Anda di halaman 1dari 25

Detailed Project Report

Siras Engineering Pvt. Ltd.

Page 1 of 2

www.Credit-Mantra.com

TABLE OF CONTENTS
1

EXECUTIVE SUMMARY .................................................................................................................. 1


1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11

PROPOSED PROJECT..................................................................................................................... 6
2.1
2.2
2.3
2.3.1
2.3.2
2.3.3
2.4
2.5
2.6
2.7
2.8

INTRODUCTION .......................................................................................................................... 1
THE PROJECT............................................................................................................................. 1
PRODUCT .................................................................................................................................. 1
LOCATION ................................................................................................................................ 1
PROJECT COST AND MEANS OF FINANCE ................................................................................. 2
KEY FACTORS OF PROJECT FOR DEBT ........................................................................................ 2
M ANAGEMENT .......................................................................................................................... 3
CAPITAL STRUCTURE .................................................................................................................. 4
NET WORTH OF PROMOTERS ...................................................................................................... 4
PROJECTED FINANCIALS ............................................................................................................ 5
SENSITIVITY ANALYSIS ................................................................................................................. 5
RAW M ATERIAL ......................................................................................................................... 6
M ARKETING ARRANGEMENTS- ................................................................................................... 6
INFRASTRUCTURE ........................................................................................................................ 6
Land and Building.......................................................................................................... 6
Water................................................................................................................................. 6
Electricity .......................................................................................................................... 7
PLANT AND M ACHINERY ........................................................................................................... 7
M ANPOWER.............................................................................................................................. 7
PROJECT IMPLEMENTATION SCHEDULE ...................................................................................... 8
M AJOR STATUTORY APPROVALS ............................................................................................... 8
INDUSTRY ANALYSIS ................................................................................................................... 8

RISK & SWOT ANALYSIS .............................................................................................................. 11


3.1
RISK ANALYSIS & MITIGATION MECHANISM............................................................................. 11
3.2
SWOT ANALYSIS..................................................................................................................... 12
3.2.1
Strengths:........................................................................................................................ 12
3.2.2
Weakness: ...................................................................................................................... 12
3.2.3
Opportunities: ............................................................................................................... 12
3.2.4
Threats:............................................................................................................................ 12

PROFITABILITY PROJECTIONS.................................................................................................... 13

CONCLUSION & RECOMMENDATIONS.................................................................................. 14

Detailed Project Report

Siras Engineering Pvt. Ltd.


1

1.1

EXECUTIVE SUMMARY

Introduction

Siras Engineering Pvt. Ltd. was incorporated on 23/03/2015 vide CIN No.
U29253PN2015PTC154447. Its registered office is at Flat No. I-1104, Greens
Society, Thergaon, Chinchwad, Pune, Maharashtra with an objective to set up
an Integrated Machining Shop of Forging and Casting material.
Company promoted by following Directors.
Mr. Sadanand Nilkanth Patil
Mr. Parthasarthy Venkateshwaralu
Mr. Kaustubh Avinash Palekar

1.2

The Project

Siras Engineering Pvt. Ltd. proposes to set up a Precision Machining Shop to


Manufacture components for Hydraulic, Industrial and automotive customers.
Capacity of 50,000 pcs per year, Production hours of 25,000 Hrs, total tonnage
of 500 MT at 148/1-E, Next to Rinder, Om Gurudev Industrial Estate, Mahalunge,
Chakan, Pune 410501.

1.3

Product

Hydraulic industry complex core casting and machining valve bodies,


port blocks and housing.

1.4

Passenger car/ heavy duty turbine bearing housing.

Drive train components to heavy duty and passenger cars.

Assembly products for Industrial Market segment.

Location

The proposed project site is located Plot no. 148/1-E, Next to Rinder, Om
Gurudev Industrial Estate Mahalunge, Chakan, Pune 410501.

P ag e |1

Detailed Project Report


1.5

Siras Engineering Pvt. Ltd.

