STANDARD FOUNDATION
TOWER 62 m
FOUNDATION ANALYSIS
TOWER 62 m
qc1 := 25
qc S1 = qC1
kgf
cm
qc2 := 25
qc S2 = qC2
kgf
cm
qall :=
15
qall = 1.667
kgf
cm
8/13/2014
D w := "none"
STANDARD FOUNDATION
TOWER 62 m
Fx + Fy
Fa = 1665.433 kgf
3) DIMENSION FOUNDATION
Concrete
Width of pedestal
bb := 0.5m
bt := bb
bt = 0.5 m
height of pedestal at the bottom
hts := h hm
hts = 1.9 m
Tie Beam
8/13/2014
STANDARD FOUNDATION
TOWER 62 m
0m if h ht + hg + htb + hm < 0
h ht + hg + htb + hm
if h ht + hg + htb + hm 0
hs = 1.3 m
Check hc = h
ht = 0.3 m
htb = 0.3 m
hm = 0.4 m
hg = 0
hs = 1.3 m
hc := ht + hg + hs + hm + htb
hc = 2.3 m
Must be equal to
h = 2.3 m
Depth of Foundation
hdepth := hc ht
hdepth = 2 m
4) MATERIAL SPECIFICATION
f y1 := 240
mm
f y2 := 390
mm
K := 22.5
mm
f c := 0.83K
f c = 18.675
N
mm
8/13/2014
STANDARD FOUNDATION
TOWER 62 m
w := 9810
c := 2400
csat := 1400
s := 7850
kgf
m
kgf
m
kgf
m
1.40
f y2
mm
min = 0.00359
Balanced Reinforcem ent ratio
bal :=
0.85 fc 1
fy2
600
mm
600
N
mm
+ fy2
bal = 0.021
8/13/2014
STANDARD FOUNDATION
TOWER 62 m
Breq :=
qall
Breq = 1.824 m
Adopt Width of Pad
B := 2.1m
Must be >
Breq = 1.824 m
OK!!
Shallow Foundation
hc ht
B
= 0.952
Must be < 1
OK!!
5) CHECK STABILITY
WEIGHT OF CONCRETE
Weight of Foot Plate
W fp := 6B B hm c
W fp = 25401.6 kgf
Weight of Pedestal
W ped := 6 bb bt hts c
W ped = 6840 kgf
Weight of tie Beam
W tb := 7 btb htb Ltie c
W tb = 2520 kgf
Weight of Concrete
W con := W tb + W ped + W fp
W con = 34761.6 kgf
8/13/2014
STANDARD FOUNDATION
TOWER 62 m
Volume of Concrete
W con
Vcon :=
Vcon = 14.484 m
hx := hg + hs + hm + htb
bf := 30deg
x := hx tan bf
( )
hx = 2 m
x = 1.155 m
Volume of Soil
Vsoil := Acap +
Vsoil = 22.075 m
(Acap) (
Acap + 2 x
)2 + (
)2 3x
h
Acap + 2 x
Vbf = 7.891 m
1.25
SFuplift1 = 1.23
SFuplift2 :=
W bf
OK!!
W con + W bf
SFuplift2 = 1.709
T
must be > 1.50
OK!!
8/13/2014
STANDARD FOUNDATION
qsmax :=
TOWER 62 m
C
B B
6 Mmax
qsmax = 1.505
( B)
kgf
cm
SFallow :=
must be <
qall = 1.667
kgf
cm
OK!!
qall
qsmax
SFallow = 1.11
OK!!!!
Friction Coefficient
fr := 0.45
SFsliding :=
fr FZC max
Fa
SFsliding = 14.98
OK!!!!
C comp
B
u = 12571.644
kgf
m
8/13/2014
STANDARD FOUNDATION
TOWER 62 m
d2 = 0.2 m
b3 :=
B bb + 2d2
2
ht = 0.3 m
hg = 0
htb = 0.3 m
hdepth = 2 m
d2 = 0.2 m
d2 = 0.2 m
hs = 1.3 m
hm = 0.4 m
b3 = 0.6 m
bb + 2d2 = 0.9 m
b3 = 0.6 m
B = 2.1 m
)2
Vu := C comp bb + 2 d2 u
Vu = 443828.571 N
Strenght reduction factor for shear
sh := 0.85
Perimeter of critical section
bo := 4 bb + 2 d2
bo = 3.6 m
N
mm
Vc = 1.746 10 N
SFpunch1 :=
Vc
Vu
bo d
Must be >
Vu = 4.438 10 N
SFpunch1 = 3.93
OK!!
