later chapter.
3.1.2

Top -down testing

Long tendons which are encapsulated from near to the top of the tendon to the hole mouth are
less common than bottom-up types, and at the time of writing, only the Megastrand system
uses this type of encapsulation, in the UK. The Megastrand comprises a grouping of steel wires
around a central hollow steel tube. The distal end of the assembly is welded together to form a
termination, and the proximal end has a more sophisticated arrangement which locks the
individual wires around a fitting which is threaded. The fitting is hollow, designed to
accommodate a grouting lance, and is also fitted with a nut. An end plate can be placed over this
end, and a hydraulic jack can also be connected to facilitate loading the installed strand (or
pretensioning). The Megastrand is designed to be encapsulated with grout injected into the
central tube which has an outlet at least 2 m below the distal end of the assembly. A systematic
and steady flow of grout down the assembly to the mouth of the hole requires the use of a
thixotropic grout. However, for pretensioning, the assembly is first spun through a resin capsule
placed at the top of the installation hole, and anchored prior to loading and subsequent grouting.
Resin anchored length is usually around 2 m.
Testing equipment and procedure were similar to that described above. A 6 m Megastrand was
located in a clear pvc tube and a grout lance attached to the feed connection in the end fitting of
the strand. The mouth of the hole/tube was not sealed, and a successful test would be where
grout would fully encapsulate the strand from top to bottom and start to issue from the hole
mouth. The grout selected was Pozament HPRG thixotropic grout which is designed to have a
water-to- solids ratio (WSR) of 0.3. This is the only thixotropic grout currently accepted for use
in UK mines.
The tests used the standard pump / mixing system currently used in UK mines - Whyte-Hall
GB7 pump and mixing assembly sourced from Australia, powered by a mobile compressor
delivering 0.69 MPa (100 psig). The tests identified problems with the mixing and pumpability
of the HPRG grout at the recommended water:solids ratio (WSR) of 0.3. It was found that it was
necessary to add further water to achieve a pumpable mix, even though it was later found that
the grout was supplied in bags low in weight, resulting in an already higher WSR than expected
when mixing the required quantity of water with a bag of grout. [All future tests were carried
out with accurate weighing of grout and water prior to mixing]. Tests on grout cubes indicated
relatively low strength due to low densities derived from excessive water quantities. The results
suggested the possibility that the system may not be being used properly underground, with
additional water added to the grout to achieve pumpability. It was found that it was possible to
achieve full encapsulation with a higher WSR of 0.33, the thixotropic nature of the grout being
maintained, but the additional water consequently reduced the strength of the grout. This
problem was referred to the manufacturers (grout and strand) for resolution and a revised
thixotropic grout formulation (AGH10) with modified properties and a higher recommended
WSR was developed.
Three laboratory pump tests were undertaken with the new grout at the recommended WSR
(0.33) and these were all successful. Tests on cube samples cured for 28 days, taken from two of
the mixes, produced mean strengths of 70 and 77.5 MPa respectively, compared with the current
British Standard requirement of 80 MPa. This result contrasted to the manufacturers UCS cube

23

test results which indicated compliance with the Standard. The probable explanation for this
discrepancy is the difference between the laboratory mixing and curing regimes specified in the
Standard in comparison with those achieved with the mixing system and regimes used
underground (and in the laboratory encapsulation tests), which could include air entrapment and
curing temperature variation.
An underground field placement trial of the HPRG and AGH10 thixotropic grouts for top
down tensionable reinforcement tendons was carried out with Megastrands at colliery B but
this was inconclusive due to on-site limitations, in particular very low pneumatic pressure. The
results were at odds with the laboratory experience in that the standard grout performed (in
encapsulation terms) at least as well as the variant. On-site air and water temperatures were very
high (in excess of 34 deg C), and it is possible that this could have affected the thixotropic
nature / viscosity of the grout. Grout samples were taken during the trials and laboratory tested
after curing for 28 days. Results for UCS and density were low compared to the manufacturers
specification, for both the standard and variant grout, despite careful attention to mixing ratios.
This, however, is fairly typical of field trial results and (to some extent) results from laboratory
trials.
These trials and underground experience at other mines suggested that the grout pumping
equipment currently being used in the UK may not provide the performance required for this
application. Therefore an alternative pump / mixer unit (Blue Heeler) was imported from
Australia by the Megastrand supplier and a further set of two laboratory pump tests was
undertaken using the AGH10 grout (with a WSR of 0.33) and Megastrand combination, again
6 m of encapsulation being sought. However these tests were problematic with one failing to
achieve grout flow into the cable and the other achieving two-thirds encapsulation before the
grout delivery hose burst. The issue of whether these tendons can be installed satisfactorily
with an appropriate thixotropic grout has still to be resolved. Nevertheless the top down pump
test has been fully documented and recommended for inclusion in the revised Standard.
3.2

VARIATION OF BOND PERFORMANCE WITH GROUT STRENGTH

The problems which arose during the encapsulation trials of Megastrand led to some debate in
the revision committee as to the requirement for a 28 day grout strength of 80 MPa. The figure
was carried forward to the revised draft from the original Standard, and there was some
discussion that if this could be lowered, a more easily pumpable grout could be used, leading to
more reliable encapsulation of the Megastrand tendon. The original strength criterion was
decided upon so that system bond strength, as measured in a laboratory short encapsulation pull
test (LSEP), could be optimised, and it follows that any reduction in strength might lead to
reduction in bond performance.
In order to resolve the issue, a laboratory test programme was set up to determine the variation
of bond performance with grout strength. The test was based on the LSEP procedure used for
determination of long tendon performance for research work carried out for an earlier project,
and fully described in reference 2. Samples of Megastrand 1 m long were encapsulated to a
depth of 325 mm in sandstone cores using Pozament CBG grout. The cores were housed in a
biaxial cell pressurised to simulate typical underground stresses. CBG was chosen as the
encapsulant as this grout was easier to mix using bench equipment, more pourable for easy
sample assembly, and its properties with respect to curing time very well known (when
compared with thixotropic grouts). At the same time as the samples were encapsulated, grout
from the same batch was poured into sample bottles and cube moulds. The intention was to pull
test groups of two Megastrand samples and to crush test corresponding cube and bottle samples
at intervals as the grout cured, so producing measured bond performance over a range of grout
strengths. Eight samples were prepared with grout mixed to the standard WSR, and two more

24

with a weak mix to be tested within 24 hours at a very low grout strength. The samples with a
standard grout mix were tested with 1 day, 3 days, 7 days and 42 days curing time.
The bond performance results are shown graphically in Figures 3.1 and 3.2 as variation of load
with bond displacement for samples cured from 1 to 3 days, and 7 to 42 days respectively. The
graphs were used to determine maximum load, bond strength, and system bond strength in the
load range 150 300 kN. Bond strength is defined as load at which the slope of the load /
displacement characteristic falls below 20 kN/mm, and system stiffness is the slope of the load /
displacement characteristic over the load range given above. The values determined were then
plotted against corresponding grout strength from cube crushing tests, and the results are shown
Figure 3.3. A logarithmic curve fit was applied to each set of data points and these are also
shown in Figure 3.3.
It will be seen from Figure 3.3 that all fitted curves show increasing bond performance with
grout strength, as would be expected, although the bond strength individual values tend to
plateau above a grout UCS of 60 MPa. Although the existing Standard (reference 1) calls for a
minimum UCS of 80 MPa after 28 days, it was known that CBG, and the associated thixotropic
grout, would continue to increase in strength beyond this time, and 42 day results confirm this,
with an average cube strength of 94 MPa. However, it should be noted that grout strengths
determined from field samples, although often measured well in excess of 28 days curing, rarely
achieve the 28 day requirement, and are often well below this figure. This issue is outlined fully
in the next section. Since bond performance has been shown to continue to increase with grout
strength, and field measurements indicate that the existing requirement for strength is not being
met (see below), it is difficult to justify a relaxation in the requirement.
3.3

FIELD SAMPLE GROUT TESTING

UK coal mines have used only one type of cementitious grout for bottom-up long tendon
encapsulation, and some other applications, for at least the last 12 years. Pozament CBG grout
is subject to routine sampling at the mines, and the bottle samples are always weighed for
density but usually also crushed at a specialist laboratory to determine strength. Crushing after
28 days curing is recommended. Applications requiring a thixotropic grout utilise Pozament
HPRG grout which is also required to meet strength criteria specified in the Standard, and also
subjected to routine testing as described above.
A database of bottle sample test results for CBG was established in 2001. In 2006 the database
was brought up to date, and results for HPRG included. The database was further revised in
2007 to include CBG and HPRG samples from colliery A. The variation of grout strength with
density for bottle samples of CBG grout up to an including 2007 data is shown in Figure 3.4.
The results indicate that the CBG grout had consistently met the current British Standard,
provided that it had achieved the density (2090 kg/m3) previously furnished by the manufacturer
as being consistent with their recommended WSR. However, on many occasions, this density
had not been achieved in the field. This is particularly true of 2007 samples supplied by colliery
A. Only one of 36 samples collected during 2007 from colliery A achieved the 28 day UCS (80
MPa) and none reached the 2090 kg/m3 density. This prompted a mixing test, witnessed by the
manufacturers, which was conducted on the surface at the colliery, using the Whyte Hall mixer
and pump, and where cube samples were taken. Tests on these samples showed a problem with
the CBG grout strengths. This was referred to the manufacturer who reformulated the grout in
order to resolve the issue. With reference to achievable density, the manufacturer, at one stage,
proposed to lower the requirement to 2.045 kg/m3. However, this was an error arising from
quoting the requirement for density at 24 hours curing. The 28 day figure quoted above is
correct, and still valid.

25

The results from HPRG bottle samples collected at colliery A are given in Figure 3.5. None of
the samples achieved the required 28 day strength and density values of 80 MPa and
2090 kg/m3 respectively.

26

4 UNDERGROUND MONITORING OF PERFORMANCE AND


EFFECTS OF TENSIONED LONG TENDONS

The effectiveness of tensioned long tendon systems in UK mining conditions was to be


determined in two ways:
a) analysis of the historical and monitoring data available at UK Coal collieries and
Headquarters in order to compare the actual in-situ behaviour of tensioned and un
tensioned systems. In the event, as described in chapter 1 above, this work was
abbreviated so that issues arising from the use of thixotropic grouts could be more fully
explored and resolved.
b) underground monitoring to be undertaken on the effects of installing and tensioning
long tendons on the surrounding strata and accompanying support systems. This work
was carried out during installation and tensioning of Megastrands at a face line drivage
at colliery A.
4.1

HISTORICAL DATA ANALYSIS

4.1.1

Introduction

Tensioned long tendon systems were first used in UK mines in the late 1990s but came to more
prominence in 2002 when the Megastrand system was used for remedial support in a main gate
at colliery C. This project was regarded as a success and use of the Megastrand became more
widespread. Although installation of the Megastrand was intended to be a staged process where
initial installation and pretensioning would be quickly followed by grouting, development in the
UK became oriented toward delaying grouting due to operational constraints. This development
led ultimately to a failure at a UK mine, where inspection of a fall of ground clearly showed that
Megastrands had not been previously grouted and so would not have been as effective as
properly installed (fully grouted) long tendons.
In the UK the Megastrand has been widely used at colliery C and at some sites at collieries A, B
and D.
We have tried to establish the success or otherwise of use of the Megastrand in terms of its
contribution to the stability of a site during development and face retreat but time constraints
and availability of analysable information have limited the study to two sites at colliery C, and
to a lesser extent, a face heading at colliery B.
4.1.2

Site studies 10s main gate, colliery C

10s main gate at colliery C was driven 1638 m inbye to the face start position. Primary support
was via 2.4 m full column roofbolts. Cablebolting was carried out systematically over at least
1000 m of the drivage using non-tensioned mini-cage cables, 8 m long, in various
configurations, but well behind the development face and in response to action levels indicated
by monitoring.
A diagram of the drivage layout and snapshots of development monitoring are given in Figure
4.1. At the development stage, a section of the maingate at around the 500 to 600MM suffered
significant roof deformation and stability was re-established by installation of minicage cable
bolts in response to telltale action levels. On face reteat, a section of the maingate roof inbye of

27

the 500 metre mark (MM) area, which had been stabilised by cable bolting on development,
began to move again well ahead of the retreating face resulting in severe problems close to the
face end. Eventually the face was halted with face end machinery jammed. Following salvage
work, Megastrands were installed ahead of the retreating face together with steel supports. The
6 m Megastrands were installed in pairs with 1.2 m spacing along the gate, tensioned to 25
tonnes and then grouted with thixotropic grout. Conditions no longer deteriorated ahead of the
face and the face was able to resume and continue to complete extraction of the panel.
Conditions were reported to be superior to most recent experience in the same seam.
Figures 4.2, 4.3 and 4.4 show monitoring results for monitoring stations at 607, 423 and 248
metre marks respectively. The results span several months and indicate increasing movement at
the inbye stations with the face retreating to within 100 m or so of these stations. In particular
Figure 4.2 shows the activation of previously stabilised roof at a horizon just above the rock
bolts at 607MM.
Results from tell tale measurements - both those installed for roofbolts and after cable bolts
were installed are shown in Figures 4.5, 4.6 and 4.7. These give histograms of ground
behaviour along the main gate from the face positioned at the 1000m mark through to
completion. Figure 4.6 and 4.7 both show the B indicator cable bolt tell tale results but from
differing perspectives. They indicate a particularly large roof dilation at the 565 MM. but the
dilation here did not progress significantly with face retreat and the effects of front abutment.
Figure 4.7 shows how the roof inbye of 565MM remained stabilised for some time after cable
bolt installation but then began to deteriorate significantly as the face approached.
It is probably fair to conclude from the above that the significant roof dilation experienced on
development where support was via roofbolts and passive mini-cage cablebolts, was prevented
from progressing significantly during face retreat by the installation of the additional tensioned
support.
4.1.3

Site studies 22s main gate, colliery C

Following the introduction of tensioned tendons in 10s main gate, their mode of application
was changed for 22s development in that 8 m Megastrands were installed behind the
development face as secondary support in place of the previously used passive mini-cage cables.
The 8 m Megastrands were installed in pairs, 1.2 m apart, tensioned to 25 tonnes and grouted
using thixotropic grout. This was successful and conditions in 22s main gate were significantly
better than those experienced during 10s drivage and retreat. Figure 4.8 is a histogram of the
complete development / retreat history of 22s main gate via type A tell tale results. It will be
seen that roof dilation was moderate along the gate during drivage and face retreat did not
produce any significant additional roof movement.
4.1.4

Site studies 19s tail gate, colliery C

The successes experienced with 10s recovery and the retreat of 22s panel encouraged the mine
to modify the deployment of tensioned systems still further, to the extent that Megastrands were
installed at the development face in pairs, 6 m long and tensioned to 20 tonnes. However
grouting was carried out outbye of the face and behind the development machinery in order to
speed up or at least not impede development rate, and grouting was only undertaken in response
to the action levels set for the A type tell tales (25 mm of indicated dilation).
It was on this gate road that a major fall of ground occurred. The fall occurred during face
retreat between the 588 and 600 MM with the inbye end bounded by cribs, and the outbye end
bounded by wood props. Wood props had been removed from the area in which the fall

28

occurred to facilitate crib building. Subsequent investigation showed that high levels of roof
dilation had taken place prior to the fall. Figure 4.9 shows plots of the combined indicated
movement from A and B tell tales (in the vicinity of the fall) at the 570, 590 and 610 MM.
Total movement measured by these tell tales prior to the fall was 360, 322 and 207 mm
respectively. This level of movement would indicate that failure of rockbolts and long tendons
was highly likely, and examination of the installed roof support after the fall showed that this
was indeed the case. Examination of the (failed) Megastrands in the fall area also indicated that
grouting may not have been effective with very little grout evident around the strand assemblies.
4.1.5

Site studies T18s face line, colliery B

Drivage of T18s face line experienced support difficulties soon after commencement. Width of
the roadway was initially 6.4 m and primary support was via 2.1 m fully encapsulated roofbolts.
Monitoring results showed instability above the bolted height and, at 44 MM, cablebolting was
commenced using 8 m double nutcaged cables. Cables were installed behind the face, and a
programme of cable bolting back toward the heading entry was also commenced. At the same
time, drivage width was reduced to 4.8 m, with cheeking out to full width being carried after
initial drivage. At 62 MM, cheeking out was stopped.
Installation of Megastrands commenced at the 105 MM and continued for the rest of the
drivage. Results were reported to be favourable with anecdotal evidence of the roof being
driven back up on pretensioning i.e. strata beds separated on excavation were recompressed
by loading the Megastrands prior to grouting.
A diagram of the site is given in Figure 4.10. As the Megastrands were installed in a section of
heading driven at a substantially smaller width than the initial nutcaged section, and it was not
cheeked out during drivage, it would not be appropriate to attempt to compare the monitoring
results from the Megastrand and nutcage sections.
4.1.6

Discussion and conclusions

Initial use of tensioned long tendon reinforcement in UK mines gave encouraging results with
previously problematic longwall districts showing improved face end conditions on retreat, less
requirement for additional support around the face end, and improved retreat rates.
Tensioned systems were first used as secondary or remedial support well behind the
development face and additional to passive non-tensioned cablebolts, and then replacing the
non-tensioned support system.
Problems arose when the tensioned systems were installed at the face with subsequent grouting
delayed until some time later in response to tell tale movement reaching action level status.
This procedure can be expected to have had three major consequences. Firstly, the initial high
stiffness of a tensioned system that might have been effective in controlling early roof
movement, had the tendons been grouted on installation, was not available.
Secondly, and probably more importantly, the roof movement which occurred prior to grouting
probably restricted the tendons central and external annuli and prevented proper subsequent
grouting, The laboratory testing of thixotropic grout mixing and pumping, described elsewhere
in this report, has shown proper grouting of Megastrands to be problematic even in controlled
conditions. These problems would be exacerbated considerably in-situ especially where
immediate roof shear had been allowed to distort the bottom end of the tendon prior to grouting.

29

Thirdly, there is considerable anecdotal evidence that grouting teams in the field, have difficulty
grouting newly installed tensioned cables with thixotropic grout, and in this event, will resort to
watering down to achieve full grouting of an installation. The temptation to water down the
grout in this case will have been exacerbated by the additional grouting difficulties experienced
due to roof deformation. The operating principle behind grouting the Megastrand, and other
top down groutable tendons, is that the thixotropic nature of the grout will cause it to flow
down the strand from the ejection point in the central feed tube, encapsulating the strand until
reaching the mouth of the hole, where a show of grout will indicate successful grouting. If the
grout is watered down, compromising the thixotropic nature of the grout, then clearly the show
of grout at the mouth of the hole cannot be guaranteed to indicate successful encapsulation.
Furthermore, watered down grout will be weaker and slower to develop strength than properly
mixed material.
Less comparison of monitoring data from tensioned and untensioned long tendon sites was
possible during the project than was originally envisaged for two reasons. Firstly, considerably
more project time was required to investigate the grout mixing, pumping and strength issues
described above as these were only discovered during the course of the Project. Secondly, such
comparison was impeded by a scarcity of directly comparable examples of roadway behaviour
with and without the use of tensioned tendons.
However, the work carried out indicates that, at least initially, the deployment of tensioned
systems in gate roads where non tensioned support had failed to provide workable retreat
conditions, was successful, with colliery C achieving satisfactory retreat rates where the
previous main gate exhibited prohibitive roof failure around the face end before tensioned
systems were deployed. Use of tensioned systems replacing non-tensioned cablebolts as
additional support at 22s main gate, colliery C, was also successful, and available monitoring
information indicates good roof stability in the main gate during face retreat. However,
installation of tensioned systems at the development face with subsequent grouting dependent
on tell tale action levels appears to have been a step too far, particularly in the light of
subsequent investigation revealing the difficulties associated with grouting these systems with
available equipment.
4.2
UNDERGROUND MONITORING OF LONG TENDON TENSIONING AT
COLLIERY A
This monitoring exercise was undertaken in order to measure prior to grouting the effects of
tensioning to approximately 10 tonnes, 8 m long Megastrand reinforcement tendons in a roof
which had already been subject to a moderate level of dilation and had been previously
reinforced with a combination of 3 m long KT rockbolts and tensioned 8 m long Megastrands.
4.2.1

Drivage and support aspects

A face line at colliery A was driven from the Tailgate (left hand gate looking inbye) to Coal gate
using a Joy BM ED15 bolter miner equipped with 4 hydraulic roofbolting rigs and two rib
bolting rigs. The drivage was commenced with 8.2 m width with the roof supported using a
reinforcement row spacing of 0.8 m, each row comprising 9 x 3 m KT rockbolts, 6 x 4 m
flexible Reflex bolts, both installed through AT polyester resin capsules, and 3 x 8 m
Megastrand tensioned tendons. Two additional 1.8 m KT rockbolts were placed behind the
bolting machine to fill an unreinforced triangular area created by the bolt installation angles of
the bolter miner drill rigs. The Megastrand tendons were installed with a point anchor using a 28
x 1200 mm medium set AT resin capsule, then tensioned to a nominal 10 tonnes within several
hours of installation and finally grouted using Pozament HPRG thixotropic cementitious grout

30

as a batch at the end of each shift. The Megastrand is fitted with a central grout tube and is
designed to be grouted from the top down using a suitable thixotropic grout.
The face heading commenced at the Tailgate junction at a roof horizon approximately 1.45 m
above the top of the Two Yard seam and then, leaving a lip at the 30 m mark, moved forward
beneath a 0.8 m thick coal top. The face heading experienced considerable difficulties in
maintaining roof control at full width, requiring considerable remedial support and making poor
progress. It was therefore decided to switch to a two stage drivage system and from the 80 m
mark onwards, drivage continued at the narrower width of 5.2 m with roof support provided,
again at 0.8 m row spacing, by 10 x 3 m KT rockbolts and four x 8 m Megastrands at 0.8 m
spacing plus one central 1.8 m KT bolt.
Following thirling with the coalgate and formation of the junction, the maingate ABM25 bolter
miner commenced driving back along the face line widening it on the face side to a total width
of 8.2 m. The support pattern is shown in Figures 4.11 and 4.12. This shows that an additional 4
x 3.0 m KT bolts plus 2 x 3.85 m flexible Reflex bolts were installed across the additional
3.0 m width at a 0.8 m row spacing, with a further alternating pattern comprising rows of six
and then four 8 m Megastrands installed across the full width of the face heading at the same
row spacing.
4.2.2

Installation layout and reading of instruments

The instrumentation installed specifically for this exercise comprised 3 rows of instruments
installed between straps and centred around the cable bolting telltale (13) at 196 m (nominally
194 m). For convenience these rows have been labelled as 195 m, 196 m and 197 m, though the
strap spacing is actually 0.8 m. The relative positions of the instruments and the excavation on
21 March 07, when installed, and 27 March 07, when the neighbouring Megastrands were
tensioned, are shown on Figures 4.13 and 4.14.
The instruments were installed towards the face side of the narrow section of the face, six days
prior to the machine cutting past during the widening operation. Each row of instrumentation
included 2 x 3 m strain gauged KT rock bolts and a roof extensometer. The strain gauged bolts
were additional to the existing rockbolting pattern previously installed. Each was fitted with 9
horizontally opposed pairs of 120 ohm resistance strain gauges spaced at equal intervals along
its length and mounted in longitudinal machined slots, to measure axial and bending load
distribution These were read with both a Soil Instruments SG1041 Strain Meter and an RMT
SM01 SGMeter data logger, the latter being used for continuous readings every 10 seconds on
each bolt whilst a nearby Megastrand was being tensioned.
The extensometer in the central row of instruments was a Magnesonic type with 19 readable
anchors installed at intervals in a 43 mm diameter borehole up to a maximum height of 7.0 m.
The extensometers on either side were RMT RME04, 4 height remote reading extensometers
which could be read using a RMT RRT-1442-PR ATEX approved portable readout with a
resolution of better than 0.1 mm. The top anchors were installed at 10 m into the roof.
Figures 4.12 and 4.15 show the originally intended positions of the instruments with respect to
the existing supports. The main difference between planned and actual was that, due to practical
constraints, strain gauged bolts 2, 4 and 6 were situated on the opposite (goaf side) of the
already installed Megastrand and thus further from the positions of the nearest Megastrands to
be installed and tensioned than originally intended.