Project Cost and Means of Finance

The total project cost is estimated at Rs. 285 Lakh, which is proposed to be
funded at a debt equity ratio of 60:40 with equity of Rs. 114 Lakh and Term
debt of Rs. 171 Lakh.
Project Cost
Particulars

Amount

% of Total Cost

Plant and Machinery

185.00

71.15%

Other Fixed Assets

40.00

15.38%

Preliminary and Pre Operative Expenses

5.00

1.92%

Margin Money for Working Capital

30.00

11.54%

260.00

100%

Promoter's Contribution

104.00

40%

Term Loan from Banks

156.00

60%

260.00

100%

TOTAL
Means of Finance

TOTAL

1.6

Key Factors of Project for Debt

Project Cost

Rs 260.00 Lakh

Financing Plan

Term Debt and Equity in the ratio of 60:40

Facility

Term Debt: Rs 156.00 Lakh


Working Capital Loan -79.00 Lakh

Moratorium

Six (6) months from COD

Repayment

7 years

Security for Term

The debt shall be secured by:

Debt

1. First charge by way of mortgage of all Assets of the


Project.
2. First charge on all current assets.
3. Additional Collateral security - 70% of total Debts
4. Personal Guarantee of Directors (Net Worth 3.00 Cr)

P ag e |2

Detailed Project Report


1.7

Siras Engineering Pvt. Ltd.

Management

Mr. Sadanad Patil, age 48 years, is a Production Engineering Graduate from


University of Marathwada, Aurangabad with 3rd Rank, Having 27 years of
Industry Experience.
He implemented over 100 operations in Bajaj Auto Ltd. Hands on working for
Tool Design and Manufacturing and extended this work in Machine tool Design
and Assembly.
He also has commercial expertise in procurement of Forging and Machining
Commodity. He successfully set up the Export Operations at Badve Group. He
added the customers like INGERSOLL RAND, FICOSA, GE, BROSE, FAURECIA,
VOLVO, FIAT and HONDA.

He set up a Joint venture with Cellino group Italy

for Badve . He also executed 4 Green field project of Badve group.


Mr. Venkat Parthasarthy, age 40 years, is an Engineering graduate from PSG
College of Technology and MBA from Iowa State University (USA). He has
worked for 15 years with Major Corporate in USA (Eaton, Case and New
Holland and Mercury Marine) in capacity of Global Purchasing Head. In his last
assignment, Mr. Parthasarthy, turned around a sick Industry (Precision Machine,
USA) within 2 years, currently the organization is making around 100 crores
turnover and with a healthy margin of 15%. Mr. Parthasarthy have network
contact with major OEMs. He is stationed in USA, he will be leading the
marketing activities of Siras Engineering in USA, and this will be a major strength
for the company.
Mr. Kaustubh Palekar age 42 years, is a PGDBM from IBS Bangalore, with over
21 years of experience in manufacturing industry, including 10+ years of P&L
management, and business development, particularly in the Automobile,
construction equipment, mining and Farm Equipment sector.
He has the proficiency in technical and commercial aspects of setting up
projects from conception to completion. Operational expertise in supply chain,
including procurement, across multiple plants and locations - process

P ag e |3

Detailed Project Report

Siras Engineering Pvt. Ltd.

efficiency improvement through six sigma and lean, localization, outsourcing,


automation and ERP implementation.
Skilled at team management, talent development and resource optimization
with focus on quality deliverable and cost reduction.
1.8

Capital Structure

Presently the authorized and paid up capital of company is 1.00 Lacs which will
be increased upto 250 Lacs the extent of projected equity before getting term
loan sanction / disbursement. The shareholding pattern of Company is as on
date, is as under:
S. No.

Name of the Share Holder

% of Share Holding

1.

Mr. Sadanand Nilkanth Patil

25%

2.

Mr. Parthasarthy Venkateshwaralu

25%

3.

Mr. Kaustubh Avinash Palekar

25%

4.

Mr. Rajesh Rawoor

25%

Total

1.9

Net worth of Promoters

The net worth of the promoters as on 31st March 2014 is as follows:


S. No.
1.

Name of the Share Holder


Mr. Sadanand Nilkanth Patil

Net Worth (Lakh)


125.00 Lacs

2.

Mr. Parthasarthy Venkateshwaralu

50.00 Lacs

3.

Mr. Kaustubh Avinash Palekar

75.00 Lacs

4.