8/13/2014
STANDARD FOUNDATION
TOWER 62 m
Check beam shear on the plane at a distance d m from the face of the colum n
bb
B
b4 :=
d
2
2
b4 = 0.4 m
d = 0.4 m
B = 2.1 m
bb
2
= 0.25 m
b4 = 0.4 m
Vcp := sh ( 0.17 ) f c
mm
5
Vcp = 5.245 10 N
SFpunch2 :=
bw d
Must be >
Vcp
SFpunch2 = 5.07
Vup
Vup = 1.036 10 N
OK!!
Mu := d + b4 B u
8/13/2014
d + b4
2
STANDARD FOUNDATION
TOWER 62 m
Mu = 82848 N m
Strenght reduction factor for flexure
flex := 0.90
By The Trial Method :
a1 := 40mm
Try :
Mu
f
a1
flex y2
d
Asreq = 621.143 mm
A sreq f y2
B fc 1
a2 = 0.007 m
a2 = 0.727 cm
Must be <
a1 = 4 cm
OK !!!!
1.4
f y2
mm
bw d
Acsmin1 = 3015.385 mm
Area of Bar
dbarpad := 16mm
1
2
Abar := dbarpad
4
Abar = 201.062 mm
Number of Bar
Abar
nbar := round
nbar = 3
Used Spacing
8/13/2014
10
STANDARD FOUNDATION
S1 :=
TOWER 62 m
B
nbar 1
S1 = 1050 mm
Sbar1 :=
S 1 if S1 200mm
"used 200 mm"
if S1 > 200mm
f
FZTmax = 209.112 kN
Factored mom ent forces
Mytm := f Fy hts
Mytm = 17.932 m kN
Compression
Factored maxim um com pression forces
FZC max :=
f
FZC max = 418.223 kN
Factored mom ent forces
Mxtm := f Fx hts
Mxtm = 36.136 m kN
From the Interaction Diagram
Use Reinforcem ent as follow :
8/13/2014
11
STANDARD FOUNDATION
TOWER 62 m
C tot = 5.437 10 N
Length of Tie Beam
Ltie = 2.5 m
Uniform Load for Tie Beam
C tot
qtb :=
Ltie
8/13/2014
N
qtb = 21747.6
m
12
STANDARD FOUNDATION
TOWER 62 m
qtb
Ltie
MA
Mtbmax
Ltie 2x1
x1
MA
x1
Mtbmax :=
qtb Ltie
24
Mtbmax = 5.663 m kN
Mom ent forces at fix side
2
MA :=
qtb Ltie
12
MA = 11.327 m kN
x1 := 0.2113 Ltie
x1 = 0.528 m
Factored maxim um Moment forces
Concrete Cover
ppad := 40mm
Effective depth of Tie Beam
dtie := htb ppad
dtie = 26 cm
8/13/2014
13
STANDARD FOUNDATION
R n :=
TOWER 62 m
Mntie
mm 2
b d 2 N
m tb tie
R n = 0.931
m 1 :=
fy2
0.85 fc
m 1 = 24.569
Required Reinforcement ratio
1
req :=
1
m1
2 m 1 R n
mm
f y2
req = 0.002
Used Reinforcem ent ratio
used :=
used = 0.004
Required Area for R einforcement
Atiereq := used btb dtie
Atiereq = 186.667 mm
Ause := Atiereq
1
4
dbpad
Abar = 201.062 mm
Number of Bar
Ause
ntie :=
Abar
ntie = 0.928
So, Using no of bar
ntie = 0.928
dbpad = 16 mm
Shear Reinforcement
8/13/2014
14
STANDARD FOUNDATION
TOWER 62 m
Quantity of section
nstr := 2
For Shear Reinforcem ent, use m inim um steel shear reinforcem ent
1
2
Avtie1 := nstr dstr
4
Avtie1 = 157.08 mm
mm
btb
Stie = 918.916 mm
Maxim um Stirrup Spacing
Stie2 :=
htb ppad
2
Stie2 = 130 mm
So, Using
dstr = 10 mm
with
Stie2 = 130 mm
8/13/2014
15