31

4.2.3

Results telltale and wire extensometer data

The weekly reading history for cable bolting telltale 13, nominally at 194 m (actually 196 m),
from installation on 10 November 2006 until its replacement due to going over-scale (+75 mm
on A) on 17th May 2007, is shown in Figure 4.16. It was anchored at 7 m (A) and 9 m (B). This
shows that the roof had stabilised at a displacement of approximately 11 mm in the zone below
7 m, in the Megastrand reinforced height, with an additional 7 mm between 7 m and 9 m above
the reinforced height, prior to the widening process. By the time that the machine had just cut
past on 27th March the roof had begun to move again in the reinforced height with the readings
increased to 27 mm (A) and 6 mm (B). The roof continued to dilate in the reinforced height at a
relatively high but gradually slowing rate over subsequent weeks and had not re-stabilised by
the time the telltale went overscale on 17 May, 8 weeks later.
A 5 wire extensometer was located at 192 m, anchored to a maximum height of 7 m and
installed on 14th November 2006 near the face of the heading. This had registered 24 mm of
total roof lowering by the 19 March, just prior to installation of the new instruments, 23 mm of
which had occurred below a height of 2.9 m (first anchor height). This is shown in Figure 4.17.
4.2.4

Results remote reading extensometer data

No data was obtained from RRExto 2. It appears that, when installed, the wires were not
properly crimped to the instrument and so no subsequent changes were registered.
RRexto 1 was anchored at 10 m, 7.5 m, 3.7 m and 2.1 m with readings taken relative to roof
level. The total roof dilation measured during the 15 days between installation on 21/3/07 and
the final reading on 5/4/07, to a height of 10 m, was 32 mm of which 9 mm occurred below
2.1 m, 18 mm occurred between 2.1 m and 3.7 m and 2.5 mm occurred between 3.7 m and
7.5 m (see Figure 4.18). This compares with 39 mm total roof displacement measured on the
nearby telltale between 19/3/07 and 2/4/07.
The relative distribution of dilation between anchor bays remained similar throughout the
measurement period. The rate of roof lowering was approximately 3 mm per day over the
weekend period prior to cutting past the exto, 7 mm per day between the 26th and 27th March as
the machine cut past the station and up until the Megastrands were tensioned, 3 mm per day for
the 2 days following Megastrand tensioning and 1 mm per day over the next 7 days until
readings ceased. This final rate of 1 mm per day was the same as that measured by telltale 13 for
the 7 weeks following cutting past.
No significant change in roof dilation rate or lowering rate was measured during the tensioning
period itself (see Figure 4.19). Certainly no closure of dilation or roof lifting was measured.
4.2.5 Results sonic extensometer data
The sonic extensometer results are shown in Figures 4.20, 4.21 and 4.22. Figure 4.20 shows 2
main strain zones forming in the roof, at 1.2 m near the top of the coal roof (26 mm/m) and
3.2 m (30 mm/m). No movement was measured above a height of 4.1 m. The sonic
extensometer data agrees generally with the Remote Reading Extensometer data, showing about
6 mm more total roof lowering over the period to 29th March. The sonic extensometer was lost
to roof shear prior to the 5th April when the final RRE readings were taken. The large number of
anchors used with the sonic extensometer allowed the strain zone at 3.2 m to be identified as a
newly developed zone of dilation associated with the cut past, being above any zone of
significant strain previously detected by the wire extensometer at 192 m. This significant strain

32

zone was located just above the top of the installed 3 m rockbolts within the zone reinforced by
Megastrands alone.
4.2.6

Results strain gauged rock bolt data

The strain gauge rock bolt data is set out as mean microstrain and microstrain difference graphs
in Figures 4.23 4.28. During the period from first reading on 21st March until the day prior to
cutting past and Megastrand tensioning (26th March) there was considerable increase in bolt
loading, with most bolts reaching at least 20 tonnes towards their centre and bolt 3 definitely
going well into yield. During this period gauges were lost in the central sections of bolts 3 and
4, probably due to high strains.
Table 4.1 Sequence of SG bolt readings, Megastrand tensioning
and bolt load development on 27th March 2007
SG bolt
number

SG1

SG2

SG3

SG4

Reading
times
during
tensioning
10:44

Number
of
readings
at 10s
intervals
2

Reading
and Mega
tensioning
sequence

Comments on bolt load/strain changes during


corresponding periods

Initial
readings

10:54

Mega 1

11:14

Mega 3

Final
readings

Compression from previous day except at 1m &


2.4m
No change
No change during tensioning
Compression 1.5 2.0m
No change during tensioning
Compression 1.5 2.0m & below 1m
Reloading back to earlier tension levels in
subsequent days

Initial
readings

10:46

11:04

Mega 2

11:50

Final
readings

10:48

Initial
readings

Compression from previous day around 0.8 - 1.1m


Further compression 1.5 2.7m
No change during tensioning
Very little change
Considerable additional tensional loading 1.1 -1.5m
on subsequent days

Considerable compression from previous day

11:51

Final
readings

Some small changes (tension and compression)

during overall tensioning period.

Considerable additional tensional loading on

subsequent days

10:49

Initial
readings

Considerable tensional load development from


previous day, greatest towards centre of bolt.

33

SG5

SG6

11:52

Final
readings

10:52

Initial
readings

11:22

Mega 7

11:54

Final
readings

10:53

Initial
readings

11:18

Mega 6

11:54

Final
readings

No change during overall tensioning period.


Considerable additional tensional loading on
subsequent days

Considerable tensional load development from


previous day at 1.1m taking bolt to yield.
No change
No change
No change
Additional tensional loading on subsequent days at
1.1m and eventual gauge failure at 1.1m
Tensional load development towards centre of bolt
from previous day reaching yield.
Some further tensional load development in bottom
half of bolt
No change
No change
Considerable additional tensional strain on
subsequent days in centre of bolt leading to eventual
gauge failure at >13000 microstrain

The original plan had been for each bolt to be monitored using the data logger whilst the nearest
Megastrand was tensioned. The actual sequence of monitoring and tensioning differed
somewhat from the ideal and is set out in Table 4.1 above. The Megastrand and bolt numbers
are defined on the plan shown in Figure 4.14.
During the period when the machine cut past (26th to 27th March), different bolts behaved in
different ways. Bolts 1, 2 and 3 all moved towards axial compression along some sections of
their length, though retaining a similar shape of overall axial load distribution along their
lengths. This resulted in the tops and bottoms of the bolts going into compression with the
central sections remaining in tension. Bolts 4, 5 and 6 all continued to develop tensional loading
along their lengths. The period from installation to cut past was accompanied by very high
levels of bending in most bolts, particularly bolts 2, 4 and 6, towards the centre of the faceline.
During the intensive periods of monitoring whilst nearby Megastrands were tensioned, no
changes in bolt strain/load were measured though changes did occur on both bolts 1 and 2
before, between and/or after successive intensive periods of monitoring. In the case of Bolt 1,
the successive periods were 20 minutes apart, occurring during the period of other Megastrand
tensioning and when some other bolts were moving into tension.
Following the machine cut past and Megastrand installation, tensioning and grouting, all bolts
continued to develop load, with some gauges being lost due to high strain and each bolt
probably going beyond yield at some location along its length. Some gauges reached 18000
microstrain (1.8%) prior to failure. This should be considered in the context of the steel
characteristics, with yield occurring at approximately 0.3% and strain at maximum force being
above 8% according to the BS7861-Part 1:1996 (reference 3).

34

4.2.7

Results grouting

Two bottle samples (samples 7 & 8) were taken from the mix of Pozament HPRG thixotropic
grout which was used to encapsulate the newly installed Megastrands on 27th March 2007.
These were tested at an accredited test house at an age of 38 days. Sample 7 had a density of
1.950 g/cc and UCS of 62.8 MPa and Sample 8 had a density of 1.925 and UCS of 60.7 MPa.
Sample 8 was slightly misshapen due to storage and two small air pockets had formed on the
sample surface.
BS7861 Part 2:1997 (reference 1) calls for a 28 day cube strength of at least 80 MPa, for
samples cast in the laboratory. The manufacturers data sheet states that a density of 2.2 g/cc
will be achieved with the correct water solids ratio of 0.3 and proper mixing without air
entrapment. However the measured bottle sample strengths and densities are comparable or
higher than those typically obtained for HPRG from other underground sites in the UK, though
higher strengths can be achieved for a pumpable mix in laboratory conditions using the same
equipment. It is probable that the densities and strengths achieved on site were attributable to a
combination of the following factors:
problematic pumpability of HPRG at the recommended water to solids ratio,
probable air entrapment during the mixing process using the Whyte Hall pump and
mixer system,
strength reduction due to higher water temperatures than those specified for laboratory
tests.
4.2.8

Discussion and conclusions

The Megastrand tensioning process to approximately 10 tonnes at this site did not produce any
re-closure of previous roof dilation measurable with the highly sensitive extensometers used.
This was the case even though the immediate roof had dilated by approximately 20 mm during
the preceding 5 days. It can therefore be concluded that, previous reports of the roof being lifted
during Megastrand tensioning most probably refer to relatively exceptional circumstances where
very large displacements have already occurred. Also when roof lifting does occur it is likely
only to apply to the very bottom roof strata where discrete bed separations and bolt debonding
or bolt failure may have already occurred.
The strain gauged rock bolt results are difficult to interpret. Although no change in strain was
measured on any of the six bolts specifically during the one or two minutes of tensioning of a
nearby Megastrand, there was definitely a trend towards bolt compression on bolts 1, 2 and 3
over the period when Megastrands were being tensioned in the vicinity and in some cases the
amount of compression was significant. The compressive strain experienced along sections of
these bolts was 2000 to 4000 microstrain, equivalent to localised compressive loading of up to
25 tonnes or more. However this did not appear to prevent these bolts developing further
tensional loading over subsequent days as the widening process progressed away from the
measurement site. Whilst it is possible that this bolt compression was associated with the
Megastrand tensioning operations, it is also possible, that it was associated with the general
redistribution of loading within the roof which would have occurred during the widening
operations, with cantilever and destressing effects occurring in the previously exposed section
of roof, where these bolts were located, as the face heading width increased.
It can be concluded that the Megastrand tensioning operation in itself did not damage the roof
and there is no evidence that it impaired the operation of the previously installed reinforcement.

35

36

5 IMPROVED MODELLING OF FLEXIBLE LONG TENDONS


As described in Chapter 2, very few modelling studies of tensioned tendons in mining have
been reported. The work undertaken during this Project has concentrated on incorporation of
tensioned long tendons into geotechnical numerical models using the FLAC finite difference
continuum modelling package supplied by ITASCA Inc. FLAC is an acronym for Fast
Lagrangian Analysis of Continua. The work has involved the following;
a) developing a methodology for incorporating pre-tensioning of fully grouted tendons
into the FLAC models generally used for assessing and comparing reinforcement
designs for underground coal mining applications,
b) developing a methodology for examining tensioned truss type supports incorporating
flexible long tendons using FLAC this was prompted by a suggestion from senior
personnel within the UK mining sector that application of such systems, as used in the
USA, could be highly cost effective if adopted in the UK
c) use of FLAC models for comparison of the effectiveness of the two systems described
above (grouted tensioned long tendon reinforcement and tensioned truss systems)
with conventional non tensioned flexible reinforcement.
d) application of the techniques developed to specific support design problems at a UK
colliery
A further area of flexible long tendon modelling work under the Project has been to compare
alternative support strategies for both hypothetical and specific sites where the use of a less
dense primary rock bolt support pattern at the face of the heading combined with a secondary
support system installed outbye incorporating flexible long tendons has been considered as an
alternative to a higher density of reinforcement applied close to the face of the heading. The
incentive for such strategies comes from the potential increase in drivage rates that may be
achievable and it is important to identify whether this is a safe option.
The work has therefore concentrated on developing an approach for representing tensioned and
untensioned long tendons in FLAC and applying the resulting models to real mining problems,
rather than fundamental studies of tendon / grout / rock interaction.
All the modelling described has used FLAC3D to represent a short slice of mine roadway and
the surrounding strata one support cycle thick. This has allowed the spacing of reinforcement
along the roadway to be more realistically represented than in a purely two dimensional model,
but avoids the complexities and long run times associated with a truly three dimensional model
of the complete tunnel including the heading face
5.1

REPRESENTATION OF TENSIONED TENDONS AND TRUSS SYSTEMS

Both FLAC and FLAC3D allow a pre-tension to be specified for a bolt or cable as it is installed.
However, when using this feature the forces in the tendon will not be in equilibrium with those
elsewhere in the model. As a result a substantial proportion of the specified pretension may be
lost as the model deforms to achieve equilibrium. The alternative is to model pre-tensioning as
it is actually achieved, by applying load to the bolt or cable. The procedure adopted was as
follows:

Specify bolt geometry, dimensions & steel properties


Set bond properties for anchored length at top of bolt (spin into resin)

37

Apply load to base of bolt and reaction force to roof (pressurise jack)
Step model to equilibrium
o Tension spreads along free length of bolt
o Balancing loads develop along anchored length
Fix base of bolt to rock in roof (tighten against face plate)
Remove applied loads at base of bolt (remove jack)
Set bond properties for rest of bolt (if fully grouted)

Pre-tensioned truss systems are sometimes employed as an alternative or in addition to bolts to


provide confinement and support to mine roadway roofs [Oldsen et al 1997, Pile et al 2004].
They consist of angled bolts or cables installed each side of the roadway connected by a truss
bar or cable which is tensioned during installation. The reaction forces where the truss bears
against the rock generates horizontal in addition to vertical confining stresses in the roof. The
structural elements and commands provided in FLAC allow a truss system to be simulated
either by continuous cables or separate components with appropriate connections. Pretensioning of the truss was achieved in a similar manner to that for pre-tensioning bolts by
applying the tensioning force to each end of the truss, stepping the model to reach equilibrium,
connecting the truss ends and then removing the tensioning forces.
The effectiveness of these systems as remedial support was compared by modelling a non
specific roadway (5.2 m wide x 3.0 m high) with weak roof that softened on excavation. This
comprised mudstone up to 3.2 m into the roof with a seam thickness of 2.4 m as shown in
Figure 5.1 (strata sequence and model grid). The material behaviour adopted for the rock
incorporated the following features:

Increasing strength with confinement


Bi-linear strength envelope with higher friction at low confinement
Reduced strength parallel with stratification
Post-failure softening or strength loss

The property values assigned to the different rock types were typical of those found applicable
in UK coal measures from previous work. The strengths used were reduced from those typically
measured in the laboratory to represent the in-situ or rock-mass strengths. Figure 5.2 shows the
strength envelopes assigned for the three rock types used in the model.
The initial vertical stress in the models was set to 20 MPa at the level of the roadway,
corresponding to a depth of 800 m. The lateral stress acting across the roadway was set at
16 MPa in rock, with a lower value of 12 MPa in coal.
The models incorporated 7 x 22 mm x 2.4 m fully encapsulated high strength steel rockbolts per
row in the roof with a yield strength of 280 kN, bond strength of 100 kN/m and bond stiffness
of 200 MN/m/m. Each rib was reinforced by 3 x 24 mm x 1.8 m GRP rockbolts per row with a
yield strength of 300 kN, bond strength of 100 kN/m and bond stiffness of 20 MN/m/m. Model
runs were undertaken at various bolt densities to identify sensitivity. These showed that
increasing the bolt density beyond 1.9 bolts per m2 (0.7 m spacing) did not improve roof control
significantly. Also increased bolt length from 2.4 to 3.0 m had little positive effect. Subsequent
models examining the effects of flexible long tendons therefore used a row spacing of 0.7 m.
The flexible tendons were 2 x 4 m long flexible bolts per row with a yield strength of 450 kN,
bond strength 430 kN/m and bond stiffness of 200 MN/m/m. Encapsulation length was 2 m.
The model sequence comprised, installing the remedial support systems, then failing the
original roof-bolts and following the model response. The model roof displacements with no

38

secondary support installed are plotted in Figure 5.3 showing the vertical roof movement or
lowering and the horizontal convergence of two points either side of the roof (termed roof
shortening). On excavation of the roadway, both roof lowering and shortening increased but
then stabilised. When the roof-bolts were failed, the roof displacements increased again. The
roof lowering continued to increase with no evidence of stabilising, in effect indicating a roof
fall.
The response with tensioned cables installed as remedial support is plotted in Figure 5.4 (a). In
this case the roof lowering started to increase again after the bolts were failed but soon re
stabilised. Figure 5.4(b) plots the tension in the cables showing the initial application of pre
tension to 200 kN. On failure of the roof-bolts the cable tension increased to 450 kN, the yield
strength of the cabled specified in the model.
The response with non tensioned cables installed as remedial support is plotted in Figure 5.5 (a).
The roof lowering again stabilised after the primary bolts were failed and was slightly lower
than with pre-tension. The final tension developed (Figure 5.5 (b)) was significantly less than
with pre-tension and the flexible bolts did not reach yield in this case. This is a significant
consideration with regard to the advisability of using tensioned reinforcement systems.
The response with a tensioned truss system as remedial support is plotted in Figure 5.6 (a). The
roof lowering again stabilised but after substantially more movement than for the tensioned
cables. The response of the truss tension in Figure 5.6(b) is of particular interest. Once again it
shows the initial application of pre-tension. However, when the roof bolts were failed the
tension in the truss first started to reduce as a result of the roof shortening before finally
increasing again as the roof lowering became more significant.
Figures 5.7 and 5.8 illustrate the final state of the models showing strain contours and cable
tensions for the two cases. The results showed both systems stabilising the roof. The truss
system allowed much larger roof displacements before the roof stabilised, the tension generated
in the truss was less than in the tensioned cables. The initial reduction in the truss tension
illustrates what may be a general point, that tensioning of roof truss systems is unlikely to be
effective in mining environments where the roof is shortening.
5.2

APPLICATION TO MAINGATE SUPPORT ON DRIVAGE AT COLLIERY C

Colliery C was working longwall retreat panels at a depth of approximately 1000 m. Conditions
experienced in the Maingate of the previous panel during retreat had been poor resulting in
production delays. For the next face being developed, a dense pattern of reinforcement was
planned as follows:

installed at face during development at 1.5 m cycles


o 7/8 x 2.4 m x 22 mm roof bolts
o 2 x 8 m tensioned tendons
o 3/2 x 1.8 m x 22 mm rib bolts

installed approximately 70 m behind the face


o 1 x 8 m tensioned tendons
o 2 x 8 m tensioned tendons, angled above ribs with provision to attach truss/sling

Installed before retreat


o 2 x 3.8 m rib tendons
o Truss/sling between angled tensioned tendons

39

The mine operator was concerned that this support would result in slow drivage rates and RMT
were requested to examine alternatives to enable faster drivage rates. The support system had to
be adequate for development and additional support could be installed for retreat if required.
The alternative support patterns examined concentrated on a reduced density of 2.4 m roof bolts
but with a higher than usual density of longer tendons, in the form of un-tensioned flexible
bolts.
The comparison between different reinforcement patterns was made using computer modelling
using the techniques described in section 5.1. An initial comparison was made for expected
conditions during development of the gate, with the reinforcement represented in the model
being that intended to be installed at the face during development. Additional support or
reinforcement to be installed back from the face or prior to retreat were not included at this
stage, nor were stress increases that might be experienced during face retreat allowed for.
The FLAC3D models described in section 5.1 were modified to reflect the geological sequence,
rock properties and stresses expected at the site. Rock properties were available from tests
carried out for previous modelling exercises for the mine.
5.2.1. Site description
For the modelled panel the depth varied between 970 m-1030 m and the seam thickness was
1.8 m - 2.2 m. In-situ stress measurements were available from two sites at the mine, the results
are summarised in Table 5.1.
Table 5.1 Measured in situ stress
Site

Method

Depth from
surface
(m)

Elastic
modulus of
strata
(GPa)

Maximum
horizontal
stress
(MPa)

Minimum
horizontal
stress
(MPa)

Underground
Surface borehole
Surface borehole

Overcore
Hydrofrac
Breakout

960
916-1001
-

25
-

24
26-29
-

13
14-15
-

Azimuth
of
maximum
horizontal
stress
334o
149o-154o
142o

The gates of the previous and planned panels were oriented with azimuths of 150o/330o placing
them approximately in-line with the expected maximum horizontal stress direction.