Mr. Rajesh Rawoor

200.00 Lacs

Total

400.00 Lacs

P ag e |4

Detailed Project Report

Siras Engineering Pvt. Ltd.

1.10 Projected Financials


The projected profitability statement of the project is as given below:
(Rs. Lakhs)
Particulars

1st Year

2nd Year

3rd Year

4th Year

5th Year

6th Year

7th Year

550

577.5

606.38

636.69

668.53

701.95

737.05

Profit Before Tax

41.54

49.1

56.87

64.9

73.13

81.61

90.37

Profit After Tax

33.23

38.39

42.06

46.14

50.56

55.31

60.41

6%

7%

7%

7%

8%

8%

8%

1.55

1.71

1.87

2.06

2.3

2.61

3.01

Sales

NP Ratio
DSCR
IRR

21.52%

1.11

Sensitivity Analysis

Particulars

Average DSCR

IRR

Actual

2.07

21.52%

5% Reduction in selling price

1.18

4.09%

5% Increase in variable cost

1.33

7.26%

P ag e |5

Detailed Project Report

Siras Engineering Pvt. Ltd.

PROPOSED PROJECT

Siras Engineering Pvt. Ltd. proposes to set up a Precision Machining Shop to


Manufacture components for Hydraulic, Industrial and automotive customers.
Capacity of 50,000 pcs per year, Production hours of 25,000 Hrs, total tonnage
of 500 MT at 148/1-E, Next to Rinder, Om Gurudev Industrial Estate, Mahalunge,
Chakan, Pune 410501.

2.1

Raw Material

Main Raw material is the Aluminum and Cast Iron which are easily available
across:

The major purchase of Aluminum will be from Hindalco & Jindal.

The purchase of cast Iron will be mainly from Indo Shell Mould Ltd,
Coimbatore due to quality approval of final product.

2.2

Marketing arrangements-

Siras Engineering has made the strategic tie-up with ABB Ltd, Eton Ltd. and
Stewart Mfg for the machining job / business. The complete production
capacity will be utilized above companies, and 80% production will export.

2.3

Infrastructure

2.3.1 Land and Building


Company has taken a constructed shed measuring 4000 Sqft on rental to run
the workshop. After competition of construction on its own MIDC land
company will shift the plant and machinery there.
This shed is sufficient to accommodate plant and machinery, Raw material and
Finish Goods godown, stores, security, canteen and laboratory etc.

2.3.2 Water
Water requirement in the project will be very less. Total consumption for the
entire production process will 3000 Ltr/ Day.
P ag e |6

Detailed Project Report

Siras Engineering Pvt. Ltd.

2.3.3 Electricity
The existing rented premises has MSEB approved connection, Demand of 100
KVA will be increased by MSEB before machines are installed. The rented
permises is located in Chakan area, where major OEMs are located,
government ensured uninterrupted power supply.

2.4

Plant and Machinery

The Company is process to purchase the following plant and machinery from
M/s Surin Automotive Pvt. Ltd, Pune.
Machine Description

Make

Horizontal Machining center


4000
Horizontal Machining center
Vertical Machining Center 410 A-2 with 4th Axis
Vertical Machining center
with pallet changer
Vertical Machining center
with pallet changer
2.5

Capacity

Mazak

Power
consumption
30KW

5000 hrs

Tonnage
Per Year
150

BFW

30 KW

5000 hrs

150

Mazak

18.5 KW

5000 hrs

75

BFW

18.5 KW

5000 hrs

50

BFW

18.5 KW

5000 hrs

50

Manpower

The Company proposes to recruit well-trained staff for the proposed project.
The total of 20 personnel will be required as follows for operation of plant in
direct, administration and other categories. The skilled operator must have
necessary experience and adequate qualification.

Category

Nos

Manager

Engineers

supervisors

Skilled Labour
Administrative Staf
Total

12
2
20

P ag e |7

Detailed Project Report


2.6

Siras Engineering Pvt. Ltd.

Project Implementation Schedule

Since Company will install all machines on readymade rented premises which
is already taken, The Installation will be completed by Oct-15 and commercial
production could be started in Nov-15.

2.7

Major Statutory Approvals

As per the information provided by the Company, the status of major statutory
approvals required for the implementation of the project is given below:
Approval/ Consent

Agency

Status

SSI Certification

DIC (Govt. of Maharashtra)

Applied

Pollution Clearance

NA

NA

Electricity

Maharashtra State Electricity Applied


Board
Central excise & Sales tax Excise Department and Sales Received
registration
Tax Department

2.8

Industry Analysis

India Market
Revenue in the Machine Shop Services industry has experienced robust growth
during the five years to 2015. As the industry's major markets, including
Passenger Auto sector, Commercial Transportation manufacturing, picked up,
so did revenue. During the five years to 2020, operators will devote further
resources to satisfying growing demand from manufacturers in industries like
automobile manufacturing, commercial transport manufacturing and metal
forging.
India stands 14th in production and 10th in the consumption of machine tools
in the world as per the 2015 Gardner Business Media survey. The country is set
to become a key player in the global machine tools industry and is likely to see
substantial high-end machine tool manufacturing. With emphasis on Make in
P ag e |8

Detailed Project Report

Siras Engineering Pvt. Ltd.

India and manufacturing growth, for which the machine tools sector serves as
the mother industry.
The Indian Machine tool Industry has around 1000 units in the production of
machine tools, accessories/attachments, subsystems and parts. Of these,
around 25 in the large scale sector account for 70 percent of the turnover and
the rest are in the SME sector of the industry. Approximately, 75 per cent of the
Indian machine tool producers are ISO certified.
Ref: Indian Machine Tool Manufacturing Association (www. imtma.in)
The industry can be segmented in several ways:
CNC

Conventional

Forming

Rs. 126 Cr

RS. 336 Cr

Cutting

Rs. 3295 Cr

Rs. 473 Cr

Indian Machine Tool Industry 2013-14 & 2014-15 (INR Crores)


2013-14

2014-15

Growth Rate

Production

3481

4320

22%

Exports

246

280

13%

Imports

4672

5317

14%

Consumption

7907

9358

18%

The Indian machine tools sector offers several opportunities for investment.
Given the current gap between demand and supply, there is a clear need for
adding capacities in this sector. The industry is moving towards increasingly
sophisticated CNC machines, driven by demand from key user segments, such
as, automobiles and consumer durables, Aerospace etc.
Machine tool manufacturers need to develop capabilities to cater to this
demand and investments in this area could yield long term benefits.

P ag e |9

Detailed Project Report

Siras Engineering Pvt. Ltd.

US machine tool industry is highly fragmented with over 20,000 independently


owned business units. Total industry sales revenue is about $40 Billion with top 50
players make only 10% of the total revenue.
Customers are OEMs that procure components from suppliers and further
process/assemble and convert to final product. OEMs are focusing on core
competence and divesting noncore activities. OEMs are allocating capital
investment to R&D, and core competence activities.
OEMs are outsourcing most of the machining work. Machined components
are mostly leveraged commodity, with many players in the market; it is suitable
for the buyer to outsource. Buyers have more buying power.
Market is in need of suppliers with the following, Engineering expertise, global
manufacturing foot print, supply chain expertise, warehouse, and vertical
integration of foundry.
Global Analysis
China currency valuation (appreciated over 30%) and local growth spurred for
more local consumption. It is forecasted that china growth will predominantly
come from local consumption.
OEMs are shifting the manufacturing base. India will play a major role in
absorbing the work. New government of India is focusing on making India as
one of the low cost manufacturing hub. Government is planning to do the
following

Ease of doing business

Tax reform

Infrastructure

Incentive for foreign investment (especially in manufacturing).

Reduce interest rate.

P a g e | 10

Detailed Project Report


3
3.1

Siras Engineering Pvt. Ltd.

RISK & SWOT ANALYSIS


Risk Analysis & Mitigation Mechanism

Type of Risk

Risk

Mitigation Measures

Category
Project Cost &

Low

Time Overrun

The project cost has been estimated based on the final


quotations and the estimates made by the Company
on basis of its promoters experience same field.