5.2.2. Model description


The proposed nominal width for the Maingate was 4.7 m. The model roadway was represented
as 4.8 m wide and 3.2 m high with the roof horizon formed at the top of the seam. The planned
reinforcement system as represented in the computer model is illustrated in Figure 5.9. In all
cases the lower end of the bolts or cables was set to be rigidly connected to the model grid,
representing a strong plate to retain bolt load as well as the grout bond between bolt and rock.
The bolt properties used are summarised in the table below:

40

Table 5.2 Modelled support parameters

Bolt type
Bolt yield strength (kN)
Bond strength (kN/m)
Pre-tension (kN)

Roof
KT
280
400
0

Solid rib
KT
280
50
0

Face rib
GRP
400
50
0

Roof
Tensioned tendon
600
430
100

Roof
Flexible
500
400
0

Model runs were conducted comparing alternative reinforcement patterns with the two
geological sequences shown in Figure 5.10. The main difference between the sequences is that
sequence B includes a band of weaker mudstone in the roof at 4 m above the seam not present
in sequence A. The properties assigned to the different strata types were obtained from previous
modelling work.
Results obtained with the planned reinforcement system are illustrated in Figures 5.11 and 5.12
showing shear strain contours, bolt and cable loads and simulated roof extensometer
displacements. The range of roof displacements indicated by the simulated extensometers is
representative of those that can be experienced during gate development at the mine. Except for
the lowest of the stresses plotted, the results showed both bolts and cables (in this case tensioned
tendons) being loaded up to their yield strength.
The difference between the two geological sequences examined was relatively small. The
mudstone at 4m in sequence B allowed additional movement at this horizon for the highest
value of lateral stress used. This value for the lateral stress range was higher than the expected
range. In effect this would be similar to the rock mass strength being lower than represented in
the model.
5.2.3

Comparison of alternative reinforcement patterns on drivage

Model runs were carried comparing the performance of alternative reinforcement patterns. The
basic form of the alternatives examined is shown in Figure 5.13. The tensioned tendon bolts
were omitted from the original pattern and 7 of the 2.4 m KT bolts replaced by flexible bolts in
a staggered 4/3 pattern.
Results obtained using geological sequence A are plotted in Figure 5.14 (showing roof
extensometer movement at roof level and at 2 m into the roof) and in Figure 5.15 (showing
maximum bolt and cable strains). With the tensioned tendon cables omitted but no flexible bolts
installed the roof displacements and KT bolt strains increased.
Replacing 7 KT bolts with 4 m flexible bolts reduced the roof displacements, but the total
movement remained more than for the original pattern. The bolt strains reduced below those for
the original pattern. The strains developed in the flexible bolts were similar to those for the
tensioned tendons.
Increasing the flexible bolt length from 4 m to 6 m did not result in a major difference in the
results.
A final run was conducted to check the potential effect if full encapsulation could not be
achieved with 6 m flexible bolts. The upper 4 m of the bolts was assigned the same bond
strength as previously, the lower 2 m was not bonded. The results obtained indicated
considerably poorer roof control with increased roof displacements and higher strains in the KT

41

bolts. This result demonstrates the importance of obtaining full encapsulation and of
maintaining a high density of effective reinforcement in the bolted horizon.
The shear strain contours, bolt and flexible bolt loads obtained form the run with 4 m flexible
bolts indicated that the two outer flexible bolts were not fully loaded and were less effective
than the others. This is likely to be the case where the roadway behaviour is symmetrical (as in
the model) with displacements extending higher into the roof above the centre of the roadway.
In these circumstances, longer tendon reinforcement is likely to be more effective placed
towards the centre of the roadway than at the sides.
Results obtained using geological sequence B were very similar to those obtained with sequence
A. There was slightly more benefit to longer flexible bolts in this case.
5.2.4

Conclusions from modelling drivage support design

The following conclusions can be drawn from the modelling of alternative support on drivage
for the particular set of conditions modelled.
The results obtained indicated that to maintain roof conditions during gate development
in these conditions it is important to maintain a high bolt density.
If flexible bolts are adopted to replace ordinary (KT) roof bolts as part of the pattern
then it is important that they are fully encapsulated.
The roof condition was not strongly sensitive to varying the length of flexible bolt
between 4 m and 6 m.
The alternative patterns examined used flexible bolts in place of KT bolts. These gave
roof conditions comparable to the original pattern but no clear improvement.
Using flexible bolts in addition to rather than in place of KT bolts may produce
improved roof control and condition.
5.3

APPLICATION TO MAINGATE SUPPORT ON RETREAT AT COLLIERY C

As described above, the next panel to be developed at Colliery C was planning to use a
combination of tensioned tendons and a trussing system as additional support to be installed at
various stages following drivage and during face retreat.
The work described in section 5.2 for development included examination of different geological
sequences and initial stresses. For the modelling of face retreat, these variations were not
included. The geological sequence used was Sequence A (see Figure 5.10). The vertical stress
was taken as 25 MPa and the lateral stress acting across the gate was set as 16 MPa.
5.3.1 Simulation of face retreat
When the face is retreated, the gate road ahead of the face will be subjected to altered, and
probably increased, stresses. The effect of this was simulated by starting with the existing model
for development of the roadway and increasing the stresses acting at the outer boundary in
several stages. This procedure has been used effectively to provide guidance on expected
conditions during retreat at many sites.
The stress redistribution around a longwall face and the resultant stress changes for the gate are
complex and will be dependant on a large number of factors including:
Caving geometry

42

Waste consolidation
Rock properties
In-situ stress regime

The stress increases applied to the model are shown in Figure 5.16. Although model runs were
conducted using both the stress-notched and non-stress-notched options shown in Figure 5.16,
only the results obtained for the stress-notched option are included in this report.
5.3.2

Support system

The support system planned for the gate was listed in section 5.2 and involved support
components being installed at different stages during the life of the gate. For the modelling of
secondary support described here, there was no differentiation in the model between support
installed 70 m behind the face and that to be installed prior to retreat, both were added to the
model at the same stage.
Model runs were conducted both with and without the additional support planned for retreat.
For the runs with the additional support, this was added to the model after the development
phase had been completed and prior to the stress increases being applied.
The bond properties for the tensioned long tendons were also set at the same stage, implying
that they were grouted immediately after installation. The truss/sling was assigned a tensile
yield strength of 600 kN and tensioned to 100 kN when installed.
5.3.3

Results

Model results obtained with the planned additional support installed are illustrated in Figure
5.17, showing shear strain contours, bolt and cable loads and simulated roof extensometer
displacements. As the stresses were increased the roof extensometer displacements also
increased, but the height of softening did not extend further into the roof. By the final stage, all
the roof bolts and cables were loaded up to yield.
The model results showed a substantial increase in roadway convergence, primarily due to floor
heave and rib movement, as the stress increases were applied. The additional support had a
relatively minor effect in reducing this convergence.
The roof displacements generated in the model are plotted in Figure 5.18. Despite the high
support/reinforcement density installed, the roof displacements were still large, although they
were much less than those in the floor or ribs.
The (maximum) axial strains generated in the roof bolts and cables are plotted in Figure 5.19.
With the bolts at yield, higher strains imply a greater risk of broken bolts. The additional
support planned to be installed for retreat was effective in reducing the strains generated in roof
and long tendons.
It was found that although the truss/sling was tensioned to 100 kN when installed, the tension in
this support element actually reduced as the model was run and the stresses increased. This was
due to the separation between the end-points of the truss (where it was anchored to the cables)
reducing as the stresses were increased and the roadway profile reduced.
Final model runs were conducted with the roof bolts and/or long tendons deliberately failed.
With this done the roof displacements (which had stabilised) increased rapidly, Figure 5.20.

43

With no additional support installed and all the original bolts and cables failed, the roof
displacements continued to increase with no sign of stabilising; this effectively indicates the
roof falling out. With additional support installed and the original bolts and cables failed, the
displacements stabilised. With the additional vertical cables failed but the truss system left
intact, the roof again stabilised although after a larger amount of movement. In this instance it
was the truss system providing support; in doing so the tension in it had increased again
although it remained well below yield, the loads in the angled tendons to which the truss was
attached did reach yield.
5.3.4

Conclusions from modelling face retreat effects on support system

As the stresses were increased to simulate the effects of face retreat, the model results
showed large deformations, particularly in the ribs and floor resulting in severe
convergence of the gate.
The roof displacements generated in the model also increased substantially, but the
height of softening remained below the height of the long tendons.
The increasing roof displacements generated increasing strains in the roof and long
tendons, increasing the risk of tendon failure. The additional support planned to be
installed prior to face retreat reduced the strains developed in the roof bolts and long
tendons.
With the rest of the support system failed, the truss system was effective in stabilising
the roof although it allowed substantial displacements before doing so. The loads within
the truss remained below yield, although those in the angled long tendons to which the
truss was attached did reach yield.
5.4

CONCLUSIONS ON MODELLING FLEXIBLE LONG TENDONS

The work described in this Chapter has shown that a method has been developed for modelling
and comparing the behaviour of tensioned and untensioned flexible long tendon reinforcement
when used as part of a coal mine support system in realistic geological and geotechnical
conditions. The method developed simulated the process of tendon installation and tensioning
so as to ensure that the tension was retained in the tendon following grout encapsulation. The
modelling code used was FLAC3D which allowed reinforcement row spacing to be included in
the analysis. The work was extended to examine the effectiveness and applicability of tensioned
cable truss systems.
For the particular examples modelled, both hypothetical and real, no benefit was seen from
applying pre-tension to the flexible tendons. Indeed, the effect of pre-tensioning appeared to be
to take the tendons beyond their yield load at an earlier stage in the loading process resulting in
marginally higher roof displacements before stability was established. However the limitations
of the modelling should be noted. In particular the models used could not realistically simulate
loss of shear resistance in the bedded strata due to bed relaxation prior to tendon installation and
so could not simulate any benefit which may be derived from pre-tension in remobilisation of
such shear resistance, a claimed benefit of tensioned tendons. Considerable further work is
required to investigate this claimed benefit through modelling.
The modelling exercise investigated the effect of not achieving full grout encapsulation of a non
tensioned long tendon. In the particular conditions modelled, typical of UK coal mining, full
encapsulation was shown to be critical for achieving stability, as would be expected due to the
major loss of reinforcement stiffness resulting from non encapsulation.

44

It was also found that, in the symmetrical geotechnical conditions modelled, flexible long
tendon reinforcement was more beneficial when biased towards the centre of the roadway. This
may not be the case in asymmetric conditions such as those resulting from a lateral stress
notch or due to geological and structural variations.
The investigations into the applicability of trussing systems employing flexible long tendons
indicated that, where horizontal stresses are relatively high, as found in most UK underground
coal mining situations, any tension applied to the truss was rapidly lost during roof shortening
following installation. Trusses did not supply any useful control or support of the roof until
there had been very high levels of roof failure and roof lowering, at which point they were
capable of acting as a last resort sling support provided the density was sufficient to avoid
failure of the anchoring cables. The cables used for anchoring the trusses would have been much
more effective if used as a reinforcement system towards the centre of the roof span and had
little effectiveness as reinforcement when placed over the ribsides as required for truss
anchorage.

45

46

6 ADVICE AND DRAFTS PROVIDEDTO BS REVISION

COMMITTEE

The need to revise the British Standard for cablebolting consumables (reference 1) was
recognised following the widespread introduction of long tendon designs not covered by the
original standard, in particular, tensioned tendons. Advice and material input to the revision
committee was enabled by an earlier project reported in reference 2, and continued via the
project reported here.
Advice and recommendations were given at the regular monthly meetings of the committee, and
draft test procedures (suggested for inclusion as annexes to the revised Standard) were
submitted when appropriate. A summary of advice given, plus draft test procedures submitted
during the period covered by this project are reported below.
6.1

ADVICE AND RECOMMENDATIONS

6.1.1

Scope of the revised Standard

The existing Standard covers only birdcaged cablebolts of single and double strand
configuration, with corresponding capacities of 300 and 600 kN. Since publication, usage of
long tendons has evolved so that tendons with 300 kN are used only for ribside reinforcement. It
was recommended that this should be formally recognised in the revised Standard, in that the
scope should include roof reinforcement only, and so exclude single strand systems. This would
allow minimum strength criteria to be based on:

the Reflex bolt for resin encapsulated (or non-post grouted) systems, and
the double minicage cablebolt (or similar) for cementitious post grouted systems.

The single strand configuration would continue to be usable for ribside reinforcement, and
would probably be included in a future addition to the Standard BS7861:Part 3 covering
flexible tendons for reinforcement of ribsides. Some initial work on this is described in Chapter
7.
6.1.2

Organisation of the revised Standard

Advice to the revision committee regarding the way the revised Standard would categorise long
tendons was that categorisation should be based on whether or not a system was designed to be
post grouted, i.e. whether grout encapsulation would take place after or during installation of the
long tendon.
Post grouted systems include birdcaged (rarely used now), minicage, and nutcaged cablebolts,
and the Reflex bolt when equipped for post grouting. A cementitious grout would normally be
used, and, as this would require many days to develop full strength, a post grouted system
would not be regarded as providing reinforcement on installation. Post grouted systems could
also be classified as cementitious grouted systems.
Tensionable strands should be regarded as a subset of post grouted systems, since they would
normally be post grouted after tensioning. Again, since the cementitious grout will require many
days to develop full strength, a tensionable system would not be regarded as providing full

47

reinforcement capability upon installation. Since these tensionable systems utilise resin as well
as grout encapsulants, they could also be classified as composite systems.
Non-post grouted systems currently comprise only the Reflex bolt, and only when installed in,
and fully encapsulated with, resin. Since resin takes less than one hour to achieve near-to full
strength, these systems would be regarded as providing full reinforcement upon installation.
Non-post grouted systems could also be classified as resin grouted systems.
6.1.3

Tensionable system issues

It was advised and agreed that performance tests carried out on tensionable systems would be
carried out in the untensioned state, as this was the worst case scenario. This would enable
tests developed for non-tensionable systems to be applied to tensionable ones as well.
A recommendation was given as to an adequate anchorage length for initial installation of a
tensionable system, so that the required tensioning load could be applied safely. The
recommended criterion was that the anchorage length provided at initial installation should be
sufficient to withstand a tensile load of at least the minimum ultimate strength of the tendon.
This anchorage length (in mm) would be equivalent numerically to 3 x the ultimate tendon
strength (in kN). This is based on a requirement to be included in the revised Standard which
specifies that a resin bonded length of 450 mm shall have a minimum system bond strength of
300 kN and a 2:1 in-situ factor of safety (FOS).
6.1.4

Encapsulant properties

It was recommended that encapsulating resin should have the same mechanical performance and
characteristics as those required by BS7861: Part 1: 2007 (reference 4).
Cementitious grout should have mechanical properties, as specified in the existing BS7861: Part
2: 1997 (reference 1), with additional requirements regarding water quality.
6.2

DRAFT TEST PROCEDURES / ANNEXES

Procedures for tests to be carried out on long tendons as part of an acceptance programme, and
suggested for inclusion in the revised Standard, were developed during the project period and
are described below.
6.2.1

Grout encapsulation test bottom up grouting

A series of tests intended to fully encapsulate long tendons from the proximal end upwards
(bottom up) were carried out in the laboratory. The objectives of the tests were to
fully encapsulate commonly used long tendons using the only currently approved grout,
and
establish a standardised method for inclusion as an annex to the revised Standard.
The test programme is described in Chapter 3. The method used was based on that given in the
present Standard, but altered to;
reflect use of new long tendon types
allow new grouts to be included, provided they meet other approval criteria, and
enable encapsulation of the length of strand specified by the supplier for use in the field.

48

The procedure should be applied with a caveat that this must be a system test, i.e. a candidate
long tendon must be tested with the grout and hole size specified by the supplier(s) and the
result, and any approval statement would apply only to that system. A change to the tendon /
hole size / grout combination would require new tests.
The draft procedure is given, in full, in Appendix 1.
6.2.2

Grout encapsulation test top down grouting

A method for grouting from the distal end of a tendon downwards (top down) was developed
from a testing programme, as mentioned in section 6.2.1 above and reported in Chapter 3.
Although the test programme was not fully successful in terms of encapsulation of the
Megastrands tested, the test is regarded as valid for this type of system.
The comments regarding the need for a system test, noted in 6.2.1, also apply here.
The draft procedure is given, in full, in Appendix 2.
6.2.3 Determination of bond strength and system stiffness cementitious grout
anchored system
A test procedure for determination of bond performance of resin encapsulated long tendons was
supplied to the revision committee in the timescale of a previous project (reference 2). A further
procedure, for cementitious grouted systems, has been finalised during the current project, and,
as with the encapsulation tests given above, it is intended that this should be a system test of the
long tendon, hole size and the grout intended for use with it. The test results obtained from it
would apply only to the test combination, and should it be intended to use a different
combination, further tests would be required since the performance of the new combination
would be an unknown quantity.
The pass criteria for this performance test were determined by the revision committee, following
provision of results from a comprehensive series of tests undertaken in the previous HSE
project. The acceptance criteria are as follows:
the minimum system bond strength (load at which the slope of the load / displacement
characteristic falls below 20 kN/mm) shall be 400 kN, and
the minimum system stiffness (slope of the load / displacement characteristic) shall be
95 kN/mm, measured between loads of 150 kN and 300 kN.
The draft test procedure is given, in full, in Appendix 3.
6.2.4

Shear test on tendon / grout system

A test procedure for testing long tendons encapsulated with resin or cementitious grout under
shear load conditions was supplied to the committee during the project period together with
proposed acceptance criteria derived from tests undertaken in the previous HSE project. The
acceptance criteria are as follows:
the mean of three test results should exceed 325 kN for resin encapsulated tendons, and
the mean of three test results should exceed 380 kN for grout encapsulated tendons.
The draft test procedure is given, in full, in Appendix 4.

49

6.2.5

Composite systems

It was recommended that the components of a composite system should meet the requirements
of the tests described in 6.2.3 and 6.2.4 above for the resin and grout encapsulated lengths
respectively.

50

7 LABORATORY TESTING OF ALTERNATIVE RIB


REINFORCEMENT SYSTEMS

The revised Standard for cablebolting materials is not expected to include within its scope,
systems intended for use in reinforcement of the sides of underground roadways (ribsides). But,
very difficult conditions experienced with longwall roadways at colliery A, due to very large
displacements of ribsides, and culminating in a fatality attributed to a fall of ground from ribs,
have highlighted the importance of rib reinforcement. An extensive testing programme has been
conducted on existing and candidate materials for ribside use, over an eleven month period. The
results of this work are expected to provide two major benefits:
optimisation of ribside materials bolts, long tendons and encapsulants for UK coal
mines, thus facilitating a safer working environment, and
provision of key data for inclusion in a possible new section (Part 3) of the British
Standard 7861 specifying ribside consumables.
The analytical objectives of the test programme were to:
compare a range of potential rib tendon systems, it being necessary to compare both
flexible and non flexible systems. Modelling had shown the need for at least 100 kN/m
of encapsulation bond strength to have a significant effect on rib behaviour at
colliery A,
determine whether this could be achieved with polyurethane which was perceived to
have possible advantages in ribside use,
develop a set of tests and possible acceptance criteria for ribs which would be different
to those for roof in particular, residual load after 50 mm displacement and
displacement to maximum load, rather than look for high system stiffness and bond
strength, and
determine whether a test could be developed in coal core, and how results in coal
compared with those in sandstone as specified for current and proposed British Standard
tests.
The results of the test programme are summarised below.
7.1

RIB REINFORCEMENT SYSTEMS TESTED

Rib reinforcement in colliery A longwall face roadways has previously been via:

on the cuttable side, FT500 (Weldgrip) solid GRP dowels and FT500 (Weldgrip)
hollow dowels installed using cementitious grout injected through the centre hole.
on the solid side, KT type steel rockbolts and, (where necessary) grout injected FT500
hollow dowels.

Solid KT and FT500 bolts have both been encapsulated with Minova Lokset AT capsule resin.
Other systems have also been used, including Osborn Reflex steel flexible bolts, again with
AT resin.
For this laboratory testing exercise, it was agreed that a comprehensive series of tests would be
carried out with the FT500 dowel and performance of this product would be taken as the
benchmark against which other products/ systems could be assessed. The initial programme of

51

tests set out below in coal/CBG cylinders (except where stated) and comprising 3 tests for each
combination of parameters in each was agreed with colliery A:
Weldgrip FT500 GRP bar / CBG grout at 10MPa confinement (in sandstone)
Weldgrip FT500 GRP bar / CBG grout at 3 confinements (1 MPa, 5 MPa and 10 MPa)
Weldgrip FT500 GRP bar / AT resin (43 mm hole) at 2 confinements to be decided
Weldgrip FT500 GRP bar / AT resin (27 mm hole) at 2 confinements
Weldgrip 28 mm GRP bar / CBG grout at 2 confinements
Weldgrip 28 mm GRP bar / AT resin at 2 confinements
Weldgrip 28 mm GRP bar / PUR resin at 2 confinements
Big (28 mm) steel bolt / CBG grout at 2 confinements
Big (28 mm) steel bolt / AT resin at 2 confinements
KT steel bolt / CBG grout at 2 confinements
KT steel bolt / AT resin at 2 confinements
KT steel bolt / PUR resin at 2 confinements
Osborn Reflex bolt / CBG grout at 2 confinements
Osborn Reflex bolt / AT resin at 2 confinements
Osborn Reflex bolt / PUR resin at 2 confinements
7.2

TEST PROCEDURES

The laboratory short encapsulation pull test (LSEP test) is now a well established tool in
deriving and comparing the performance of reinforcement systems, and is incorporated into the
current British Standard for rockbolting consumables used in coal mines (reference 4). The
method documented in the British Standard uses a homogeneous rock core (sandstone) of
known properties housed in a cell which provides a bi-axial confining pressure. For comparison
purposes, some of the initial tests were conducted in sandstone, but in order to try to determine
more effectively the performance of rib reinforcement systems in the coal seam, it was decided
to manufacture cores with an axially central section composed of coal lumps obtained from
colliery A as described below.
Lumps of coal were machined and glued together to form a piece approximately 200 mm long
and of sufficient diameter to fit inside a cylindrical plastic mould of 145 mm diameter. The coal
piece was set in sufficient CBG grout to form a 145 mm diameter core that was long enough to
fit in a biaxial cell. After sufficient curing time, the grout / coal cores were held in a biaxial cell
on a lathe, under a nominal light load, and a hole was drilled into the coal to a depth of 160 mm,
using a drill bit of appropriate diameter for the bolt size and resin / grout type that were to be
installed in that core. The internal diameters of the drilled holes were measured and, in due
course, the bolts were set in the cores using whichever resin or grout was pertinent to the test.
After an appropriate length of time, at least 24 hours for polyester and polyurethane resins and
14 days for CBG grout, the core assemblies were pull-tested in the biaxial cell. The LSEPT test
requires a confining pressure simulating stresses exerted on reinforcement systems
underground. A nominal 10 MPa is used in the British Standard Test (reference 4). For these
tests in coal it was intended to use a range of pressures simulating the effect of increasing depth
into the rib, from 1 MPa to 10 MPa. It was found however, during the initial testing programme,
that the coal cores could not reliably withstand 10 MPa and it was agreed to carry out tests at
1 MPa and 5 MPa.

52

Bond length is obviously critical to performance and, initially, a length of 320 mm was trialled
in line with that used for assessment of long tendons. However the initial test programme
results, including those from tests in sandstone cores, showed that it would not be possible to
determine the peak and residual load characteristics at this embedment length. Results showed
bond strengths exceeding yield strength of the tendons used. It was decided, therefore, to reduce
the bond length to 160 mm in line with that used for assessment of rock bolts in the British
Standard (reference 4).
7.3

TEST RESULTS AND DISCUSSION

The results of the pull tests on the various bolt types with the different confining pressures and
resin/grout types are best summarised as a series of tables. The mean figures take into account
all available data for tests under a particular set of parameters. This will usually be a mean of 3
tests. A figure in brackets indicates the number of tests averaged if other than 3.
7.3.1

Weldgrip FT500 24 mm GRP bolts

The initial tests were carried out with 320 mm embedment. These are not tabulated below for
reasons previously mentioned (see above). The results of the tests conducted on the Weldgrip
FT500 24 mm GRP bolt at 160 mm embedment are summarised in Tables 7.1 and 7.2, below:
Table 7.1 LSEP test results for Weldgrip FT500 GRP:
160 mm embedment in coal
Grout/resin
type

Test nos.

Confining
pressure
(MPa)

Mean
bond
strength
(kN)

Mean
system
stiffness
(kN/mm
between
40-80kN)

Mean
maximum
load (MPa)

Mean residual
load (kN) at
50mm
displacement

AT

1, 2, 3

96.7

70.3

116.2

32.7 (2)

AT

4, 5, 6

51.9

n/a

58.8

22

CBG

8, 16, 17

76.2

41.2 (1)

79.0

9.5

CBG

7, 18, 19

106.9

110.8

113.0

19.9

CBG

20

10

138.2 (1)

153.8 (1)

144.9 (1)

n/a

PUR

15P, 16P, 17P

24.1

n/a

25.0

9.1

PUR

18P, 19P

14.3(2)

n/a

15.2(1)

3.9

In AT resin, the pull tests were characterised by multiple failures where the load built up and
was then rapidly released as stick/slip behaviour. Higher performance parameters were achieved
at the higher confining pressure and the consistency between the tests under each confining
pressure was good. All samples failed at the coal / resin interface.

53

Table 7.2 LSEP test results for Weldgrip FT500 GRP:


160 mm embedment in sandstone
Grout/resin
type

Test nos.

Confining
pressure
(MPa)

Mean
bond
strength
(kN)

Mean
system
stiffness
(kN/mm
between
40-80kN)

Mean
maximum
load (MPa)

Mean residual
load (kN) at
50mm
displacement

CBG

13, 14, 15

10

138.8

149.5

139.8

23

In CBG grout the consistency between tests under similar conditions was also good. Again, the
higher the confining pressure, the higher the performance parameters. Test No.20 was
conducted at 10 MPa confining pressure, but the core sample fractured during the test. The tests
were generally characterised by stick / slip behaviour. All samples failed at the bolt / grout
interface although sample No.8 also failed at the coal/grout interface. The CBG tests in coal
produced higher mean bond strengths, mean maximum loads and mean bond stiffnesses than the
equivalent tests in AT resin, but lower residual loads.
Three CBG tests carried out in sandstone at 10 MPa confining pressure showed similar results.
The tests were characterised by stick / slip behaviour and all failed at the bolt / grout interface.
Interestingly the mean performance parameters for these tests were similar to those achieved in
coal at 10 MPa confinement (Test 20).
The tests carried out in PUR resin gave significantly lower performance parameters than those
in AT resin and CBG grout. After achieving maximum load at a similar displacement to the
other tests, the loads rapidly levelled to values similar to the residual loads. Tests carried out at
1 MPa confining pressure showed markedly lower results than those at 5 MPa. All failed at the
coal/resin interface, although sample No. 19P also failed partially at the bolt / resin interface.
7.3.2

Weldgrip 28 mm GRP bolts

The results of the tests conducted on the Weldgrip 28 mm GRP bolt are summarised in Table
7.3, below.
In AT resin at 5 MPa confining pressure, the tests were characterised by a rapid increase to
maximum or near maximum load. This was followed by stick / slip behaviour, each slip being
followed by a steady increase in load before the next slip. Successive peak loads were lower
than the previous peak and all three tests showed broadly similar results. All samples failed at
the coal / resin interface.
In AT resin at 1 MPa confining pressure, after an initial increase in load, bolt load was
maintained or developed steadily for 15-25 mm of displacement. Abrupt failures did not occur
on 2 of the tests until peak load had been well exceeded and one test did not show any sudden
failure at all. All samples failed at the coal / resin interface. Again all mean performance
parameters were higher for 5 MPa confinement than for 1 MPa confinement.

54

Table 7.3 LSEP test results for Weldgrip 28 mm GRP:


160 mm embedment in coal
Grout/resin
type

Test nos.

Confining
pressure
(MPa)

Mean
bond
strength
(kN)

Mean
system
stiffness
(kN/mm
between
40-80kN)

Mean
maximum
load (MPa)

Mean residual
load (kN) at
50mm
displacement

AT

24, 25, 26

136.5

103.2

190.6

68

AT

44, 45, 46

41.8

8.13 (1)

81.3

39.5 (2)

CBG

9, 9A, 10, 11

143.8

134.9 (3)

266.3

16.7 (2)

CBG

12, 13, 14

68.8

14.9

89.3

17.2

PUR

27, 28, 29

13.7

n/a

15.4

6.4

PUR

30 ,31

12.1 (2)

n/a

13.4 (2)

n/a

In CBG grout at 5 MPa confining pressure, the tests were characterised by extreme stick / slip
behaviour with rapid increase in load to a high maximum followed by alternate cycles of rapid
failure and increase in load, often to near maximum. The tests were concluded with a rapid
decline in loading to a low residual load. Two samples failed at the grout / coal interface and
two failed at the bolt / grout interface. The general behaviour in these tests was extremely
unusual and could warrant repeat testing to examine whether it is truly representative. The
unusual graphs may have been generated by a combination of high stress build up in the flexible
bolt followed by sudden release leading to shock loading of the pressure transducer and rebound
of the displacement transducer during the extreme stick / slip behaviour.
In CBG grout at 1 MPa confining pressure, again there was a rapid increase in load with little
displacement after which minor stick / slip behaviour occurred. In two of the tests, loading
gradually increased after these failures and maximum load was achieved after 27 mm and
37 mm displacement, respectively. The loading rapidly decreased to residual level after
maximum load was achieved. All samples failed at the bolt / grout interface. Again the
performance parameters at 5 MPa were higher than those at 1 MPa. Also, as for the FT500 GRP
bolts, the CBG tests produced higher bond strength, maximum load and system stiffness results
than the AT resin, but significantly lower residual strengths.
In PUR resin, at both confining pressures, a low maximum loading was rapidly achieved and the
loads then gradually decreased to residual level. All samples failed at the coal / resin interface.
7.3.3

28 mm steel big bolts

The results of the tests conducted on the 28 mm steel bolt are summarised in Table 7.4, below.
In AT resin at 5 MPa confining pressure, loading rapidly increased with very low bolt
displacement followed by a gradual increase in displacement as maximum load was reached.
Test Nos. 42 and 43 gave very similar results in that after maximum load was passed there was

55

stick / slip behaviour as mean loading decreased with bolt displacement to a consistent residual
load. Test No. 41 followed a similar shaped loading curve to a much higher maximum load, but
with only one significant sudden failure after maximum load was passed. This test failed at the
bolt / resin interface, whilst the other two failed at the coal / resin interface.
Table 7.4 LSEP test results for 28 mm steel:
160 mm embedment in coal
Grout/resin
type

Test nos.

Confining
pressure
(MPa)

Mean
bond
strength
(kN)

Mean
system
stiffness
(kN/mm
between
40-80kN)

Mean
maximum
load (MPa)

Mean residual
load (kN) at
50mm
displacement

AT

41, 42, 43

164.2

451.1

199.8

49.7

AT

38, 39, 40

55.9

5.8 (2)

75.4

43.6

CBG

47, 48, 49

194.3

622.2

196.1

41.1

CBG

50, 51, 52

67.9

50.1 (2)

78.6

45.9

In AT resin at 1 MPa confining pressure the three tests showed similar load / displacement
graphs. A rapid initial increase in load with very low displacement was followed by a gradual
climb to maximum load with several minor failures after which the loading gradually decreased
to a steady residual load. All tests failed at the coal / resin interface.
As with the GRP tests, all performance parameters were lower at the lower confinement
although residual load was only a little lower.
In CBG grout at 5 MPa confining pressure, loading increased with very low bolt displacement
and a high maximum load was rapidly achieved. Thereafter, the load decreased rapidly with
displacement. All three tests had a similar residual load. Test No. 47 had a lower maximum load
than the other two and failed at the bolt / grout interface. The other two tests failed at the
coal / grout interface.
In CBG grout at 1 MPa confining pressure, the initial load increased to an initial failure. After
that, the load increased slowly to a maximum before a gradual reduction to a consistent residual
loading. All three tests failed at the coal / grout interface.
In contrast to the other tests commented upon so far, the mean residual load achieved at 1 MPa
confinement was a little higher than that at 5 MPa. The other mean performance parameters
were lower at 1 MPa than at 5 MPa confinement. Comparison of the results of the tests on Big
steel bolts with those on GRP bolts shows similarity in that mean bond strengths and system
stiffnesses were greater for CBG than for AT resin at each confinement, but a difference in that
the mean maximum loads and residual loads were similar for the CBG and AT for each
confinement.

56

7.3.4

KT 22 mm steel bolts

The results of the tests conducted on the KT 22 mm steel bolt are summarised in Table 7.5,
below:
Table 7.5 LSEP test results for KT 22 mm steel:
160 mm embedment in coal
Grout/resin
type

Test nos.

Confining
pressure
(MPa)

Mean
bond
strength
(kN)

Mean
system
stiffness
(kN/mm
between
40-80kN)

Mean
maximum
load (MPa)

Mean residual
load (kN) at
50mm
displacement

AT

32, 33, 34

110.9

165.2

115.5

32.7

AT

35, 36, 37

54.2

n/a

64.7

34.7

CBG

66, 67

153.6 (2)

533.9 (2)

153.6 (2)

26.5 (2)

CBG

68, 69

97.6 (2)

259.5 (2)

97.6 (2)

34.5 (2)

PUR

71, 75, 76

93.7

1454.6
(2)

94.7

37

PUR

72, 77, 78

85.4

90.91 (1)

85.8

21.7

In AT resin at 5 MPa confining pressure, all three tests showed a rapidly increasing load to a
maximum. After maximum load was achieved, mean bond load gradually reduced with
displacement often accompanied by moderate stick / slip behaviour to a consistent residual load.
All three samples failed at the coal / resin interface.
In AT resin at 1 MPa confining pressure, loading increased rapidly initially. In two tests, the
maximum load occurred at a considerable displacement beyond the bond strength determination
point. After maximum load, all three samples gradually declined to a similar residual load.
In CBG grout at 5 MPa confining pressure, maximum load was achieved very quickly. There
was no significant stick / slip behaviour and both load / displacement graphs have a high degree
of similarity.
In CBG grout at 1 MPa confining pressure maximum load was achieved very quickly. One test
maintained a high consistent load resulting in a high residual load, whilst in test No.69 the
loading reduced rapidly to a much lower residual load.
Similarly to the Big steel bolts and again in contrast to the GRP bolts, the mean residual loads
achieved at 1 MPa confinement for both CBG and AT resin were higher than those achieved at
5 MPa confinement. Other performance parameters were higher at 5 MPa than at 1 MPa
confinement. The general trend of performance parameters between CBG and AT resin for the
KT bolts is similar to that found for the GRP bolts in that mean bond strengths, maximum loads
and system stiffnesses were greater for CBG at each confinement but mean residual loads were
lower.

57

Problems were experienced in mixing the components of the PUR resin in some earlier tests
with KT bolts and the results of these tests have been discounted. On pulling the bolts, it was
seen that some of the resin had not set properly. Further investigations indicated that, whichever
component of the PUR capsule was poured first, the components always settled into two layers
of immiscible fluid and rotating the bolts in the hole in the sample cores was not sufficient to
mix them properly. Therefore, an alternative approach to mixing was adopted whereby the
components from the PUR capsules were extracted, separately weighed and then mixed in the
correct proportions and poured into the hole and the bolt installed before gelling had taken
place.
In these (reported) tests for PUR resin at 5 MPa confining pressure, maximum load (and bond
strength) with high system stiffness was achieved rapidly. After maximum load, the loading
dropped but relatively high residual load was achieved. Results of tests for PUR resin at 1 MPa
confining pressure were very similar in shape to those conducted at 5 MPa, but with lower mean
performance indicators.
These results with PUR are significantly better than those achieved in earlier reported tests on
GRP bolts and the performance parameters are much closer to those achieved with CBG and AT
resin than was the case for the GRP bolt tests. In fact some of the performance parameters
achieved for PUR were better than those achieved in the equivalent tests with CBG and AT
resin. This suggests that comparable results may be achievable with PUR provided the
components can be properly mixed on site in the correct proportions. It also suggests that
retesting of PUR with GRP bolts may be warranted.
7.3.5

Reflex flexible steel bolts

The results of the tests conducted on the Reflex flexible steel bolt are summarised in Table 7.6,
below:
Table 7.6 LSEP test results for Reflex flexible steel:
160 mm embedment in coal
Grout/resin
type

Test nos.

Confining
pressure
(MPa)

Mean
bond
strength
(kN)

Mean
system
stiffness
(kN/mm
between
40-80kN)

Mean
maximum
load (MPa)

Mean residual
load (kN) at
50mm
displacement

AT

56, 57, 59

83.0

65.2

99.9

55.9

AT

60, 61, 62

53.2

n/a

60.6

25.5

CBG

1, 2, 3

81.4

70.8 (2)

119.1

65.0 (2)

CBG

53, 54, 55

44.4

n/a

64.5

22.2

PUR

73, 79, 80

85.5

366.7 (2)

96.6

55.9

PUR

74, 81, 82

51.0

n/a

54.3

33.2

58

The shapes of the load displacement curves for AT resin at 5 MPa confinement were similar to
those achieved with steel bolts, particularly the KT bolt, with steep initial profiles followed by a
plateau of variable length with gradual load shedding to a relatively high residual load. During
load shedding two bolts displayed moderate stick / slip behaviour and one did not, this one
achieving a significantly higher residual load than the others.
Again, for 1 MPa confinement, the shapes were similar to steel bolts at the same confinement
with good consistency between residual loads and only minor stick / slip behaviour. All
performance parameters were lower at 1 MPa than at 5 MPa confinement.
For CBG embedment at 5 MPa, the load displacement curves obtained were significantly
different to those for steel bolts. Rather than a high peak load being achieved at very low
displacement with rapid load shedding, load development was more gradual and a relatively
long load plateau was achieved before bond failure and the onset of stick / slip behaviour. Mean
performance parameters for Reflex bolts in CBG grout at 5 MPa confinement, were lower than
for all other steel bolts, except for residual load which was higher than for all other steel bolts in
CBG at 5 MPa confinement.
At 1 MPa confinement, the curves were more similar in shape to those obtained with other steel
bolts in CBG grout, with relatively low bond strengths and peak loads but gradual load shedding
with increased displacement.
For both CBG and AT resin, all performance parameters, including residual strengths, were
lower at 1 MPa confinement than those achieved at 5 MPa confinement.
The shapes of the curves for two of the PUR embedded Reflex bolts at 5 MPa were very similar
to the shapes of the curves for KT bolts but with some post failure stick / slip. One curve
showed different behaviour with a long gradually rising curve, following initial steep load
development, with peak load occurring at between 30 and 35 mm displacement.
The performance parameters for PUR at 5 MPa confinement were of a similar order or better
than those obtained with CBG and AT resin.
In contrast the curves for PUR embedded Reflex bolts at 1 MPa confinement were a little
different to those obtained for the KT steel bolt. The bond strengths and peak loads were
considerably lower but the curves had well developed post yield plateau and reached
comparable or better residual loads. As for 5 MPa confinement, the performance parameters for
PUR at 1 MPa confinement were of a similar order to those obtained with CBG and AT resin.
7.3.6

Discussion of residual loads

One of the most important performance parameters for coal rib reinforcement is probably the
residual load achieved, as relatively large displacements of coal rib can be expected, particularly
at colliery A. For this series of tests, this parameter was quantified at a displacement of 50 mm.
Figure 7.1 shows a graph of the mean residual loads at 50 mm displacement plotted for each
bolt type, embedment material and confinement.
It can be seen that, at low confinements, as are likely to be encountered in the yielded rib up to a
depth of several metres at colliery A, for GRP bolts the AT resin gave considerably higher
residual loads than the other embedment materials, CBG grout gave 40-45% of the AT resin
residual loads and PUR gave very low residual loads. The bigger diameter bolts gave the higher
residual loads.