Raw Material

Low

Availability

The major raw material required for the proposed


facilities is Cast Iron and Aluminum. These materials
can be procured from reputed manufacturer Jindal,
Hindalco and foundries in Coimbatore and Kolhaphur ,

Cost Risk

Low

For the purpose of financial analysis, the raw material


and other costs have been assumed based on the
average market prices. Moreover, the sensitivity
analysis at 5% increase in variable costs shows that the
Company can withstand reasonable adverse
fluctuations in the cost levels.

Off Take Risk

Low

These machines can be used for various customers,


only change required is develop the program to
machine the component.

Price Risk

Medium

Raw material escalation is a pass through to customers,


this is done through Long Term Agreement.

Funding Risk

Low

Promoters already arranged 100% of the equity


contribution

and

ready

to

bring

upfront

before

sanctioning the loans. The project is financially viable


with a comfortable Avg. DSCR of 2.07.

P a g e | 11

Detailed Project Report


3.2

Siras Engineering Pvt. Ltd.

SWOT Analysis

3.2.1 Strengths:
High growth rate
High Profitability and revenue due to upgraded Technology and low
labor cost
Promoter of the company is a highly experienced and qualified person.
They also have sound financial background.

3.2.2 Weakness:
Investments in research and development
Future competition

3.2.3 Opportunities:
New acquisitions
New markets
Growing demand

3.2.4 Threats:
Only prominent threat is 3D printing technology, but these will be a
threat for shops that are specializing in 1 to 5 pcs range. Hence 3D is not
suitable for mass production.

As could, be seen from the above, the strengths and opportunities are more.
The weaknesses and threats can be surmounted by adopting appropriate
managerial strategy / business tactics.

P a g e | 12

Detailed Project Report


4

Siras Engineering Pvt. Ltd.


PROFITABILITY PROJECTIONS

The following Annexure listed below will provide the complete financial model
of the project:
Annexure -1

Project cost estimate

Annexure -2

Projected Profitability Statement

Annexure -3

Projected Balance sheet

Annexure -4

Term Loan Repayment Schedule

Annexure -5

Projected Cash flow statement

Annexure -6

Projected Working Capital Requirement

Annexure -7

Key Financial Indicator, Ratio, Sensitivity Analysis

Annexure -8

Income Tax Calculation

Annexure -9

Depreciation Calculation

P a g e | 13

Detailed Project Report

Siras Engineering Pvt. Ltd.

CONCLUSION & RECOMMENDATIONS

The project is technologically and economically viable. There is no scarcity for


raw material.
Overall growth outlook for the industry appears positive. Some of the factors
that would drive growth in the industry are:
1) Low cost operations
2) Research-based processes
3) Improvements in API
4) Availability of skilled manpower.
Overall the project is well conceived and conceptualized, with sound
commercial viability. The expected financial returns are quite satisfactory.
The project is being implemented by promoters having requisite background
and experience and with employment of experienced professionals, experts
and consultants. All perceived risks have adequate safeguards.
Thus, based on the foregoing analysis and suitable mitigation of risks
enumerated in the risk analysis, the proposed project of Rs. 285.00 Lakhs by
M/s Siras Engineering Pvt. Ltd. is viewed as financially viable and bankable.

P a g e | 14

Total Project Cost and Mean of Finance

Annexure -1
Rs. In Lakhs.

PROJECT COST
SL No

Particulars

Amount

% of Total Cost

Land

0.00

0.00%

Civil and Building Construction

0.00

0.00%

2
4
5
6
7
8

Site Development

0.00

Plant and Machinery


Other Fixed Assets

Pre Operative and Premilary Expenses


Interest During Construction

Margin Money for Working Capital

0.00%

185.00

71.15%

5.00

1.92%

40.00

0.00

15.38%

0.00%

30.00

260.00

100.00%

Promoter's Contribution

104.00

40%

TOTAL MEANS OF FINANCE

260.00

100%

TOTAL COST OF THE PROJECT

11.54%

MEANS OF FINANCE
1
2

Term Loan from Banks

156.00

60%

Annexure -2

Projected Profitability Statement

Particulars
Total Sales

1st Year

2nd Year 3rd Year

4th Year

5th Year

6th Year

In Lacs

7th Year

550.00

577.50

606.38

636.69

668.53

701.95

737.05

Cost of Raw Material

330.00

346.50

363.83

382.02

401.12

421.17

442.23

Power

27.50

28.88

30.32

31.83

33.43

35.10

36.85

Cost of Production.