59

For higher confinements (5 MPa) with GRP bolts, as are likely to be encountered deeper into
the yielded coal, the residual loads were generally higher and, again, the AT resin gave higher
residual loads than the CBG grout with poor results for the PUR.
For the steel bolts, the differences in the residual loads achieved between embedment materials
and confinements were much less marked and they were generally higher than for the equivalent
size GRP bolt in the same embedment material with the exception of the large diameter GRP
bolt in AT resin.
The residual loads achieved by the Reflex bolts were somewhat lower than for the 22 mm KT
steel bolts at 1 MPa confinement but considerably better at 5 MPa confinement. Again the
embedment material was much less influential and high residual loads were achieved with the
PUR resin
7.3.7 Discussion of maximum loads
Figure 7.2 shows a graph of the mean maximum loads achieved with the different tendons, in
the various grouts and at the two confining pressures with respect to increasing (nominal, i.e.
bit) hole size. Increasing hole size means, of course, increasing bolt diameter except in the case
of the use of CBG grout. In these cases all holes were drilled with a 43mm bit as the installation
of CBG grouted tendons requires an additional grout tube in the hole. The unreliable results
with PU grout and GRP bolts have been omitted from the analysis.
The graph shows that, at 1MPa confining pressure, there is little difference in the mean
maximum loads achieved, irrespective of bolt type, grout type or hole size. The maximum loads
for all five bolt types are only marginally higher in the 43mm diameter hole. At 5MPa
confining pressure, however, the higher maximum loads are readily discernible. Both the 28mm
steel bolt and the 28mm GRP bolt achieved higher maximum loads, over twice, at 5MPa
confining pressure than at 1MPa confining pressure. The KT bolt recorded a higher maximum
load in CBG grout (and therefore the largest diameter hole) than in other hole sizes, but
otherwise the KT bolt, the Reflex bolt and the FT500 GRP bolt did not show much variation in
maximum load with increasing hole size. Higher mean maximum loads were achieved with
larger diameter bolts in larger diameter holes.
7.4 CONCLUSIONS AND RECOMMENDATIONS
The earlier performed tests with PUR capsule resin and GRP bolts gave relatively poor results.
Later tests with steel bolts, where the resin components were carefully weighed and mixed to
the manufacturers recommended proportions by weight outside the hole, gave much improved
results. This may warrant repetition of the PUR tests with GRP bolts.
However, the experience of mixing capsule PUR in the laboratory indicated that it was likely to
be problematic to achieve satisfactory mixing underground. The fact that the proportion of
components, vigour of mixing, application of confinement and exclusion of water were all
critical to the good results achieved with PUR and steel bolts mitigates against PUR being a
practical reinforcement encapsulant. The presence of water causes the material to foam with
consequently very poor reinforcement performance. Loss of relatively small amounts of either
one of the components appears to result in failure of the PUR to gel properly and absence of
confinement, even without the presence of water, was found to result in foaming on some
occasions.
Generally the GRP bolts produced significantly more pronounced post failure stick / slip
behaviour than the steel bolts. It is not clear whether this is an undesirable behaviour.

60

GRP bolts generally achieved lower or similar residual loads and other performance parameters
when compared with the equivalent steel bolts, encapsulant and confinement, a significant
exception being the 28 mm GRP bolt in AT resin at 5 MPa confinement. As GRP bolts are
known to be very weak in bending, it is recommended that steel bolts are used for rib
reinforcement wherever possible.
Where GRP bolts are used then encapsulation in AT resin is to be preferred, where this can be
achieved to good standards and installation is at the face of the heading. Elsewhere, loss of AT
resin into rib breaks may mean that good installation with this encapsulant is not possible.
However, the achievement of better than 10 tonnes residual load per metre of encapsulation (as
indicated necessary by previous modelling) for the 28 mm GRP bolts with CBG grout at both
confinements, indicates that they can provide significant reinforcement to the coal ribs at
colliery A. This was only achieved by the 24 mm GRP bolts at the higher confinement. It should
be noted however that the CBG grout was tested after 14 days compared with 1 day for the AT
resin. The reinforcement provided by CBG will be highly time dependent over the first 14 days.
The Reflex bolt performance was mixed when compared with the equivalent diameter solid
steel bolt, with some performance parameters being better and some worse. Its residual loads
were worse at lower confinement and better at higher confinement. However in relation to the
28 mm Big steel bolts, the Reflex bolt performed generally less well on most measures, though
residual loads at 5 MPa confinement were still a little higher. On balance, as Reflex bolts have
lower elongation to failure than steel bolts and are more problematic to install, it would seem
advisable to use Big steel bolts in the ribside where practicable.
The similar performances achieved by both steel bolts and Reflex bolts in different encapsulants
indicates that whichever encapsulant is likely to produce the best quality embedment from a
practical viewpoint is to be preferred. The low rate of strength development with time achieved
by CBG should also be considered. All tests with CBG grout were undertaken in 43 mm
diameter holes in order to provide sufficient annulus for a grout tube.
This work confirms that AT resin is suitable for application at the face of the heading where
immediate reinforcement is required and that CBG is more likely to be appropriate for
application outbye as remedial or secondary support where the lower rate of strength increase
can be accommodated by additional temporary support measures where necessary and loss of
AT resin into breaks during installation is likely to be more severe.

61

62

8 SUGGESTED REVISION OF DMCIAC CABLEBOLTING


GUIDANCE DOCUMENT
8.1

INTRODUCTION

Guidance on the use of cablebolts in coal mine roadways was issued by HM Inspectorate in
1996 (reference 5). Since then, as has been amply illustrated earlier in this document,
cablebolting technology and methodology has moved on, for example with respect to long
tendon system design, and use of pretensioning.
A comprehensive revision of the DMCIAC document has been drafted under this Project
incorporating latest practices and systems. The draft revised guidance includes installation of
long tendons in ribsides as well as roof, but does not include flexible bolts which, although
included in the revision of the British Standard for cablebolting materials, are the subject of
separate DMCIAC guidance on use.
The revised guidance document is intended for introduction following official adoption of the
revised BS7861 Part2 currently being prepared.
A full text of the suggested revision of the guidance document is given below.
8.2

SUGGESTED REVISION OF DMCIAC CABLEBOLTING GUIDANCE

Guidance on the use of cablebolts to support roadways in coal mines


Introduction
1 The introduction of new designs of cablebolt, largely replacing previously used birdcaged
types, has prompted a review of the guidance on use of cablebolts to support roadways in coal
mines originally published in 1996. This revised guidance is appropriate to current use of
cablebolts, and includes a section on use of tensionable tendons which are now being used in
some roadways, and which require particular attention in use, especially with regard to grouting
using thixotropic grouts.
Application
2 This guidance applies to situations where cablebolts are installed as additional support when
excessive strata movement is experienced or expected in places principally supported by
rockbolts.
3 Operational necessity usually requires that cablebolts are installed outbye of the face, often
weeks or months after roadway excavation. Recent developments in cablebolt design, however,
have allowed installation at or near the face. Even in these circumstances, the cablebolts must be
regarded as additional support, since they cannot achieve optimum performance immediately.
Definitions
4 The following definitions apply throughout this guidance:

Cablebolt: a flexible tendon comprising one or more steel strands, or a group of steel wires,

installed using a pumped fully encapsulating grout, to provide reinforcement of a mine roadway

roof or side. For the purposes of this document a flexible bolt is not a cablebolt as it is installed

63

in a single operation through encapsulating resin capsules and provides immediate


reinforcement in a similar manner to a rockbolt. Flexible bolts are covered by a separate
supplementary document to the guidance on use of rockbolts to support roadways in coal mines
(NB definition of flexible bolt in flexible bolt guidance needs revising to bring into line)
Tensionable cablebolt: a cablebolt, as above, designed to be installed with a short upper
anchorage with rapid strength development so that a tensioning load can be applied prior to full
encapsulation with a pumped grout.
Rockbolt: a bar inserted into the roof or side of a roadway which is used in conjunction with
fully encapsulating resin or some other appropriate substance to provide reinforcement of the
roof and sides of a roadway or working place in a mine.
Rockbolted heading/roadway: a heading/roadway in which rockbolts provide the principal
means of support.
Site Investigation and cablebolting scheme design
5 The Approved Code of Practice The control of ground movement in mines (reference 1),
hereinafter referred to as ACOP, requires a detailed technical analysis of ground conditions
and the preparation of a design document, where rockbolting or any other support system is
being considered for principal support in coal mines. The ACOP lists the factors to be taken into
account, and the contents of the design document. The work required can be summarised as an
investigation of site conditions and an assessment of geotechnical factors which affect support
system design for that site. The ACOP also requires that the assessment of ground conditions
and design document be reviewed if there is a reason to suspect a material change in the matters
to which they relate. For rockbolted roadways this includes response to the results of the
managers monitoring scheme
6 In accordance with the ACOP, the manager would carry out these functions, if suitably
qualified, or appoint a competent person or persons to carry out these and other functions
defined by this guidance document.
7 Where the site investigation, geotechnical assessment and/or monitoring indicate that the
strata require the use of cablebolts, a support design needs to be prepared. Where an existing
design has already been proven, reference to it may be made for other roadways of similar
dimensions, in the same seam, provided that suitable and sufficient steps are taken to show that
the geological conditions, rock properties, stress fields and monitoring results at both sites are
substantially similar.
8 Where cablebolts are to form part of the systematic support, the initial design of the
cablebolting system should be prepared on the basis of the results of the site investigation. As a
minimum, the design needs to take account of the following:
the profile of the heading;
the length and type of cablebolts and any associated equipment to be used in the roof
and ribs;
the density and pattern of cablebolts in the roof;
the distance of installation from the face of the heading.
9 When the initial design has been completed, documentation needs to be prepared detailing:

. the use of the roadway/junction;

. the free-standing supplementary support if applicable;

64

the layout and dimensions of the cablebolting pattern;


the specification of cablebolting materials to be used;
the method of work;
the design verification monitoring system.

10 The design documentation will be incorporated into the Design Document for rockbolted
support required by the ACOP.
11 Where cablebolts are used as a remedial support system, in response to monitoring or where
previous experience has shown that roof movement is occurring or likely to occur above the
rockbolted height, their length, position and density should be determined by the mine manager
or a competent person and incorporated into a revised design document. The design should take
into account location, mechanism and degree of roof movement.
Cablebolt specification
12 Cablebolts used in coal mines for reinforcement of the roof must comply with the
requirements of the British Standard for strata reinforcement support system components, part
two, (ref 2).
13 Cablebolts used in coal mines for reinforcement of the roof should normally have a
minimum length of 8 m when used in roadways less than 5 m wide, and 10 m when used in
other applications, unless monitoring and geotechnical information indicates otherwise.
14 Holes drilled for cablebolts will be formed in such a way as to optimise system bond
strength. Suppliers will advise on the most suitable hole diameter and drill bits to be used.
15 Cablebolts will not be considered fit for purpose unless and until full column grouted.
16 Where cementitious grouts are used, the supplier will specify the water to solids ratio of the
mixed grout. The mine manager or competent person should ensure that means are available at
the workplace to allow accurate measurement of water volume, and that operators understand
the importance of ensuring that the correct water to solids ratio is used, and that watering
down of the grout is not acceptable.
17 The mine manager or competent person should put in place a sampling procedure to monitor
the properties of the mixed grout, and should specify sampling frequency. See Appendix 1.
Failure to achieve the required properties may necessitate additional cablebolts being installed.
18 Where possible, sufficient grout to fully encapsulate a cablebolt installation should be mixed
in one operation.
19 Where thixotropic grouts are used, grouting must be carried out in one continuous operation,
and care should be taken to ensure sufficient grout is mixed to allow this. Experience shows that
thixotropic grouts can be difficult to place, and the greatest vigilance is required to ensure that
the required grout properties are achieved.
20 All cablebolts installed in the roof should be installed as near to vertical as is practicable,
unless the design specifies otherwise.
21 All cablebolts shall be fitted with an end termination capable of transferring load to the
surrounding rock surface, unless they are to be connected to other cablebolts. End fittings, and

65

couplings used for cable connection, must comply with the requirements of the British Standard
for strata reinforcement support system components, part two, (ref 2).
Tensionable Cablebolts
22 Tensionable cablebolts are installed using an initial point anchorage with rapid strength
development to allow a tensioning load to be applied. A tensioning load is applied using a
tensioning jack or other means of tensioning approved by the tendon supplier, prior to full grout
encapsulation of the remaining cable length. The cable supplier shall provide technical data on
suitable tensioning equipment, safe tensioning procedures, and the maximum tensioning load
which may safely be applied.
23 Tensionable cablebolts used in coal mines for reinforcement of the roof must comply with
requirements of the British Standard for strata reinforcement support system components, part
two, (ref 2).
24 Tensionable cables will normally be installed via a machine which will thrust the cable to the
back of the hole through an encapsulating material such as resin. Particular care should be taken
to ensure that the correct hole depth is drilled in order that
a) the required encapsulation length is achieved, and
b) the proximal end of the cable is properly located to allow safe and efficient
tensioning.
25 Where encapsulated resin is used for the initial point anchorage of a tensionable cablebolt
used for reinforcement of the roof, this must comply with the performance requirements
specified in the British Standard for strata reinforcement support system components, part two,
(ref 2). The gel and setting times should be appropriate to the installation time required for the
cablebolt used.
26 Resin capsule requirement should be determined from a calculation of the safe cablebolt

encapsulation length. .The bond length requirement is given by the formula:

Minimum bond length (mm) = numerical equivalent of [3 x cable ultimate tensile strength (kN)]

27 Tensionable cables should be fully grouted as soon as possible after installation, and within a
maximum period of 24 hours.
Monitoring
28 The ACOP makes reference to the necessity for a monitoring scheme based on a
comprehensive system of instrumentation and trend analysis, where rockbolts are used as
principal support. Where cablebolts are to be installed systematically as part of the principal
rockbolting support system, the manager or competent person should prepare a monitoring
scheme which takes account of this. Where cablebolts are to be installed as remedial support, an
addendum to the scheme will be required.
29 The scheme or addendum should set out the managers requirements for:
the procedures for the auditing of routine monitoring devices where cablebolts
form part of the support system;
the equipment to be used;
the duties of individuals;
plans, schedules and reports;

66

the maximum levels of movement allowable on the monitoring devices before action is
required;
the action to be taken and the person responsible for taking the action.
30 The scheme or addendum needs to recognise:
the need to monitor and report physical changes affecting the security of the support
system;
the need to take remedial measures.
Routine monitoring devices
31 Cablebolt dual height tell-tales are normally used for the routine monitoring of the roofs of
roadways where cablebolts form part of the support system. Where cablebolts are to be installed
systematically, and close to the face, it may be appropriate to combine rockbolt and cablebolt
tell-tales using triple height units as described in the guidance for use of flexible bolts document
(ref 3). The construction, installation procedures and method of reading of cablebolt tell-tales
are shown in Appendices 2 and 3 below.
32 Tell-tales need to be installed:
to at least the height of the cablebolt length + 1 m;
at intervals not greater than 20 metres;
as near vertical as practicable and sited as close to the centre of the roadway, and
as soon after cablebolting as practicable, or as directed by a competent person.
33 Tell-tales can also be set at increased frequencies by persons working on site or through
supervisory or managerial instruction.
34 All other arrangements for monitoring should be the same as for rockbolts. Alternative
arrangements for monitoring roadway sides reinforced by cable bolts may be appropriate.
Training (See Appendix 4)
35 All personnel involved with the installation of cablebolts should have received appropriate
operational and safety training, and be duly authorised.
36 Management and officials/supervisors should have general training on the action of
cablebolts, correct installation techniques, monitoring arrangements and testing procedures.
They should be aware of the need for routine grout sampling, and the need to implement and
maintain such a procedure. Maintenance of drilling and mixing/pumping equipment is of great
importance and training to appropriate personnel must be given.
37 Operators should receive training to ensure that they are competent in the use of the
machinery and materials to be used and the procedures to be followed when installing
cablebolts. Emphasis needs to be given to maintaining satisfactory standards at all times,
particularly with regard to correct grout mixing and full column encapsulation.
Cablebolting materials
38 All cablebolting reinforcement materials forming part of the roadway support system must
be suitable for the purpose for which they are to be used.
39 A material intended for cablebolt roof reinforcement shall be regarded as suitable if:

67

a) it has previously received an acceptance number under the British Coal Corporations
procedures for the Acceptance of Strata Reinforcement Materials and Equipment
between 1 April 1992 and 30 June 1995; or
b) it can be shown, by means of independently conducted and assessed type testing, to
meet the criteria set out in the British Standard for strata reinforcement support system
components used in coal mines, Part 2 (ref 2).
40 A material intended for cablebolt reinforcement of the side of a roadway shall be regarded as
suitable if:
a) it has previously received an acceptance number under the British Coal Corporations
procedures for the Acceptance of Strata Reinforcement Materials and Equipment
between 1 April 1992 and 30 June 1995; or
b) it can be shown, by means of independently conducted and assessed type testing, to
meet the criteria set out in the British Standard for strata reinforcement support system
components used in coal mines, Part 2 (ref 2) or,
c) if it does not meet the above criteria, it is:
i) subjected to an independently conducted and assessed laboratory test
programme, designed to simulate as accurately as possible, conditions of use,
and
ii) independently risk assessed with respect to safety and/or health, with due
regard to conditions of intended use, and
iii) the results of the laboratory test programme and the risk assessment are
found to be satisfactory
41 All material should be subjected to carefully controlled field trial before being accepted for
general use.
Installation equipment
42 Drill rigs, grout mixers, grout pumps, tensioning equipment, and associated cablebolt
installation equipment must be suitable for purpose, and independently assessed in terms of
performance, and safety in use. Where appropriate, testing should be carried out according to
procedures given in the British Standard for strata reinforcement support system components
used in coal mines, Part 2 (ref 2).
43 Equipment suppliers shall provide evidence via documentation of such assessment, full
instructions as to use, maintenance and health and safety, and be prepared to provide training to
operators.
44 Mine management should ensure:
a) where compressed air operated equipment is used, that the compressed air supply is
adequate (with respect to pressure and volume flow rate) for its correct operation and
suitably filtered,
b) that mine water supplies are adequate, and of suitable quality, and
c) that maintenance procedures are in place to ensure that equipment is maintained
correctly and at suitable intervals, in accordance with manufacturers instructions.
References

68

1 Approved code of practice and guidance. The control of ground movement in mines, the
mines (control of ground movement) regulations 1999. HSE Books.
2 British Standard BS7861:rev. Strata reinforcement support system components used in coal
mines. Part 2. Specification for cablebolting. British Standards Institution, 389 Chiswick High
Road, London W4 4AL.
3 Supplementary guidance on the use of flexible bolts in reinforcement systems for coal mines .
Mines04 pdf. HSE website. May 2007.
4 British Standard BS EN ISO 7500-1: 2004 Metallic materials. Verification of static uniaxial
testing machines. Tension/compression testing machines. Verification and calibration of the
force-measuring system. British Standards Institution, 389 Chiswick High Road, London W4
4AL.
5 British Standard BS 6319-2: 1983 Testing of resin compositions for use in construction.
Method for measurement of compressive strength. British Standards Institution, 389 Chiswick
High Road, London W4 4AL.

69

8.3 REVISED CABLEBOLTING GUIDANCE APPENDIX 1


Appendix 1
Sampling and testing of grout mixed underground
Principle
A1.1 Cementitious grout is prepared underground by mixing a known weight of powder with a
specified volume of water in an approved mixing unit. With a cablebolt installed in a pre-drilled
hole, the mixed grout is pumped into the hole to fully encapsulate the cablebolt.
A1.2 It is vital to achieve the correct water to solids ratio if optimum grout strength
development is to be achieved. Experience has shown that, frequently, grout quality is poor due
to over watering, usually because difficulties in grout pumping are encountered. It is very
important therefore that the grout quality is monitored by sampling and testing on a regular
basis according to the Managers sampling procedure.
Preparation of test specimens
A1.3 The samples should be collected in plastic bottles having nominal internal dimensions of
57 mm diameter x 100 mm deep (250 ml capacity).
A1.4 After mixing the grout to the manufacturers instructions, pump a sample into a plastic
bottle of the size specified, sufficient to completely fill the bottle. At least three specimens
should be prepared in this way.
A1.5 The samples should be clearly labelled with the date sampled, name of the mine,
district/heading location, and type of grout.
A1.6 Store the samples upright in a secure place underground for 24 hours.
Testing
A1.7 The manager or an appointed person will decide whether the samples should be tested at
the mine (i.e. weighed for density determination) or sent to a laboratory for density and strength
measurement.
A1.8 Frequency of sampling should be carried out according to the Managers instructions.
A1.9 The grout supplier will provide the following information to allow verification of grout
quality:
a) a chart showing the variation of filled bottle weight with density, and indicating the
range of acceptable weight / density, at 2, 3, 5 and 7 days curing, and
b) a table indicating the acceptable range of density and unconfined compressive strength
at 28 days curing for samples collected in bottles.
Procedure 1 - Testing at the mine (density measurement)
A1.10 Remove the samples from the mine after 24 hours and test as soon as possible.
A1.11 Weigh the bottle, cap and grout (filled to the brim). Check this weight against the chart
provided by the manufacturer. If this comes within the range indicated on the chart, the grout is
being mixed correctly.
A1.12 If the bottle is not completely full of grout, the following procedure should be used:
i)

weigh the bottle, cap and grout, and record the weight.

70

ii)
iii)
iv)

top up the bottle with water, replace the cap and record the weight.
take the difference between the two weights, double it and add to the original
weight of bottle, cap and grout.
consult the manufacturers chart, as in A.1.11 above.

An example calculation is as follows:


Weight of cap, bottle and grout
600 grams
Weight of cap, bottle, grout and water
610 grams
Weight of water
10 grams
Water weight corrected to grout weight =
(10 grams) x 2
20 grams
Corrected weight of full bottle = 600 + 20 =
620 grams
Compare the result with the manufacturers chart as in A.11 above.
Procedure 2 Laboratory testing (density and strength measurement)
A1.13 Samples should be tested after curing for 28 days. Samples received at the laboratory
prior to this time should remain sealed in the bottle and stored at a temperature of 20 deg C +/
1 deg C until required for testing.
A1.14 Remove the bottle from around the sample, and prepare the ends to give a cylinder
90 mm long with parallel faces.
A1.15 Weigh and measure the sample length, and diameter. Calculate and record density (i.e.
weight of sample (gm) / volume of sample (cm3)) to a resolution of 0.1 gm/cm3.
A1.16 Use a testing machine calibrated to BS EN ISO 7500-1:2004 (ref 4) with a suitable
capacity and load rate capability. When spacing blocks are used between the platens and test
specimen, the requirements of BS 6319-2:1983 (ref 5) apply.
A1.17 Wipe clean the bearing surfaces of the testing machine and of any auxiliary platens.
Remove any loose grit or other material from the surfaces of the test specimen that are to be in
contact with the compression platens. Place the test sample on the lower machine platen and
carefully centre. Load should be applied to the prepared parallel faces. Do not use packing at
any of the interfaces between the test specimen, auxiliary platens, spacing blocks and machine.
A1.18 Apply load (without shock) and increase it continuously at a nominal rate of 45
N/mm2/min until no greater load can be sustained. Record the maximum load applied to the
specimen.
A1.19 The uniaxial compressive strength (UCS) of each laboratory sample is calculated as
follows:
UCS (N/mm2) = Maximum load (N) /Original cross sectional area (mm2) - equation 1
Calculate values of UCS to the nearest 0.1 N/mm2.
If the height/diameter ratio (h/d) of the prepared sample is other than 2:1, then a
correction should be applied as indicated below:
o Corrected UCS N/mm2 = UCS (equation 1) / (0.304 x d/h + 0.848)
where d = diameter of the sample (mm)

h = height of the sample (mm)

A1.20 Compare the results with the manufacturers supplied data.

71

8.4 REVISED CABLEBOLTING GUIDANCE APPENDIX 2


Appendix 2
Cablebolt dual height tell-tale
Introduction
A2.1 This device is designed to be installed in vertical holes as soon as practicable following the
installation of long tendon reinforcement, by purpose trained personnel. The general assembly
of a water diverting type, which is designed to reduce corrosion of the tell-tale indicators, is
shown in Figure 8.1.
Installation (water diverting type)
A2.2 Drill hole using recommended bit to 1 m plus above reinforcement height or 6 m,
whichever is the greater.
e.g. 11 m for 10 m cablebolts

6m " 4m "
"

A2.3 Insert top anchor, attached to smallest indicator B to top of hole. Use graduated purposedesigned insertion rods to confirm anchor position. Ensure the water seal sleeves are not pushed
up the hole. Tug wire to seat anchor and check for firm anchorage.
A2.4 Position lower anchor attached to larger indicator A, at 1 m below the top of the
reinforcement height using graduated purpose designed insertion rods, but not beyond.
e.g. 9 m for 10 m cablebolts

3m 4m

A2.5 Ensure the water seal sleeves are fully located to the top of the reference tube.
A2.6 Keeping the suspension cables under tension, the reference tube can now be inserted into
the tell-tale hole. The reference tube should be pushed fully into the hole to ensure that the
stabilising fins locate against the hole mouth.
A2.7 Position indicator A, zero line (top of white band) to be level with bottom of reference
tube. Align to scale. Crimp ferrule in position using crimping pliers.
A2.8 Position indicator B, zero line (top of white band) to be level with bottom of indicator
A. Align to scale. Crimp ferrule in position using crimping pliers.
A2.9 Record details. At all tell-tale sites, a sign must be placed bearing a unique reference code
for reporting and identification purposes giving the type of tell-tale, its position, date and time
of installation, and anchor heights. This information should be passed to relevant officials.
Reading methods
A2.10 By colour

Report whole and part bands visible, for example:

A : white, blue, yellow

B : 3/4 white, blue, yellow

See Figure 8.1

A2.11 By scale

Report measurement, in millimetres, lining up with reference mark for each anchor.

Reference for A is bottom of reference tube.

Reference for B is bottom of indicator A.

72

Scale has millimetre divisions, with centimetre marks.

For example:

A : = 12 mm; B : = 31 mm; total = A + B = 43 mm

Interpretation
A2.12 1.Movement of A relative to its reference (bottom of plastic tube) represents the strata
expansion within the reinforced height.
A2.13 Movement of B relative to its reference (bottom of A represents the strata expansion
above the reinforced height (assuming no movement above top anchor).
A2.14 The total strata expansion is A plus B.
A2.15 Expansion of strata above the top anchor is not detected.

73

8.5 REVISED CABLEBOLTING GUIDANCE APPENDIX 3


Appendix 3
Cablebolt triple height tell-tale
Introduction
A3.1 This device is designed to be installed where cablebolts are installed systematically as part
of the rockbolting support system. It should be installed in vertical holes as close to the face as
possible immediately after grouting of the cablebolts, and by purpose trained personnel. The
general assembly of a water diverting type, which is designed to reduce corrosion of the tell-tale
indicators, is shown in Figure 8.2.
Installation (water diverting type)
A3.2 Drill hole using the recommended drill bit to 1 m plus above longest reinforcement height
or 6 m, whichever is the greater.
e.g. 7 m for 6 m cablebolt

6m 4m

A3.3 Insert top anchor, attached to smallest indicator C to top of hole. Use purpose-designed,
graduated, insertion rods to confirm anchor position. Ensure the water seal sleeves are not
pushed up the hole. Tug wire to seat anchor and check for firm anchorage.
A3.4 Position mid anchor attached to middle indicator B 1m below the top of the longest
reinforcement height using purpose graduated insertion rods, but not beyond. Tug wire to seat
anchor and check for firm anchorage.
A3.5 Position lower anchor attached to thickest indicator A at 0.3 m below the top of the
rockbolts e.g. 2.1 m for 2.4 m rockbolts, 1.5 m for 1.8 m rockbolts using purpose graduated
insertion rods, but not beyond. Tug wire to seat anchor and check for firm anchorage.
A3.6 Ensure the cable guide sleeves are fully located to the top of the reference tube.
A3.7 Keeping the suspension cables under tension, the reference tube can now be inserted into
the tell-tale hole. The reference tube should be pushed fully into the hole to ensure that the
stabilising fins locate against the hole mouth.
A3.8 Position indicator A, zero line (top of green band) to be level with bottom of reference
tube. Align to scale. Crimp ferrule in position using crimping pliers.
A3.9 Position indicator B, zero line (top of green band) to be level with bottom of indicator
A. Align to scale. Crimp ferrule in position using crimping pliers.
A3.10 Position indicator C, zero line (top of green band) to be level with bottom of indicator
B. Align to scale. Crimp ferrule in position using crimping pliers.
A3.11 Record details. At all tell-tale sites, a sign must be placed bearing a unique reference
code for reporting and identification purposes giving the type of tell-tale, its position, date and
time of installation, and anchor heights. This information should be passed to relevant officials.
Reading methods
A3.12 By colour
Report whole and part bands visible, for example:
A : green, yellow, red

74

B : green, yellow, red

C : yellow, red

See Figure 8.2.

A3.13 By scale
Report measurement, in millimetres, lining up with reference mark for each anchor.
Reference for A is bottom of reference tube.
Reference for B is bottom of indicator A.
Reference for C is bottom of indicator B.
Scale has millimetre divisions, with centimetre marks.
For example:
A : = 12 mm
B : = 31 mm
C : = 40 mm
Total = A + B + C = 83 mm
Interpretation
A3.14 Movement of A relative to its reference (bottom of plastic tube) represents the strata
expansion within the rockbolt bolted height.
A3.15 Movement of B relative to its reference (bottom of A) represents strata expansion
within the section of roof reinforced by the cablebolt only.
A3.16 Movement of C relative to its reference (bottom of B) represents
expansion above the reinforced height (assuming no movement above top anchor).
A3.17 The total strata expansion is A plus B plus C.
A3.18 Expansion of strata above the top anchor is not detected.

75

the strata

8.6 REVISED CABLEBOLTING GUIDANCE APPENDIX 4

Appendix 4
Training
A4.1 Training courses must be provided for all personnel involved in or responsible for

decisions as to whether cablebolting is to be carried out, and in implementation and monitoring

of such activity. Content of these courses must include the following topics.

For managers
A4.2 Provide an understanding of the forces present in the rock and the redistribution of these as

a consequence of mining operations.

A4.3 Illustrate the differences between passive support, rockbolting and cablebolting.

A4.4 Explain the action of cablebolts in limiting roof movement and roadway deformation.

A4.5 Highlight the adverse effects of poor installation standards and describe the Managers

grout sampling scheme.

A4.6 Provide an appreciation of monitoring techniques and the information obtained, together

with details of the installation and inspection procedures for the telltale monitoring system and

also the setting of action levels and associated actions.

A4.7 Give guidance on the construction and implementation of the managers Scheme for the

routine monitoring of rockbolted roadways.

A4.8 Give instruction on the inspection of bolted roof and ribs for signs of excessive bolt

loading or deterioration, and the action to be taken if these are discovered.

For rockbolting co-ordinators / engineers


As for managers (above) plus

A4.9 An introduction to rock mechanics principles as applied to cablebolting including such

topics as stress, the strata, design of reinforcement systems, underground engineering,

consumables and several detailed case histories, including site visits where possible.

A4.10 Management of the managers Scheme for the routine monitoring of rockbolted

roadways.

A4.11 Installation, replacement and reading of all routine monitoring devices used at the mine.

A4.12 Familiarisation and use of the appropriate computer software.

A4.13 Setting of appropriate routine monitoring action levels for each area of the mine.

A4.14 Setting of appropriate corresponding remedial action for action levels for each area of the

mine.

A4.15 Determination of appropriate measuring frequencies for routine monitoring devices

within the mine.

A4.16 Follow up on remedial actions to secure stability.

A4.17 Formulation and updating of the Schedule of measurement zones and measuring

frequency and related measuring timetables.

A4.18 Production of tell-tale checklists for officials.

For officials / supervisors


A4.19 An appreciation of basic rock mechanics as applied in cablebolting.

A4.20 Aspects of the mine monitoring system.

A4.21 Action levels.

A.4.22 Action, duties and responsibilities.

A4.23 Remedial measures.

A4.24 Follow up actions.

A4.25 Communication links.

A4.26 All aspects of the tell-tale checklist system at the mine.

A4.27 Appreciation of tell-tales.

76

A4.28 The correct installation of tell-tales.

A4.29 The replacement of tell-tales.

A4.30 The identification of tell-tales.

A4.31 Reading of tell-tales and appropriate action levels and the associated action to be taken.

A4.32 Instruction on the inspection of bolted roof and ribs for signs of excessive bolt loading or

deterioration and the actions to be taken if these are discovered.

A4.33 Appropriate types of extra support to secure the roof in adverse conditions.

A4.34 Highlight the adverse effects of poor installation standards and describe the Managers

grout sampling scheme.

For Operators
A4.35 The action of cablebolts and typical cablebolt patterns, highlighting the importance of

good installation practice.

A4.36 Correct installation of cablebolts including adequate practical on-site training.

A4.37 The sequence of operations and the time at which cablebolting is carried out.

A4.38 Maintenance of the cablebolting equipment (drilling machines etc) to ensure that

performance is maintained at designed levels. (Particular attention needs to be directed to

ensuring provision of a sufficient supply of either hydraulic fluid, or compressed air (as

appropriate) to allow the drilling equipment to operate within design parameters).

A4.39 Provision of the correct length of drill-rods in an undamaged condition and arrangements

to ensure that the correct depth of hole is drilled.

A4.40 The type of grout together with the importance of the recommended mixing and pumping

procedures. Highlight the adverse effects of poor installation standards and describe the

Managers grout sampling scheme.

A4.41 An appreciation of the managers Scheme for the routine monitoring of rockbolted

roadways, the information indicated by means of the tell-tale monitoring system and action,

where appropriate.

A4.42 An instruction that operators, in the event of difficulty in the application of cablebolting

and monitoring, need to bring those matters to the attention of those having statutory

responsibility for the supervision of operations.

A4.43 Personal protective equipment.

A4.44 Experience has shown that particular attention needs to be paid by all personnel involved

in cablebolting to the following, and any training course should stress their particular

importance:

that grout mixers and pumps are approved for use, well maintained and unmodified
from the manufacturers specification
that air supplies (in the case of compressed air equipment) are adequate in terms of
delivery pressure, flow rate and are filtered
that hosing is in good condition, of adequate bore and of minimal length conducive to
carrying out the task safely
that operators are aware of the grout bag weight and the necessary water volume
required for that weight
that means is available to accurately apportion the required water volume
that the correct mixing technique is used, and mixing time is as required
that grouting of a cablebolt is carried out in one continuous operation (implying that
sufficient grout should be mixed to achieve this)
that the mixed grout is sampled in accordance with requirements (Managers scheme),
and the samples stored properly
that, during grouting, the operators ensure that a flow of air bubbles followed by
cessation and show of grout (if possible) occur in the case of bottom-up grouting, and
that a flow of grout at the bottom of the hole occurs in the case of top-down grouting.

77

A4.44 The above factors are important where any cablebolting operations take place, but
become even more acute when thixotropic grouts are used - because the viscosity of the grout
causes extra demands to be made on equipment and people.

78

9 CONCLUSIONS AND RECOMMENDATIONS


There is some evidence in the literature of field trials of tensioned reinforcement tendon systems
indicating enhanced performance over untensioned systems, though conclusive proof has not
been identified. The wider adoption of increased pretension loads provides further
circumstantial evidence of advantages from tensioned reinforcement. Laboratory tests to date do
not appear to have demonstrated any significant advantages, though effective laboratory
simulation of insitu conditions is very difficult to achieve.
A mechanism by which higher pretension loads may improve support effectiveness has still to
be confirmed. The most widely asserted explanation - that higher pretension increases shear
resistance across joints and bedding planes - would not appear to have been demonstrated by
laboratory studies reported in the literature. For encapsulated bolts crossing a shear plane these
have consistently shown that an increased initial shear stiffness up to bolt yield is the only
measurable effect of pretension. Even this effect would be limited to the zone of compression in
the vicinity of the end plate.
An alternative explanation is that applying high pretension loads closes bed separations which
develop prior to bolting, and therefore re-establishes frictional contact between beds in the
immediate roof. This would provide a significant enhancement to the roof shear strength. Some
modelling work suggests that bed separations do develop at weak interfaces and that the
installation of tensioned bolts can close separations within the compressed zone-the higher the
pretension, the higher into the roof that separations can be closed. The concept of buckling
immediate roof beds, which can be stabilised by centrally placed pretensioned tendons, also
involves the bed separation idea. Acknowledging the practical difficulties associated with
underground investigations, it should still be possible to use field measurements to check the
validity of these ideas by monitoring roof deformations at multiple points as tendons are
installed and tensioned, but this does not appear to have been carried out to date. A field
measurement exercise to measure this phenomenon carried out under this Project did not show
any measureable re-closure at the site concerned. The identification of an underlying
mechanism would be key to confirming that high pretension loads improve roof support.
The question of disadvantages associated with pretensioning has been assessed. The main one
cited in available research work is reduction of available tendon capacity. Additional strain
resulting from rock deformation will add directly to that imposed by the pretension load, so the
tendon yield strain will be reached with less additional strain. Tendon failure could in theory
also be expected at a slightly lower level of roof movement. However by far the major
proportion of total tendon strain to failure occurs post yield, and this is unaffected by
pretensioning. So in deforming roof conditions in which tendons are strained beyond yield this
disadvantage is unlikely to be important.
It follows from this that it is inadvisable to use pretensioned bolts for lifting loads as the load
capacity is reduced both by the pretension load and by any subsequent strata loading. The latter
load is unknown unless instrumented bolts are used.
There are other possible drawbacks. Progressive debonding is one. There is at least a theoretical
possibility of failing the bond through this phenomenon, by application of higher pretension
loads, or subsequent additional loading, and this needs to be considered.
A reduction in rock confining stress above the anchor position is another potential drawback.
The pretension load generates a tensile reaction at the top of the tendon anchor length. In

79

practice this should only slightly reduce the compressive stresses acting at this position due to
the in-situ stress field, but it could initiate instability in a marginal case.
It can be concluded that tensioned tendons should be post grouted, for the following reasons:
i. It locks in the pretension load, minimising subsequent loss.
ii. It ensures the tendon acts as an effective stiff support even without any benefit from
the pretension itself - the belt and braces principle.
iii. It reduces moisture access to the rock through the annular space-this can cause long
term deterioration in weaker mudstones (Unrug et al 2004).
iv. It reduces potential corrosion of the tendon from moisture and salts emanating from
the rock.
v. It reduces the risk of injury to personnel through violent failure of the tendon or end
fittings.
Post grouting could also provide a precaution against progressive debonding, should this prove
necessary.
It seems to be generally assumed that post grouting locks in the pretension load, preventing
subsequent tension loss, although this does not appear to have been verified by test work, either
in the laboratory or in-situ. Some laboratory work suggests that the initial load distribution may
change with time. However, pretensioned bolts are typically used in actively deforming roof
where additional loading rapidly develops, so longer term load change or loss is usually not an
issue.
It follows that the optimum tensioned bolting system for this application combines the facility to
pretension and post grout, with a high bond strength and stiffness in both the anchor and post
grouted lengths. There is however insufficient information to reach definitive conclusions on the
optimum pretension load and tendon length.
In order to fully resolve the considerable uncertainties which still surround the practice of
pretensioning, the following investigation programme is recommended:
i.

The question of the mechanism(s) by which higher pretension loads may improve
support effectiveness needs to be resolved. Field measurement, supplemented by
numerical modelling, appears to be the appropriate method in this case. Field
studies should seek to identify in detail the pattern of deformation of roadway roof
and, in particular, confirm the development of bed separations (as opposed to bed
dilation) prior to support, and establish if these are reduced or closed by the
installation of pretensioned support. Field measurements carried out at colliery A,
and presented in this report indicated no significant re-closure of roof dilation
during tensioning to 100kN, but this needs further confirmation. Numerical
modelling should be used to simulate the field situation and add parametric studies.
It is likely that a number of field sites will be needed to obtain a representative
range of conditions.

ii.

The detailed mechanics of tendon load transfer do not seem to be fully known, and
this adds to the difficulty in resolving the pretension question. Laboratory studies of
rock deformation and tendon behaviour under more realistic loading conditions
should be carried out to investigate load distributions in bonded tendons. These
should make use of findings regarding in-situ rock deformation processes obtained
in the field studies. In particular the difference between load distributions associated
with tensioning the bolt and those induced by rock deformation within the bonded
length needs to be explained, and if necessary allowed for in the experimental

80

procedures. Factors to be investigated should include pre and post yield interface
shear strengths and stiffnesses, the progressive debonding process, tension losses
and the effect of post grouting.
iii.

The use of 3D modelling adequately simulating the tendon, encapsulant and rock, is
considered essential to complete the study of both the load transfer and
pretensioning processes. The shear behaviour of the resin/rock and tendon/resin
interfaces, especially at large strains, is an important factor and laboratory
measurements should be used to obtain the necessary data to allow simulation of
this behaviour.

NOTE: Some of the work recommended above was expected to be carried out during the
lifetime of this project. However, the need to concentrate on practical aspects of safely and
effectively designing, installing and using tensioned tendons has resulted in a lack of time
available to address the complex laboratory testing and numerical modelling required to fully
understand the mechanisms involved.
It was found that a considerable amount of project time needed to be allocated to the issue of
post grouting of Megastrands, and many laboratory tests were carried out. It must be concluded
from this work that, in the form tested during this Project, the Megastrand cannot be reliably
post grouted using thixotropic grouts and mixing / pumping equipment currently approved for
the UK coal mining industry. This is probably a function of the small internal diameter (10mm)
of the central grout tube in the tested Megastrands. Operators using this system, and available
grout and equipment, are almost certain to water down the grout to enable encapsulation,
resulting in a weakened grout, and therefore compromised system performance.
Studies of field samples of cementitious grouts, both thixotropic and non-thixotropic, have
shown that, in the main, grout pumped into tendon installations does not meet the required
density, and, it follows, strength. It is recommended that guidance on use of cablebolts is
updated, partly with a view to stressing and reinforcing the need to mix grout to the required
water to solids ratio. A suggested, updated guidance document is included in this report.
A laboratory study of the effect on tendon bond performance of varying grout strength showed
increasing bond performance with grout strength, as would be expected, although the bond
strength individual values tend to plateau above a grout UCS of 60 MPa. In view of this and the
fact that field measurements indicate that the existing requirement for strength is not being met,
it is difficult to justify a relaxation in the grout strength requirement specified in the existing
Standard for cablebolting materials.
A study of available monitoring data from sites where tensioned tendons were installed in UK
mines, suggests that use of these systems was at least partially successful. However, installation
of tensioned systems at the development face with subsequent grouting dependent on tell tale
action levels appears to have been a step too far, particularly in the light of subsequent
investigation revealing the difficulties associated with grouting these systems with available
equipment. It is essential that post grouted tendons are grouted as early as is practical after
installation and certainly no longer than 24 hours after installation (earlier in rapidly deforming
ground).
The newly developed ability to underground data log strain gauged rockbolts, and the newly
developed intrinsically safe remote reading extensometer system with a portable readout,
allowed accurate and detailed measurements of the effects on roof behaviour of in-situ
tensioning of a flexible tendon. Results from the highly sensitive extensometers used at colliery
A showed that the Megastrand tensioning process to approximately 10 tonnes at this site did not

81

produce any re-closure of previous roof dilation measurable with the equipment used. This was
the case even though the immediate roof had dilated by approximately 20 mm during the
preceding 5 days. It can therefore be concluded that, previous reports of the roof being lifted
during Megastrand tensioning most probably refer to relatively exceptional circumstances where
very large displacements had already occurred. Also when roof lifting does occur it is likely
only to apply to the very bottom roof strata where discrete bed separations and bolt debonding
or bolt failure may have already occurred.
A method has been developed for modelling and comparing the behaviour of tensioned and
untensioned flexible long tendon reinforcement when used as part of a coal mine support system
in realistic geological and geotechnical conditions. For the particular examples modelled, both
hypothetical and real, no benefit was seen from applying pre-tension to the flexible tendons.
Indeed, the effect of pre-tensioning appeared to be to take the tendons beyond their yield load at
an earlier stage in the loading process resulting in marginally higher roof displacements before
stability was established. The modelling exercise also investigated the effect of not achieving
full grout encapsulation of a non tensioned long tendon. In the particular conditions modelled,
typical of UK coal mining, full encapsulation was shown to be critical for achieving stability, as
would be expected due to the major loss of reinforcement stiffness resulting from non
encapsulation. However, the limitations of the modelling should be noted. In particular the
models used could not realistically simulate loss of shear resistance in the bedded strata due to
bed relaxation prior to tendon installation and so could not simulate any benefit which may be
derived from pre-tension in remobilisation of such shear resistance, a claimed benefit of
tensioned tendons. Considerable further work is required to investigate this claimed benefit
through modelling.
Considerable effort was directed to developing test procedures for establishing the performance,
and installation characteristics of tensionable systems in the laboratory, and from this work, the
project facilitated drafting of a revised British Standard, provided information valuable in
development of a new section directed to ribside reinforcement materials, and provided a draft
Guidance Document revision.