Consumables (Stores & Spares )


Man Power Cost

Repair and Maintinance Cost


Selling and admin Expenses

22.00
55.00
11.00
11.00

23.10
57.75
11.55
11.55

24.26
60.64
12.13
12.13

25.47
63.67
12.73
12.73

26.74
66.85
13.37
13.37

28.08
70.20
14.04
14.04

29.48
73.71
14.74
14.74

Rent of WorkShop

Total Cost of Production

6.00

462.50

6.00

485.33

6.00

509.31

6.00

534.45

6.00

560.88

6.00

588.63

617.75

EBDIT

87.50

92.17

97.07

102.24

107.65

113.32

119.30

Less : Interest on Term Loan

19.56

16.55

13.54

10.53

7.52

4.51

1.50

Less : Depreciation

13.98

45.86

13.98

53.13

13.98

9.18

36.68

12.26

0.00

Less : Interest on CC
Profit Before Tax

Provision for Taxation


Profit After Tax

Less Dividend

Retained Earnings

Cumulative Retained Earnings

8.11

36.68
36.68

8.52

76.29

13.98

10.87

68.35

13.98

10.35

60.61

13.98

9.86

84.48

92.95

40.87

16.11

44.50

19.84

48.51

23.44

52.85

26.98

57.51

30.47

62.48

0.00

0.00

0.00

0.00

0.00

0.00

40.87
77.55

8.94

44.50

122.05

9.39

6.00

48.51

170.56

52.85

223.41

57.51

280.92

13.98

62.48

343.40

Annexure -3

Projected Balance Sheet


Particulars
Sources of Funds

1st Year

2nd Year

3rd Year

4th Year

5th Year

6th Year

7th Year

Capital

Reserves (Cumulative PAT)

104.00

327.41

280.92

104.00

274.56

223.41

104.00

226.05

170.56

104.00

181.55

122.05

104.00

140.68

77.55

104.00

Sub Total a

36.68

104.00

384.92

447.40

Secured Term Loans

133.71

133.71

111.43

111.43

89.14

89.14

66.86

66.86

44.57

44.57

22.29

22.29

0.00

0.00

Creditors

77.98

127.75

34.62

104.50

121.67

32.97

99.52

115.88

31.40

94.78

110.36

29.90

90.27

105.10

28.48

85.97

Sub Total c

27.12

81.88

134.14

140.85

Total Sources

379.50

403.34

431.07

463.09

499.74

541.34

588.25

Gross Block

230.00

160.12

83.86

230.00

174.09

69.88

230.00

188.07

55.91

230.00

202.05

41.93

230.00

216.02

27.95

230.00

Net Block

13.98

230.00

146.14

132.16

Inventories (Finished Goods)

45.21

47.47

49.84

52.33

54.95

57.69

60.58

Sundry Debtors

67.81

71.20

74.76

78.50

82.42

86.54

90.87

Sub Total b

Current Liabilities

Working Capital (CC)

343.40

36.35

Application of Funds
Fixed Asset

Less Dep. To date


Current Asset

Inventories (RM)