82

10 REFERENCES

1.

British Standards Institute. Strata reinforcement support system components used in


coal mines. Part 2. Specification for cable bolts. BS 7861-2:1997.

2.

Rock Mechanics Technology Ltd. Testing and standards for rock reinforcement
consumables. Final report, HSE project D5017. September 2005

3.

British Standards Institute. Strata reinforcement support system components used in


coal mines. Part 1. Specification for rockbolting. BS 7861-1:1996.

4.

British Standards Institute. Strata reinforcement support system components used in


coal mines. Part 1. Specification for rockbolting. BS 7861-1:2007.

5.

Health and Safety Executive. Guidance on the use of cablebolts to support mine
roadways. July 2007.

83

84

Anchor Load Distribution


for Normal Anchor

Tendon Bond Length

Ultimate Loading

Initial Loading
Bond Stress

Loading

O
Load Distribution along Fixed Anchor

Fixed Anchor Length


Generally 10m Max

Unit Anchor Tendons


Single Bore Multiple Anchor
Load Distribution

Bond Stress

O
Load Distribution along Fixed Anchor

Figure 2.1 Comparison of the load distribution of a normal anchor

and a single bore multiple anchor

(after Barley and Windsor, 2000)

85

Roof

Displacement

Tensile bending
Roof measures sub-divide into discrete units
Buckling roof-high displacements

0.5Uh

0.5Uh
Uv

Mechanical Advantage (MA)= Uv / Uh


Beam Equilibrium Condition : F = P/MA
(ignoring the load bearing capacity of the beam itself)
At small values of Uv : F<<P for equilibrium

Figure 2.2 The buckling beam concept for roof stability


(after Strata Engineering, 2001)

86

a) Bolt Pretensioned
C

Joint

Joint compression force C = Bolt pretension force T

C, T
Joint Stiffness >> Bolt Stiffness

Joint Compression

Bolt Extension

b) External force Fe applied


T
Fe

Fe = C + T
Bolt Tension = T + T
Joint Compression Force = C C

Joint Compression

Bolt Extension

Most of the external load is absorbed by reduction in joint


compression force

Figure 2.3 External load applied to a pretensioned bolted joint

87

a) Bolt Stiffness >> Rock Stiffness

C, T

Force

Rock compression

Bolt extension

b) External force Fe applied

Fe

Fe = C + T
Bolt Tension = T + T
Joint Compression Force = C C

C, T

Most of the external load is added to the bolt pretension

Figure 2.4 External load applied to a pretensioned lifting bolt

88

Figure 3.1 Laboratory short encapsulation pull test results for megastrands
and CBG grout at 1 and 3 days curing.

89

Figure 3.2 Laboratory short encapsulation pull test results for megastrands
and CBG grout at 7 and 42 days curing.

90

91

Figure 3.3 Variation of maximum load, bond strength and system stiffness with
grout unconfined compressive strength (cube samples).

92

Figure 3.4 Variation of unconfined compressive strength with density for bottle
samples of CBG grout obtained from UK coal mines

93

Figure 3.5 Variation of unconfined compressive strength with density for bottle
samples of HPRG grout obtained from UK coal mines

94

Figure 4.1 Schematic of 10s main gate colliery C

DS10s new main gate station 4 @ 607m mark

Figure 4.2 Monitoring results for station 4, 10s main gate, colliery C

Station 3 @ 423m ( 5 wire roof exto) 10s main gate

Figure 4.3 Monitoring results for station 3, 10s main gate, colliery C
95

Station 2 @ 248m

Figure 4.4 Monitoring results for station 2, 10s main gate, colliery C

96

97

Figure 4.5 Monitoring results from type B telltales, 10s main gate, colliery C

98

Figure 4.6 Monitoring results from cablebolt type A telltales, 10s main gate, colliery C

99

Reading (mm)

585

545

505

465

425
Roadway Position (MM)

905

865

825

765

725

685

645

618

385

345

305

265

227

160

19 Nov 01

03-Dec-01

22-Dec-01

14-Jan-02

11-Feb-02

13-Mar-02

25 Mar 02

02-Apr-02

25 Mar 02

17-Mar-02

13-Mar-02

25-Feb-02

11-Feb-02

23-Jan-02

14-Jan-02

05-Jan-02

22-Dec-01

17-Dec-01

03-Dec-01

27-Nov-01

19 Nov 01

Figure 4.7 Monitoring results from cablebolt type A telltales, 10s main gate, colliery C (alternative view)

50

100

150

200

250

300

350

400

450

500

Harworth 10's Main Gate Cable Bolt Type 'A' Tell Tales

945

100

Figure 4.8 Monitoring results from type A telltales, 22s main gate, colliery C

101

Figure 4.9 Combined displacement from type a and B telltales, 570, 590 and 610mm, 19s tail gate, colliery C

Figure 4.10 Schematic of t18s face line, colliery B

102

Figure 4.11 Planned support pattern in widened face line

103

104

SG
Bolt

Figure 4.12 Section of widened face line support and instrumentation pattern

SG
Bolt

Extensometer

TT 196MM
X6

R2

X5

X4

+s

X3

X2

R1

X1

TT 207MM approximately
3.5m from cut/dint

Cut

Dint

Cut and Dint

KEY
Pre Installed Mega Strands

+s Sonic Extensometer

X1 Positions of Installed Strain Gauged Bolts

R1 Remote Reading Telltale

Figure 4.13 Approximate position of installed instruments


on 21 March 2007

105

Tail Gate

Machine approximately 4-5m


beyond TT position.

X6 R2 7

X5

X4 +s 1

X3

X2 R1

X1

TT 196MM

1.2m
4

KEY
Installed Mega Strand and order of Tension

+s Sonic Extensometer

Pre Installed Mega Strands

R1 Remote Reading Telltale

X1 Positions of installed Strain Gauged Bolts

Figure 4.14 Approximate position of installed megastrands


and tensioning on 27 March 2007

106

R
S

196mm (Telltale)

Planned Megastrand positions

Planned Sonic Extensometer position

Planned SG Bolt positions

Planned Remote Reading Exto positions

Figure 4.15 Proposed megastrand monitoring instrumentation


302s faceline march 07
107

108

Figure 4.16 Time trend for cable bolt telltale number 13 at 196m

109

Figure 4.17 Colliery C 302s faceline station 6 at 192m

110

Figure 4.18 Colliery C 302s face 197m cl 297 rrexto 1

111

Figure 4.19 Colliery C 302s face 197m cl 297 rrexto 1

Figure 4.20 Sonic extensometer 196m, displacement & strain


against distance in strata
112

113

Figure 4.21 Sonic extensometer 196 m, displacement against time

114
Figure 4.22 Sonic extensometer 196 m, displacement against time
during megastrand tensioning period

Figure 4.23 Strain gauged rockbolt 1. mean microstrain


and microstrain difference against
distance along bolt
115

Figure 4.24 Strain gauged rockbolt 2. mean microstrain


and microstrain difference against
distance along bolt
116

Figure 4.25 Strain gauged rockbolt 3. mean microstrain


and microstrain difference against
distance along bolt
117

Figure 4.26 Strain gauged rockbolt 4. mean microstrain


and microstrain difference against
distance along bolt
118

Figure 4.27 Strain gauged rockbolt 5. mean microstrain


and microstrain difference against
distance along bolt
119

Figure 4.28 Strain gauged rockbolt 6. mean microstrain


and microstrain difference against
distance along bolt
120

COAL

Siltstone

100
90

Mudstone
80

Axial stress, MPa

70

Coal

60
Hoek-Brown
50

bilinear fit

40
30
20
10

Mudstone
0
-5

Figure 5.1 Modelled strata sequence


3.2 m roof mudstone

10

15

Confining stress, MPa

Figure 5.2a Coal strength


properties

MUDSTONE

SILTSTONE

100

100

90

90

80

80

70

70
Axial stress, MPa

Axial stress, MPa

Hoek-Brown
60
Hoek-Brown
50

bilinear fit

40

60

bilinear fit

50
40

30

30

20

20

10

10
0

0
-5

10

-5

15

10

15

Confining stress, MPa

Confining stress, MPa

Figure 5.2c Mudstone


strength properties

Figure 5.2b Siltstone


strength properties

121

Roof sag/bulking

Roof shortening

Excavate
roadway

Fail bolts

Figure 5.3 Modelled roof displacements with roof bolts


failed and no additional support
(a. Displacements)

Roof shortening
Roof sag/bulking

Excavate
roadway

Install flexible
bolt tension to
200kN

Fail bolts
Flexible bolt
tension

(b. Tension)

Figure 5.4 Modelled roof displacements with roof bolts

failed and pre-tensioned flexible bolts

as additional support

122

(a. Displacements)

Roof shortening
Roof sag/bulking

Excavate roadway

Fail bolts

Install flexible
bolts

Flexible bolt tension

(b. Tension)

Figure 5.5 Modelled roof displacements with roof bolts failed and
untensioned flexible bolts as additional support
123

(a. Displacements)

Roof sag/bulking

Roof shortening

Excavate roadway

Fail bolts

Install truss Tension to 200kN

Truss tension

(b. Tension)

Figure 5.6 Modelled roof displacements with roof bolts failed and
tensioned truss system as additional support

124

Figure 5.7 Shear strains and bolt loads with pre-tensioned


flexible bolts as additional support

Figure 5.8 Shear strains and bolt loads with pre-tensioned


truss system as additional support

125

Density

Length

KT bolts

2.1

2.4m

Tensioned
tendons x

0.28

6.0m

Flexible
+
bolts

Figure 5.9 Proposed bolt pattern


at development face

Sequence - a

Sequence - b

8
7
Silty mudstone (UCS 40MPa)

6
5
Mudstone (UCS 30MPa)

4
3

Silty mudstone (UCS 40MPa)

Silty mudstone (UCS 40MPa)

Siltstone (UCS 50MPa)

Siltstone (UCS 50MPa)

Silty mudstone (UCS 40MPa)

Silty mudstone (UCS 40MPa)

Coal seam

Coal seam

2
1
0
-1
-2
-3

Figure 5.10 Strata sequences

126

ROOF EXTENSOMETER

Height above roof, mm

5
Lateral stress MPa
12

16
20

0
0

20

40

60

80

100

Displacement, mm

Figure 5.11 Roof condition with proposed support and sequence A

127

ROOF EXTENSOMETER
7

Height above roof, mm

5
Lateral stress MPa
4

12
16

20

0
0

20

40

60

80

100

Displacement, mm

Figure 5.12 Roof condition with proposed support and sequence B

128

Density

Length

1.1

2.4m

Tensioned
tendons x

Flexible
+
bolts

1.0

4/5/6m

KT bolts

+
+

+
+

+
+

+
+

+
+

+
+

+
+

+
+

Figure 5.13 Alternative bolt


patterns at development face

+
+

TOTAL ROOF EXTENSOMETER MOVEMENT


Movement, mm

140

120

7+8, 2.4mKT @ 1.5m 2, 6m Megastrand

100

7+8, 2.4mKT @ 1.5m no long tendons

80

4+4, 2.4m KT @1.5m 4+3, 4m FB

60

40

4+4, 2.4m KT @1.5m 4+3, 6m FB

20

4+4, 2.4m KT @1.5m 6m FB 2m free length

0
10

12

14

16

18

20

22

Figure 5.14 Roof movement


with alternative support patterns
(sequence A)

Lateral stress, MPa


MOVEMENT ABOVE 2m

Movement, mm

35

30

7+8, 2.4mKT @ 1.5m 2, 6m Megastrand

25

7+8, 2.4mKT @ 1.5m No long tendons

20

4+4, 2.4m KT @1.5m 4+3, 4m FB

15

4+4, 2.4m KT @1.5m 4+3, 6m FB

10

4+4, 2.4m KT @1.5m 6m FB 2m free length

0
10

12

14

16

18

20

22

Lateral stress, MPa

129

BOLT STRAIN
5.0%
4.5%

7+8, 2.4mKT @ 1.5m 2, 6m Megastrand


4.0%

Sdtrain

3.5%

7+8, 2.4mKT @ 1.5m No long tendons

3.0%

4+4, 2.4m KT @1.5m 4+3, 4m FB

2.5%
2.0%

4+4, 2.4m KT @1.5m 4+3, 6m FB

1.5%

4+4, 2.4m KT @1.5m 6m FB 2m free length

1.0%
0.5%
0.0%
10

12

14

16

18

20

22

Lateral stress, MPa

CABLE STRAIN
5.0%
4.5%

7+8, 2.4mKT @ 1.5m 2, 6m Megastrand


4.0%
3.5%

7+8, 2.4mKT @ 1.5m No long tendons

Strain

3.0%

4+4, 2.4m KT @1.5m 4+3, 4m FB

2.5%
2.0%

4+4, 2.4m KT @1.5m 4+3, 6m FB

1.5%

4+4, 2.4m KT @1.5m 6m FB 2m free length

1.0%
0.5%
0.0%
10

12

14

16

18

20

22

Lateral stress, MPa

Figure 5.15 Bolt strains with alternative support patterns (sequence A)

Stage

Face position

Development

120 160 m

50 100 m

30 50 m

20 30m

10 20m

STAGE

<10m

Lateral stress for development = 16MPa

higher than
expected

STRESS INCREASE

200%

Vertical stress

150%

Lateral stress no
stress notch

100%

Lateral stress slight


Stress notch

50%

0%
0

Figure 5.16 Stress increase to represent face retreat


130

ROOF EXTENSOMETER

7
Stage

Height above roof, mm

0
1

2
3

4
5

6
7

2
1

0
0

20

40

60

80

100

Displacem ent, m m

Figure 5.17 Modelled roof condition for retreat

131

ROOF EXTENSOMETER MOVEMENT

200
180
Movement, mm

160
140

Additional support for retreat

120
100
80

No additional support

60
40
20
0
0

Stage

Figure 5.18 Roof movements for face retreat

MOVEMENT ABOVE 2m
45
40
Movement, mm

35
30
Additional support for retreat

25
20

No additional support

15
10
5
0
0

Stage

BOLT STRAIN
6%
5%

Strain

4%

Additional support for retreat


3%

No additional support

2%
1%
0%
0

Stage

Figure 5.19 Bolt strains for face retreat


CABLE STRAIN
6%
5%

Strain

4%

Additional support for retreat

3%

No additional support

2%
1%
0%
0

Stage

132

Additional support
installed
fail bolts and cables

R
OOF L
O W ER ING
ROOF
LOWERING
1400
1600
1200
1400

Unstable roof

Movement, mm
Movement, mm

1200
1000
1000
800

Roof movements
stabilise

800
600
600

Fail bolts and cables

400
400
200
200
00
00

Increase stresses for


face retreat

Initial
drivage

100000
100000

200000
300000
200000
300000
Solution
steps
S o lu tio n ste p s

400000
400000

No additional support installed - Fail roof bolts and cables


N o additional s upport ins talled - F ail roof bolts and c ables
Additional support installed - Fail roof bolts and old cables
A dditional s upport ins talled - F ail roof bolts and c ables
Additional support installed - Fail roof bolts and cables
A dditional s upport ins talled - F ail roof bolts and old c ables

Figure 5.20 Fail bolts and cables

133

500000
500000

134

Mean residual load (kN)

10

20

30

40

50

60

70

80

9.5

20

Weldgrip GRP
FT500 24mm

22

33

17

#N/A

17
6

22

33
27

37

Bolt type

KT Steel 22mm

35 35

#N/A

50
41

Big Bolt Steel


28mm

44

46

#N/A

22

56
48

56

Osborn Reflex

Steel Strand

22mm

26

33

Figure 7.1 Mean residual loads at 50 mm displacement

Weldgrip GRP
Big Bolt 28mm

40

68

PU resin at 5MPa

CBG grout at 5 MPa

AT resin at 5 MPa

PU resin at 1 MPa

CBG grout at 1MPa

AT resin 1 MPa

135

M e a n M a x im u m L o a d ( k N )

50

100

150

200

250

300

27m m
ho le A T
re s in

33m m
ho le A T
re s in

43mm
ho le C B G
g ro ut

27m m
ho le P U
re s i n

33m m
ho le A T
re s in

43mm
ho le C B G
g ro ut
5 M P a C o n fin in g P re s s u re

27m m
ho le A T
re s i n

Figure 7.2 Comparison of achieved mean maximum loads between


different bolt types and increasing hole size

1 M P a C o n fin in g P re s s u re

27m m
ho le P U
re s in

B ig B o lt S te e l 2 8 m m

W e ld g rip G R P B ig B o lt 2 8 m m

O s b o rn R e fle x S te e l S tra nd 2 2 m m

K T S te e l 2 2 m m

W e ld g rip G R P F T 5 0 0 2 4 m m

Figure 8.1 Water diverting dual height tell-tale for cablebolting


&
(white, blue, yellow bands)
&

Figure 8.2 Water diverting triple height tell-tale for cablebolting


&
(green yellow red bands)
&

136
)

APPENDIX 1 DRAFT TEST PROCEDURE

GROUT ENCAPSULATION TEST BOTTOM UP GROUTING

A1.1 PRINCIPLE
This test is used to verify that a bottom-up flexible reinforcement system, where grouting
takes place from the proximal end of the tendon toward the distal end, can consistently achieve
full encapsulation.
A1.2 APPARATUS
A suitable test arrangement is shown in Figure A1.1.
The overall length of the test tendon should be equal to the manufacturers maximum
recommended length for vertical installation using standard pumping equipment. It should be
installed in a clear rigid tube with an internal diameter equal to the manufacturers
recommended installation hole diameter +/- 1mm. The tube should have a minimum wall
thickness of 2mm. The tube may be a continuous length or be made up from several pieces
provided the joints are made with made-for-purpose sockets and bonded with a suitable
proprietary cement. One end of the tube will be capped with a made-for-purpose end fitting
again bonded with a suitable proprietary cement. The joints of the assembled tube must be air
tight. It is important that the wall thickness, construction of the tube and all ancillary
components are selected taking full account of the pressures that could be generated during the
test.
Flexible breather and grouting tubes may be required and, if used, should conform to the
recommendations of the tendon manufacturer.
The assembled test tendon and tube will need to be supported in a vertical position, and this
may be via a structure attached to the side of a building, a scaffolding tower, a support pole
erected into the vertical position via a pivoting bracket, or other suitable arrangement.
The mixing and pumping equipment should be selected from the range typically used and
accepted for underground use in coal mines. If the manufacturer recommends a specific
pumping and mixing system then this should be used. If pneumatically operated, an adequate
supply of compressed air (consult the manufacturers literature) should be made available, and
connected with suitable low-restriction hosing and couplings. A 25mm bore hose should be
used for grouting. The hose should be no less than 10m long and fitted with a suitable connector
at one end for connection to the pump, and a means of connection to the test tendon grouting
tube at the other. The apparatus should include a T-piece arrangement at the pump outlet with
associated valves, couplings and an additional hose to provide a means of relieving the pressure
at the pump after grouting, and delivery of excess grout or flushings to a suitable container.
Sufficient grout for efficient mixing in the apparatus to be used, to fully encapsulate the test
tendon, and to fill grout sample moulds, should be available.

137
)

A1.3 PROCEDURE
A1.3.1 Preparation of the test tendon.
Assemble the tube components and bond together. Fit the breather tube and grouting tube (if
required) to the tendon and secure using pvc or other suitable tape. Ensure sufficient tubing
extends beyond the proximal end of the tendon for immersion in water (breather) and
connection to the grout hose. The test tendon can be anchored either at the top of the tube using,
for example, mixed encapsulated resin, and/or at the bottom using a combination of a seal and
clips/tape. The test assembly must be sealed at the proximal end and this can be affected using a
surgical sock filled with pre-mixed grout as is typically practiced underground or some other
means.
Erect the test assembly to the vertical using a means of support as described above. Ensure that
the test tendon is straight to within 100mm of the notional vertical axis of the test assembly. The
proximal end of the test tendon should be approximately 2.5m above ground level.
A1.3.2 Preparation of the grout.
The grout should be stored at a temperature of 20 +/-1 deg C. Water for mixing should also be
at this temperature as a result of storage or blending. Weigh the components (water and grout)
in the proportions required with reference to the manufacturers recommended water-to-solids
ratio, using a digital scale calibrated using equipment with calibration traceable to National
Standards. Sufficient material should be available for efficient operation of the mixing
equipment, encapsulation of the grout, and for cube samples.
A1.3.3 Test Method.
Ensure that the test tendon is securely in position. If a grout seal has been used, this should be
allowed to cure for at least six hours. Immerse the breather tube outlet in a container of clear
water.
Pour the water for grout mixing into the mixing tank, having first established that the tank is
clean and empty. Add the grout in increments while using a suitable rotational speed for the
mixing paddle. Once all the grout has been added, continue to mix for the period recommended
by the grout manufacturer prior to grouting. Continue mixing throughout the grouting operation.
Having established that the grout hose is clear of water and contaminants (by, for example,
blowing through with compressed air), connect the hose to the pump outlet, direct the other end
to the mixing tank, and commence pumping to establish a return flow to tank. Observe the flow
to establish that it is continuous, free of air voids and that the flow appears to be consistent with
the pump manufacturers quoted flow rates. Note: flow can be checked by filling a known
volume and timing the event.
Stop the pump, and connect the grout hose securely to the test bolt grouting tube.
Start the pumping operation and record events as follows:
show of grout at the proximal end of the test tendon (time required)
full encapsulation of the test tendon (time required)
cessation of bubbles and /or show of grout at the breather outlet (time required).
Terminate the test when full encapsulation has been achieved, indicated by either
a) a show of grout at the breather tube outlet if a breather tube with a bore of 7mm or
more is used, or
b) a cessation of bubbles at the breather tube outlet
or, there is an event, such as pump stall or leakage, which prevents full encapsulation being
achieved.

138
)

manufacturers maximum
recommended pumped
column length

End Cap

Clear Tube

Flexible
Tendon
Grout Pump
Grout Tube
0.5m into Clear
Tube
Mixer Motor

Seal

2.5 m

Breather
Immersed in
Water
Container
At least 10m

Mixing Tank

Figure A1.1 Example of an arrangement for grout encapsulation


test bottom-up grouting
Disconnect the hose from the test assembly having first de-pressurised the circuit by opening
the secondary line at the pump outlet. Use the grout hose to fill three moulds with the remaining
grout for density and UCS measurements in accordance with annex C.
A1.4 RESULTS
Leave the test tendon in position for at least 12 hours to allow the grout to cure. Remove the
tendon to the ground and remove any supports. Photograph the tendon in approximately 1m
long segments in order to have a record of the encapsulation. Inspect the test tendon and
confirm that full encapsulation has been achieved or otherwise. Inspect for any suspected voids
in the encapsulation and note their position. Section the tendon at points where possible voids
have been noted, or at four points equi-spaced along the tendon. Photograph the sections.
Five tests should be carried out. For a candidate system to be acceptable, all tests should be
completed satisfactorily as described above.

139
)

140

APPENDIX 2 DRAFT TEST PROCEDURE

GROUT ENCAPSULATION TEST TOP DOWN GROUTING


'

A2.1 PRINCIPLE
This test is used to verify that a candidate top-down flexible reinforcement system, where
grouting takes place from or near the distal end of the tendon toward the proximal end, can
consistently achieve full encapsulation.
A2.2 APPARATUS
A suitable test arrangement is shown in Figure A2.1.
A breather tube may not be required, and the grouting tube may be either integrated into the
tendon structure (internal) or attached along the length of the tendon (external). Determine the
exact positioning of an external grouting tube using the manufacturers specification.
For other aspects of the apparatus, see Appendix 1.
A2.3 PROCEDURE
A2.3.1 Preparation of the test tendon.
Assemble the tube components and bond together. Fit the grouting tube (if required) to the
tendon and secure using pvc or other suitable tape. Ensure that the grouting tube arrangement
complies with the manufacturers recommendation and it is not blocked during assembly and
anchorage. Ensure sufficient tubing extends beyond the proximal end of the tendon for
connection to the grout hose. The tendon can be anchored either at the top of the tube using, for
example, mixed encapsulated resin, and/or at the bottom using a combination of a seal and
clips/tape. The test tendon must be sealed at the proximal end. This arrangement will depend
upon whether an end plate is used to complete the installation. If not, a tape seal around the joint
between tube and tendon will probably be effective.
Erect the test tendon to the vertical using a means of support as described in Appendix 1.
Ensure that the test tendon is straight to within 100mm of the notional vertical axis of the test
assembly. The proximal end of the test tendon should be approximately 2.5m above ground
level. A means of egress of air at the proximal end will be required: this may be furnished via an
end plate, but if not, drill an 6mm hole in the tube just above the seal.
A2.3.2 Preparation of the grout.
See Appendix 1.
A2.3.3 Test method.
Ensure that the test tendon is securely in position. Pour the water for grout mixing into the
mixing tank, having first established that the tank is clean and empty. Add the grout in
increments while using a suitable rotational speed for the mixing paddle. Once all the grout has
been added mix for the period recommended by the grout manufacturer. Continue mixing

141
)

throughout the grouting operation. Having established that the grout hose is clear of water and
contaminants (by, for example, blowing through with compressed air), connect the hose to the
pump outlet, direct the other end to the mixing tank, and commence pumping to establish a
return flow to tank. Observe the flow to establish that it is continuous, free of air voids and that
the flow appears to be consistent with the pump manufacturers quoted flow rates. Note: flow
can be checked by filling a known volume and timing the event. Stop the pump, and attach the
grout hose securely to the test tendon using a proprietary lance, grouting tube or other suitable
fitting.
Start the pumping operation and record events as follows:
show of grout at the distal end of the test tendon (time required), and
full encapsulation of the test tendon (time required).
Terminate the test when grout issues from the breather hole, or there is an event, such as pump
stall, which prevents full encapsulation being achieved.
Depressurise the circuit by opening the secondary line at the pump outlet and then disconnect
the hose from the test assembly. Use the grout hose to fill three moulds with the remaining grout
for density and UCS measurements in accordance with appropriate annex.
A2.4 RESULTS
See Appendix 1.

manufacturers maximum
recommended pumped
column length

End Cap

Clear Tube

Flexible
Tendon
Grout Pump
Grout Tube
Breather Hole
Seal

Mixer Motor

2.5 m

Mixing Tank

At least 10m

Figure A.2.1 Example of an arrangement for grout encapsulation


testing top-down arrangement

142
)

APPENDIX 3 DRAFT TEST PROCEDURE

DETERMINATION OF BOND STRENGTH AND SYSTEM

STIFFNESS CEMENTITIOUS GROUT ANCHORED SYSTEM

A3.1 PRINCIPLE
The bond performance of a flexible tendon and an associated cementitious grout is determined
from a laboratory short encapsulation pull test where the tendon sample is installed in a
confined, rock core using cementitious grout which complies with Part 5 of this standard, and,
after grout curing, is pull tested under controlled conditions. Bond performance is assessed in
terms of load and slope values obtained from the load / bond displacement characteristic.
A3.2 APPARATUS
A3.2.1 The installation apparatus comprises a machine tool lathe, such as that shown in Figure
A3.1, a hydraulic biaxial cell, a water feed system and drill assembly. Use pull test equipment,
as shown in Figure A3.2, to carry out the test. An autographical recording facility or other
means of producing a load / extension graph for recording the test data during pull testing are
required, as indicated in Figure A3.2, and as described below.
A3.2.2 Machine Tool Lathe
A machine tool lathe with a sufficient bed length to allow the drilling operations to be carried
out in a single pass is required. The lathe should be capable of a traverse of at least 320mm, a
rotational speed of 440 rpm, and offer a minimum torque of 200Nm. An automated feed rate of
1.25mm/revolution is also desirable, but not essential.
A3.2.3 Biaxial Cell
A hydraulic biaxial pressure cell is shown in Figure A3.3. The cell should have a nominal
internal diameter of at least 145mm and a minimum confining membrane length of 500mm. The
cell should be capable of applying a confining pressure of at least 10MPa.
A3.2.4 Water Feed
The system should allow flushing water to be delivered effectively through a rotating drill rod,
fixed in the chuck of the lathe, to the tip of the drill bit during drilling operations.
A3.2.5 Drilling Consumables
A drill bit as typically used for the underground installation of the candidate tendon should be
used where possible. Most underground installations exhibit rifling of the hole wall, and this
should be duplicated in the laboratory test through choice of drilling equipment (bit and rod)
and positioning of the drill rod, as indicated in the test procedure for resin grouted systems.
However, hole wall rifling is not as critical to bond performance when testing cementitious
grout bonded tendons, principally because the larger hole diameter used provides a high level of
shear strength at the rock /grout interface (relative to that achieved with smaller diameter holes
used for resin bonded systems) without relying on geometrical discontinuity.

143
)

A3.2.6 Pull Test Equipment


Pull test equipment must be suitably calibrated, and will comprise a hydraulic hollow ram jack,
a pressure bearing plate or stressing stool, hydraulic hose, pressure gauge and/or load cell, and
hydraulic pump fitted with a non-return valve, as shown in Figure A3.2. The centre hole of the
hollow ram should be sufficiently large to allow assembly onto a steel embedment tube.
Experience shows that a 95 tonne capacity ram is required to provide a sufficiently large centre
hole.
A3.2.7 Recording Apparatus
Use a Linear Variable Differential Transformer (LVDT) or dial indicator to record displacement
and an in-line pressure gauge, preferably with an electronic sensor and / or suitable capacity
load cell, to record the applied pressure and hence load. See Figure A3.2.
A3.2.8 Rock Test Specimens
The rock test specimens should consist of sandstone rock cores with an external diameter to
match the internal diameter of the biaxial cell used, and of sufficient length to extend
approximately 10mm beyond the membrane at both ends of the cell. The rock test specimens
should have suitable properties and meet the performance criteria specified in A3.5. The core
should comprise poorly cemented, medium grained, homogeneous sandstone with rounded,
well-sorted grains. When tested according to ISRM Suggested Methods, the uniaxial
compressive strength should lie between 21 and 31 MPa and the Youngs Modulus should lie
between 7 and 10 GPa. An example of a suitable rock is Hollington Stone, extracted from
Hollington Quarry, Hollington in Staffordshire.
A3.2.9 Embedment Tube
The tendon should be installed in the core and a steel embedment tube mounted on the core. The
tube is used to facilitate loading of the section of tendon embedded in the rock core, while
maintaining the shape of the tendon where it exits the core. The tube should be 450mm long,
and have an internal diameter nominally the same as the diameter of the drill bit used to drill the
core. The internal surface should be machined with a groove 1mm deep and 2mm in pitch along
its full length. Tube thickness should be a minimum 10mm and the material should have a
minimum yield stress of 400 MPa. One end of the tube should be threaded on the outer surface
to accept a reaction plate.
A3.3 PROCEDURE
A3.3.1 Rock Core Preparation
Core specimens with major irregularities, bedding or discontinuities should be discarded. Any
minor irregularities or depressions found in the outer surface of the rock core must be removed
or filled with a suitable self hardening filler compound to avoid localised deformation of the cell
membrane under pressure.
A3.3.2 Installing Rock Core in Biaxial Cell
The biaxial cell should be securely mounted on the lathe stock such that the axis of the rock core
is in alignment with the axis of the lathe chuck. The rock core should be located inside the
biaxial cell ensuring that the cell membrane has full circumferential and axial contact with the

144
)

rock core. Approximately 10mm of rock core should overlap the membrane at both ends of the
cell. A confining pressure of 10MPa should then be applied to the rock core.
A3.3.3 Drilling
Sharp undamaged drill bits of the correct type and dimensions (see A3.2.5) should be used. Drill
rods in good condition, which are clear of debris and with full flushing functionality, should be
used. Mark the drill rod 320mm from the bit end. Mount the drill rod in the lathe chuck such
that it is concentric, that the required length of drill rod extends beyond the face of the chuck,
and the water feed is attached. Advance the lathe stock until the face of the rock core is close to
the drill bit. Operate the lathe at the correct rotational speed (approximately 440rpm), apply
flushing water, then, manually advance the lathe stock to initiate drilling. Once the drill bit has
begun to penetrate the rock core, ensure that rock penetration continues at the appropriate rate
(approximately 1.25mm/revolution), preferably by engaging an autofeed mechanism. When the
rock core has been drilled to the correct depth (320mm), disengage the feed mechanism and
withdraw the stock slowly, maintaining lathe rotation and flushing water pressure. Ensure the
hole is free of debris and has a depth of 320mm.
A3.3.4 Tendon Installation and Pull Testing
Measure and record the internal diameter of the drilled hole using a calibrated borehole
micrometer, recording the diameter for at least six positions evenly distributed along the length
of the borehole. From these readings determine the average borehole diameter. Ensure the
flexible tendon to be tested is clean and free from contaminants. The tendon, in its design
geometrical form (complete with cages, bulbs etc) should be of sufficient length to allow
installation into the borehole and a 450mm long embedment tube placed on top of the rock core.
Additionally the tendon should have a tail section of straight strand(s) which will protrude
beyond the embedment tube and be of sufficient length to allow fitting of spacer plates and
barrel/wedge assemblies or other end termination. Overall length of the test tendon is likely to
be around 1 metre. The end of the tendon to be inserted into the rock core should have a fully
developed profile (not tail section) and should be cut normal to the axis of the tendon.
Depending on the application, a tendon to be used underground would be fitted with a breather
or grout tube along most of its length. Complete the assembly of the test tendon by securing a
320mm length of breather or grout tube, as specified by the tendon supplier, to the distal end. A
breather tube of less than 10mm bore should be sealed at both ends. A larger breather tube, or
grout tube, should be left open to admit grout.
Remove the biaxial cell, complete with confined rock core, from the lathe and place it upright
on the laboratory floor. Place a sealing membrane around the periphery of the mating face of the
steel tube and place the tube on top of the core, taking care to centralise the core and tube holes.
Carefully insert the tendon into the assembly and locate to the back of the core hole. Prepare a
sufficient quantity of grout to fully encapsulate the tendon, taking care to adhere to
manufacturers requirements for water-to-solids ratio, mixing time etc. Pump the grout slowly
into the assembly until full. Top up as necessary as settling occurs. Fill a 100mm cube mould
from every mix prepared, for UCS testing of the grout. Allow the grout to cure for 14 days
before testing.
With the core installed in the biaxial cell and pressurised to 10 MPA, install the pull test
equipment on the test assembly, as shown in Figure 3.2. Install a reaction plate onto the
embedment tube, fit an end termination onto the tendon, and locate to bear on the reaction plate.
Fit a dial indicator or LVDT to the end fitting in order to record bond displacement.

145
)

Operate the hydraulic pump at a slow and smooth rate (approximately 1 kN/sec) applying
increasing pressure to the hydraulic jack. Record load and bond displacement incrementally so
that a minimum of twenty data points have been recorded when displacement exceeds 10mm in
total, or at 90% of the load at which the yield strength of the tendon would be reached. Cease
pump operation at this point. After pull testing, relieve the pressure from the pull test jack and
then relieve the pressure in the biaxial cell.
A3.3.5 Core Examination
After testing, withdraw the rock core from the biaxial cell and split the core in the axial plane in
order to inspect the quality of installation and mode of bond failure. Examine the grout / tendon
and the grout / rock interfaces and note the location of any shear failure.
A3.4 RESULTS
Plot load to a base of measured displacement and determine
a) bond strength which is the load at which the slope of the load / displacement
characteristic falls below 20 kN / mm
b) system stiffness which is the slope of the load / displacement characteristic in the
load range 150 - 300 kN.
A3.5 ROCK CORE PERFORMANCE CRITERIA
A standard test is required to determine the performance characteristics of the rock core under
pull test conditions to ensure consistent rock material is used. When tested in accordance with
the procedure described in Annex E of Part One of this Standard, and using the standard
consumables and criteria listed in Table A3.1, the rock core should provide test results which lie
within the performance envelope shown in Figure A3.4. Bond failure must be at the rock/resin
interface.
Table A3.1 Standard Consumables and Criteria for Rock Core Performance Testing
Hole diameter
Bond length
Confining pressure
(biaxial cell)
Drill rod type
Bar type
Grout type

28.5mm+/- 0.5mm
160mm
10MPa
19mm AF, hollow, hexagonal
M24 High tensile continuously threaded
steel bar, grade 10.9 steel
(Yield Strength 312kN, UTS 346kN)
Resin grout complying with Part 1 of
this Standard.

146
)

Figure A3. 1 Lathe test


&

Figure A3. 2 Pull test equipment


&

147
)

Tendon End
Fitting and
Bearing
Plate
Upper M/C
LVDT
'
Attached to

Tendon
'
Lower M/C
Bearing Plate

Bi-axial Cell
with Test
Sample
Installed

Figure A3.3 Tensile testing machine


&

Figure A3.4 Biaxial cell

148
)

ve
&

149
)

150

APPENDIX 4 DRAFT TEST PROCEDURE

SHEAR TEST ON TENDON / GROUT SYSTEM

4.1 PRINCIPLE
The ultimate shear strength of a flexible reinforcement system is determined in the laboratory
using a single shear frame in conjunction with a flexible tendon / grout double embedment
assembly.
4.2 APPARATUS
4.2.1. The design of a single (guillotine) shear frame suitable for the testing of a flexible tendon
/ grout double embedment assembly is shown in figure A4.1. Use a test machine calibrated to
BS EN ISO 7500 Part 1 1999, having an autographic recording facility or other means of
producing a force / displacement graph.
4.2.2. The arrangement of the test assembly is shown in figure A4.1. It consists of two thickwalled hollow steel tubes, each 450mm long, with an internal diameter nominally the same as
the diameter of the drill bit recommended for tendon installation. The tubes should have a wall
thickness of at least 10mm, and have a 1.0mm deep by 2.0mm pitch thread machined onto their
internal surface in order to provide a standard surface finish intended to inhibit failure between
this surface and the grout.
4.2.3. Use a displacement transducer, for example the stroke measurement device on the testing
machine, to record the separation of the two tubes.
4.3 PROCEDURE
4.3.1. Sample size
Prepare three test assemblies.
4.3.2. Preparation of test assemblies resin bonded systems
Blank off one end of each tube with strong adhesive tape. Prepare sufficient slow set resin,
mixed in accordance with the manufacturers instructions, to fully encapsulate one tube / tendon
assembly, and pour into one tube. Push the tendon, which should be 900mm long, into the resin
by hand, whilst at the same time slowly rotating the tendon and ensuring as far as is possible
that the tendon is centrally positioned within the tube assembly. Remove any excess resin from
the tube outer surface and face. Allow to cure for one hour. Prepare another batch of resin, as
described above, and fill the second tube. Encapsulate the remaining section of tendon in the
second tube, taking care to centralise the tendon within the tube and that the tube faces are fully
butted together. Allow the assembly to cure for at least 24 hours at a room temperature of 20+/- 2
deg C.
4.3.3. Preparation of test assemblies cementitious grout bonded systems
Blank off the end of one of the tubes with strong adhesive tape, and butt together the open ends,
securing the joint temporarily with strong adhesive tape. Prepare sufficient grout, mixed in
accordance with the manufacturers instructions, to fully encapsulate the tube / tendon assembly

151
)

whilst at the same time slowly rotating the tendon, and ensuring, as far as is possible, that the
tendon is centrally positioned within the tube assembly. Allow the assembly to cure at a room
temperature of 20+/- 2 deg C for 14 days.
4.3.4. Method
Place a test assembly in the test machine and apply load at a rate not exceeding 2 kN / sec until
such time as the maximum force is achieved. Record load and displacement (platen
displacement or piston stroke are sufficient) at intervals of not more than 2 seconds during the
test.
4.4 RESULTS
Plot a load vs displacement characteristic and note maximum load. The ultimate shear strength
of the grouted flexible tendon is determined from the mean of the three test results.

Figure A4. 1 Sectional diagram of shear frame

Published by the Health and Safety Executive

02/11

Health and Safety


Executive

Evaluation of tensioned and non-tensioned


long tendon reinforcement in UK deep
mining conditions
A research programme has been carried out
by RMT in support of the revision of Part 2 of
the British Standard for strata reinforcement
components in coal mines, covering flexible
systems for roof reinforcement. This continued work
commenced under a previous HSE Project, Testing
and standards for reinforcement consumables.
A particular focus was to compare tensionable and
non-tensionable reinforcement systems, prompted
by the introduction of tensionable systems to
British coal mines. A review of previous research
indicated conflicting claims for tensionable systems
in terms of theoretical advantages and practical
experience. The research included laboratory
testing, underground measurement and analysis
of underground monitoring data. Advice and draft
Annexes were provided to the BS Committee and
a revision of the DMCIAC guidance on the use
of cable bolts to support roadways in coal mines
drafted. The work highlighted practical problems
concerning application of the tensionable systems
in use in UK coal mines but did not exclude their
future applicability provided they comply with the
revised Standard.
This report and the work it describes were funded by
the Health and Safety Executive and co-funded by
the EU Research Fund for Coal and Steel. Aspects
were also co-funded by UKCoal Ltd and various
manufacturers through supply of materials for testing.
The reports contents, including any opinions and/
or conclusions expressed, are those of the authors
alone and do not necessarily reflect HSE policy nor
the opinions of any of the co-funding parties.

RR831

www.hse.gov.uk

Anda mungkin juga menyukai