Other Current Assets

Cash & Bank Balances

Sub Total: Current Assets


Total Applications

27.12
11.00
12.34

163.48

379.50

28.48
11.55
42.60

201.29

403.34

29.90
12.13

31.40
12.73

32.97
13.37

34.62
14.04

97.84

36.35
14.74

76.37

114.04

155.91

202.31

253.55

431.07

463.09

499.74

541.34

588.25

243.00

289.00

339.62

395.20

456.08

Annexure -4

REPAYMENT SCHEDULE
Particulars

Opening Balance
Addition
Total

Repayment

Closing Balance

Interest @13.5%

1st Year

2nd Year

3rd Year

4th Year

5th Year

6th Year

7th Year

0.00

133.71

111.43

89.14

66.86

44.57

22.29

156.00

133.71

111.43

89.14

66.86

44.57

22.29

133.71

111.43

89.14

66.86

44.57

22.29

0.00

156.00

22.29
19.56

0.00

22.29
16.55

0.00

22.29
13.54

0.00

22.29
10.53

0.00

22.29
7.52

0.00

22.29
4.51

0.00

22.29

1.50

Annexure -5

CASH FLOW STATEMENT


Particulars
PAT As per P&L Account
Depreciation

Increase in a) Capital

b) Secured Term Loans


c) Cash Credit Facility

Increase in Current Liability


Total of Sources

1st Year

2nd Year

3rd Year

4th Year

5th Year

6th Year

7th Year

36.68

40.87

44.50

48.51

52.85

57.51

62.48

156.00

13.98

104.00

77.98
27.12

415.76

Project Capital Expenses

225.00

Repayment of Term Loan

22.29

Preliminary Expenses

Increase in Fixed Assets

Increase in Current Asset


Total Applications

Opening Cash Balance


Cash Surplus/Deficits
Closing Cash Balance

5.00
0.00

13.98
-

3.90
1.36

13.98
-

4.09
1.42

13.98
-

4.30
1.50

13.98
-

4.51
1.57

13.98
-

4.74
1.65

13.98
-

4.98
1.73

60.10

63.99

68.28

72.91

77.87

83.17

22.29

22.29

30.22

30.62

31.03

31.47

31.93

12.34

12.34
30.26

42.60
33.77

76.37

114.04

155.91

202.31

42.60

76.37

37.67

114.04

41.87

155.91

9.18

22.29

29.84

12.34

8.75

22.29

7.56

8.33

22.29

151.14

403.42

7.94

22.29

46.40

202.31

9.64

51.24

253.55

Annexure -6

COMPUTATION OF WORKING CAPITAL REQUIREMENTS


Particulars

Stock of raw materials


Finished goods

Sundry Debtors

Total Current Assets


Sundry Creditors

Total Current Liabilities

Holding
level
(days)
30
30
45
30

Working capital gap

Less 25% of current assets


MPBF

Utilisation
ROI

Interest

1st Year

27.12
45.21
67.81

13%

28.48
47.47
71.20

3rd Year

29.90
49.84
74.76

4th Year

31.40
52.33
78.50

5th Year

32.97
54.95
82.42

6th Year

34.62
57.69
86.54

7th Year

36.35
60.58
90.87

140.14

147.14

154.50

162.23

170.34

178.85

187.80

27.12

28.48

29.90

31.40

32.97

34.62

36.35

27.12

28.48

29.90

31.40

32.97

34.62

36.35

113.01

118.66

124.60

130.83

137.37

144.24

151.45

77.98

81.88

85.97

90.27

94.78

99.52

104.50

13%

13%

35.03

80%

2nd Year

62.38

13%

8.11

36.79
65.50

13%

8.52

38.63
68.78

13%

8.94

40.56
72.22

13%

9.39

42.58
75.83

13%

9.86

44.71
79.62
10.35

46.95
83.60
10.87

Sl No

Particulars

Net Profit Ratio

Current Ratio

2
4
5
6
7
8

EBDIT/Sales

Debt & Equity Ratio


FACR

TOL/TNW

Debtors Days

Crediors Days

1st Year
6.67%

15.91%
1.56
0.95
1.62
1.70
45
30

Key Financial Indicators

Annexure -7

2nd Year

3rd Year

4th Year

5th Year

6th Year

7th Year

16.0%

16.0%

16.1%

16.1%

16.1%

16.2%

7.08%
1.82
0.61
1.81
1.22
45
30

7.34%
2.10
0.39
2.11
0.91
45
30

7.62%
2.38
0.24
2.60
0.69
45
30

7.91%
2.66
0.14
3.59
0.53
45
30

8.19%
2.95
0.06

8.48%
3.24
0.00

6.56

#######

45

45

0.41
30

0.31
30

Annexure -8

COMPUTATION OF INCOME TAX AS PER INCOME TAX ACT 1961

Sl No

Particulars

1st Year

2nd Year 3rd Year

4th Year

5th Year

6th Year

7th Year

Profit Before Taxes

45.86

53.13

60.61

68.35

76.29

84.48

92.95

Total

59.83

67.11

74.59

82.33

90.27

98.46

106.93

0.00

0.00

2
4
5
6
7
8
9

10

11

Add Depreciation on SLM


Less Depreciation on WDV
Less: Unabsorbed Dep

13.98
34.50
0.00

13.98
29.33
0.00

13.98
24.93
0.00

13.98
21.19
0.00

13.98
18.01
0.00

13.98
15.31

13.98
13.01

Balance

25.33

37.78

49.66

61.14

72.26

83.15

93.92

Profit Taxable as per MAT

45.86

53.13

60.61

68.35

76.29

84.48

92.95

Taxable at Normal rates


Normal tax @32.445%
MAT @ 20.00775%

Income Tax Payable

25.33
8.22
9.18

9.18

37.78
12.26
10.63

12.26

49.66
16.11
12.13

16.11

61.14
19.84
13.68

19.84

72.26
23.44
15.26

23.44

83.15
26.98
16.90

26.98

93.92
30.47
18.60

30.47

Annexure -9

DEPRECIATION SCHEDULE
Under the Companies Act
Particulars

Plant & Machinery

Gross Block

Additions/Adjustment

Depreciation brought forward


Depreciation for the year

5.28%

Total Depreciation
Net Block

Other Fixed Assets

Gross Block

Additions/Adjustment

Depreciation brought forward


Depreciation for the year

9.75%

Total Depreciation
Net Block

Total Gross Block


Additions/Adjustment

Depreciation for the year

Additions/Adjustment
Total

Depreciation for the year


Closing WDV

15%

Opening WDV
Total

Depreciation for the year


Closing WDV

Total Depreciation for the year

0.00

9.98

19.96

29.94

39.92

49.90

59.88

189.00

9.98
9.98

0.00

189.00

9.98

19.96

0.00

189.00

9.98

29.94

15%

0.00

189.00

9.98

39.92

0.00

189.00

9.98

49.90

0.00

189.00

9.98

59.88

0.00

189.00

9.98

69.85

179.02

169.04

159.06

149.08

139.10

129.12

119.15

41.00

41.00

41.00

41.00

41.00

41.00

41.00

0.00

4.00

8.00

11.99

15.99

19.99

23.99

41.00

4.00
4.00

0.00

41.00

4.00

0.00

41.00

4.00

0.00

41.00

4.00

41.00

4.00

41.00

4.00

41.00

4.00

11.99

230.00

230.00

230.00

230.00

230.00

230.00

230.00

13.98

27.95

41.93

55.91

69.88

83.86

97.84

0.00

230.00

13.98

202.05

0.00

230.00

13.98

188.07

2nd Year

3rd Year

0.00

230.00

13.98

174.09
4th Year

21.01

0.00

230.00

13.98

160.12
5th Year

23.99

0.00

8.00

25.01

19.99

0.00

33.01

29.01

15.99

0.00

37.00

Under the Income Tax Act

Office Equipments

Additions/Adjustment

189.00

Dep rate 1st Year

Opening WDV

7th Year

189.00

216.02

Plant and Machinery

6th Year

189.00

13.98

Net Block

5th Year

189.00

230.00

Total Accumulated Depreciation

4th Year

189.00

0.00

Total

3rd Year

189.00

0.00

Total

2nd Year

189.00

0.00

Total

PARTICULARS

1st Year

17.02

0.00

230.00

13.98

146.14
6th Year

27.98
13.02

0.00

230.00

13.98

132.16
7th Year

189.00

160.65

136.55

116.07

98.66

83.86

71.28

28.35

24.10

20.48

17.41

14.80

12.58

10.69

0.00

189.00
160.65

0.00

160.65
136.55

0.00

136.55
116.07

0.00

116.07

98.66

0.00

98.66
83.86

0.00

83.86
71.28

0.00

71.28
60.59

41.00

34.85

29.62

25.18

21.40

18.19

15.46

6.15

5.23

4.44

3.78

3.21

2.73

2.32

0.00

41.00
34.85
34.50

0.00

34.85
29.62
29.33

0.00

29.62
25.18
24.93

0.00

25.18
21.40
21.19

0.00

21.40
18.19
18.01

0.00

18.19
15.46
15.31

0.00

15.46
13.14
13.01

Anda mungkin juga menyukai